Other: L-MT-12-092, Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), L-MT-13-016, Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), L-MT-13-080, Monticello'S First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), L-MT-14-015, Plant'S Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), L-MT-14-072, Plant'S Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), L-MT-15-005, Plant'S Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), L-MT-15-046, Plant Completion of Reqiuired Action by NRC Order EA-12-051, Reliable Spent Fuel Pool Instrumentation, ML15072A098
|
MONTHYEARML12054A6792012-03-12012 March 2012 Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation Project stage: Approval L-MT-12-092, Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2012-10-29029 October 2012 Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other L-MT-13-016, Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2013-02-28028 February 2013 Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other ML13176A3312013-06-0707 June 2013 NRR E-mail Capture - Monticello Nuclear Generating Plant - Requests for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation Project stage: RAI L-MT-13-058, Responses to Requests for Additional Information Regarding Monticello Overall Integrated Plan Submitted in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrument2013-07-12012 July 2013 Responses to Requests for Additional Information Regarding Monticello Overall Integrated Plan Submitted in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentati Project stage: Response to RAI L-MT-13-080, Monticello'S First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2013-08-28028 August 2013 Monticello'S First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other ML13275A1872013-10-28028 October 2013 Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051 Project stage: RAI L-MT-14-015, Plant'S Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2014-02-28028 February 2014 Plant'S Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other L-MT-14-072, Plant'S Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2014-08-28028 August 2014 Plant'S Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other ML14290A3672014-10-22022 October 2014 Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Order EA-12-049 and EA-12-051 Project stage: Acceptance Review L-MT-15-005, Plant'S Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2015-02-24024 February 2015 Plant'S Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other ML15072A0982015-03-17017 March 2015 Report for the Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Other L-MT-15-046, Plant Completion of Reqiuired Action by NRC Order EA-12-051, Reliable Spent Fuel Pool Instrumentation2015-07-28028 July 2015 Plant Completion of Reqiuired Action by NRC Order EA-12-051, Reliable Spent Fuel Pool Instrumentation Project stage: Other 2013-08-28
[Table View] |
|
---|
Category:Letter type:L
MONTHYEARL-MT-24-028, Response to RCI for RR-017 ISI Impracticality2024-08-28028 August 2024 Response to RCI for RR-017 ISI Impracticality L-MT-24-022, – Preparation and Scheduling of Operator Licensing Examinations2024-07-0909 July 2024 – Preparation and Scheduling of Operator Licensing Examinations L-MT-24-019, Submittal of ASME Section XI, Section IWB-3720 Analytical Evaluation in Accordance with 10 CFR 50.55a(b)(2)(xliii)2024-06-10010 June 2024 Submittal of ASME Section XI, Section IWB-3720 Analytical Evaluation in Accordance with 10 CFR 50.55a(b)(2)(xliii) L-MT-24-017, Response to Request for Additional Information Regarding License Amendment Request to Revise Monticello Technical Specification Surveillance Requirement 3.8.6.6 (EPID-L-2023-LLA-01602024-06-0404 June 2024 Response to Request for Additional Information Regarding License Amendment Request to Revise Monticello Technical Specification Surveillance Requirement 3.8.6.6 (EPID-L-2023-LLA-0160 L-MT-24-015, Response to Request for Additional Information - Alternative Request VR-09 for OMN-172024-05-16016 May 2024 Response to Request for Additional Information - Alternative Request VR-09 for OMN-17 L-MT-24-013, 2023 Annual Radiological Environmental Operating Report2024-05-14014 May 2024 2023 Annual Radiological Environmental Operating Report L-MT-24-016, 