2-PTI-003A-03, Rev 000, Main Feedwater System Functional Test.
ML13162A312
Person / Time
Site: Watts Bar Tennessee Valley Authority icon.png
Issue date: 11/16/2012
From: Wooten J
Tennessee Valley Authority
To:
Office of Nuclear Reactor Regulation
References
2-PTI-003A-03, Rev 000
Download: ML13162A312 (371)


Text

WATTS BAR NUCLEAR PLANT UNIT 2 PREOPERATIONAL TEST TITLE: MAIN FEEDWATER SYSTEM FUNCTIONAL TEST Instruction No: 2-PTI-003A-03 Revision No: 0000 PREPARED BY: Joe Wooten DATE: I______/__

PRINT NAMIGNATURE REVIEWED BY: Ryan Lisa DATE: I1 -/i PRINT NKME I SIGNATURE INSTRUCTION APPROVAL JTG MEETING No: 2--/;I,- Da2>

JTG CHAIRMAN: 4, A.1 DATE: / -

_13/_z_

APPROVED BY: DATE: I Z/13l PREOIfERATIONAL STARTUP MANAGER TEST RESULTS APPROVAL JTG MEETING No:

JTG CHAIRMAN: DATE:

APPROVED BY: DATE:__ _ _ _ _ _

PREOPERATIONAL STARTUP MANAGER SM P-8.0, Administration of Preoperational Test instructions, Appendix B 12/07/2010

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 2 of 371 Revision Log Revision Affected or Change Effective Page Number Date Numbers Description of Revision/Change 0000 I ALL Original Issue

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 3 of 371 Table of Contents

1.0 INTRODUCTION

..................................................................................................... 7 1.1 TEST OBJECTIVES ................................................................................................. 7 1.2 SCOPE ......................................................................................................................... 7

2.0 REFERENCES

............................................................................................................. 7 2.1 Performance References ........................................................................................... 7 2.2 Developmental References ..................................................................................... 8 3.0 PRECAUTIONS AND LIMITATIONS .................................................................... 17 4.0 PREREQUISITE ACTIONS .................................................................................... 21 4.1 Preliminary Actions ................................................................................................. 21 4.2 Special Tools, Measuring and Test Equipment, Parts, and Supplies ...................... 30 4.3 Field Preparations .................................................................................................... 32 4.4 Approvals and Notifications ................................................................................... 44 5.0 ACCEPTANCE CRITERIA .................................................................................... 45 6.0 PERFORMANCE .................................................................................................... 51 6.1 2-FCV-3-205, STANDBY MAIN FEEDWATER PUMP DISCHARGE ISOL, Logic Test ...................................................................................................... 52 6.2 2-FCV-3-208, STANDBY MAIN FEEDWATER PUMP MIN FLOW, Logic T e st ............................................................................................................................. 55 6.3 2-FCV-3-204, STANDBY MAIN FEEDWATER PUMP NON-RETURN, Logic Test ................................................................................................................... 61 6.4 2-FCV-3-72,.MAIN FEEDWATER PUMP A REVERSE FLOW CHECK, Logic Test ................................................................................................................... 63 6.5 2-FCV-3-88, MAIN FEEDWATER PUMP B REVERSE FLOW CHECK, Logic Test ................................................................................................................... 65 6.6 2-FCV-3-3, MFW HEATER Al INLET, Logic Test .................................................. 67 6.7 2-FCV-3-1 0, MFW HEATER Al OUTLET, Logic Test ............................................ 72 6.8 2-FCV-3-13, MFW HEATER B1 INLET, Logic Test ................................................ 77 6.9 2-FCV-3-20, MFW HEATER B1 OUTLET, Logic Test ............................................ 82 6.10 2-FCV-3-23, MFW HEATER C1 INLET, Logic Test ................................................ 87

