August 26, 2013 Administrative Judge Administrative Judge William J. Froehlich, Chair Dr. William E. Kastenberg Atomic Safety and Licensing Board Atomic Safety and Licensing Board Mail Stop: T-3F23 Mail Stop: T-3F23 Washington, DC 20555-001 Washington, DC 20555-0001 Administrative Judge Dr. Michael F. Kennedy Atomic Safety and Licensing Board Mail Stop: T-3F23 Washington, DC 20555-0001 In the Matter of EXELON GENERATION COMPANY, LLC (Limerick Generating Station, Units 1 and 2)
Docket Nos. 50-352-LR/ 50-353-LR RE: Change to the Schedule for the Site-Specific Environmental Impact Statement
Dear Administrative Judges:
This letter informs the Board that the NRC Staff has updated the schedule for its environmental review regarding the license renewal application for the Limerick Generating Station. The attached letter from John W. Lubinski, Director, Division of License Renewal, Office of Nuclear Reactor Regulation, to Michael P. Gallagher, Vice President, License Renewal Projects, Exelon Generation Company, LLC, provides the updated schedule. The updated schedule indicates that the NRC Staff intends to publish the Final Supplemental Environmental Impact Statement for the Limerick Generating Station in January of 2014.
Sincerely, Signed (electronically) by Catherine E. Kanatas Counsel for NRC Staff U.S. Nuclear Regulatory Commission Office of the General Counsel Mail Stop - O-15D21 Washington, DC 20555 Telephone: (301) 415-2321 E-mail: catherine.kanatas@nrc.gov Date of signature: August 26, 2013
Attachment:
As Stated
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of )
)
EXELON GENERATION COMPANY, LLC ) 50-352-LR/ 50-353-LR
)
(Limerick Generating Station, Units 1 and 2) )
)
CERTIFICATE OF SERVICE I hereby certify that copies of the foregoing Letter Regarding Change to the Schedule for the Site-Specific Environmental Impact Statement in the above captioned proceeding have been served over the Electronic Information Exchange, the NRCs E-Filing System, this 26th day of August, 2013.
/Signed (electronically) by/
Catherine E. Kanatas Counsel for NRC Staff U.S. Nuclear Regulatory Commission Office of the General Counsel Mail Stop - O-15D21 Washington, DC 20555 Telephone: (301) 415-2321 E-mail: catherine.kanatas@nrc.gov Date of signature: August 26, 2013
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 August 15, 2013 Mr. Michael P. Gallagher Vice President, License Renewal Projects Exelon Generation Company, LLC 200 Exelon Way Kennett Square, PA 19348
SUBJECT:
SCHEDULE REVISION FOR THE ENVIRONMENTAL REVIEW OF THE LIMERICK GENERATING STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION
Dear Mr. Gallagher:
By letter dated June 22, 2011, Exelon Generation Company, LLC (Exelon) submitted an application pursuant to Title 10 of the Code of Federal Regulations Part 54 (1 0 CFR Part 54), to renew Operating Licenses NPF-39 and NPF-85 for Limerick Generating Station, Units 1 and 2 (LGS) for review by the U.S. Nuclear Regulatory Commission (NRC or the staff). This letter is to inform you of a change in the environmental review schedule for the LGS license renewal review.
Enclosed is the NRC staff's revised environmental review schedule for the LGS license renewal application. The schedule is being revised because the NRC staff requires the additional time to allow for the internal review of additional items related to the Supplemental Environmental Impact Statement (SEIS) in a manner which balances the internal workload across numerous ongoing reviews. The schedule has been updated to reflect a change in the date of the issuance of the final SEIS.
If you have any questions on the revised schedule, Ms. Leslie Perkins, Project Manager for the LGS LRA environmental review may be contacted by telephone at 301-415-2375 or by e-mail at Leslie. Perkins@nrc.gov.
Docket Nos. 50-352 and 50-353
Enclosure:
Revised environmental review schedule cc: Ustserv
- .. ML13205A119 OFFICE PM:DLR/RPB2 LA:DLR/RPB2* BC:DLR/RPB2 D:DLR NAME LPerkins YEdmonds ASimmons Jlubinski DATE 7/25/13 7/24/13 7/25/13 8/15/13 Letter to Mr. Michael Gallagher from J. Lubinski dated August 15, 2013
SUBJECT:
SCHEDULE REVISION FOR THE ENVIRONMENTAL REVIEW OF THE LIMERICK GENERATING STATION UNITS, 1 AND 2, LICENSE RENEWAL APPLICATION DISTRIBUTION:
E-MAIL:
PUBLIC RidsNrrDir Resource RidsNrrDirRpb1 Resource RidsNrrDirRpb2 Resource RidsNrrDirRarb Resource RidsNrrDirRapb Resource RidsNrrDirRasb Resource RidsNrrDirRerb Resource RidsNrrDirRpob Resource RidsNrrDraApla Resource LPerkins ASimmons RPiasse YDiaz-Sanabria REnnis, DORL CKanatas, OGC EDiPaolo, SRI NMcNamara, Rl DScrenci, Rl NSheehan, Rl
LIMERICK GENERATING STATION, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION UPDATED ENVIRONMENTAL REVIEW SCHEDULE Schedule Actual Milestones Date Date Receive license renewal application (LRA) 06/22/11 06/22/11 Publish Federal Register Notice (FRN) - LRA receipt and 07/2011 07/26/11 availability Publish FRN - LRA acceptability, environmental seeping period, 08/2011 08/24/11 and opportunity for hearing Publish FRN - intent to conduct environmental seeping 08/2011 08/26/11 Public Meeting - license renewal process and environmental 09/22/11 09/22/11 seeping Audit - seeping and screening methodology 09/19-23/11 09/19-23/11 Deadline for filing hearing requests and petitions for intervention 10/24/11 10/24/11 Environmental seeping periods ends 10/28/11 10/28/11 Audit -aging management programs (AMPs) 10/03-14/11 10/03-14/11 Audit - environmental 11/07-10/11 11/07-10/11 Inspection - seeping, screening, and AMPs 06/04-08/12 06/04-08/12 06/18-22/12 06/18-22/12 Issue safety evaluation report (SER) with open item(s) 07/2012 07/31/12 Issue draft supplemental environmental impact statement (SEIS) 04/2013 04/30/13 Publish FRN - draft SEIS available for comments 04/2013 05/10/13 ACRS subcommittee meeting on SER with open item(s) 09/2012 09/05/12 Public Meeting- draft SEIS meeting 05/2013 05/23/13 End of comment period for the draft SEIS 06/2013 06/27/13 Issue final SER 01/2013 01/10/13 ACRS full committee meeting on SER 02/2013 02/04/13 Issue final SEIS 01/2014 U.S. Environmental Protection Agency FRN-availability of final 01/2014 SEIS NRR decision TBD
- To be determined (TBD)
ENCLOSURE