2023 Annual Report of Individual Monitoring for the Monticello Nuclear Generating Plant (MNGP)2024-05-0808 May 2024 2023 Annual Report of Individual Monitoring for the Monticello Nuclear Generating Plant (MNGP) L-MT-24-012, Reactor Scram, Containment Isolation, and Cooldown Rate Outside of Limits Following Technician Adjustment of Wrong Component2024-04-25025 April 2024 Reactor Scram, Containment Isolation, and Cooldown Rate Outside of Limits Following Technician Adjustment of Wrong Component L-MT-24-002, Submittal of Revision 41 to the Updated Safety Analysis Report2024-04-17017 April 2024 Submittal of Revision 41 to the Updated Safety Analysis Report L-MT-24-004, Submittal of 10 CFR 72.48 Report for Monticello Nuclear Generating Plant (MNGP)2024-04-17017 April 2024 Submittal of 10 CFR 72.48 Report for Monticello Nuclear Generating Plant (MNGP) L-MT-24-006, Subsequent License Renewal Application Annual Update 1 and Supplement 92024-02-29029 February 2024 Subsequent License Renewal Application Annual Update 1 and Supplement 9 L-MT-24-007, Response to NRC Request for Additional Information on Proposed Inservice Inspection Alternative RR-002 for the Sixth Ten-Year ISI Interval2024-02-15015 February 2024 Response to NRC Request for Additional Information on Proposed Inservice Inspection Alternative RR-002 for the Sixth Ten-Year ISI Interval L-MT-24-001, 10 CFR 50.55a Request RR-017 - Inservice Inspection (ISI) Impracticality in Accordance with 10 CFR 50.55a(g)(5)(iii) During the Fifth Ten-Year Interval2024-01-30030 January 2024 10 CFR 50.55a Request RR-017 - Inservice Inspection (ISI) Impracticality in Accordance with 10 CFR 50.55a(g)(5)(iii) During the Fifth Ten-Year Interval L-MT-23-054, Subsequent License Renewal Application Supplement 82024-01-11011 January 2024 Subsequent License Renewal Application Supplement 8 L-MT-23-047, License Amendment Request: Revision to the MNGP Pressure Temperature Limits Report to Change the Neutron Fluence Methodology and Incorporate New Surveillance Capsule Data2023-12-29029 December 2023 License Amendment Request: Revision to the MNGP Pressure Temperature Limits Report to Change the Neutron Fluence Methodology and Incorporate New Surveillance Capsule Data L-MT-23-056, Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information - Set 1 Part 22023-12-18018 December 2023 Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information - Set 1 Part 2 L-MT-23-042, 2023 Annual Report of Changes in Emergency Core Cooling System Evaluation Models Pursuant to 10 CFR 50.462023-12-11011 December 2023 2023 Annual Report of Changes in Emergency Core Cooling System Evaluation Models Pursuant to 10 CFR 50.46 L-MT-23-053, Condition Prohibited by Technical Specifications Due to Inoperable Main Steam Line Low Pressure Isolation Switch2023-12-0404 December 2023 Condition Prohibited by Technical Specifications Due to Inoperable Main Steam Line Low Pressure Isolation Switch L-MT-23-052, Subsequent License Renewal Application Supplement 72023-11-30030 November 2023 Subsequent License Renewal Application Supplement 7 L-MT-23-051, Update to the Technical Specification Bases2023-11-28028 November 2023 Update to the Technical Specification Bases L-MT-23-049, Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information - Set 12023-11-21021 November 2023 Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information - Set 1 L-MT-23-043, 10 CFR 50.55a(z)(1) Request Regarding OMN-17, Revision 1. VR-092023-11-13013 November 2023 10 CFR 50.55a(z)(1) Request Regarding OMN-17, Revision 1. VR-09 L-MT-23-038, License Amendment Request to Revise Monticello Technical Specification Surveillance Requirement 3.8.6.62023-11-10010 November 2023 License Amendment Request to Revise Monticello Technical Specification Surveillance Requirement 3.8.6.6 L-MT-23-046, Subsequent License Renewal Application Response to Request for Additional Information Round 2 - Set 12023-11-0909 November 2023 Subsequent License Renewal Application Response to Request for Additional Information Round 2 - Set 1 L-MT-23-041, Subsequent License Renewal Application Response to Request for Confirmation of Information Set 22023-10-0303 October 2023 Subsequent License Renewal Application Response to Request for Confirmation of Information Set 2 L-MT-23-037, Subsequent