Southern California Edison Company 23 PARKER STREET IRVINE, CALIFORNIA 92718 WALTER C. MARSH June 29, 1994 TELEPHONE MANAGER OF NUCLEAR REGULATORY AFFAIRS (714) 454-4403 U.S. Nuclear Regulatory Commission Attention:

Document Control Desk Washington, D.C. 20555 Gentlemen:

Subject:

Docket No. 50-206 Seventeenth Edition of the Integrated Implementation Schedule (IIS)

San Onofre Nuclear Generating Station, Unit 1

Reference:

1. Letter from W. C. Marsh (SCE) to Document Control Desk (NRC),

dated December 30, 1993;

Subject:

Sixteenth Edition of the Integrated Implementation Schedule (IIS), San Onofre Nuclear Generating Station, Unit 1

2. Letter from Richard M. Rosenblum (SCE) to Document Control Desk (NRC), dated April 18, 1994;

Subject:

Amendment Application No. 209, San Onofre Nuclear Generating Station, Unit 1 In accordance with License Condition 2.C.(5) to Operating License DPR-13 (Possession Only), this letter provides the seventeenth edition of the San Onofre Unit 1 Integrated Implementation Schedule (IIS).

Because of the permanent shutdown of Unit 1, Edison has submitted a license amendment (Reference 2) to delete this reporting requirement.

Please note there have been no changes since our last schedule update (Reference 1).

If there are any questions on the enclosure or if you require additional information, please contact me.

Very truly you Enclosure cc:

L. J. Callan, Regional Administrator, NRC Region IV K. E. Perkins, Director, Walnut Creek Field Office, NRC Region IV M. K. Webb, NRC Project Manager, San Onofre Unit 1 Louis Carson, Regional Project Inspector, San Onofre Unit 1 R. F. Dudley, Section Chief, Decommissioning Section 9407010282 940629 PDR ADOCK 05000206 P

PDR

ENCLOSURE INTEGRATED IMPLEMENTATION SCHEDULE SAN ONOFRE NUCLEAR GENERATING STATION, UNIT 1

INTEGRATED IMPLEMENTATION SCHEDULE SAN ONOFRE NUCLEAR GENERATING STATION, UNIT 1 SEVENTEENTH EDITION JUNE 1994 INTRODUCTION This report, the seventeenth edition of the Integrated Implementation Schedule (IIS), provides the required status update for the period January 1994 through June 1994.

The sixteenth edition of the IIS was provided to the NRC by letter, W. C. Marsh to the NRC Document Control Desk, dated December 30, 1993.

PROGRESS IN IMPLEMENTING NRC REQUIREMENTS N/A - None Pending CHANGES SINCE THE LAST REPORT AND THE REASONS FOR SCHEDULE CHANGES ASSOCIATED WITH SCHEDULES A AND B As noted in the fourteenth edition on the IIS, because of the decision to permanently cease reactor operation following fuel Cycle 11, all Schedule A, B, and C modifications and major evaluations/submittals scheduled for Cycle 12 and 13 have been cancelled.

EXPECTED PERCENTAGES ALLOCATION OF RESOURCES ON REGULATORY AND BETTERMENT PROJECTS FOR THE NEXT REFUELING/MODIFICATION OUTAGE N/A

INTEGRATED IMPLEMENTATION SCHEDULE (Continued)

1. INTEGRATED IMPLEMENTATION SCHEDULE A
a. Modifications Associated with a Rule, Regulation or Order None
b. Ongoing Major Evaluations Requiring Edison Submittal None
2. INTEGRATED IMPLEMENTATION SCHEDULE B
a. Modifications Associated with NRC Commitments and Other Requirements None
3. INTEGRATED IMPLEMENTATION SCHEDULE C
a. Plant Betterment Items None