Category:Letter type:RS
MONTHYEARRS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations RS-24-057, License Amendment to Technical Specification 3.7.9, Ultimate Heat Sink2024-06-0404 June 2024 License Amendment to Technical Specification 3.7.9, Ultimate Heat Sink RS-24-044, License Amendment to Transition to Framatome Gaia Fuel and Exemptions to 10 CFR 50.46 and 10 CFR 50 Appendix K. Attachments 1 to 11 Enclosed2024-05-28028 May 2024 License Amendment to Transition to Framatome Gaia Fuel and Exemptions to 10 CFR 50.46 and 10 CFR 50 Appendix K. Attachments 1 to 11 Enclosed RS-24-043, Application to Remove Power Distribution Monitoring System (Pdms) Details from Technical Specifications2024-05-24024 May 2024 Application to Remove Power Distribution Monitoring System (Pdms) Details from Technical Specifications RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests RS-24-026, License Amendment to Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, Technical Specifications 5.6.5, Core Operating Limits Report (COLR)2024-04-25025 April 2024 License Amendment to Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, Technical Specifications 5.6.5, Core Operating Limits Report (COLR) RS-24-034, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors2024-04-10010 April 2024 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report RS-24-024, Response to Request for Additional Information Regarding Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds2024-03-22022 March 2024 Response to Request for Additional Information Regarding Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds RS-24-013, Response to Request for Additional Information Regarding Proposed Alternative to Distribution Requirements of ASME Code Table IWC-2411-1 for the Steam Generators2024-02-13013 February 2024 Response to Request for Additional Information Regarding Proposed Alternative to Distribution Requirements of ASME Code Table IWC-2411-1 for the Steam Generators RS-24-004, Proposed Alternative to the Distribution Requirements of ASME Code Table IWC-2411-1 for the Steam Generators2024-01-11011 January 2024 Proposed Alternative to the Distribution Requirements of ASME Code Table IWC-2411-1 for the Steam Generators RS-23-118, Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information2023-11-10010 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information RS-23-114, Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds2023-11-0101 November 2023 Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans RS-23-108, Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles2023-10-11011 October 2023 Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles RS-23-105, Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections2023-10-10010 October 2023 Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections RS-23-093, License Amendment to Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, Technical Specifications 3.7.15, Spent Fuel Pool Boron Concentration, 3.7.16, Spent Fuel.2023-09-29029 September 2023 License Amendment to Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, Technical Specifications 3.7.15, Spent Fuel Pool Boron Concentration, 3.7.16, Spent Fuel. RS-23-083, Withdrawal - Proposed Alternatives Related to the Steam Generators2023-06-27027 June 2023 Withdrawal - Proposed Alternatives Related to the Steam Generators RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations RS-23-074, Supplement to Application for License Amendment to Braidwood Station, Units 1 and 2, Technical Specification 3.7.9, Ultimate Heat Sink2023-06-0909 June 2023 Supplement to Application for License Amendment to Braidwood Station, Units 1 and 2, Technical Specification 3.7.9, Ultimate Heat Sink RS-23-075, Application for Technical Specification Improvement to Extend the Completion Time for Condition B of Technical Specification 3.5.1, Accumulators, Using the Consolidated Line Item Improvement Process2023-06-0707 June 2023 Application for Technical Specification Improvement to Extend the Completion Time for Condition B of Technical Specification 3.5.1, Accumulators, Using the Consolidated Line Item Improvement Process RS-23-050, Supplement to Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube.2023-05-22022 May 2023 Supplement to Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube. RS-23-056, Response to Request for Additional Information to Braidwood Station, Unit 1, and Byron Station, Unit 1, for Steam Generator License Renewal Response to Commitment 102023-04-20020 April 2023 Response to Request for Additional Information to Braidwood Station, Unit 1, and Byron Station, Unit 1, for Steam Generator License Renewal Response to Commitment 10 RS-23-055, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors2023-04-10010 April 2023 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors RS-23-052, License Amendment to Braidwood Station, Units 1 and 2, Technical Specification 3.7.9, Ultimate Heat Sink2023-03-24024 March 2023 License Amendment to Braidwood Station, Units 1 and 2, Technical Specification 3.7.9, Ultimate Heat Sink RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-23023 March 2023 Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations RS-23-045, Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.2032023-02-28028 February 2023 Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.203 RS-23-040, Constellation Energy Generation, LLC, Supplemental Information - Proposed Alternatives Related to the Steam