License Renewal Application Response to Request for Additional Information Set 32023-09-22022 September 2023 Subsequent License Renewal Application Response to Request for Additional Information Set 3 L-MT-23-036, Subsequent License Renewal Application Response to Request for Additional Information Set 2 and Supplement 62023-09-0505 September 2023 Subsequent License Renewal Application Response to Request for Additional Information Set 2 and Supplement 6 L-MT-23-035, Subsequent License Renewal Application Supplement 52023-08-28028 August 2023 Subsequent License Renewal Application Supplement 5 L-MT-23-034, Subsequent License Renewal Application Response to Request for Additional Information Set 12023-08-15015 August 2023 Subsequent License Renewal Application Response to Request for Additional Information Set 1 L-MT-23-032, 10 CFR 50.55a(z)(2) Request Regarding MO-2397, VR-112023-07-31031 July 2023 10 CFR 50.55a(z)(2) Request Regarding MO-2397, VR-11 L-MT-23-028, 2023 Refueling Outage 90-Day Inservice Inspection (ISI) Summary Report2023-07-31031 July 2023 2023 Refueling Outage 90-Day Inservice Inspection (ISI) Summary Report L-MT-23-031, Subsequent License Renewal Application Supplement 4 and Responses to Request for Confirmation of Information - Set 12023-07-18018 July 2023 Subsequent License Renewal Application Supplement 4 and Responses to Request for Confirmation of Information - Set 1 L-MT-23-030, Subsequent License Renewal Application Supplement 32023-07-0404 July 2023 Subsequent License Renewal Application Supplement 3 L-MT-23-025, Subsequent License Renewal Application Supplement 22023-06-26026 June 2023 Subsequent License Renewal Application Supplement 2 L-MT-23-019, Submittal of 2022 Annual Radiological Environmental Operating Report2023-05-10010 May 2023 Submittal of 2022 Annual Radiological Environmental Operating Report L-MT-23-020, Submittal of 2022 Annual Radioactive Effluent Release Report2023-05-10010 May 2023 Submittal of 2022 Annual Radioactive Effluent Release Report L-MT-23-021, Core Operating Limits Report (COLR) for the Monticello Nuclear Generating Plant for Cycle 322023-05-0202 May 2023 Core Operating Limits Report (COLR) for the Monticello Nuclear Generating Plant for Cycle 32 L-MT-23-017, 2022 Annual Report of Individual Monitoring for the Monticello Nuclear Generating Plant (MNGP)2023-04-18018 April 2023 2022 Annual Report of Individual Monitoring for the Monticello Nuclear Generating Plant (MNGP) L-MT-23-010, Subsequent License Renewal Application Supplement 12023-04-0303 April 2023 Subsequent License Renewal Application Supplement 1 L-MT-23-013, Core Operating Limits Report (COLR) for Cycle 31, Revision 32023-03-28028 March 2023 Core Operating Limits Report (COLR) for Cycle 31, Revision 3 L-MT-23-012, Core Operating Limits Report (COLR) for Monticello Nuclear Generating Plant Cycle 31, Revision 22023-03-17017 March 2023 Core Operating Limits Report (COLR) for Monticello Nuclear Generating Plant Cycle 31, Revision 2 L-MT-23-008, 10CFR50.55a Request to Use Later Edition of ASME Section XI for ISI Code of Record (RR-003)2023-02-0707 February 2023 10CFR50.55a Request to Use Later Edition of ASME Section XI for ISI Code of Record (RR-003) L-MT-23-004, CFR 50.55a Request RR-001, Request to Use a Provision of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI for the Monticello Third Interval Containment Inservice Inspection Program2023-01-23023 January 2023 CFR 50.55a Request RR-001, Request to Use a Provision of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI for the Monticello Third Interval Containment Inservice Inspection Program L-MT-23-005, Response to the NRC Request for Additional Information Regarding the 50.55a Request Pr 08, HPCI Pump Quarterly Testing (EPID Number L-2022-LLR-0088)2023-01-0606 January 2023 Response to the NRC Request for Additional Information Regarding the 50.55a Request Pr 08, HPCI Pump Quarterly Testing (EPID Number L-2022-LLR-0088) L-MT-22-049, Industry Groundwater Protection Initiative Special Report2022-12-15015 December 2022 Industry Groundwater Protection Initiative Special Report L-MT-22-052, L-MT-22-052 Monticello Nuclear Generating Plant 10 CFR 50.55a Request No. Pr 08, Request for HPCI Pump Quarterly Alternative2022-12-15015 December 2022 L-MT-22-052 