Letter Sequence Other |
---|
|
Results
Other: L-PI-12-093, Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), L-PI-13-006, Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), L-PI-13-081, Prairie Island'S First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation, L-PI-14-017, Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), L-PI-14-079, Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), L-PI-15-022, Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), L-PI-15-064, Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation, L-PI-15-099, Completion of Required Action by NRC Order EA-12-051, Reliable Spent Fuel Pool Instrumentation, L-PI-16-001, Enclosure 2: Responses to Open and Pending Items from the NRC Audit Report, ML13060A363, ML15083A415, ML15224B396, ML16014A754, ML16014A755
|
MONTHYEARL-PI-12-093, Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2012-10-29029 October 2012 Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other ML13060A3632013-02-26026 February 2013 Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other L-PI-13-006, Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2013-02-26026 February 2013 Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other ML13205A3552013-07-11011 July 2013 NRR E-mail Capture - Prairie Island Units 1 and 2 - Draft RAI OIP for Reliable SFP Instrumentation Project stage: Draft RAI L-PI-13-077, Responses to Requests for Additional Information Regarding Overall Integrated Plan Submitted in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool...2013-08-0606 August 2013 Responses to Requests for Additional Information Regarding Overall Integrated Plan Submitted in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool... Project stage: Response to RAI L-PI-13-081, Prairie Island'S First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation2013-08-26026 August 2013 Prairie Island'S First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation Project stage: Other ML13311A4862013-11-14014 November 2013 Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation Project stage: RAI L-PI-14-017, Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2014-02-26026 February 2014 Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other L-PI-14-079, Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2014-08-25025 August 2014 Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other L-PI-15-022, Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2015-02-26026 February 2015 Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other ML15083A4152015-03-31031 March 2015 Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Other ML15224B3962015-08-20020 August 2015 Report for the Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Order EA-12-049 and EA-12-051 Project stage: Other L-PI-15-064, Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation2015-08-25025 August 2015 Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation Project stage: Other L-PI-15-099, Completion of Required Action by NRC Order EA-12-051, Reliable Spent Fuel Pool Instrumentation2015-12-0808 December 2015 Completion of Required Action by NRC Order EA-12-051, Reliable Spent Fuel Pool Instrumentation Project stage: Other ML16014A7552016-01-14014 January 2016 Enclosure 1, Compliance with NRC Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events. Project stage: Other L-PI-16-001, Enclosure 2: Responses to Open and Pending Items from the NRC Audit Report2016-01-14014 January 2016 Enclosure 2: Responses to Open and Pending Items from the NRC Audit Report Project stage: Other ML16014A7542016-01-14014 January 2016 Notification of Compliance with NRC Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events. Project stage: Other 2014-02-26
[Table View] |
|
---|
Category:Letter type:L
MONTHYEARL-PI-23-034, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.7.8, Cooling Water (Cl) System,2024-01-0202 January 2024 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.7.8, Cooling Water (Cl) System, L-PI-23-035, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications Section 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report2023-12-20020 December 2023 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications Section 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report L-PI-23-033, Supplement to License Amendment Request to Revise Technical Specification 3.8.1, Surveillance Requirement 3.8.1.2, Note 32023-12-0505 December 2023 Supplement to License Amendment Request to Revise Technical Specification 3.8.1, Surveillance Requirement 3.8.1.2, Note 3 L-PI-23-025, License Amendment Request to Revise Technical Specification 3.8.1, Surveillance Requirement 3.8.1.2, Note 32023-09-28028 September 2023 License Amendment