Text
ReG(J~
UNITED STATES "1)oo~
NUCLEAR REGULATORY COMMISSION
(>
WASHINGTON, D.C. 20555-0001 o
~
~
f;;
August 15, 2013 "C"',.
~
~.,
..,.0 LICENSEE:
Entergy Nuclear Operations, Inc.
FACILITY:
Indian Point Nuclear Generating Unit Nos. 2 and 3 SUB~IECT:
SUMMARY
OF CONFERENCE CALL HELD ON JULY 19, 2013, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY NUCLEAR OPERATIONS, INC., CONCERNING DRAFT REQUEST FOR ADDITIONAL INFORMATION RELATED TO REACTOR VESSEL INTERNALS PROGRAM AND INSPECTION PLAN -INDIAN POINT NUCLEAR GENERATING UNIT NOS. 2AND 3 The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Entergy Nuclear Operations, Inc., held a telephone conference call on July 19, 2013, to discuss and clarify the staff's draft request for additional information (D-RAI) related to reactor vessel internals program and the reactor vessel internals inspection plan. The telephone conference call was useful in clarifying the intent of the staff's D-RAI.
During the telephone call, the staff informed the applicant that it will delete a portion of the request in D-RAI 11-B, number 5, because the staff's position, as described in the D-RAI, is that either the plant-specific analysis needs to be provided in a timely fashion or the applicant should inspect the components during the initial inspection. The RAI will be reworded as follows:
In the absence of an NRC-approved plant-specific analysis for the lower support column bodies, please explain how these components will maintain their intended function during the PEO, or why they should not be inspected during the initial inspections.
No other changes to the requests for additional information were needed.
The enclosure provides a listing of the participants.
The applicant had an opportunity to comment on this summary.
t<~~
L Kimberly J. Gr n, Sr. Mechanical Engineer Aging Management of Plant Systems Branch Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-247 and 50-286
Enclosure:
List of Participants cc: Listserv
- concurrence via e-mail OFFICE LA: DLRlRPB1*
PM: DLRJRAPB Be: RPB1:DLR LA: DLR/RPB1 PM: DLR/RAPB NAME YEdmonds KGreen YDiaz (ESayoc For)
YEdmonds KGreen DATE 8/8/13 8/15/13 8/15/13 8/8113 8/15/13
SUBJECT:
SUMMARY
OF CONFERENCE CALL HELD ON JULY 19, 2013, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY NUCLEAR OPERATIONS, INC., CONCERNING DRAFT REQUEST FOR ADDITIONAL INFORMATION RELATED TO REACTOR VESSEL INTERNALS PROGRAM AND INSPECTION PLAN - INDIAN POINT NUCLEAR GENERATING UNIT NOS. 2AND 3 DISTRIBUTION:
HARDCOPY:
DLRRF E-MAIL:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRapb Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsNrrDraAfpb Resource RidsNrrDeEeeb Resource RidsNrrDeEicb Resource RidsNrrDeEmcb Resource RidsNrrDeEpnb Resource RidsNrrDeEsgb Resource RidsNrrDeEvib Resouce RidsNrrDssSrxb Resource RidsNrrDssSbpb Resource RidsNrrDssScvb Resource RidsOgcMailCenter Resource YDiaz GMeyer, RI KGreen JTrapp, RI JPoehler DonaldJackson, RI SRosenberg DScrenci, RI OPA DPickett PCataldo, RI STurk,OGC NMcNamara, RI BMizuno, OGC BWelling, RI SBurnell, OPA KDunham, RI DMclntyre, OPA MCatts, RI EDacus,OCA SStewart, RI NSheehan, RI OPA AmiPatel, RI
TELEPHONE CONFERENCE CALL INDIAN POINT NUCLEAR GENERATING UNIT NOS. 2 AND 3 LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS JULY 19, 2013 PARTICIPANTS:
AFFILIATIONS:
Kim Green U.S. Nuclear Regulatory Commission (NRC)
Stacey Rosenberg NRC Jeff Poehler NRC Roger Waters Entergy Nuclear Operations, Inc. (Entergy)
Ron Williams Entergy John Curry Entergy Bob Dolansky Entergy Cheryl Boggess Westinghouse Randy Lott Westinghouse Karli Szweda Westinghouse Bradford Grimmel Westinghouse David Radonovich Westinghouse Michael Burke Westinghouse ENCLOSURE