Monticello Nuclear Generating Plant 10 CFR 50.55a Request No. Pr 08, Request for HPCI Pump Quarterly Alternative L-MT-22-046, 2022 Annual Report of Changes in Emergency Core Cooling System Evaluation Models Pursuant to 10 CFR 50.462022-12-13013 December 2022 2022 Annual Report of Changes in Emergency Core Cooling System Evaluation Models Pursuant to 10 CFR 50.46 L-MT-22-048, Update to the Monticello Technical Specification Bases2022-11-28028 November 2022 Update to the Monticello Technical Specification Bases L-MT-22-047, Withdrawal of Request for Relief from ASME OM Code for the Sixth Inservice Testing Interval2022-11-10010 November 2022 Withdrawal of Request for Relief from ASME OM Code for the Sixth Inservice Testing Interval L-MT-22-045, Letter Submitting Post-Exam Package2022-11-0404 November 2022 Letter Submitting Post-Exam Package 2024-08-28
[Table view] Category:Status Report
MONTHYEARML23089A0762023-03-29029 March 2023 Decommissioning Funding Status Reports ML23044A3662023-02-15015 February 2023 Calendar Year 2022 Reactor Oversight Process Baseline Inspection Program Completion - Region III L-MT-18-079, Ninth Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions ...2018-12-17017 December 2018 Ninth Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions ... ML18029A2712018-01-29029 January 2018 Corrected Decommissioning Funding Status Reports L-MT-17-081, Seventh Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order ...2017-12-21021 December 2017 Seventh Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order ... L-MT-17-042, Sixth Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions2017-06-14014 June 2017 Sixth Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions ML17087A2462017-03-28028 March 2017 Decommissioning Funding Status Reports L-MT-16-072, Fifth Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order EA-13-109)2016-12-19019 December 2016 Fifth Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order EA-13-109) L-MT-16-038, Seventh Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049)2016-08-19019 August 2016 Seventh Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049) L-MT-16-034, Fourth Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions ...2016-06-17017 June 2016 Fourth Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions ... L-MT-16-009, Sixth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2016-02-22022 February 2016 Sixth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) L-MT-15-090, Phase 2 Overall Integrated Plan in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order EA-13-109) Including Phase 1.2015-12-17017 December 2015 Phase 2 Overall Integrated Plan in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order EA-13-109) Including Phase 1.. L-MT-15-059, Fifth Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2015-08-20020 August 2015 Fifth Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) L-MT-15-031, Second Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order EA-13-109), Phase 12015-06-22022 June 2015 Second Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order EA-13-109), Phase 1 ML15089A3622015-03-30030 March 2015 ISFSI, Units 1 and 2, and Monticello - Submittal of Decommissioning Funding Status Reports L-MT-15-004, Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Mitigation Strategies for Beyond-Design-Basis External Events (EA-12-049)2015-02-24024 February 2015 Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Mitigation Strategies for Beyond-Design-Basis External Events (EA-12-049) L-MT-15-005, Plant'S Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2015-02-24024 February 2015 Plant'S Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) L-MT-14-092, First Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions2014-12-16016 December 2014 First Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions L-MT-14-073, Plant'S Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2014-08-28028 August 2014 Plant'S Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) L-MT-14-015, Plant'S Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2014-02-28028 February 2014 Plant'S Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) L-MT-14-014, Plant'S Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049)2014-02-28028 February 