Request to Revise Technical Specification 3.8.1, Surveillance Requirement 3.8.1.2, Note 3 L-PI-23-023, Baffle Former Bolts Alternate Aging Management Strategy2023-09-11011 September 2023 Baffle Former Bolts Alternate Aging Management Strategy L-PI-23-018, License Amendment Request to Revise ISFSI Technical Specification 4.4 to Allow Use of a Code Alternative to ASME Code, NB-5130, Examination of Weld Edge Preparation Surfaces, for the TN-40HT2023-07-14014 July 2023 License Amendment Request to Revise ISFSI Technical Specification 4.4 to Allow Use of a Code Alternative to ASME Code, NB-5130, Examination of Weld Edge Preparation Surfaces, for the TN-40HT L-PI-23-006, License Amendment Request to Revise Technical Specification 3.7.8 Required Actions2023-06-22022 June 2023 License Amendment Request to Revise Technical Specification 3.7.8 Required Actions L-PI-23-016, 2022 10 CFR 50.46 LOCA Annual Report2023-06-14014 June 2023 2022 10 CFR 50.46 LOCA Annual Report L-PI-23-010, Annual Report of Individual Monitoring2023-04-27027 April 2023 Annual Report of Individual Monitoring L-PI-23-007, Supplement to Application to Revise Technical Specification Section 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR)2023-03-28028 March 2023 Supplement to Application to Revise Technical Specification Section 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR) L-PI-23-005, CFR 50.55a Requests Nos. 1-RR-5-15 and 2-RR-5-15, Proposed Use of Subsequent ASME Code Edition and Addenda in Accordance with 10 CFR 50.55a(g)(4)(iv)2023-03-0303 March 2023 CFR 50.55a Requests Nos. 1-RR-5-15 and 2-RR-5-15, Proposed Use of Subsequent ASME Code Edition and Addenda in Accordance with 10 CFR 50.55a(g)(4)(iv) L-PI-23-001, Day Steam Generator Tube Inspection Report2023-01-30030 January 2023 Day Steam Generator Tube Inspection Report L-PI-22-047, Resubmittal of Prairie Island Nuclear Generating Plant (PINGP) 2018 Unit 1 180-Day Steam Generator Tube Inspection Report2022-12-21021 December 2022 Resubmittal of Prairie Island Nuclear Generating Plant (PINGP) 2018 Unit 1 180-Day Steam Generator Tube Inspection Report L-PI-22-020, Application to Revise Technical Specification Section 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR)2022-12-0202 December 2022 Application to Revise Technical Specification Section 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR) L-PI-22-040, Supplement to Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections2022-10-0606 October 2022 Supplement to Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections L-PI-22-037, Updated Approach for Prairie Island Unit 1 and Unit 2 Baffle Former Bolts2022-09-20020 September 2022 Updated Approach for Prairie Island Unit 1 and Unit 2 Baffle Former Bolts L-PI-22-032, CFR 50.46 LOCA Annual Report2022-06-16016 June 2022 CFR 50.46 LOCA Annual Report L-PI-22-033, Response to Request for Additional Information Prairie Island Nuclear Generating Plant, Units 1 and 2, Amendment to Adopt 24-Month Operating Cycles2022-06-10010 June 2022 Response to Request for Additional Information Prairie Island Nuclear Generating Plant, Units 1 and 2, Amendment to Adopt 24-Month Operating Cycles L-PI-22-003, Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections2022-06-0707 June 2022 Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections L-PI-22-024, Supplement to Application for License Amendment to Implement 24-Month Operating Cycle2022-03-0707 March 2022 Supplement to Application for License Amendment to Implement 24-Month Operating Cycle L-PI-21-047, Response to Request for Additional Information 24-Month Cycle Amendment Prairie Island Nuclear Generating Plant, Units 1 and 22021-12-0707 December 2021 Response to Request for Additional Information 24-Month Cycle Amendment Prairie Island Nuclear Generating Plant, Units 1 and 2 L-PI-21-045, Response to Request for Additional Information Cooling Water System License Amendment Request2021-11-0404 November 2021 Response to Request for Additional Information Cooling Water System License Amendment Request L-PI-21-029, Exigent License Amendment Request to Revise Technical Specification 3.7.8 to Allow a One-Time Extension of the Completion Time of Required Action B.12021-10-0707 October 2021 Exigent License Amendment Request to Revise Technical Specification 3.7.8 to Allow a One-Time Extension of the Completion Time of Required Action B.1 L-PI-21-006, License Amendment Request to Revise Technical Specification 3.3.1, Reactor Trip System (RTS) Instrumentation, to Incorporate Installed Bypass Test Capability for the Power Range RTS Functions2021-10-0202 October 2021 License Amendment Request to Revise Technical Specification 3.3.1, Reactor Trip System (RTS) Instrumentation, to Incorporate Installed Bypass