NL-13-1601, Joseph M. Farley, Units 1 and 2, Evacuation Time Estimate Update

From kanterella
(Redirected from ML13214A045)
Jump to navigation Jump to search
Joseph M. Farley, Units 1 and 2, Evacuation Time Estimate Update
ML13214A045
Person / Time
Site: Farley  Southern Nuclear icon.png
Issue date: 07/31/2013
From: Pierce C R
Southern Nuclear Operating Co, Southern Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NL-13-1601
Download: ML13214A045 (2)


Text

Charles R. Pierce Southern Nuclear Regulatory Affais Director Operating Company, Inc.40 Inverness Center Parkway Post Offiwe Box 1295 Birmingham, Alabama 35201 Tel 205.992.7872 Fax 205.992.7601 July 31, 2013 SOUTHERN COMPANY Docket Nos.: 50-348 NL-13-1601 50-364 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C. 20555-0001 Joseph M. Farley Nuclear Plant -Units 1 and 2 Evacuation Time Estimate Update Ladies and Gentlemen:

By letter dated December 7, 2012 (ML1 2346A41 1), and as updated by letter dated March 28, 2013 (ML13088A036), Southern Nuclear Operating Company (SNC) submitted the Joseph M. Farley Nuclear Plant (FNP), Units 1 and 2, Evacuation Time Estimate (ETE) Update. Based upon further discussion between SNC and the Nuclear Regulatory Commission (NRC), SNC is revising the ETE Update to more closely align with the guidance provided in NUREG/CR-7002, Criteria for Development of Evacuation Time Estimate Studies.Specifically, the assumptions utilized for the ETE have been modified to be consistent with the assumptions provided in NUREG/CR-7002.

Based on the revised assumptions, the existing evacuation strategy remains functional.

The Enclosure provided in this letter supersedes the Enclosures provided in letters dated December 7, 2012 and March 28, 2013 in their entirety.This letter contains no NRC commitments.

If you have any questions, please contact Ken McElroy at (205) 992-7369.Sincerely, C.R. Pierce Regulatory Affairs Director CRP/RMJ/

Enclosure:

Evacuation Time Estimate for the Joseph M. Farley Nuclear Plant U. S. Nuclear Regulatory Commission NL-13-1601 Page 2 cc: Southern Nuclear Operating Company Mr. S. E. Kuczynski, Chairman, President

& CEO Mr. D. G. Bost, Executive Vice President

& Chief Nuclear Officer Mr. T. A. Lynch, Vice President

-Farley Mr. B. L. Ivey, Vice President

-Regulatory Affairs Mr. B. J. Adams, Vice President

-Fleet Operations Mrs. P. Reister, Fleet Emergency Planning Manager RTYPE: CFA04.054 U. S. Nuclear Regulatory Commission Mr. V. M. McCree, Regional Administrator Mr. R. E. Martin, NRR Project Manager -Farley Mr. P. K. Niebaum, Senior Resident -Farley Mr. J. R. Sowa, Senior Resident -Farley State of Alabama Mr. A. Faulkner, Director -Alabama Emergency Management Agency Ms. Z. Darby -Acting Planning Section Chief State of Georgia Mr. C. English, Director -Georgia Emergency Management Agency Mr. S. Clark, Radiological Emergency Preparedness Program Director Houston County Mr. S. Carlise, Houston County EMA Director