2014 Plant'S Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049) L-MT-13-079, Monticello'S First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2013-08-28028 August 2013 Monticello'S First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) L-MT-13-080, Monticello'S First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2013-08-28028 August 2013 Monticello'S First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) ML13084A0502013-03-22022 March 2013 Enclosures - Decommissioning Funding Status Reports L-MT-12-088, Initial Status Report in Response to March 12, 2012 Commission Order Modifying - Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2012-10-29029 October 2012 Initial Status Report in Response to March 12, 2012 Commission Order Modifying - Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) ML1108711212011-03-28028 March 2011 Independent Spent Fuel and Monticello, Decommissioning Funding Status Reports L-HU-06-011, Decommissioning Funding Status Report2006-03-29029 March 2006 Decommissioning Funding Status Report ML0520103172005-04-11011 April 2005 National Climatic Data Center - Tornados Reported in Sherburn and Wright Counties 1950-2004 L-HU-05-008, Decommissioning Funding Status Reports2005-03-31031 March 2005 Decommissioning Funding Status Reports ML0329009652003-10-16016 October 2003 Decommissioning Funding Status Reports - Supplemental Response for Duane Arnold, Kewaunee, Monticello, Palisades, Point Beach, Units 1 and 2, and Prairie Island, Units 1 and 2 ML0520105062002-08-0202 August 2002 Xcel Energy/Usfws Avian Protection Memorandum of Understanding, Semi-Annual Report #1 2023-03-29
[Table view] |
Text
Xcel Energy Monticello Nuclear Generating Plant 2807 W County Road 75 Monticello, MN 55362 August28,2013 L-MT-13-080 10 CFR 2.202 10 CFR 50.4 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Monticello Nuclear Generating Plant Docket No. 50-263 Renewed Facility Operating License No. DPR-22 Monticello's First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)
References:
- 1. NRC Order EA-12-051, "Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation," dated March 12, 2012 (ADAMS Accession No. ML12054A679).
- 2. NRC Interim Staff Guidance JLD-ISG-2012-03, "Compliance with Order EA-12-051, Reliable Spent Fuel Pool Instrumentation," Revision 0, dated August 29, 2012 (ADAMS Accession No. ML12221A339).
- 3. NEI 12-02, "Industry Guidance for Compliance with NRC Order EA 051, 'To Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation,"' Revision 1, dated August 2012.
- 4. NSPM Letter to NRC, "Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051),"
dated October 29, 2012 (ADAMS Accession No. ML12305A383).
- 5. NSPM Letter to NRC, "Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051),"
dated February 28, 2013 (ADAMS Accession No. ML13060A447).
Document Control Desk Page 2
- 6. NSPM Letter to NRC, "Responses to Requests for Additional Information Regarding Monticello Nuclear Generating Plant's Overall Integrated Plan Submitted in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) (TAC No. MF0924)," dated July 12, 2013, (ADAMS Accession No. ML13193A324).
On March 12, 2012, the NRC staff issued Order EA-12-051, "Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation,"
(Reference 1) to all NRC power reactor licensees and holders of construction permits in active or deferred status. Reference 1 was immediately effective and directs Northern States Power Company, a Minnesota corporation, doing business as Xcel Energy, to have a reliable indication of the water level in the spent fuel storage pool for Monticello Nuclear Generating Plant (MNGP). Specific requirements were outlined in Attachment 2 of Reference 1.
Pursuant to Condition C of Section IV, Reference 1 required submission of an initial status report 60 days following issuance of the final interim staff guidance (ISG), an overall integrated plan, and status reports at six-month intervals following the submittal of the overall integrated plan. The ISG (Reference 2) endorsed, with exceptions and clarifications, the methodologies described in industry guidance document, NEI 12-02, "Industry Guidance for Compliance with Order EA-12-051, 'To Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation,"' Revision 1 (Reference 3).