Generators2023-02-21021 February 2023 Constellation Energy Generation, LLC, Supplemental Information - Proposed Alternatives Related to the Steam Generators RS-23-003, Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-102023-01-31031 January 2023 Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-10 RS-22-123, Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator2022-12-0707 December 2022 Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator RS-22-126, Constellation Energy Generation, LLC - Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI2022-11-30030 November 2022 Constellation Energy Generation, LLC - Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI RS-22-118, Withdrawal of License Amendment Request to Revise Braidwood Station, Units 1 and 2, Technical Specification 3.7.9, Ultimate Heat Sink2022-10-31031 October 2022 Withdrawal of License Amendment Request to Revise Braidwood Station, Units 1 and 2, Technical Specification 3.7.9, Ultimate Heat Sink RS-22-110, Supplemental Information - Proposed Alternatives Related to the Steam Generators and Request.2022-09-20020 September 2022 Supplemental Information - Proposed Alternatives Related to the Steam Generators and Request. RS-22-093, Advisement of Leadership Changes for Constellation Energy Generation, LLC and Submittal of Updated Standard Practice Procedures Plans2022-08-18018 August 2022 Advisement of Leadership Changes for Constellation Energy Generation, LLC and Submittal of Updated Standard Practice Procedures Plans RS-22-086, R. E. Ginna Nuclear Power Plant - Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam.2022-08-10010 August 2022 R. E. Ginna Nuclear Power Plant - Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam. RS-22-084, Response to Request for Additional Information Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator .2022-06-17017 June 2022 Response to Request for Additional Information Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator . RS-22-072, Response to Request for Additional Information Regarding License Amendment to Revise Braidwood Station, Units 1 and 2, Technical Specification 3.7.9, Ultimate Heat Sink2022-06-0606 June 2022 Response to Request for Additional Information Regarding License Amendment to Revise Braidwood Station, Units 1 and 2, Technical Specification 3.7.9, Ultimate Heat Sink RS-22-075, License Amendment to Braidwood Station, Units 1 and 2, Technical Specification 3.7.9, Ultimate Heat Sink2022-06-0202 June 2022 License Amendment to Braidwood Station, Units 1 and 2, Technical Specification 3.7.9, Ultimate Heat Sink RS-22-074, Response to Request for Additional Information - Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds .2022-05-20020 May 2022 Response to Request for Additional Information - Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds . RS-22-073, Supplemental Information Regarding License Amendment Request -Adoption of Technical Specification Task Force (TSTF) Traveler TSTF-501, Revision 1, Relocate Stored Fuel Oil and Lube.2022-05-19019 May 2022 Supplemental Information Regarding License Amendment Request -Adoption of Technical Specification Task Force (TSTF) Traveler TSTF-501, Revision 1, Relocate Stored Fuel Oil and Lube. RS-22-037, License Amendment Request - Adoption of Technical Specification Task Force (TSTF) Traveler TSTF-501, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control2022-04-21021 April 2022 License Amendment Request - Adoption of Technical Specification Task Force (TSTF) Traveler TSTF-501, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control RS-22-051, Constellation Energy Generation, LLC - Update to Correspondence Addressees and Service Lists2022-04-12012 April 2022 Constellation Energy Generation, LLC - Update to Correspondence Addressees and Service Lists RS-22-050, Supplemental Information - Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds2022-04-0808 April 2022 Supplemental Information - Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds RS-22-047, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors2022-04-0808 April 2022 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors RS-22-049, Constellation Energy Generation, LLC, Supplemental Information to Correct Typographical Errors in Constellation'S Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for2022-04-0404 April 2022 Constellation Energy Generation, LLC, Supplemental Information to Correct Typographical Errors in Constellation'S Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for V RS-22-045, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations2022-03-25025 March 2022 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations RS-22-014, Application to Adopt TSTF-246, RTS Instrumentation, 3.3.1 Condition F Completion Time2022-03-24024 March 2022 Application to Adopt TSTF-246, RTS Instrumentation, 3.3.1 Condition F Completion Time RS-22-041, Withdrawal of License Amendment Request to Revise Technical Specifications 5.6.5, Core Operating Limits Report (COLR) to Add References to NRC Approved Topical Report with Administrative Changes2022-03-22022 March 2022 Withdrawal of License Amendment Request to Revise Technical Specifications 5.6.5, Core Operating Limits Report (COLR) to Add References to NRC Approved Topical Report with Administrative Changes RS-22-036, Supplemental Information - Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds2022-03-10010 March 2022 Supplemental Information - Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds 2024-06-04