Test Capability for the Power Range RTS Functions L-PI-21-032, Response to Request for Additional Information Amendment Request to Adopt TSTF-471 and 571-T for Prairie Island2021-09-30030 September 2021 Response to Request for Additional Information Amendment Request to Adopt TSTF-471 and 571-T for Prairie Island L-PI-21-016, Application for License Amendment to Implement 24-Month Operating Cycle2021-08-0606 August 2021 Application for License Amendment to Implement 24-Month Operating Cycle L-PI-21-027, 2020 10 CFR 50.46 LOCA Annual Report2021-06-28028 June 2021 2020 10 CFR 50.46 LOCA Annual Report L-PI-21-023, Independent Spent Fuel Storage Installation - 2020 Annual Radiological Environmental Monitoring Program Report2021-05-14014 May 2021 Independent Spent Fuel Storage Installation - 2020 Annual Radiological Environmental Monitoring Program Report L-PI-21-007, Application to Revise Technical Specifications to Adopt TSTF-471, Eliminate Use of the Term Core Alterations in Actions and Notes2021-04-19019 April 2021 Application to Revise Technical Specifications to Adopt TSTF-471, Eliminate Use of the Term Core Alterations in Actions and Notes L-PI-20-050, Request for a One-Time Exemption from 10 CFR 50, Appendix E, Biennial Emergency Preparedness Exercise Requirements, Due to COVID-19 Pandemic2020-10-0707 October 2020 Request for a One-Time Exemption from 10 CFR 50, Appendix E, Biennial Emergency Preparedness Exercise Requirements, Due to COVID-19 Pandemic L-PI-20-051, Supplement to Application to Revise Technical Specifications to Adopt TSTF-547, Clarification of Rod Position Requirements2020-09-28028 September 2020 Supplement to Application to Revise Technical Specifications to Adopt TSTF-547, Clarification of Rod Position Requirements L-PI-20-026, Response to Request for Additional Information: License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiativ2020-09-0101 September 2020 Response to Request for Additional Information: License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4 L-PI-20-035, = Request for Revision to Reactor Vessel Material Surveillance Capsule Removal Schedule2020-07-28028 July 2020 = Request for Revision to Reactor Vessel Material Surveillance Capsule Removal Schedule L-PI-20-023, Independent Spent Fuel Storage Installation, Response to Request for Additional Information: License Amendment Request to Expand the Storage Capacity of the Independent Spent Fuel Storage Installation (ISFSI)2020-06-10010 June 2020 Independent Spent Fuel Storage Installation, Response to Request for Additional Information: License Amendment Request to Expand the Storage Capacity of the Independent Spent Fuel Storage Installation (ISFSI) L-PI-20-014, Supplement to License Amendment Request: Expand the Storage Capacity of the Independent Spent Fuel Storage Installation (ISFSI2020-04-29029 April 2020 Supplement to License Amendment Request: Expand the Storage Capacity of the Independent Spent Fuel Storage Installation (ISFSI L-PI-20-004, License Amendment Request to Revise Technical Specifications (TS) to Remove Note I from Limiting Condition for Operating (LCO) 3.4.12 and LCO 3.4.132020-03-30030 March 2020 License Amendment Request to Revise Technical Specifications (TS) to Remove Note I from Limiting Condition for Operating (LCO) 3.4.12 and LCO 3.4.13 L-PI-20-001, License Amendment Request to Address Issues Identified in Westinghouse Nuclear Safety Advisory Letter NSAL-09-5, Revision 1, and NSAL-15-12020-01-29029 January 2020 License Amendment Request to Address Issues Identified in Westinghouse Nuclear Safety Advisory Letter NSAL-09-5, Revision 1, and NSAL-15-1 L-PI-19-041, Application to Revise Technical Specifications to Adopt TSTF-547, Clarification of Rod Position Requirements2019-12-23023 December 2019 Application to Revise Technical Specifications to Adopt TSTF-547, Clarification of Rod Position Requirements L-PI-19-031, License Amendment Request: Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2019-12-16016 December 2019 License Amendment Request: Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b L-PI-19-040, License Amendment Request: Revise Technical Specification 5.5.14 to Permanently Extend Containment Leakage Rate Test Frequency2019-10-0707 October 2019 License Amendment Request: Revise Technical Specification 5.5.14 to Permanently Extend Containment Leakage Rate Test Frequency L-PI-19-038, Submittal of Revised Pressure and Temperature Limits Report2019-09-19019 September 2019 Submittal of Revised Pressure and Temperature Limits Report L-PI-19-037, Response to Request for Additional Information: 10 CFR 50.55a Requests Nos. 1-RR-5-10 and 2-RR-5-10, Proposed Alternative to Reactor Vessel Inservice Inspection (ISI) Intervals2019-09-16016 September 2019 