Reschedules Completion of Four Listed Actions Identified in Util Re Emergency Operating Instruction Program. Harsh Environ Info Will Be Included in Instructions Prior to End of Cycle 12 Refueling Outage
ML13309A150
Person / Time
Site: San Onofre 
Issue date: 12/20/1991
From: Rosenblum R
SOUTHERN CALIFORNIA EDISON CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9112260333
Download: ML13309A150 (2)


Text

Southern California Edison Company 23 PARKER STREET IRVINE, CALIFORNIA 92718 R. M. ROSEN8LUM December 20, 1991 TELEPHONE MANAGER OF (714) 454-4505 NUCLEAR REGULATORY AFFAIRS U. S. Nuclear Regulatory Commission Attention:

Document Control Desk Washington, D.C. 20555 Gentlemen:

Subject:

Docket No. 50-206 Emergency Operating Instruction Program San Onofre Nuclear Generating Station Unit 1

Reference:

F. R. Nandy (SCE) to Document Control Desk (NRC) letter dated January 28, 1991; Same Subject.

The purpose of this letter is to reschedule completion of four of the actions identified in the above referenced letter. These actions are:

1)

Include EOI attachments with the EOI's.

(This is Item I, Control Room and Plant Walkdowns, Part 2, EOI Attachments in the attachment to the referenced letter)

2)

Verify that the EOI's are consistent with the EOI's writers guide.

(This is Item I, Human Factors Review of EOIs (Writers Guide) in the attachment to the referenced letter)

3)

Resolve 47 Human Factors EOI issues. (This is Item II, paragraph 5 in the attachment to the referenced letter)

4)

Include Harsh environment information in the EOI's.

(This is Item I, Procedure Reviews in the attachment to the referenced Letter)

Actions 1, 2, and 3 above will be completed by March 29, 1992.

Action 4 will be completed prior to the end of the Unit 1 Cycle 12 refueling outage. We have previously discussed rescheduling these actions with Mr. G. Johnston of your staff.

Y--

Document Control Desk

-2 This schedule change has been made to coordinate revision of the Unit 1 EOIs with several other ongoing issues. These other issues are completion of the Unit 1 Plant Specific Simulator, the next scheduled update of the Unit 1 EOIs, and completion of Loop Uncertainty Studies.

SCE anticipates completion of these issues will require changes to the EOIs and believes coordinating these changes in a single EOI revision to be prudent.

If you have any questions, please feel free to contact me.

Very truly yours, cc:

J. B. Martin, Regional Administrator, NRC Region V George Kalman, NRC Senior Project Manager, San Onofre Units 1, 2&3 J. 0. Bradfute, NRC Project Manager, San Onofre Unit 1 C. W. Caldwell, NRC Senior Resident Inspector, San Onofre Units 1, 2&3