[Table view] Category:Status Report
MONTHYEARML23044A3662023-02-15015 February 2023 Calendar Year 2022 Reactor Oversight Process Baseline Inspection Program Completion - Region III RS-17-045, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2017-03-30030 March 2017 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations RS-16-046, Annual Property Insurance Status Report2017-03-29029 March 2017 Annual Property Insurance Status Report RS-16-145, Seventh Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2016-08-26026 August 2016 Seventh Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) RS-16-094, Property Insurance Status Report for Braidwood Station, Byron Station, Calvert Cliffs, Clinton Power, Dresden Nuclear, LaSalle County, Limerick Generating, Nine Mile Point, Oyster Creek, Peach Bottom, Quad Cities, R.E Ginna, Three Mile Isl2016-04-25025 April 2016 Property Insurance Status Report for Braidwood Station, Byron Station, Calvert Cliffs, Clinton Power, Dresden Nuclear, LaSalle County, Limerick Generating, Nine Mile Point, Oyster Creek, Peach Bottom, Quad Cities, R.E Ginna, Three Mile Isla RS-16-020, Sixth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2016-02-26026 February 2016 Sixth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) ML16008A1172016-01-20020 January 2016 U.S. Nuclear Regulatory Commission Analysis of Excelon Generation'S Decommissioning Funding Status Report RS-15-208, Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2015-08-28028 August 2015 Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) RS-15-016, Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying License with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2015-02-27027 February 2015 Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying License with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) RS-15-026, Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2015-02-27027 February 2015 Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) RS-14-195, Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2014-09-0505 September 2014 Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) RS-14-205, Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2014-08-28028 August 2014 Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) RS-14-007, Second Six-Month Status Report in Response to March 12,2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2014-02-28028 February 2014 Second Six-Month Status Report in Response to March 12,2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) RS-14-017, Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2014-02-28028 February 2014 Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) RS-13-113, First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2013-08-28028 August 2013 First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) RS-13-112, First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2013-08-28028 August 2013 First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) RS-13-100, Report on Status of Decommissioning Funding for Reactors2013-04-0101 April 2013 Report on Status of Decommissioning Funding for Reactors RA-13-030, Annual Property Insurance Status Report2013-04-0101 April 2013 Annual Property Insurance Status Report RA-12-032, Annual Property Insurance Status Report2012-03-30030 March 2012 Annual Property Insurance Status Report ML1009200492010-04-0101 April 2010 Annual Property Insurance Status Report ML0909202562009-04-0101 April 2009 Annual Property Insurance Status Report RS-09-041, Submittal of Exelon Generation Company, LLC, Report on Status of Decommissioning Funding for Reactors Owned by EGC2009-03-31031 March 2009 Submittal of Exelon Generation Company, LLC, Report on Status of Decommissioning Funding for Reactors Owned by EGC ML0508703272005-03-25025 March 2005 Annual Property Insurance Status Report RS-05-035, Report on Status of Decommissioning Funding for Reactors2005-03-24024 March 2005 Report on Status of Decommissioning Funding for Reactors ML0224007812002-01-18018 January 2002 E-mail from Jacob Zimmerman, Bulletin 2001-01 Status Report 2023-02-15
[Table view] |
Text
1 ti Order No. EA-12-051 RS-13-112 August 28, 2013 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Braidwood Station, Units 1 and 2 Facility Operating License Nos. NPF-72 and NPF-77 NRC Docket Nos. STN 50-456 and STN 50-457
Subject:
First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)
References:
- 1. NRC Order Number EA-12-051, "Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation," dated March 12,2012
- 2. NRC Interim Staff Guidance JLD-ISG-2012-03, "Compliance with Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation,"
Revision 0, dated August 29,2012
- 3. NEI12-02, Industry Guidance for Compliance with NRC Order EA-12-051, "To Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation," Revision 1, dated August 2012
- 4. Exelon Generation Company, LLC's Initial Status Report in Response to March 12,2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), dated October 25,2012
- 5. Exelon Generation Company, LLC Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), dated February 28,2013 (RS-13-027)
On March 12, 2012, the Nuclear Regulatory Commission ("NRC" or "Commission") issued an order (Reference 1) to Exelon Generation Company, LLC (EGC). Reference 1 was immediately effective and directs EGC to install reliable spent fuel pool level instrumentation. Specific requirements are outlined in Attachment 2 of Reference 1.
