First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)
ML13241A242
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 08/28/2013
From: Kaegi G
Exelon Generation Co
To:
Office of Nuclear Reactor Regulation, Document Control Desk
References
EA-12-051, RS-13-118
Download: ML13241A242 (13)


Text

1 ti Order No. EA-12-051 RS-13-118 August 28,2013 u.s. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Dresden Nuclear Power Station, Units 2 and 3 Renewed Facility Operating License Nos. DPR-19 and DPR-25 NRC Docket Nos. 50-237 and 50-249

Subject:

First Six-Month Status Report in Response to March 12,2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)

References:

1. NRC Order Number EA-12-051, " Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation," dated March 12, 2012
2. NRC Interim Staff Guidance JLD-ISG-2012-03, "Compliance with Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation,"

Revision 0, dated August 29, 2012

3. NEI12-02, Industry Guidance for Compliance with NRC Order EA-12-051, "To Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation," Revision 1, dated August 2012
4. Exelon Generation Company, LLC's Initial Status Report in Response to March 12,2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), dated October 25,2012
5. Exelon Generation Company, LLC Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), dated February 28,2013 (RS-13-030)

On March 12,2012, the Nuclear Regulatory Commission ("NRC" or "Commission") issued an order (Reference 1) to Exelon Generation Company, LLC (EGC). Reference 1 was immediately effective and directs EGC to install reliable spent fuel pool level instrumentation. Specific requirements are outlined in Attachment 2 of Reference 1.

Reference 1 required submission of an initial status report 60 days following issuance of the final interim staff guidance (Reference 2) and an overall integrated plan pursuant to Section IV, Condition C. Reference 2 endorses industry guidance document NEI 12-02, Revision 1 (Reference 3) with clarifications and exceptions identified in Reference 2. Reference 4 provided

U.S. Nuclear Regulatory Commission Integrated Plan Report to EA-12-051 August 28, 2013 Page 2 the EGC initial status report regarding reliable spent fuel pool instrumentation. Reference 5 provided the Dresden Nuclear Power Station, Units 2 and 3 overall integrated plan.

Reference 1 requires submission of a status report at six-month intervals following submittal of the overall integrated plan. Reference 3 provides direction regarding the content of the status reports. The purpose of this letter is to provide the first six-month status report pursuant to Section IV, Condition C.2, of Reference 1, that delineates progress made in implementing the requirements of Reference 1. The enclosed report provides an update of milestone accomplishments since the last status report, including any changes to the compliance method, schedule, or need for relief and the basis, if any.

This letter contains no new regulatory commitments. If you have any questions regarding this report, please contact David P. Helker at 610-765-5525.

I declare under penalty of perjury that the foregoing is true and correct. Executed on the 28 th day of August 2013.

Respectfully submitted,

~;:~

Glen T. Kaegi Director - Licensing & Regulatory Affairs Exelon Generation Company, LLC

Enclosure:

1. Dresden Nuclear Power Station, Units 2 and 3 First Six-Month Status Report for the Implementation of Order EA-12-051 , Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation cc: Director, Office of Nuclear Reactor Regulation NRC Regional Administrator - Region III NRC Senior Resident Inspector - Dresden Nuclear Power Station, Units 2 and 3 NRC Project Manager, NRR - Dresden Nuclear Power Station, Units 2 and 3 Ms. Jessica A. Kratchman, NRR/JLD/PMB, NRC Mr. Robert J. Fretz, Jr, NRR/JLD/PMB, NRC Mr. Robert L. Dennig, NRR/DSS/SCVB, NRC Illinois Emergency Management Agency - Division of Nuclear Safety

Enclosure Dresden Nuclear Power Station, Units 2 and 3 First Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying licenses with Regard to Reliable Spent Fuel Pool Instrumentation (10 pages)

Dresden Nuclear Power Station, Units 2 and 3 First Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation 1 Introduction Dresden Nuclear Power Station, Units 2 and 3, developed an Overall Integrated Plan (Reference 1 in Section 8), documenting the requirements to install reliable spent fuel pool level instrumentation (SFP LI), in response to Reference 2. This enclosure provides an update of milestone accomplishments since submittal of the Overall Integrated Plan including any changes to the compliance method, schedule, or need for relief/relaxation and the basis, if any.

