Other: L-2013-248, First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation(Order Number EA- 12-051), L-2013-249, First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA- 12-049), L-2014-041, Florida Power and Light Companys Turkey Point Units 3 & 4, Second Six-Month Status Report in Response to 03/12/2012, Commission Order Modifying Licenses with to Requirements for Mitigation Strategies for Beyond-Design-Basis External Exter, L-2014-042, Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), L-2014-243, Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, L-2014-244, Florida Power and Light Companys, Turkey Point, Units 3 and 4 - Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation(Order Number EA- 12-05, L-2015-017, Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA- 12-049), L-2015-018, Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), L-2015-193, Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), ML14002A160, ML14029A252, ML15188A507, ML15307A314
|
MONTHYEARL-2013-061, Florida Power and Light Companys Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-02013-02-26026 February 2013 Florida Power and Light Companys Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049 Project stage: Other ML13191A1342013-07-11011 July 2013 Request for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051) Project stage: RAI L-2013-225, Response to Request for Additional Information Regarding Overall Integrated Plan in Response to Order EA-12-051 Reliable Spent Fuel Pool Instrumentation2013-07-30030 July 2013 Response to Request for Additional Information Regarding Overall Integrated Plan in Response to Order EA-12-051 Reliable Spent Fuel Pool Instrumentation Project stage: Response to RAI L-2013-248, First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation(Order Number EA- 12-051)2013-08-21021 August 2013 First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation(Order Number EA- 12-051) Project stage: Other L-2013-249, First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA- 12-049)2013-08-21021 August 2013 First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA- 12-049) Project stage: Other ML13280A1772013-11-19019 November 2013 Interim Staff Evaluation and Request for RAI Re. the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation Project stage: RAI ML14029A2522014-01-29029 January 2014 Mega-Tech Services, LLC Technical Evaluation Report Regarding the Overall Integrated Plan for Turkey Point Nuclear Plant, Units 3 and 4, TAC Nos.: MF0982 and MF0983 Project stage: Other ML14002A1602014-02-0606 February 2014 Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies) Project stage: Other L-2014-042, Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2014-02-26026 February 2014 Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other L-2014-041, Florida Power and Light Companys Turkey Point Units 3 & 4, Second Six-Month Status Report in Response to 03/12/2012, Commission Order Modifying Licenses with to Requirements for Mitigation Strategies for Beyond-Design-Basis External Exter2014-02-26026 February 2014 Florida Power and Light Companys Turkey Point Units 3 & 4, Second Six-Month Status Report in Response to 03/12/2012, Commission Order Modifying Licenses with to Requirements for Mitigation Strategies for Beyond-Design-Basis External Externa Project stage: Other L-2014-244, Florida Power and Light Companys, Turkey Point, Units 3 and 4 - Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation(Order Number EA- 12-052014-08-15015 August 2014 Florida Power and Light Companys, Turkey Point, Units 3 and 4 - Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation(Order Number EA- 12-0511 Project stage: Other L-2014-243, Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2014-08-27027 August 2014 Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other L-2015-018, Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2015-02-13013 February 2015 Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other L-2015-017, Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA- 12-049)2015-02-26026 February 2015 Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA- 12-049) Project stage: Other ML15013A4982015-03-13013 March 2015 Relaxation of the Scheduler Requirements of Order EA-12-049, Issuance of Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design Basis External Events Project stage: Approval ML15188A5072015-07-0808 July 2015 Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Other L-2015-194, Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA- 12-051)2015-08-11011 August 2015 Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA- 12-051) Project stage: Other L-2015-193, Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2015-08-11011 August 2015 Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other ML15307A3142015-11-12012 November 2015 Report for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Other L-2016-002, Final Compliance in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2016-01-0606 January 2016 Final Compliance in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other 2014-08-15
[Table View] |
Text
August 21, 2013 P L L-2013-248 FPL.
U. S. Nuclear Regulatory Commission Attn.: Document Control Desk Washington, D.C. 20555-0001 Re:
Turkey Point Units 3 and 4 Docket Nos. 50-250 and 50-251 Florida Power and Light Company's, Turkey Point Units 3 and 4, First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation(Order Number EA-12-051)
References:
- 1.
U.S. Nuclear Regulatory Commission, Order Number EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Effective Immediately), dated March 12, 2012 (ML12056A044)
- 2.
FPL Letter, L-2013-062, Florida Power and Light Company's, Turkey Point Units 3 and 4, Overall Integrated Plan in Response to March 12, 2012 U.S. Nuclear Regulatory Commission's Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), dated February 26, 2013 (ML130720690)
On March 12, 2012, the Nuclear Regulatory Commission (NRC) issued Reference 1, an immediately effective Order to all licensees including Florida Power and Light Company's (FPL)
Turkey Point. In Reference 2, FPL submitted an Overall Integrated Plan for the implementation of this Order. The Order required Licensee's to provide periodic status reports for the Overall Integrated Plan.