Response to Request for Additional Information: 10 CFR 50.55a Requests Nos. 1-RR-5-10 and 2-RR-5-10, Proposed Alternative to Reactor Vessel Inservice Inspection (ISI) Intervals L-PI-19-025, Request to Approve Site-Specific Probabilistic Risk Assessment (PRA) Model for Flowserve N-Seal Abeyance Seal and Dynamic Testing for the Prairie Island Nuclear Generating Plant (PINGP)2019-08-27027 August 2019 Request to Approve Site-Specific Probabilistic Risk Assessment (PRA) Model for Flowserve N-Seal Abeyance Seal and Dynamic Testing for the Prairie Island Nuclear Generating Plant (PINGP) L-PI-19-029, Supplement to Response to Request for Additional Information: Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components For...2019-08-0505 August 2019 Supplement to Response to Request for Additional Information: Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components For... L-PI-19-002, 10 CFR 50.55a Requests Nos. 1-RR-5-10 and 2-RR-5-10, Proposed Alternative to Reactor Vessel Inservice Inspection (ISI) Intervals for Prairie Island, Unit 1 and Unit 22019-06-13013 June 2019 10 CFR 50.55a Requests Nos. 1-RR-5-10 and 2-RR-5-10, Proposed Alternative to Reactor Vessel Inservice Inspection (ISI) Intervals for Prairie Island, Unit 1 and Unit 2 L-PI-19-014, Response to Request for Additional Information: Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors2019-04-29029 April 2019 Response to Request for Additional Information: Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors L-PI-19-003, Request for Revision to Reactor Vessel Material Surveillance Capsule Removal Schedule for Prairie Island Nuclear Generating Plant (PINGP)2019-02-0404 February 2019 Request for Revision to Reactor Vessel Material Surveillance Capsule Removal Schedule for Prairie Island Nuclear Generating Plant (PINGP) L-PI-19-006, Emergency License Amendment Request Regarding One-Time Extension for Technical Specification Completion Time Requirements2019-01-29029 January 2019 Emergency License Amendment Request Regarding One-Time Extension for Technical Specification Completion Time Requirements L-PI-19-005, Online Reference Portal for NRC Review of License Amendment Request to Implement 10 CFR 50.692019-01-15015 January 2019 Online Reference Portal for NRC Review of License Amendment Request to Implement 10 CFR 50.69 L-PI-18-063, Response to Request for Additional Information: Revise License Condition Associated with Implementation of NFPA 8052018-12-0606 December 2018 Response to Request for Additional Information: Revise License Condition Associated with Implementation of NFPA 805 2024-01-02
[Table view] |
Text
Xce l Energy@ Prairie Island Nuclear Generating Plant 1717 Wakonade Drive East Welch, MN 55089 August 26, 2013 L-PI-13-081 10 CFR 2.202 10 CFR 50.4 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Prairie Island Nuclear Generating Plant Units 1 and 2 Docket Numbers 50-282 and 50-306 Renewed Facility Operating License Nos. DPR-42 and DPR-60 Prairie Island's First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)
References:
- 1. NRC Order EA-12-051, "Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation," dated March 12, 2012 (ADAMS Accession No. ML12054A679).
- 2. NRC Interim Staff Guidance JLD-ISG- 2012-03, "Complian ce with Order EA-12-051, Reliable Spent Fuel Pool Instrumen tation," Revision 0, dated August 29, 2012 (ADAMS Accession No. ML12221A339).
- 3. NEI 12-02, "Industry Guidance for Compliance with NRC Order EA 051, 'To Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation,"' Revision 1, dated August 2012.
- 4. NSPM Letter to NRC, "Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)," dated October 29, 2012 (ADAMS Accession No. ML12305A313).
- 5. NSPM Letter to NRC, "Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order
Document Control Desk Page 2 Number EA-12-051)," dated February 26, 2013 (ADAMS Accession No. ML13064A268).
- 6. NSPM Letter to NRC, "Responses to Requests for Additional Information Regarding Prairie Island Nuclear Generating Plant's Overall Integrated Plan Submitted in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) (TAC Nos. MF0832 and MF0833)," dated August 6, 2013.
On March 12, 2012, the NRC staff issued Order EA-12-051, "Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation,"
(Reference 1) to all NRC power reactor licensees and holders of construction permits in active or deferred status. Reference 1 was immediately effective and directs Northern States Power Company, a Minnesota corporation (NSPM), doing business as Xcel Energy, to have a reliable indication of the water level in the spent fuel storage pool for Prairie Island Nuclear Generating Plant (PINGP) Units 1 and 2. Specific requirements are outlined in Attachment 2 of Reference 1.