2 Milestone Accomplishments The following milestones have been completed since the development of the Overall Integrated Plan (Reference 1), and are current as of August 19, 2013.

  • Submitted responses to USNRC RAls (Ref. 3 and 4) on July 18, 2013 3 Milestone Schedule Status The following provides an update to the milestone schedule to support the Overall Integrated Plan. This section provides the activity status of each item, and the expected completion date noting any change. The dates are planning dates subject to change as design and implementation details are developed.

Revised Target Completion Activity Target Milestone Date Status Completion Date Submit 60 Day Status Report October 25,2012 Complete Submit Overall Integrated Plan February 28, 2013 Complete Submit Response to RAls July 19, 2013 Complete Submit 6 Month Updates:

Complete with Update 1 August 28, 2013 this submittal Update 2 February 28, 2014 Not Started Update 3 August 28, 2014 Not Started Page 1 of 10

Dresden Nuclear Power Station, Units 2 and 3 First Six-Month Status Report for the Implementation of SFP LI August 28, 2013 Revised Target Completion Activity Target Milestone Date Status Completion Date Update 4 February 28, 2015 Not Started Update 5 August 28, 2015 Not Started Update 6 February 28, 2016 Not Started Update 7 August 28, 2016 Not Started Modifications:

Conceptual Design 302012 Complete Issue Exelon Fleet contract to 102015 Complete procure SFPI Equipment Begin Detailed Engineering 302014 Not Started Design for Unit 2 Complete and Issue SFPI 402014 Not Started Modification Package for Unit 2 Begin Detailed Engineering 302014 Not Started Design for Unit 3 Complete and Issue SFPI 402015 Not Started Modification Package for Unit 3 Begin SFPI Installation for Unit 2 302015 Not Started Complete SFPllnstaliation for Not Started 402015 Unit 2 and Put Into Service Begin SFPI Installation for Unit 3 302016 Not Started Complete SFPI Installation for Not Started 402016 Unit 3 and Put Into Service 4 Changes to Compliance Method There are no changes to the compliance method as documented in the Overall Integrated Plan (Reference 1).

5 Need for Relief/Relaxation and Basis for the Relief/Relaxation Dresden Nuclear Power Station, Units 2 and 3 expects to comply with the order implementation date and no relief/relaxation is required at this time.

Page 2 of 10

Dresden Nuclear Power Station, Units 2 and 3 First Six-Month Status Report for the Implementation of SFP LI August28,2013 6 Open Items from Overall Integrated Plan and Draft Safety Evaluation The following tables provide a summary of the open items documented in the Overall Integrated Plan or the Draft Safety Evaluation (SE) and the status of each item.

Overall Integrated Plan Open Items 01# Description Status 1 Instruments Complete.

(Ref.1) Continuous level indication will be The Westinghouse Spent Fuel Pool provided by a guided wave radar Level Indication instrumentation was system, submersible pressure selected consistent with the guidelines of transducer, or other appropriate level NRC JLD-ISG-2012-03 and NEI 12-02.

sensing technology that will be The instrument is a guided wave radar determined during the detailed system. It provides the capability to engineering phase of the project. reliably monitor the spent fuel pool water level under normal and anticipated adverse environmental conditions.

The sensor input to the system is a guided wave radar probe. Using the principle of time domain reflectometry (TDR) to detect the SFP water level, microwave signals are pulsed down the cable probe and reflected back from the water surface. This is used to determine the level of the water in the pool.

Each water level measurement channel includes a flexible stainless-steel sensor cable probe suspended in the spent fuel pool from a seismic Category 1 bracket attached to the operating deck or to a raised curb at the side of the pool. The cable probe extends to just above the top of the spent fuel racks. The sensor electronics are mounted in seismic and missile protected areas outside of the building housing the SFP to minimize exposure to elevated radiation and environmental conditions which could result from a postulated loss of water inventory in the pool. There is an interconnecting cable between the Page 3 of 10

Dresden Nuclear Power Station, Units 2 and 3 First Six-Month Status Report for the Implementation of SFP LI August28,2013 sensor cable probe and sensor electronics.