Reference 4 provided the MNGP initial 60-day status report regarding reliable spent fuel pool instrumentation. Reference 5 provided the overall integrated plan for MNGP.
Reference 6 provided the NSPM responses to NRC Requests for Additional Information (RAis) regarding the overall integrated plan for MNGP.
The purpose of this letter is to provide the first six-month status report pursuant to Section IV, Condition C.2 of Reference 1, which delineates the progress made in implementing the requirements of the Reference 1 Order. The enclosed report provides an update of milestone accomplishments since the overall integrated plan was submitted, including changes to the compliance method, schedule, or the need and basis for relief, if any.
Please contact Lynne Gunderson, Licensing Engineer, at 612-396-0173, if additional information or clarification is required.
Document Control Desk Page 3 This letter makes no new commitments and no revisions to existing commitments.
I declare under penalty of perjury that the foregoing is true and correct.
Executed on August 28, 2013.
Mark A. Schimmel Site Vice President, Monticello Nuclear Generating Plant Northern States Power Company - Minnesota Enclosure cc: Administrator, Region Ill, USNRC Director of Nuclear Reactor Regulation (NRR), USNRC Project Manager, Monticello Nuclear Generating Plant, USNRC Resident Inspector, Monticello Nuclear Generating Plant, USNRC
L-MT-13-080 NSPM Enclosure ENCLOSURE Monticello Nuclear Generating Plant First Six-Month Status Report for Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation 1.0 Introduction The Nuclear Regulatory Commission (NRC) issued Order EA-12-051, "Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation," on March 12, 2012 (Reference 1). The Order required licensees to have reliable indication of the water level in associated spent fuel pools capable of supporting identification of the following spent fuel pool water level conditions by trained personnel: (1) level that is adequate to support operation of the normal fuel pool cooling system, (2) level that is adequate to provide substantial radiation shielding for a person standing on the spent fuel pool operating deck, and (3) level where fuel remains covered and actions to implement make-up water addition should no longer be deferred. The Order required licensees to submit an overall integrated plan, including a description of how the requirements in Attachment 2 of the Order would be achieved. Northern States Power Company, a Minnesota corporation (NSPM), doing business as Xcel Energy, submitted the overall integrated plan (Reference 2) for the Monticello Nuclear Generating Plant (MNGP) on February 28, 2013.
This Enclosure provides the MNGP first six-month status report. This status report includes an update of milestone accomplishments since submittal of the overall integrated plan including any changes to the compliance method, schedule, or the need and basis for relief, if any.
2.0 Milestone Accomplishments The original milestone schedule, with target dates, was provided in Section 2.0 of Reference 2. The following milestone has been completed since the overall integrated plan was submitted and is current as of July 31, 2013.
- Select Instrument Vendor 3.0 Milestone Schedule Status The following table provides an update of the milestone schedule to support the overall integrated plan. This includes a brief milestone status and a revised target date if the Page 1 of 5
L-MT-13-080 NSPM Enclosure date has changed. The dates are planning dates subject to change as design and implementation details are developed.
Milestone Target Activity Status Revised Completion Target Date Completion Date Submit 60 Day Status Report October 2012 Complete Submit Overall Integrated Plan February 2013 Complete Select Instrument Vendor (Target March 2013 Complete date 1st Quarter 2013)
Submit First Six-Month Status August 2013 Complete with Update this submittal Commence Engineering Design January 2014 Not Started Submit Second Six-Month Status February 2014 Not Started Update Submit Third Six-Month Status August 2014 Not Started Update (includes responses to Requests for Additional Information (RAis))
Commence Installation September Not Started 2014 Submit Fourth Six-Month Status February 2015 Not Started Update (includes responses to remaining RAis)
Reliable Spent Fuel Pool April2015 Not Started Instrumentation Operational (End of R27)
Submit Report that Full June 2015 Not Started Compliance is Achieved No target completion dates for milestones have been changed. Responses to NRC Requests for Additional Information (RAis) have been added to the third and fourth six-month status updates. Incorporation of the RAI responses into these status reports was discussed in Reference 3.
