Forwards SE Granting 921104 Relief Request from Requirement to Perform Hydrostatic Tests on Portions of CCW Sys
ML13312A650
Person / Time
Site: San Onofre 
Issue date: 12/22/1992
From: Quay T
Office of Nuclear Reactor Regulation
To: Ray H
SOUTHERN CALIFORNIA EDISON CO.
Shared Package
ML13312A651 List:
References
TAC-M84856, NUDOCS 9212310098
Download: ML13312A650 (3)


Text

December 22, 1992 Docket No. 50-206 Mr. Harold B. Ray Senior Vice President Southern California Edison Co.

Irvine Operations Center 23 Parker Street Irvine, California 92718

Dear Mr. Ray:

SUBJECT:

SAN ONOFRE NUCLEAR GENERATING STATION, UNIT NO. 1 HYDROTESTING OF CCW SYSTEM RELIEF REQUEST (TAC NO. M84856)

By letter dated November 4, 1992, Southern California Edison (the licnesee) requested relief from the requirement to perform hydrostatic tests on portions of the Component Cooling Water (CCW) System. These hydrostatic tests are currently required by paragraph 4.7 of the Technical Specifications which referencesSection XI of the ASME Code. Your letter also proposed an inservice leak test at the nominal operating temperature and pressure of the system as an alternative.

The staff has reviewed and evaluated your request and the supporting information. Based on the information submitted we have concluded that the request for relief from the Code requirements is acceptable and is hereby granted. The staff's evaluations and conclusions are presented in the enclosed Safety Evaluation.

Sincerely, Original signed by Theodore R. Quay, Director Project Directorate V Division of Reactor Projects III/IV/V Office Of Nuclear Reactor Regulation

Enclosure:

DISTRIBUTION As stated Docket Files, NRC & Local PDRs JLieberman JPartlow TMurley/Miraglia BGrimes (11E22)

EJordan (3701)

JRoe MVirgilio DHagan TQuay DFoster cc w/enclosure:

OGC (15818)

ACRS (10)(P315)

JStrosnider See next page OC/LFDCB (4503)

KPerkins, RV JBradfute PDV R/F PDV P/F GHill (4)(P137)

OPA (2G5)

SWeiss (11820)

E X-5on (11B20)

OFC LA/PDV T

PM/PDVC 0 G 0-V D/PDV NAME DFoster J

JBra ute SWeiss 640o.<?7 TQuay DATE

/P/_3/92

/Pe4/92

\\ /

/92

/;-/

2/92 1--/4/92 OFFICIAL RECORD COPY DOCUMENT NAME:

S084856.LTR 9212310098 921222 PDR ADOCK 05000206 P

PDR

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555 December 22, 1992 Docket No. 50-206 Mr. Harold B. Ray Senior Vice President Southern California Edison Co.

Irvine Operations Center 23 Parker Street Irvine, California 92718

Dear Mr. Ray:

SUBJECT:

SAN ONOFRE NUCLEAR GENERATING STATION, UNIT NO. 1 HYDROTESTING OF CCW SYSTEM RELIEF REQUEST (TAC NO. M84856)

By letter dated November 4, 1992, Southern California Edison (the licensee) requested relief from the requirement to perform hydrostatic tests on portions of the Component Cooling Water (CCW) System. These hydrostatic tests are currently required by paragraph 4.7 of the Technical Specifications which referencesSection XI of the ASME Code. Your letter also proposed an inservice leak test at the nominal operating temperature and pressure of the system as an alternative.

The staff has reviewed and evaluated your request and the supporting information. Based on the information submitted we have concluded that the request for relief from the Code requirements is acceptable and is hereby granted. The staff's evaluations and conclusions are presented in the enclosed Safety Evaluation.

Sincerely, Theodore R. Quay, Director Project Directorate V Division of Reactor Projects III/IV/V Office Of Nuclear Reactor Regulation

Enclosure:

As stated cc w/enclosure:

See next page

Mr. Harold B. Ray San Onofre Nuclear Generating Southern California Edison Company Station, Unit No. 1 cc:

Mr. Howard J. Wong Mr. Richard J. Kosiba, Project Manager U.S. Nuclear Regulatory Commission Bechtel Power Corporation Region V 12440 E. Imperial Highway 1450 Maria Lane, Suite 210 Norwalk, California 90650 Walnut Creek, California 94596 Mr. Robert G. Lacy Manager, Nuclear Department San Diego Gas & Electric Company P. 0. Box 1831 San Diego, California 92112 Resident Inspector/San Onofre NPS c/o U.S. Nuclear Regulatory Commission P. 0. Box 4329 San Clemente, California 92674 Mayor City of San Clemente 100 Avenida Presidio San Clemente, California 92672 Chairman, Board of Supervisors County of San Diego 1600 Pacific Highway, Room 335 San Diego, California 92101 Regional Administrator, Region V U.S. Nuclear Regulatory Commission 1450 Maria Lane, Suite 210 Walnut Creek, California 94596 Mr. Hank Kocol Radiologic Health Branch State Department of Health Services Post Office Box 942732 Sacramento, California 94234 Mr. Don J. Womeldorf Chief, Environmental Management Branch California Department of Health Services 714 P Street, Room 616 Sacramento, California 95814