The sensor electronics provide an instrument standard analog signal to a remote enclosure that will be installed in an accessible location. This enclosure contains the Uninterruptable Power Supply (UPS), backup battery, and water level display. The enclosure also includes the capability to connect an emergency or temporary external power source as part of the FLEX mitigating strategies.

Attachment 1 shows the components and arrangement of the guided wave radar system spent fuel pool level sensor and electronics enclosure for one channel.

2 Final sensor locations and cable Not Started.

routings are not available at this time.

(RAI-2, This information will be developed Ref A) during the detailed design process. The current plan for the design of the SFPI system based on the current Exelon Nuclear program schedule for Dresden is to begin the design phase in September of 2014 with design completion and 100% acceptance of the design in December 2014 for Unit 2 and December 2015 for Unit 3. The requested information will be provided in the February 2015, 6-month Integrated Plan Update for Unit 2 and February 2016, 6-month Integrated Plan Update for Unit 3.

3 Mounting device total loading and Not Started.

attachments are not available at this (RAI-3, time. This information will be developed Ref.4) during the detailed design process. The current plan for the design of the SFPI system based on the current Exelon Nuclear program schedule for Dresden is to begin the design phase in Page 4 of 10

Dresden Nuclear Power Station, Units 2 and 3 First Six-Month Status Report for the Implementation of SFP LI August28,2013 September of 2014 with design completion and 100% acceptance of the design in December 2014 for Unit 2 and December 2015 for Unit 3. The requested information will be provided in the February 2015, 6-month Integrated Plan Update for Unit 2 and February 2016, 6-month Integrated Plan Update for Unit 3.

4 Equipment reliability qualification Not Started.

information is not available at this time.

(RAI-4, This information will be developed Ref.4) during the detailed design process. The current plan for the design of the SFPI system based on the current Exelon Nuclear program schedule for Dresden is to begin the design phase in September of 2014 with design completion and 100% acceptance of the design in December 2014 for Unit 2 and December 2015 for Unit 3. The requested information will be provided in the February 2015, 6~month Integrated Plan Update for Unit 2 and February 2016, 6-month Integrated Plan Update for Unit 3.

5 Channel independence information is Not Started.

not available at this time. This (RAI-5, information will be developed during the Ref.4) detailed design process. The current plan for the design of the SFPI system based on the current Exelon Nuclear program schedule for Dresden is to begin the design phase in September of 2014 with design completion and 100%

acceptance of the design in December 2014 for Unit 2 and December 2015 for Unit 3. The requested information will be provided in the February 2015, 6-month Integrated Plan Update for Unit 2 and February 2016, 6-month Integrated Plan Update for Unit 3.

6 Equipment total power supply Not Started.

configuration and characteristics are not (RAI-6, Page 5 of 10

Dresden Nuclear Power Station, Units 2 and 3 First Six-Month Status Report for the Implementation of SFP LI August 28,2013 Ref.4) available at this time. This information will be developed during the detailed design process. The current plan for the design of the SFPI system based on the current Exelon Nuclear program schedule for Dresden is to begin the design phase in September of 2014 with design completion and 100%

acceptance of the design in December 2014 for Unit 2 and December 2015 for Unit 3. The requested information will be provided in the February 2015, 6-month Integrated Plan Update for Unit 2 and February 2016, 6-month Integrated Plan Update for Unit 3.

? Channel accuracy information is not Not Started.

available at this time. This information (RAI-?,

will be developed during the detailed Ref.4) design process. The current plan for the design of the SFPI system based on the current Exelon Nuclear program schedule for Dresden is to begin the design phase in September of 2014 with design completion and 100%

acceptance of the design in December 2014 for Unit 2 and December 2015 for Unit 3. The requested information will be provided in the February 2015, 6-month Integrated Plan Update for Unit 2 and February 2016, 6-month Integrated Plan Update for Unit 3.