Reference 1 required submission of an initial status report 60 days following issuance of the final interim staff guidance (Reference 2) and an overall integrated plan pursuant to Section IV, Condition C. Reference 2 endorses industry guidance document NEI 12-02, Revision 1
u.s. Nuclear Regulatory Commission Integrated Plan Report to EA-12-051 August 28, 2013 Page 2 (Reference 3) with clarifications and exceptions identified in Reference 2. Reference 4 provided the EGC initial status report regarding reliable spent fuel pool instrumentation. Reference 5 provided the Braidwood Station, Units 1 and 2 overall integrated plan.
Reference 1 requires submission of a status report at six-month intervals following submittal of the overall integrated plan. Reference 3 provides direction regarding the content of the status reports. The purpose of this letter is to provide the first six-month status report pursuant to Section IV, Condition C.2, of Reference 1, that delineates progress made in implementing the requirements of Reference 1. The enclosed report provides an update of milestone accomplishments since the last status report, including any changes to the compliance method, schedule, or need for relief and the basis, if any.
This letter contains no new regulatory commitments. If you have any questions regarding this report, please contact David P. Helker at 610-765-5525.
I declare under penalty of perjury that the foregoing is true and correct. Executed on the 28 th day of August 2013.
Respectfully submitted, G~r:¥ Director - Licensing & Regulatory Affairs Exelon Generation Company, LLC
Enclosure:
- 1. Braidwood Station, Units 1 and 2 First Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation cc: Director, Office of Nuclear Reactor Regulation NRC Regional Administrator - Region III NRC Senior Resident Inspector - Braidwood Station, Units 1 and 2 NRC Project Manager, NRR - Braidwood Station, Units 1 and 2 Ms. Jessica A. Kratchman, NRR/JLD/PMB, NRC Mr. Robert J. Fretz, Jr, NRRlJLD/PMB, NRC Mr. Robert L. Dennig, NRR/DSS/SCVB, NRC Illinois Emergency Management Agency - Division of Nuclear Safety
Enclosure Braidwood Station, Units 1 and 2 First Six-Month Status Report for the Implementation of Order EA-12-0S1, Order Modifying licenses with Regard to Reliable Spent Fuel Pool Instrumentation (9 pages)
Braidwood Station, Units 1 and 2 First Six-Month Status Report for the Implementation of Order EA-12-0S1, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation 1 Introduction Braidwood Station, Units 1 and 2, developed an Overall Integrated Plan (Reference 1 in Section 8), documenting the requirements to install reliable Spent Fuel Pool Level Instrumentation (SFPLI), in response to Reference 2. This enclosure provides an update of milestone accomplishments since submittal of the Overall Integrated Plan including any changes to the compliance method, schedule, or need for relief/relaxation and the basis, if any.
2 Milestone Accomplishments The following milestones have been completed since the development of the Overall Integrated Plan (Reference 1), and are current as of August 19, 2013.
- Submitted responses to USNRC RAls (Ref. 3 and 4) on July 31,2013 3 Milestone Schedule Status The following provides an update to the milestone schedule to support the Overall Integrated Plan. This section provides the activity status of each item, and the expected completion date noting any change. The dates are planning dates subject to change as design and implementation details are developed.
The revised milestone target completion dates do not impact the order implementation date.
Revised Target Activity Target Milestone Completion Date Status Completion Date Submit 60 Day Status Report October 25, 2012 Complete Submit Overall Integrated Plan February 28, 2013 Complete Submit Responses to RAls July 31, 2013 Complete Submit 6 Month Updates:
Complete with Update 1 August 28, 2013 this submittal Update 2 February 28,2014 Not Started Page 1 of9
Braidwood Station, Units 1 and 2 First Six-Month Status Report for the Implementation of SFPLI August28,2013 Revised Target Activity Target Milestone Completion Date Status Completion Date Update 3 August 28, 2014 Not Started Update 4 February 28, 2015 Not Started Update 5 August28,2015 Not Started Modifications:
Conceptual Design 3Q2012 Complete Issue Exelon Fleet contract to 2Q2013 Complete procure SFPI Equipment Begin Detailed Design 3Q2013 Not Started 4Q2013 Engineering Complete and Issue SFPI 4Q2013 Not Started 2Q2014 Modification Package Begin Installation 1Q2015 Not Started Complete SFPllnstallation and 2Q2015 Not Started Put Into Service 4 Changes to Compliance Method There are no changes to the compliance method as documented in the Overall Integrated Plan (Reference 1).
