Notification of ACRS Subcommittee on San Onofre 2 & 3 810311 Meeting & Full Committee 810312 Meeting in Washington,Dc to Discuss SER & Suppl 1 to Ser.Agendas Encl
ML13302B008
Person / Time
Site: San Onofre  
Issue date: 03/09/1981
From: Tedesco R
Office of Nuclear Reactor Regulation
To: Grimes B
Office of Nuclear Reactor Regulation
References
NUDOCS 8103170772
Download: ML13302B008 (7)


Text

DISTRIBUTION:

Docket File 50-361/362 KKniel PDR JSkovholt LPDR GWKnighton NSIC RLBaer TERA EAdensam LB#3 File AThadani JPKnight BGrimes VSNoonan HRood C

DRMuller JLee C4 PSCheck PCollins to to WEKreger RBenedict r

LSRubenstein CThomas TMNovak SSalah RLTedesco CHinson GCLainas RVan Niel FSchroeder PHearn MLErnst THuang RJBosnak DThatcher FPSchauer CLiang REJackson RFitzpatrick GELear BMann SSPawlicki HSchierling WSHaass CGaskin ZRRosztoczy LPhillips VBenaroya ACappucci RLBallard KCampe WHRegan DPowers JDSaltzman DBeckman ODParr WLong FRosa DScaletti TPSpeis JWing RWHouston WPGammill TDMurphy WButler WJohnston JFStolz VAMoore DBVassallo DLZiemann HNBerkow GGZech SAVarga TIppolito RAClark RWReid BJYoungblood ASchwencer FMiraglia JRMiller DMCrutchfield BRussell JOlshinski

C fRREGIJ4 UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D. C. 20555 1R 91981 NOTE TO:

NRR Assistant Directors and Branch Chiefs B. Grimes FROM:

R. L. Tedesco

SUBJECT:

FORTHCOMING ACRS MEETINGS ON SAN ONOFRE, MARCH 11 & 12, 1981 The San Onofre 2 and 3 SER was issued on February 6, 1981 and Supplement No. 1 to the SER was issued on February 25, 1981.

The ACRS Subcommittee on San Onofre 2 and 3 will meet on March 11, 1981, and the full Committee will consider San Onofre 2 and 3 on March 12, 1981. In order to get a favorable letter from the full committee on March 12, and 'thereby avoid delays in the project schedule, substantive staff support at both meetings is necessary. Keep in mind that all our efforts to issue a timely Safety Evaluation will be for naught if the ACRS concludes that the staff effort is not sufficiently complete, and requires that the project be addressed again at a later meeting.

The agendas for the two meetings are attached. At the subcommittee meeting on March 11, 1981, staff presentations by R. Benedict, P. Collins, J. Knight, and C. Thomas are requested. Attendance by other staff members is requested, as indicated on the agendas, to answer ACRS questions in areas where the applicant or the staff Project Manager will be making the presentation. Your cooperation in helping to advance this project will be appreciated.

Robert L. Tedesco, Assistant Director for Licensing Division of Licensing

Tentative Presentation Schedule ACRS Subcommittee on San Onofre 2&3 Washington, D.C.

March 11, 1981 Organizational Presentation Approximate Speaker Time (min.)

Time

1. Opening Remarks by the 5

1:30 p.m.

Subcommittee Chairman

2. NRC Staff Presentation 2.1 Introduction 5

1:35 p.m.

o Plant schedule/staffing requirements 2.2 Standards for Operator 10 1:40 p.m.

Training, Including Simulators 2.3 Management Evaluation c

10 1:55 p.m.

o Assessment of the Independent Review Groups, their charter, and how they interrelate 2.4 Structural Evaluation 10 2:10 p.m.

o Structural audit, comparison with Diablo Canyon review o Safety factors for containment stress levels 2.5 Systems Interactions Evaluation..

D.J7omA&

10 2:25 p.m.

o Comparison with Zion, Indian Point and Diablo Canyon o Review group conclusions Break 10 2:40 p.m.

-2 3 Applicant Presentation 3.1 Introduction SCE/W. Moody 5

2:50 p.m.

3.2 Training Program and Facilities SCE/J. Willis 10 2:55 p.m.

3.3 Simulator SCE/B. Katz 10 o

10 p.m.

3.4 Systems Interaction B/J. Hosmer 10 11 os 3:25 p.m.

3.5 ALARA B/J. Purucker 10 o

3:40 p.m.

