ML13176A366

From kanterella
Jump to navigation Jump to search
Audit Proposed Questions
ML13176A366
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 06/21/2013
From:
Plant Licensing Branch 1
To:
Hughey J
Shared Package
ml13176a208 List:
References
Download: ML13176A366 (3)


Text

Preliminary questions for discussion at Hope Creek flooding walkdown audit 6/25-6/27/2013

  1. Background/issue description Question(s) 1 Page 38 of the Hope Creek walkdown report states the following: Penetrations in - Given that the design-basis flood elevation, exterior walls and slabs of the SSWS intake structure are protected against water including wave runup, at the south and west inflow up to Elevation 121 feet PSD for the north and east exterior walls and up to walls of the intake structure is 134.4 ft PSD Elevation 128.5 feet PSD for other exterior walls and slabs. and the penetrations protect against water intrusion to elevation 128.5 ft PSD, were the Page 17 of the Hope Creek walkdown report indicates that the maximum stillwater penetration seals identified as having negative elevation at the intake structure is 113.8 ft PSD and maximum wave runup is to margin?

elevations of 134.4 ft PSD (south and west SWIS walls) and 119.08 ft PSD (north - How were these issues dispositioned (and and east SWIS). using what criteria) as part of the CAP?

Notes: - Do these features represent deficiencies (per definition in NEI 12-07) or instances of small SSWS = station service water system SWIS = service water intake structure margin and significant consequences (per question 27 of the walkdown record form in NEI 12-07)?

- How was available physical margin (APM) measured for these features?

2 Page 38 of the Hope Creek walkdown report states: As described in HCGS UFSAR - What is the basis for the conclusion that the Section 2.4.2 [Ref. 13], the SSWS intake structure may be subjected to hurricane water levels will not exceed the top of the wall produced waves which could overtop the roof of the western portion of the at the intake screen at elev. 128.5 ft PSD in structure at Elevation 128 feet. However, worst case water levels will not exceed light of the wave-runup on the south and west the top of the wall at the air intake screens at Elevation 128.5 feet PSD. The SSWS walls to elev. 134.4 ft PSD?

intake structure air intake screens are located on an indented section of the intake structure exterior east wall. Waves overtopping the intake structure from the west will not have sufficient standing height to enter the air intakes at elevation 128.5 feet PSD. Therefore, flood water will not enter into the dry area of the SSWS intake structure.

Page 17 of the Hope Creek walkdown report indicates that the maximum stillwater elevation at the intake structure is 113.8 ft PSD and maximum wave runup is to elevations of 134.4 ft PSD (south and west SWIS walls) and 119.08 ft PSD (north and east SWIS).

3 Footnote 12 on pg. 48 of the Hope Creek walkdown report indicates the total - Does the site have seals that are unable to

Preliminary questions for discussion at Hope Creek flooding walkdown audit 6/25-6/27/2013 number of deficiencies and potential deficiencies includes features with withstand the required hydrostatic loads?

documentation insufficient for determining hydrostatic rating. - How were these issues dispositioned (and using what criteria) as part of the CAP?

Attachment A, p. 1 4 states the following: There are several penetration seals - Do these features represent deficiencies (per throughout the plant that do not have sufficient documentation to determine their definition in NEI 12-07) or instances of small hydrostatic rating. Further investigation is required to ensure the hydrostatic margin and significant consequences (per rating is sufficient to provide protection from an external flood. The same page of question 27 of the walkdown record form in the attachment also states the following: Existing plant documentation for three NEI 12-07)?

penetration seals is insufficient to determine the seals hydrostatic rating for external flood protection. These seals require further investigation.

4 Appendix D of NEI 12-07 states that the walkdown report should include the - What conditions listed in Attachment A following: Description of all deficiencies as determined by the CAP. Observations represent deficiencies and what conditions that are entered into the CAP and not dispositioned as deficiencies do not need to are awaiting disposition?

be reported. In addition, NEI 12-07 states: All flooding walkdown observations - How were these issues dispositioned (and identified as deficiencies by the Corrective Action Program (CAP) and other items using what criteria) as part of the CAP?

identified during the walkdowns, but awaiting final disposition by the CAP, must be - Do these features represent deficiencies (per reported to the NRC in the walkdown report. definition in NEI 12-07) or instances of small margin and significant consequences (per The Hope Creek walkdown report states Attachment A of this Report identifies question 27 of the walkdown record form in and provides a summary of the issues identified during the HCGS Flood Protection NEI 12-07)?

Walkdowns that have been dispositioned as a deficiency and corrected as well as those potential deficiencies that have not yet been dispositioned. However, based on the information in Attachment A, it is not clear which conditions have been dispositioned as deficiencies and which are awaiting disposition.

5 NEI 12-07 states that available physical margin (APM) should be evaluated for - Was APM computed for all barriers and flood protection features. For barriers and penetrations, NEI 12-07 provides penetration seals?

specific examples to demonstrate the calculation of APM: - How was APM evaluated/measured for barriers and penetration seals?

The top of the lowest flood barrier is a flood gate in the auxiliary building (a Category 1 structure). The top of the flood gate is at an elevation of 1014 ft.

If the river rises above this elevation, water will enter the building. The current licensing basis states that the maximum predicted flood level is elevation 1014 ft. Therefore the APM = 0 ft.

Cables from the switchyard enter the structure at site grade where the site grade is at elevation 400 ft. These cable penetrations are protected with

Preliminary questions for discussion at Hope Creek flooding walkdown audit 6/25-6/27/2013 seals guaranteed for a 40- foot static head. Therefore this structure is protected to elevation 440 ft (400 ft + 40 ft). Other flood protection features on the structure, such as door seals and sandbags, provide flood protection to elevation 445 ft. The current licensing basis states that the maximum predicted flood level at the site is elevation 430 ft. Therefore, the APM = 10 ft.

6 Question 27 of the walkdown record form in NEI 12-07 provides a format for - Were instances of small or negative margin documenting available physical margin (APM) and identification of small margin observed for flood protection features?

with potentially significant safety consequences (including observations related to - What features were identified as having small APM, affected equipment, and entry into the CAP). or negative margin?

- How were these issues dispositioned (and using what criteria) as part of the CAP?

- Were safety consequences of small margin evaluated and (if appropriate) entered into the CAP?

- Do these features represent deficiencies (per definition in NEI 12-07) or instances of small margin and significant consequences (per question 27 of the walkdown record form in NEI 12-07)?

7 NEI 12-07, Attachment A provides examples of inspection considerations. For - What features (e.g., seals) were associated penetration seals, the following consideration is included for wall, ceiling, and floor with these observations?

seals (e.g., penetration seals): Penetration sleeves, link seals, piping, and conduit - How were these issues dispositioned (and should have an absence of corrosion on the exposed steel surface. Conduit seal using what criteria) as part of the CAP?

material should have an absence of water stains below the penetrations. - Do these features represent deficiencies (per definition in NEI 12-07) or instances of small Attachment A to the Hope Creek walkdown report describes conditions in which margin and significant consequences (per cracking, missing seals, leakage (or signs of historical leakage), rust, calcification, question 27 of the walkdown record form in or seal degradation was observed. The report does not identify features types, but NEI 12-07)?

rather indicates a feature ID. - Was in-leakage (i.e., amount of water leaking through barriers) measured?