The purpose of this letter is to provide the first six-month status report pursuant to Section IV, Condition C.2, of Reference 1, that delineates progress made in implementing the requirements of Reference 1. The enclosure to this letter provides a status update of milestone accomplishments since the submittal, including any changes to the compliance method, schedule, or need for relief and the basis, if any.
Should you have any questions regarding this submittal, please contact Mr. Robert J. Tomonto, Turkey Point Licensing Manager, at 305-246-7327.
Turkey Point Units 3 and Unit 4 Docket No. 50-250 and 50-251 L-2013-248 Page 2 of 2 I declare under penalty of perjury that the foregoing is true and correct.
Executed on August,/, 2013 This letter contains no new Regulatory Commitments and no revisions to existing Regulatory Commitments.
Sincerely, Michael Kiley Site Vice President Turkey Point Nuclear Plant Enclosure cc:
USNRC Regional Administrator, Region II USNRC Project Manager, Turkey Point Nuclear Plant USNRC Senior Resident Inspector, Turkey Point Nuclear Plant
L-2013-248 Enclosure Florida Power and Light Company's Turkey Point Units 3 and 4 First Six-Month Status Report in Response to March 12,2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)
Page 1 of 4
L-2013-248 Enclosure 1 Introduction Florida Power and Light Company's (FPL) Turkey Point Units 3 and 4 developed an Overall Integrated Plan (Reference 1, Section 7), documenting the modification with regards to Reliable Spent Fuel Pool (SFP) Instrumentation in response to Reference 2. This attachment provides an update of milestone accomplishments since submittal of the Overall Integrated Plan, including any changes to the compliance method, schedule, or need for relief/relaxation and the basis, if any.
2 Milestone Accomplishments FPL has selected a vendor to procure SFP level instruments that, when installed, will meet all the criteria designated in the Integrated Response Plan submitted on February 26, 2013.
3 Milestone Schedule Status There are no changes to the status of the milestones in the integrated plan that was submitted on February 26, 2013.
Target Revised Target Milestone Completion Activity Status Completion Date Date Commence Engineering and Design-Unit 3 IQ 2013 Complete NA Complete Engineering Design-Unit 3 3Q 2014 Started NA Complete Procurement of SFP Instruments-4Q 2014 Not started NA Unit 3 Complete Installation of SFP Instruments-1Q 2015 Not started NA Unit 3 Instruments Operational and Training -
IQ 2015 Not started NA completed-Unit 3 Commence Engineering and Design-Unit 4 IQ 2013 Complete NA Complete Design-Unit 4 3Q 2015 Started NA Complete Procurement of SFP Instruments-4Q 2015 Not Started NA Unit 4 Complete Installation of SFP Instruments-IQ 2016 Not Started NA Unit 4 Instruments Operational and Training 2Q 2016 Not Started NA completed-Unit 4 Page 2 of 4
L-2013-248 Enclosure 4
Changes to Compliance Method There are no changes to the compliance method as documented in the Overall Integrated Plan (Reference 1).
5 Need for Relief/Relaxation and Basis for the Relief/Relaxation FPL expects to comply with the order implementation date and no relief/relaxation is required at this time.
6 Open Requests for Additional Information A response to the Request for Additional Information (RAL) received on July 11, 2013 (Reference 3) was submitted by FPL on July 30, 2013 (Reference 4). At this time, there are no additional information requests by NRC.
The following Table provides a summary of the open RAIs that were received on July 11, 2013 (Reference 3) in response to the initial Overall Integrated Plan submittal.
Open RAIs Status RAI Arrangement In progress RAI-3 a, b, c - Mounting In progress RAI-4 a, b, c - Qualification In progress RAI-5 a, b - Independence In progress RAI-6 a, b - Power Supplies In progress RAI-7 a, b - Accuracy In progress RAI-8 a, b, c, d - Testing In progress RAI-9 a, b, c - Display In progress RAI-10 a, b - Procedures In progress RAI-1 1 a, b, c - Testing and Calibration In progress The response to the open RAIs in the table above requires design information that is not available at this time. A response to the RAIs will be provided in the February 2014 semi-annual update.
Page 3 of 4
L-2013-248 Enclosure 7
References
- 1. FPL Letter L-2013-062, Florida Power and Light Company's, Turkey Point Units 3 and 4, Overall Integrated Plan in Response to March 12, 2012 U.S. Nuclear Regulatory Commission's Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), dated February 26, 2013 (ML130720690)
- 2.
U.S. Nuclear Regulatory Commission, Order Number EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Effective Immediately), dated March 12, 2012 (ML12056A044)
- 3. U.S. NRC Letter, J. Page (NRC) to M. Nazar (FPL), Turkey Point Nuclear Generating Unit Nos.
3 And 4 -Request For Additional Information Regarding Overall Integrated Plan For Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051) (TAC NOS. MF0988 and MF0989), dated July 11, 2013 (ML13191A134)
- 4. FPL Letter, L-2013-225, Response To Request For Additional Information Regarding Overall Integrated Plan In Response To Order EA-12-051, "Reliable Spent Fuel Pool Instrumentation,"
dated July 30, 2013.
Page 4 of 4