3.6 Emergency Planning SCE/D. Pilmer 5 V*mrN 3:55 p.m.

3.7 TMI-related Issues 3.7.1 Hydrogen Control II Provisions B/R. Tosetti 10 Me.

1% 4:05 p.m.

3.7.2 Inadequate Core Cooling CE/W. Burchill 15 4:20 p.m.

Instrumentation 3.7.3 Miscellaneous Items SCE/R. Phelps 20 4:40 p.m.

o Reg. Guide 1.97 Implementation o EPRI Relief Valve Tests (ATWS) o Loss of CCW to RCP --------

Seal s Break 10 5:05 p.m.

3.7.4 Critical Function CE/W. Gill 10 5:15 p.m.

Monitor 3.7.5 SCE Grid Reliability SCE/W. Schmus 15Fjy 5:30 p.m.

DC Power Reliability B/E. Richardson 3.7.6 NUREG-0660, Oper-SCE/W. Strom 5

5:55 p.m.

ations Feedback to Design & Procedures

& Safety Review Groups 3.7.7 Post Accident Plant CE/R. Turk 5

6:05 p.m.

Depressurization 3.7.8 Water Hammer CE/R. Turk 5

4 6:15 p.m.

Prevention in CE Plants

-3 3.7.9 Operations Related Items SCE/Fisher 15 6:25 p.m.

o Symptomatic Analysis of Accifdents o Control Panel Tag Out Procedures o RV Vent Controls 3.7.10 Air Cleaning System B/

5 IS. 1 IL 6:45 p.m.

Capabilities including Control Room Intake 3.7.11 Application of NUREG-0660 10 6:55 p.m.

Transients and Accidents 3.8 Industrial Security SCE/K. Hadley lb 7:10 p.m.

(Closed) 3.9 Summary and Conclusions SCE/W. Moody 5

7:30 p.m.

4. Closing Remarks by the Subcommittee Chairman 5

7:35 p.m.

Adjournment 7:40 p.m.

DLCox:wpc

Tentative Presentation Schedule ACRS Meeting on San Onofre 2&3 Washington, D.C.

March 12, 1981 Organizational Presentation Approximate Speaker Time (min.)

Time

1. Report by the San Onofre 15 1:00 p.m.

Subcommittee Chairman o Report by the Electrical Ices Systems Subcommittee Chairman on the Computerized Protection System

2. Staff Presentation OC I 2.1 Summary and Schedule 45P 10 11o 1:15 p.m.

2.2 Open Items -

plans and 15 1:25 p.m.

schedule for resolution o Comparison of AMO-2 T.

v4r Design with San Onofre 2&

3. Applicant Presentation 3.1 Introduction SCE/W. Moody 5

2:00 p.m.

o Response to NRC Staff Position on Open Items 3.2 Applicant Organization SCE/D.

Fogarty, 15 2:05 p.m.

R. Dietch and K. Baskin 3.2.1 Organizational Structure 3.2.2 Personnel/Qualifications 3.2.3 INPO 3.3 Training Program and Facilities SCE/J. Willis 10 L '6 2:35 p.m.

3.4 Station Blackout B/E. Richardson 10O 3

' :5 0 p.m.

3.5 Hydrogen Control Provisions B/S. Freid 10 4.bsrt 3:05 p.m.

3.6 Natural Circulation CE/H. Windsor 10 3:20 p.m.

Break 10 3:35 p.m.

-2 3.7 Human Factors Engineering 3.7.1 Control Room B/J. Singer 10ewe*

3:45 p.m.

3.7.2 Critical Function CE/W. Gill 10 Monitor.

3.7.3 Outside Control Room B/E. Richardson 5

3.8 Secondary System Chemistry 10 4:20 p.m.

and Materials A

3.9 Seismic/Non-Seismic Systems B/J. Hosmer 10 11 wAs 4:35 p.m.

Interaction 3.10 Emergency Planning SCE/ D. Pilmer 7

4:50 p.m.

3.11 Carry-over Items 7

5:00 p.m.

3.12 Industrial Security (Closed) SCE/K. Hadley 7

5:10 p.m.

3.13 Concluding Remarks SCE/W. Moody 5

5:20 p.m.

4. Executive Session 5

5:25 p.m.

Adjourment of San Onofre 5:30 p.m.

Discussions DLCox:wpc A r~rAE~