Pursuant to Condition C of Section IV, Reference 1 required submission of an initial status report 60 days following issuance of the final interim staff guidance (ISG), an overall integrated plan, and status reports at six-month intervals following the submittal of the overall integrated plan. The ISG (Reference 2) endorses, with exceptions and clarifications, the methodologies described in industry guidance document, NEI 12-02, "Industry Guidance for Compliance with Order EA-12-051, 'To Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation,"' Revision 1 (Reference 3).
Reference 4 provided the PINGP initial 60-day status report regarding reliable spent fuel pool instrumentation. Reference 5 provided the overall integrated plan for PINGP.
Reference 6 provided the NSPM responses to NRC Requests for Additional Information (RAis) regarding the overall integrated plan for PINGP.
The purpose of this letter is to provide the first six-month status report pursuant to Section IV, Condition C.2 of Reference 1, which delineates the progress made in implementing the requirements of the Reference 1 Order. The enclosed report provides an update of milestone accomplishments since the overall integrated plan was submitted, including changes to the compliance method, schedule, or the need and basis for relief, if any.
Please contact Lynne Gunderson, Licensing Engineer, at 612-396-0173, if additional information or clarification is required.
Document Control Desk Page 3 This letter makes no new commitments and no revisions to existing commitments.
I declare under penalty of perjury that the foregoing is true and correct.
Executed on August 26, 2013.
ie:t~
Site Vice President, Prairie Island Nuclear Generating Plant Northern States Power Company - Minnesota Enclosure cc: Administrator, Region Ill, USNRC Director of Nuclear Reactor Regulation (NRR), USNRC Project Manager, Prairie Island Nuclear Generating Plant, USNRC Resident Inspector, Prairie Island Nuclear Generating Plant, USNRC
L-PI-13-081 NSPM Enclosure ENCLOSURE Prairie Island Nuclear Generating Plant Units 1 and 2 First Six-Month Status Report for Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation 1.0 Introduction The Nuclear Regulatory Commission (NRC) issued Order EA-12-051, "Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation," on March 12, 2012 (Reference 1). The Order requires licensees to have reliable indication of the water level in associated spent fuel pools capable of supporting identification of the following spent fuel pool water level conditions by trained personnel: (1) level that is adequate to support operation of the normal fuel pool cooling system, (2) level that is adequate to provide substantial radiation shielding for a person standing on the spent fuel pool operating deck, and (3) level where fuel remains covered and actions to implement make-up water addition should no longer be deferred. The Order required licensees to submit an overall integrated plan, including a description of how the requirements in Attachment 2 of the Order would be achieved. Northern States Power Company, a Minnesota corporation (NSPM), doing business as Xcel Energy, submitted the overall integrated plan (Reference 2) for the Prairie Island Nuclear Generating Plant (PINGP) Units 1 and 2, on February 26, 2013.
This Enclosure provides the PINGP Units 1 and 2 first six-month status report. This status report includes an update of milestone accomplishments since submittal of the overall integrated plan including any changes to the compliance method, schedule, or the need and basis for relief, if any.
2.0 Milestone Accomplishments The original milestone schedule, with target dates, was provided in Section 2.0 of Reference 2. The following milestones have been completed since the overall integrated plan was submitted and is current as of July 31, 2013.
- Select Instrument Vendor (instrument vendor was selected)
- Commence Engineering Design (design process has started) 3.0 Milestone Schedule Status The following table provides an update of the milestone schedule to support the overall integrated plan. This includes a brief milestone status and a revised target date if the Page 1 of 5
L-PI-13-081 NSPM Enclosure date has changed. The dates are planning dates subject to change as design and implementation details are developed.
Milestone Target Activity Status Revised Completion Target Date Completion Date Submit 60 Day Status Report October 2012 Complete Submit Overall Integrated Plan February 2013 Complete Select Instrument Vendor (Target 1st Quarter 2013 Complete date 1st Quarter 2013)
Submit First Six-month Status August 2013 Complete with Update this submittal Commence Engineering Design 3rd Quarter 2013 Complete (Design Started)
Submit Second Six-Month Status February 2014 Not Started Update Submit Third Six-Month Status August 2014 Not Started Update Submit Fourth Six-Month Status February 2015 Not Started Update (includes responses to Requests for Additional Information (RAis))
Commence Installation 2na Quarter Not Started 2015 Submit Fifth Six-Month Status August 2015 Not Started Update (includes responses to remaining RAis)
Reliable Spent Fuel Pool End of 2R29 Not Started Instrumentation Operational Submit Report that Full 1st Quarter Not Started Compliance is Achieved 2016 No target completion dates for milestones have been changed. Responses to NRC Requests for Additional Information (RAis) have been added to the fourth and fifth six-month status updates. Incorporation of the RAI responses into these status reports was discussed in Reference 3.