5 Need for Relief/Relaxation and Basis for the Relief/Relaxation Braidwood Station, Units 1 and 2 expects to comply with the order implementation date and no relief/relaxation is required at this time.
6 Open Items from Overall Integrated Plan and Draft Safety Evaluation The following tables provide a summary of the open items documented in the Overall Integrated Plan or the Draft Safety Evaluation (SE) and the status of each item.
Overall Integrated Plan Open Items 01# Description Status 1 Identification of Spent Fuel Pool Started.
Water Levels (RAI-1a, Page 2 of9
Braidwood Station, Units 1 and 2 First Six-Month Status Report for the Implementation of SFPLI August28,2013 Ref.4) The detailed design will include a calculation to determine adequate water level to maintain normal fuel pool cooling system operation. This information will be available following acceptance of the 100% design, scheduled for April, 2014. The result will be provided in the August 2014, 6-month Integrated Plan update report to the NRC.
2 Instruments Complete.
(Ref.1 ) Continuous level indication will be The Westinghouse Spent Fuel Pool provided by a guided wave radar Level Indication instrumentation was system, submersible pressure selected consistent with the guidelines of transducer, or other appropriate level NRC JLD-ISG-2012-03 and NEI 12-02.
sensing technology that will be The instrument is a guided wave radar determined during the detailed system. It provides the capability to engineering phase of the project. reliably monitor the spent fuel pool water level under normal and anticipated adverse environmental conditions.
The sensor input to the system is a guided wave radar probe. Using the principle of time domain reflectometry (TDR) to detect the SFP water level, microwave signals are pulsed down the cable probe and reflected back from the water surface. This is used to determine the level of the water in the pool.
Each water level measurement channel includes a flexible stainless-steel sensor cable probe suspended in the spent fuel pool from a seismic Category 1 bracket attached to the operating deck or to a raised curb at the side of the pool. The cable probe extends to just above the top of the spent fuel racks. The sensor electronics are mounted in seismic and missile protected areas outside of the building housing the SFP to minimize exposure to elevated radiation and environmental conditions which could result from a postulated loss of water inventory in the pool. There is an interconnecting cable between the Page 3 of9
Braidwood Station, Units 1 and 2 First Six-Month Status Report for the Implementation of SFPLI August28,2013 sensor cable probe and sensor electronics.
The sensor electronics provide an instrument standard analog signal to a remote enclosure that will be installed in an accessible location. This enclosure contains the Uninterruptable Power Supply (UPS), backup battery, and water level display. The enclosure also includes the capability to connect an emergency or temporary external power source as part of the FLEX mitigating strategies.
Attachment 1 shows the components and arrangement of the guided wave radar system spent fuel pool level sensor and electronics enclosure for one channel.
3 The detailed design will include cable Not Started.
routing drawings from the Spent Fuel (RAI-2, Ref.4) Pool to each channel indicator. The current plan for the design of the SFPI system based on the current Exelon Nuclear program schedule for Braidwood will start the design phase in November 2013 with design completion and 100% acceptance of the design in April 2014. The requested information will be provided in the August 2014, 6-month Integrated Plan update.
4 Device total loading and mounting will Not Started.
be performed as part of the detailed (RAI-3, design process. The current plan for Ref.4) the design of the SFPI system based on the current Exelon Nuclear program schedule for Braidwood will start the design phase in November 2013 with design completion and 100%
acceptance of the design in April 2014.
The requested information will be provided in the August 2014, 6-month Integrated Plan update.
Page 4 of9
Braidwood Station, Units 1 and 2 First Six-Month Status Report for the Implementation of SFPLI August28,2013 5 Device qualification and reliability will be Not Started.
performed as part of the detailed design (RAI-4, process. The current plan for the Ref.4) design of the SFPI system based on the current Exelon Nuclear program schedule for Braidwood will start the design phase in November 2013 with design completion and 100%
acceptance of the design in April 2014.
The requested information will be provided in the August 2014, 6-month Integrated Plan update.
6 Device channel independence Not Started.
evaluation will be performed as part of (RAI-5, the detailed design process. The Ref.4) current plan for the design of the SFPI system based on the current Exelon Nuclear program schedule for Braidwood will start the design phase in November 2013 with design completion and 100% acceptance of the design in April 2014. The requested information will be provided in the August 2014, 6-month Integrated Plan update.