8 Equipment testing, calibration, Not Started.

functional checks and maintenance (RAI-8, requirements are not available at this Ref.4) time. This information will be established during process and procedure development following the detailed design phase. The current plan for the design of the SFPI system based on the current Exelon Nuclear program schedule for Dresden is to begin the design phase in September 2014 with design completion and 100%

acceptance of the design in December 2014 for Unit 2 and December 2015 for Page 6 of 10

Dresden Nuclear Power Station, Units 2 and 3 First Six-Month Status Report for the Implementation of SFP LI August28,2013 Unit 3. Following the issue of the design, procedures will start being developed with a projected completion date of July 2015 for Unit 2 and July 2016 for Unit 3. The requested information will be provided in the August 2015, 6-month Integrated Plan Update for Unit 2 and August 2016, 6-month Integrated Plan Update for Unit 3.

9 Channel display location information is Not Started.

not available at this time. This (RAI-9, information will be developed during the Ref.4) detailed design process. The current plan for the design of the SFPI system based on the current Exelon Nuclear program schedule for Dresden is to begin the design phase in September of 2014 with design completion and 100%

acceptance of the design in December 2014 for Unit 2 and December 2015 for Unit 3. The requested information will be provided in the February 2015, 6~

month Integrated Plan Update for Unit 2 and February 2016, 6-month Integrated Plan Update for Unit 3.

10 Procedural details are not available at Not Started.

this time. This information will be (RAI-10, established during process and Ref.4) procedure development following the detailed design phase. The current plan for the design of the SFPI system based on the current Exelon Nuclear program schedule for Dresden is to begin the design phase in September 2014 with design completion and 100%

acceptance of the design in December 2014 for Unit 2 and December 2015 for Unit 3. Following the issue of the design, procedures will start being developed with a projected completion date of July 2015 for Unit 2 and July 2016 for Unit 3. The requested information will be provided in the August 2015, 6-month Integrated Plan Page 7 of 10

Dresden Nuclear Power Station, Units 2 and 3 First Six-Month Status Report for the Implementation of SFP LI August28,2013 Update for Unit 2 and August 2016, 6-month Integrated Plan Update for Unit 3.

11 Testing and calibration program Not Started.

requirements and compensatory actions (RAI-11, are not available at this time. This Ref.4) information will be established during process and procedure development following the detailed design phase.

The current plan for the design of the SFPI system based on the current Exelon Nuclear program schedule for Dresden is to begin the design phase in September 2014 with design completion and 100% acceptance of the design in December 2014 for Unit 2 and December 2015 for Unit 3. Following the issue of the design, procedures will start being developed with a projected completion date of July 2015 for Unit 2 and July 2016 for Unit 3. The requested information will be provided in the August 2015, 6~month Integrated Plan Update for Unit 2 and August 2016, 6-month Integrated Plan Update for Unit 3.

Draft Safety Evaluation Open Items 01# Description Status None at this time.

7 Potential Draft Safety Evaluation Impacts There are no potential impacts to the Draft Safety Evaluation identified at this time.

Page 8 of 10

Dresden Nuclear Power Station, Units 2 and 3 First Six-Month Status Report for the Implementation of SFP LI August28,2013 8 References The following references support the updates to the Overall Integrated Plan described in this enclosure.

1. Exelon Generation Company, LLC, letter to USNRC, "Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)," dated February 28,2013 (RS 030)
2. NRC Order Number EA-12-051, "Issuance of Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation," dated March 12,2012.
3. USNRC letter to Exelon Generation Company, LLC, "Request for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation", dated June 26, 2013.
4. Exelon Generation Company, LLC, letter to USNRC, "Response to Request for Additional Information - Overall Integrated Plan in Response to Commission Order Modifying License Requirements for Reliable Spent Fuel Pool Instrumentation (Order No. EA 051)", dated July 18, 2013 (RS-13-176).

Page 9 of 10

Dresden Nuclear Power Station, Units 2 and 3 First Six-Month Status Report for the Implementation of SFP LI August28,2013 Attachment 1 Spent Fuel Pool Instrumentation System Sensor Electronics

~~~~1I Remote Enclosure containing II sensor UPS Output to Interconnecting Cable optional 1201240 alternate VAC Power display 20-30' (typical) measurement span to just above top of ...*11 40.0 II fuel racks 6 mm SST Cable Probe with Anchor Weight Spent Fuel Pool Page 10 of 10