4.0 Proposed Changes to Compliance Method There are no changes proposed to the compliance method described in the overall integrated plan (Reference 2).
Page 2 of 5
L-MT-13-080 NSPM Enclosure 5.0 Need and Basis for Relief from the Requirements of the Order NSPM expects to comply with the Order implementation date and requirements and no relief is required at this time.
6.0 Open Items from Overall Integrated Plan and Draft Safety Evaluation NSPM did not identify any open items in the overall integrated plan. The overall integrated plan did contain future actions to ensure compliance with the Order. The future actions were identified internally and are being tracked through NSPM's corrective action program (CAP).
No draft Safety Evaluation (SE) has been issued as of July 31, 2013. Closure of the draft SE open items, when issued, will be tracked to closure in future status reports.
NSPM did receive RAis (Reference 3) of which several responses were deferred to the third and fourth six-month status updates. The RAis are listed below in the draft Safety Evaluation Open Item Table as the responses are seen as necessary for NRC to complete their review.
Draft Safety Evaluation Open Items Open Description Status Item Number 1 RAI-1, Levels of Required Monitoring: Not Started b) Final mounting arrangement will be provided with the August 2014 six-month status report as part of response to RAI3.
c) Overall integrated plan, Section 3.3, Mounting, stated that an evaluation of other stored hardware will be conducted as part of the design process. The requested information will be provided with the August 2014, six-month status report.
Page 3 of 5
L-MT-13-080 NSPM Enclosure 2 RAI-2, Arrangement: Not Started The planned locations for the primary and back-up level sensors, the mounting brackets and the proposed routing of the cables have not been determined. The final component locations will be available upon completion of the final design. The requested information will be provided with the August 2014, six-month status report.
3 RAI-3, Mounting (all RAI subparts): Not Started The requested information will be provided with the August 2014, six-month status report.
4 RAI-4, Qualification (all RAI subparts): Not Started The requested information will be provided with the August 2014, six-month status report.
5 RAI-5, Independence (all RAI subparts): Not Started The requested information will be provided with the August 2014, six-month status report.
6 RAI-6, Power Supplies (all RAI subparts): Not Started The requested information will be provided with the August 2014, six-month status report.
7 RAI-7, Accuracy (all RAI subparts): Not Started Setpoints will be determined following Monticello procedure ESM-03.02, "Design Requirements, Practices & Topics (Instrumentation & Controls)." Determination of setpoints using this procedure is part of the NSPM design process.
The requested information will be provided with the August 2014, six-month status report.
8 RAI-8, Testing (all RAI subparts): Not Started The requested information will be provided with the August 2014, six-month status report.
Page 4 of 5
L-MT-13-080 NSPM Enclosure 9 RAI-9, Display (all RAI subparts): Not Started The requested information will be provided with the August 2014, six-month status report.
10 RAI-10, Procedures: Not Started The requested information will be provided with the February 2015, six-month status report.
11 RAI-11, Testing and Calibration (all RAI subparts): Not Started The requested information will be provided with the February 2015, six-month status report.
7.0 Potential Draft Safety Evaluation Impacts There are no potential impacts to the draft Safety Evaluation identified at this time.
8.0 References
- 1. NRC Order EA-12-051, "Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation," dated March 12, 2012 (ADAMS Accession No. ML12054A679).
- 2. NSPM Letter to NRC, "Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051),"
dated February 28, 2013 (ADAMS Accession No. ML13060A447).
- 3. NSPM Letter to NRC, "Responses to Requests for Additional Information Regarding Monticello Nuclear Generating Plant's Overall Integrated Plan Submitted in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) (TAG No. MF0924)," dated July 12, 2013, (ADAMS Accession No. ML13193A324).