7 Device total power supply configuration Not Started.
will be performed as part of the detailed (RAI-6, design process. The current plan for Ref.4) the design of the SFPI system based on the current Exelon Nuclear program schedule for Braidwood will start the design phase in November 2013 with design completion and 100%
acceptance of the design in April 2014.
The requested information will be provided in the August 2014, 6-month Integrated Plan update.
8 Device channel accuracy analysis will Not Started.
be performed as part of the detailed (RAI-7, design process. The current plan for Ref.4) the design of the SFPI system based on the current Exelon Nuclear program schedule for Braidwood will start the design phase in November 2013 with design completion and 100%
Page 5 of9
Braidwood Station, Units 1 and 2 First Six-Month Status Report for the Implementation of SFPLI August28,2013 acceptance of the design in April 2014.
The requested information will be provided in the August 2014, 6-month Integrated Plan update.
9 Device testing requirement analysis will Not started.
be performed as part of the detailed (RAI-a, design process just prior to turnover to Ref.4)
Operations. The current plan for the design of the SFPI system based on the current Exelon Nuclear program schedule for Braidwood will start the design phase in November 2013 with design completion and 100%
acceptance of the design in April 2014.
Following the issue of the design, procedures will start being developed with a projected July 2014 completion date. The requested information will be provided in the August 2014, 6-month Integrated Plan update.
10 Device channel display location will be Complete.
finalized during the detailed design (RAI-9, Both the primary and backup channel process. The current plan for the Ref.4) Spent Fuel Pool Instrumentation displays design of the SFPI system based on the will be located in the main control room.
current Exelon Nuclear program The primary channel display will be schedule for Braidwood will start the located on a Unit 1 main control room design phase in November 2013 with panel with the backup channel display design completion and 100%
located on a Unit 2 main control room acceptance of the design in April 2014.
panel.
The requested information will be provided in the August 2014, 6-month Integrated Plan update.
11 Device program features analysis will Not Started.
be performed as part of the detailed (RAI-10, design process just prior to turnover to Ref.4)
Operations. The current plan for the design of the SFPI system based on the current Exelon Nuclear program schedule for Braidwood will start the design phase in November 2013 with design completion and 100%
acceptance of the design in April 2014.
Following the issue of the design, procedures will start being developed Page 6 of9
Braidwood Station, Units 1 and 2 First Six-Month Status Report for the Implementation of SFPLI August 28, 2013 with a projected July 2014 completion date. The requested information will be provided in the August 2014, 6-month Integrated Plan update.
12 Device testing and calibration Not Started.
requirements analysis will be performed (RAI-11, as part of the detailed design process Ref.4) just prior to turnover to Operations. The current plan for the design of the SFPI system based on the current Exelon Nuclear program schedule for Braidwood will start the design phase in November 2013 with design completion and 100% acceptance of the design in April 2014. Following the issue of the design, procedures will start being developed with a projected July 2014 completion date. The requested information will be provided in the August 2014, 6-month Integrated Plan update.
Draft Safety Evaluation Open Items 01# Description Status None at this time.
7 Potential Draft Safety Evaluation Impacts There are no potential impacts to the Draft Safety Evaluation identified at this time.
8 References The following references support the updates to the Overall Integrated Plan described in this enclosure.
- 1. Exelon Generation Company, LLC, letter to USNRC, "Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-0S1)," dated February 28,2013 (RS 027)
- 2. NRC Order Number EA-12-0S1, "Issuance of Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation," dated March 12, 2012.
Page 7 of9
Braidwood Station, Units 1 and 2 First Six-Month Status Report for the Implementation of SFPLI August28,2013
- 3. USNRC letter to Exelon Generation Company, LLC, Request for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation, dated July 11,2013.
- 4. Exelon Generation Company, LLC, letter to USNRC, "Response to Request for Additional Information - Overall Integrated Plan in Response to Commission Order Modifying License Requirements for Reliable Spent Fuel Pool Instrumentation (Order No. EA 051)", dated July 31,2013 (RS-13-194)
Page 8 of9
Braidwood Station, Units 1 and 2 First Six-Month Status Report for the Implementation of SFPLI August 28, 2013 Attachment 1 Spent Fuel Pool Instrumentation System Sensor Electronics
~~~~11 Remote Enclosure containing II sensor UPS Output to Interconnecting Cable optional 120/240 alternate VAC Power display 20-30' (typical) measurement span to just above top of * ... 11 40.0 II fuel racks 6 mm SST Cable Probe with Anchor Weight Spent Fuel Pool Page 9 of9