Advises That Schedule for Mod to Safety Injection Sys Will Be Determined by Relative Safety Significance Established by Integrated Living Schedule
ML13310A880
Person / Time
Site: San Onofre Southern California Edison icon.png
Issue date: 08/02/1983
From: Krieger R
Southern California Edison Co
To: Crutchfield D
Office of Nuclear Reactor Regulation
References
NUDOCS 8308090289
Download: ML13310A880 (2)


Text

Southern California Edison Company P. 0. BOX 800 2244 WALNUT GROVE AVENUE ROSEMEAD, CALIFORNIA 91770 August 2, 1983 Director, Qffice of Nuclear Reactor Regulation Attention: 0. M. Crutchfield, Chief Operating Reactors Branch No. 5 Division of Licensing U. S. Nuclear Regulatory Commission Washington, D.C. 20555 Gentlemen:

Subject:

Docket No. 50-206 Redesign of the Safety Injection System San Onofre Nuclear Generating Station Unit 1

References:

A. Letter from D. M. Crutchfield, NRC, to R. Dietch, SCE, dated May 27, 1983 B. Letter from K. P. Baskin, SCE to 0. M. Crutchfield, NRC, dated September 28, 1982 C. Letter from R. Dietch, SCE, to H. R. Denton, NRC, dated June 10, 1983 D. Letter from R. Dietch, SCE, to H. R. Denton, NRC, dated June 17, 1983 Your letter (Reference A) documented the staff's review of our proposed redesign of the Safety Injection/Feedwater System and requested our schedule for submittal of final design details. The proposed redesign would provide new feedwater pumps which would then dedicate the existing system to the safety injection function. We provided a description of the conceptual design of this system in Reference B. Your review concluded that the conceptual design was acceptable, but requested a schedule for submittal of final design details.

In accordance with the plans being developed for return to service (as described in References C and D), a schedule for modification to the safety injection system will be determined by the relative safety significance established for this modification by the Integrated Living Schedule. A 830o90289 8308o2 PDR ADOCK 0500020R P

PDR!-

Mr. D.

August 2, 1983 schedule for submittal of final design details will then be established and submitted based on that implementation date.

Should you have any questions on this matter, please let me know.

Very truly yours, R. W. Kriege Supervising Engineer San Onofre Unit 1 Licensing