NOTE TO: NRR Assistant Directors f251981a 3
B. Grimes-CI FROM:
R. L. Tedesco
SUBJECT:
FORTHCOMING ACRS MEETINGS ON SAN ONOFRE, MARCH 11 &
The San Onofre 2 and 3 SER was issued on February 6, 1981 and Supplement No. 1 to the SER will be issued on February 24, 1981. The ACRS Subcommittee on San Onofre 2 and 3 will meet on March 11, 1981, and the full Committee will consider San Onofre 2 and 3 on March 12, 1981. 4n order to get a favorable letter from the full committee on March 12, and thereby avoid delays in the project schedule, substantive staff support at both meetings is necessary. Keep in mind that all our efforts to issue a timely Safety Evaluation will be for naught if the ACRS concludes that the staff effort is not sufficiently complete, and requires that the project be addressed again at a later meeing.
To make a good showing in March, the staff should be prepared to
.address the items on the list in Enclosure 1 which was developed based on the ACRS subcommittee meeting on San Onofre 2 and 3 which was held on February 18, 1981. Also, we need to focus on resolving open items (See Enclosure 2), so that we may describe their resolution or plan for resolution at the March 11 and 12 meetings. Your cooperation in meeting these objectives will be appreciated.
Robert L. Tedesco, Assistant Director for Licensing Division of Licensing DISTRIBUTION:
Docket File 50-361/362 LPDR PDR NS IC
\\ \\
TERA LB#3 R/F RTedesco FMiraglia HRood JLee OFFICE)
L D...
SURNAME).H.Jpp.d..:j.0.....Mir
.e..
e.o...
DATE) 2/$9 2/
81 2 1 NRC FORM 318(10/80) NRCM 0240 OFFICIAL RECORD COPY USGPO1980-329824
lpj PEG04 oUNITED STATES NUCLEAR REGULATORY COMMISSION VVASHINGTON, D. C. 20555 FEB 2 3 1981 NOTE TO:
NRR Assistant Directors B. Grimes FROM:
R. L. Tedesco
SUBJECT:
FORTHCOMING ACRS MEETINGS ON SAN ONOFRE, MARCH 11 & 12, 1981 The San Onofre 2 and 3 SER was issued on February 6, 1981 and Supplement No. 1 to the SER will be issued on February 24, 1981. The ACRS Subcommittee on San Onofre 2 and 3 will meet on March 11, 1981, and the full Committee will consider San Onofre 2 and 3 on March 12, 1981. In order to get a favorable letter from the full committee on March 12, and thereby avoid delays in the project schedule, substantive staff support at both meetings is necessary. Keep in mind that all our efforts to issue a timely Safety Evaluation will be for naught if the ACRS concludes that the staff effort is not sufficiently complete, and requires that the project be addressed again at a later meeting.
To make a good showing in March, the staff should be prepared to address the items on the list in Enclosure 1 which was developed based on the ACRS subcommittee meeting on San Onofre 2 and 3 which was held on February 18, 1981. Also, we need to focus on resolving open items (See Enclosure 2),
so that we may describe their resolution or plan for resolution at the March 11 and 12 meetings. Your cooperation in meeting these objectives will be appreciated.
.Robert L. Tedesco, Assistant Director for Licensing Division of Licensing
ENCLOSURE 1 ITEMS THAT WILL BE ON AGENDA, MARCH 11 AND 12 MEETINGS H2 Control, Ability of equipment inside containment to withstand H2 Burn (DSI/DOE)
Item II.F.2, ICC Instrumentation, resolution and implementation schedule (DSI)
Item I.A.1, Applicant management capabilities, staffing, training (DHFS)
System Interaction including instrument air, air/water interfaces, effect on safety systems (DSI)
Secondary water chemistry and materfals (.DOE)
Industrial security - protection of Unit 2 while Unit 3 is under construc tion (NMSS/DOL)
Emergency plan, interaction of Federal, State, Local agencies (EPPO)
AFWS Evaluation, reliability (DST/DSI)
ENCLOSURE 2 STATUS OF SAN ONOFRE 2 AND 3 OPEN ITEMS DIV./BRANCH REVIEWER OPEN ISSUE COMMENTS DE/MEB Cappucci Reactor Internals Analysis Resolvable by 3/11/F DE/MEB Cappucci Independent Piping Analysis Staff should define Add'l. info. require DE/MTEB Halapatz GDC-51 App. Submittal 2/27/81 DE/QAB Spaul Q-List Review App. Submittal 2/27/81 DE/EQB Hofmayer Seismic Qualification Staff has SCE Submittal DE/EQB DiBennedetto Environmental Qual.
Staff has SCE Submittal DE/SAB Campe Explosion Hazards App. Submittal 2/20/81 DE/SAB Campe
- Toxic Gas Hazards App. Submittal 3/20/81 DE/UFB Karlowicz Financial Qual.
App.
Submittal 3/6/81 DSI/ASB/RRAB Mann/Lakner lI.E.1,1 AFW Reliability App. Submittal 3/3/81 DSI/CPB Phillips CPC ACRS Mtg. 2/24/81 DSI/ICSB Morris CPC To discuss CPC only DSI/CPB Hsii DNBR Testing of Revised FEA App. Submittal 3/13/81 DSI/CPB Hsii Review of CENPD-183 Staff has App.
Submittal; partial resolution schedulec May 1981 2
DIV./BRANCH REVIEWER OPEN ISSUE COMMENTS DSI/CPB Huang II.F.2 ICC Instrumentation DSI/ICSB Thatcher II.F.2 ICC Instrumentation 3/6/81 DSI/SIB Thomas System Pnteraction Site Visit 3/3/81 DHFS/LQB Benedict I.A.l, I.B.l.2, I.C.5 Site Visit 2/24/81 DHFS/PTRB Cl ifford DHS/TB lifrdI.C.l
, I.C.8 Procedures Site Visit 2/18/81 DSI/RSB Sheron EPPO/EPLB Tam II LAl.1, Emergency Plan App. Submittal April 1981 NMSS Gaskin Industrial Security App. Submittal 2/27/81