4.0 Proposed Changes to Compliance Method There are no changes proposed to the compliance method described in the overall integrated plan (Reference 2).
Page 2 of 5
L-PI-13-081 NSPM Enclosure 5.0 Need and Basis for Relief from the Requirements of the Order NSPM expects to comply with the Order implementation date and requirements and no relief is required at this time.
6.0 Open Items from Overall Integrated Plan and Draft Safety Evaluation NSPM did not identify any open items in the overall integrated plan for PINGP. The overall integrated plan did contain future actions to ensure compliance with the Order.
The future actions were identified internally and are being tracked through NSPM's corrective action program (CAP).
No draft Safety Evaluation has been issued as of July 31, 2013. Closure of the draft SE open items, when issued, will be tracked to closure in future status reports. NSPM did receive RAI (Reference 3) of which several responses were deferred to the fourth and fifth six-month status updates. The RAis are listed below in the draft Safety Evaluation Open Item Table as the responses are seen as necessary for NRC to complete review.
Draft Safety Evaluation Open Items Open Description Status Item Number 1 RAI-1, Levels of Required Monitoring: Not Started a) A detailed NPSH calculations will be completed as part of the design process. Any required changes to the proposed Level 1 to support NPSH will be provided with the February 2015 six-month status report.
c) An evaluation will also be performed to assess the radiological impact from stored equipment. The requested information will be provided with the February 2015 six-month status report.
2 RAI-2, Arrangement: Not Started The final component locations and cable routing will be available upon completion of the final design. The requested information will be provided with the February 2015 six-month status report.
Page 3 of 5
L-PI-13-081 NSPM Enclosure 3 RAI-3, Mounting (all RAI subparts): Not Started The requested information is not available at this time. The requested information will be provided with the February 2015 six-month status report.
4 RAI-4, Qualification (all RAI subparts): Not Started The requested information is not available at this time. The requested information will be provided with the February 2015 six-month status report.
5 RAI-5, Independence (all RAI subparts): Not Started The requested information is not available at this time. The requested information will be provided with the February 2015 six-month status report.
6 RAI-6, Power Supplies (all RAI subparts): Not Started The requested information is not available at this time. The requested information will be provided with the February 2015 six-month status report.
7 RAI-7, Accuracy: Not Started a) The requested information is not available at this time.
The requested information will be provided with the February 2015 six-month status report.
b) Setpoints will be determined following Prairie Island procedure EM 3.3.4.1, "Instrument Setpoint/Uncertainty Calculations". Determination of setpoints using this procedure is part of the NSPM design process. The requested information will be provided with the February 2015 six-month status report.
8 RAI-8, Testing (all RAI subparts): Not Started The requested information is not available at this time. The requested information will be provided with the February 2015 six-month status report.
Page 4 of 5
L-PI-13-081 NSPM Enclosure 9 RAI-9, Display (all RAI subparts): Not Started The requested information is not available at this time. The requested information will be provided with the February 2015 six-month status report.
10 RAI-1 0, Procedures (all RAI subparts): Not Started The requested information is not available at this time. The requested information will be provided with the August 2015 six-month status report.
11 RAI-11, Testing and Calibration (all RAI subparts): Not Started The requested information is not available at this time. The requested information will be provided with the August 2015 six-month status report.
7.0 Potential Draft Safety Evaluation Impacts There are no potential impacts to the draft Safety Evaluation identified at this time.
8.0 References
- 1. NRC Order EA-12-051, "Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation," dated March 12, 2012 (ADAMS Accession No. ML12054A679).
- 2. NSPM Letter to NRC, "Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)," dated February 26, 2013 (ADAMS Accession No. ML13064A268).
- 3. NSPM Letter to NRC, "Responses to Requests for Additional Information Regarding Prairie Island Nuclear Generating Plant's Overall Integrated Plan Submitted in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) (TAC Nos. MF0832 and MF0833)," dated August 6, 2013.
Page 5 of 5