Correction of Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation
ML13326B011
Person / Time
Site: Braidwood  Constellation icon.png
Issue date: 12/17/2013
From: Joel Wiebe
Plant Licensing Branch III
To: Pacilio M
Exelon Generation Co
Joel Wiebe, NRR/DORL 415-6606
References
TAC MF0821, TAC MF0822
Download: ML13326B011 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 December 17, 2013 Mr. Michael J. Pacilio Senior Vice President Exelon Generation Company, LLC President and Chief Nuclear Officer Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555

SUBJECT:

BRAIDWOOD STATION, UNIT NOS. 1 AND 2- CORRECTION OF INTERIM STAFF EVALUATION AND REQUEST FOR ADDITIONAL INFORMATION REGARDING THE OVERALL INTEGRATED PLAN FOR IMPLEMENTATION OF ORDER EA-12-051, RELIABLE SPENT FUEL POOL INSTRUMENTATION (TAC NOS. MF0821 AND MF0822)

Dear Mr. Pacilio:

On November 4, 2013 (Agencywide Documents Access and Management System (ADAMS)

Accession No. ML13280A566), the U.S. Nuclear Regulatory Commission (NRC) issued the interim staff evaluation and request for additional information regarding the Overall Integrated Plan for implementation of Order EA-12-051, "Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation" (ADAMS Accession No. ML12054A679). The November 4, 2013, letter contained inconsistent dates when describing your schedule for achieving compliance with the order.

The purpose of this letter is to correct the inconsistent dates. Section 3.1 of the interim staff evaluation correctly states that your February 28, 2013, Overall Integrated Plan included installation of the spent fuel pool instrumentation by spring 2015. The transmittal letter and Section 1.0 should have also have identified the date as spring 2015. Based on the spring 2015 date, the requested response date to the included request for additional information is September 30, 2014.

M. Pacilio If you have any questions regarding this letter, please contact me at 301-415-6606 or via e-mail at Joei.Wiebe@nrc.gov.

Sincerely,

~/J.~r Joel S. Wiebe, Senior Project Manager Plant Licensing Branch LPL 111-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-456 and 50-457 cc w/encl: Distribution via Listserv

ML13326B011 OFFICE NRR/DO R L/LPL3-2 NRR/DORLILPL3-2 NRR/DORLILPL3-2 NRR/DORL/LPL3-2 NAME JWiebe SRohrer TTate JWiebe (EBrown for) 11/27/13 11/26/13 12/18 /13 12/17/13 DATE