Response to NRC 10CFR50.54(f) Request for Information Regarding Near-Term Task Force Recommendation 2.3, Seismic Walkdown Report Update
ML13213A195
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 07/13/2013
From: Kiley M
Florida Power & Light Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
Shared Package
ML13213A193 List:
References
L-2013-198
Download: ML13213A195 (3)


Text

0 IPL. L-2013-198 10 CFR 50.54(f)July 13, 2013 U. S. Nuclear Regulatory Commission Attn.: Document Control Desk Washington, D.C. 20555-0001 Turkey Point Units 3 and 4 Docket Nos. 50-250 and 50-251 Response to NRC 10 CFR 50.54(f) Request for Information Regarding Near-Term Task Force Recommendation 2.3, Turkey Point Seismic Walkdown Report Update

References:

1. NRC Letter, Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendations 2.1, 2.3, and 9.3, of the Near-Term Task Force Review of Insights from the Fukushima Dai-Ichi Accident; dated March 12, 2012, Accession No. ML12073A348.
2. NRC Letter to Nuclear Energy Institute, "Endorsement of Electric Power Research Institute (EPRI) Draft Report 1025286, 'Seismic Walkdown Guidance,' "dated May 31, 2012, Accession No. ML 12145A529.
3. M. Kiley (FPL) to U.S. Nuclear Regulatory Commission (L-2012-416), "Response to NRC 10 CFR 50.54(f) Request for Information Regarding Near-Term Task Force Recommendation 2.3, Seismic," Accession No. ML12349A162, dated November 27, 2012.In response to Nuclear Regulatory Commission (NRC) letter request for information pursuant to 10 CFR 50.54(f) regarding Recommendation 2.3 of the Near Term Task Force Review of Insights from the Fukushima Dai-Ichi Accident (Reference 1), Florida Power & Light Company (FPL) prepared in accordance with the approved EPRI guidance (Reference 2), and submitted to NRC the Turkey Point Units 3 and 4 Seismic Walkdown Report (Reference 3). The report identified the need for further Turkey Point seismic walkdown inspections for those deferred items that were inaccessible during the 180 day response period. These deferred seismic walkdown inspections have been completed.

The purpose of this letter is to provide the update to the Turkey Point Seismic Walkdown Report for those items that were identified as inaccessible during the 180-day response period. All affected sections of the report have been updated, including the current status of items that were entered into the Corrective Action Program (CAP). All changes and updates to the report are denoted using either revision bars or Revision 2 annotations.

The previously submitted walkdown forms have not been re-submitted, only the newly developed and completed walkdown forms are enclosed.The updated Seismic Walkdown Report for Turkey Point Units 3 and 4 is enclosed.Florida Power & Light Company 9760 SW 3 4 4 th St., Homestead, FL 33035 Turkey Point Nuclear Plant L-2013-198 Docket Nos. 50-250 and 50-251 Page 2 of 2 There were no adverse conditions identified as a result of these supplemental seismic walkdowns.

This letter contains no new Regulatory Commitments and no revision to existing Regulatory Commitments.

If you have any questions or require additional information, please contact Mr. Robert J.Tomonto, Licensing Manager, at (305) 246-7327.I declare under penalty of perjury that the foregoing is true and correct.Executed on July L7_ 2013.Sincerely, Michael Kiley Site Vice President Turkey Point Nuclear Plant Enclosure cc: USNRC Regional Administrator, Region II USNRC Project Manager, Turkey Point Nuclear Plant USNRC Senior Resident Inspector, Turkey Point Nuclear Plant Turkey Point Nuclear Plant Docket Nos. 50-250 and 50-251 L-2013-198 Enclosure Enclosure Seismic Walkdown Report in Response to the 50.54(f) Information Request Regarding Fukushima Near-Term Task Force Recommendations 2.3: Seismic for Turkey Point Unit 3, Rev. 2 134 pages Seismic Walkdown Report in Response to the 50.54(f) Information Request Regarding Fukushima Near-Term Task Force Recommendations 2.3: Seismic for Turkey Point Unit 4, Rev. 2 132 pages