ML13311B087

From kanterella
Jump to navigation Jump to search
Monthly Operating Rept for Aug 1980
ML13311B087
Person / Time
Site: San Onofre Southern California Edison icon.png
Issue date: 09/04/1980
From: Joy J
Southern California Edison Co
To:
Shared Package
ML13311B085 List:
References
NUDOCS 8009090268
Download: ML13311B087 (5)


Text

AC40 - RA NRC MONTHLY OPERATING REPORT DOCKET NO.

50-206

)ATE 9I41980 COMPLETED BY J.M.JOY TELEPHONE (714) 492-7700 OPERATING STATUS I Unit Name:

SAN ONOFRE NUCLEAR GENERATING STATION

2. Reporting Period:

AUGUST 1, 1980 THROUGH AUGUST-31, 1980

3. Licensed Thermal Power (MWt):

1347

4. Nameplate Rating (Gross MWe):

456

5. Design Electrical Rating (Net MWe): 436
6. Maximum Dependable Capacity (Gross MWe):

456

7. Maximum Dependable Capacity (Net MWe):

436

8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report, Give Reasons:

N. A.

9. Power Level To Which Restricted, If Any (Net MWe):

N.A.

10. Reasons For Restrictions. If Any:

N. A.

This Month Yr.-to-Date Cumulative

11. Hours In Reporting Period 744 5856 115,832.3
12. Number Of Hours Reactor Was Critical 0

1979.1 84,611.4

13. Reactor Reserve Shutdown Hours 0

0 0

14. Hours Generator On-Line 0

1961.5 81,114.1

15. Unit Reserve Shutdown flours 0

0 0

16. Gross Thermal Energy Generated (MWH) 0 2,552,787 104,084,261
17. Gross Electrical Energy Generated (MWH) 0 855,000 35,526,434
18. Net Electrical Energy Generated (MWH) 0

.816,676 33,664,042

19. Unit Service Factor 0

33.5 70.0

20. Unit Availability Factor 0

33.5 70.0

21. Unit Capacity Factor (Using MDC Net) 0 31 -9 71 S
22. Unit Capacity Factor (Using DER Net) 0 31.9 71.5
23. Unit Forced Outage Rate 100 22.5 10.4
24. Shutdowns Scheduled Over Next 6 Months (Type. Date, and Duration of Each):

Steam Generator repair in progress.

25. If Shut Down At End Of Report Period. Estimated Date of Startup:

11/01/80

26. Units in Test Status (Prior to Commercial Operation):

N.A.

Forecast Achieved INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION e-CE Psso(l)-371 NEW 8/78

AVERAGE DAILY UNIT POWER LEVEL DOCKET NO.

50-206 UNIT SONGS-1 DATE 9/04/80 COMPLETED BY J. M. JOY TELEPHOg (714) 492-7700 MONTH

AUGUST, 1980 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net)

(MWe-Net) 1 0

17 0

2 0

18 0

3 0

19 0

4 0

20.

0 5

0 21 6

0 22 0

7 0

23 0

8 0

24 9

0 25 0

10 0

26 0

11 0

27 0

13 0

29 0

14 0

30 0

15 0

31 0

16 0

PSSO(l) 371 NEW 8/78

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.

50-206 UNIT NAME SONGS-1 DATE 9/04/80 REPORTMONTH AUGUST, 1980 COMPLETED BY J.M_ JoY TELEPHONE (714) 492-77011 Licensee Cause & Corrective No.

Date Event Action to Report #

Prevent Recurrence 55 80-07-12 F

1224 B

1 80-014 CC HTEXCH Steam Generator Tube Repair 3-4 F: Forced Reason:

Method:

Exhibit F - Instructions S: SchedUled A-Equipment Failure (Explain) 1 -Manual for Preparation of Data B-Maintenance of Test 2-Manual Scram.

Entry Sheets for Licensee C-Refueling 3-Automatic Scram.

Event Report (I LER) File (NUREG D-Regulatory Restriction 4-Other (Explain) 0161)

E-Operator Training & License Examination F-Administrative G-Operational Error (Explain)

Exhibit H-Same Source li-Othci (Explain)

Psso(1) 371 NEW 8/78

SUMMARY

OF OPERATING EXPERIENCE FOR THE MONTH 50-206 DOCKET NO.

UNIT SONGS-1 DATE 9/04/80 COMPLETED BY J.M. JOY TELEPHONE (714) 492-7700 The unit remained in cold shutdown for the entire month for steam generator tube repair.

PSSo(I)371 NEW 8/78

REFUELING INFORMATION DOCKET NO.

50-206 UNIT SONGS-1 DATE 9/04/80 COMPLETED BY J J.M.JOY TELEPHONE (714) 492-7700

1. Scheduled date for next refueling shutdown.

Not yet determined.

2. Scheduled date for restart following refueling.

November 1, 1980

3. Will refueling or resumption of operation thereafter require a Technical Specification change or other license amendment?

Yes What will these be?

Proposed Change No. 88 to POL DPR-13, Appendix A, Technical Specification 3.5.2, Control Rod Insertion Limits.

4. Scheduled date for submitting proposed licensing action and supporting information.

February 8, 1980

5. Important licensing considerations associated with refueling, e.g.

new or different fuel design or supplier, unreviewed design or performance analysis methods, significant changes in fuel design, new operating procedures.

None

6. The number of fuel assemblies.

a) In the core 157 b) In the spent fuel storage pool.

,6

7. Licensed spent fuel storage capacity.

216 Intended change in spent fuel storage capacity.

None

8. Projected date of last refueling that can be discharged to spent fuel storage pool assuming present capacity.

April 1983 PsSO(l)371 NEW8/78