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 4 of 371 Table of Contents (continued) 6.11 2-FCV-3-30, MFW HEATER C1 OUTLET, Logic Test ........................................... 92 6.12 2-FCV-3-67, MAIN FEEDWATER PUMP A DISCHARGE ISOL, Logic T e st ............................................................................................................................. 96 6.13 2-FCV-3-81, MAIN FEEDWATER PUMP B DISCHARGE ISOL, Logic T e st ........................................................................................................................... 10 1 6.14 2-FCV-3-86, MAIN FEEDWATER PUMPS BYPASS ISOL, Logic Test .................... 105 6.15 2-FCV-3-195, MFW DEAERATION LINE CONTROL, Logic Test ............................ 109 6.16 2-FCV-3-70, MAIN FEEDWATER PUMP A RECIRC, Functional Test .......... 111 6.17 2-FCV-3-84, MAIN FEEDWATER PUMP B RECIRC, Functional Test ..................... 115 6.18 2-FIS-3-11A, Low Feedwater Flow Indicating Switch/Annunciator Test ................... 119 6.19 2-FIS-3-21A, Low Feedwater Flow Indicating Switch/Annunciator Test ................... 120 6.20 2-FIS-3-31A, Low Feedwater Flow Indicating Switch/Annunciator Test ................... 121 6.21 2-FIS-3-41A, Low Feedwater Flow Indicating Switch/Annunciator Test ................... 122 6.22 2-PCV-3-40, Deaeration Line Back Pressure Control ............................................... 123 6.23 Main Feedwater Pump Turbine 2A Auxiliary Equipment Functional Test ................. 126 6.24 Injection Water Pump 2A Control Logic Test ............................................................ 162 6.25 Injection Water Pump 2B Control Logic Test ........................................................... 166 6.26 MFPT 2A High Pressure, Low Pressure and Governor Valve Logic Test ........ 171 6.27 Main Feedwater Pump Turbine 2B Auxiliary Equipment Functional Test ................. 181 6.28 MFPT 2B High Pressure, Low Pressure and Governor Valve Logic Test ................. 217 6.29 SMFP Auxiliary Oil Pump 2A & 2B Logic Test .......................................................... 227 6.30 Standby Main Feedwater Pump Breaker Logic and Functional Test ........................ 233 6.31 Injection W ater Pumps 2A and 2B Operation ........................................................... 256 6.32 Standby Main Feedwater Pump (SMFP) Operation .................................................. 259 6.33 Main Feedwater Pump Turbine (MFPT) 2A Uncoupled Operation ........................... 263 6.34 Main Feedwater Pump (MFP) 2A Coupled Operation .............................................. 272 6.35 Main Feedwater Pump Turbine (MFPT) 2B Uncoupled Operation ........................... 277 6.36 Main Feedwater Pump (MFP) 2B Coupled Operation .............................................. 286 7.0 POST PERFORMANCE ACTIVITIES ...................................................................... 291

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 5 of 371 Table of Contents (continued) 8.0 RECORDS ................................................................................................................ 294 Appendix A: TEST PROCEDURESlINSTRUCTIONS REFERENCE R EV IEW ................................................................................................... 295 Appendix B: TEMPORARY CONDITION LOG ............................................................. 296 Appendix C: PERMANENT PLANT INSTRUMENTATION LOG .................................. 297 Appendix D: BACKGROUND CALCULATIONS .......................................................... 306 Table 1: COMPUTER POINT VERIFICATION LOG .............................................. 307 Table 2: M&TE HOOKUP LOCATIONS ................................................................. 312 Table 3: SMFP COMPUTER TRENDS ................................................................... 315 Data Sheet 1: SMFP INITIAL PUMP RUN (Prior to Start) ............................................. 316 Data Sheet 2: SMFP RECIRC FLOW ............................................................................. 318 Table 4: MFPT 2A COMPUTER TRENDS ............................................................. 320 Data Sheet 3: MFPT 2A INITIAL PUMP DATA (Prior to Start)

(Uncoupled) ............................................................................................. 322 Data Sheet 4: MFPT 2A @ 900 RPM (Uncoupled) .......................... 324 Data Sheet 5: MFPT 2A @ 1800 rpm (Uncoupled) ....................................................... 326 Data Sheet 6: MFPT 2A @ 2700 RPM (Uncoupled) ...................................................... 328 Data Sheet 7: MFPT 2A @ 3300 RPM (Uncoupled) ...................................................... 330 Data Sheet 8: MFPT 2A @ 4500 RPM (Uncoupled) ...................................................... 332 Data Sheet 9: MFPT 2A @ 5000 RPM (Uncoupled) ...................................................... 334 Data Sheet 10: MFPT 2A @ 5625 RPM (Uncoupled) ...................................................... 336 Data Sheet 11: MFP 2A INITIAL PUMP DATA (Prior to Start) (Coupled) ...................... 338 Data Sheet 12: MFP 2A RECIRC FLOW AT 2650 GPM (Coupled) ................................. 341

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 6 of 371 Table of Contents (continued)

Table 5: MFPT 2B COMPUTER TRENDS ............................................................. 344 Data Sheet 13: MFPT 2B INITIAL PUMP DATA (Prior to Start)

(Uncoupled) ............................................................................................. 346 Data Sheet 14: MFPT 2B @ 900 RPM (Uncoupled) ........................................................ 348 Data Sheet 15: MFPT 2B @ 1800 RPM (Uncoupled) ...................................................... 350 Data Sheet 16: MFPT 2B @ 2700 RPM (Uncoupled) ...................................................... 352 Data Sheet 17: MFPT 2B @ 3300 RPM (Uncoupled) ................................................ ..... 354 Data Sheet 18: MFPT 2B @ 4500 RPM (Uncoupled) ...................................................... 356 Data Sheet 19: MFPT 2B @ 5000 RPM (Uncoupled) ...................................................... 358 Data Sheet 20: MFPT 2B @ 5625 RPM (Uncoupled) ...................................................... 360 Data Sheet 21: MFP 2B INITIAL PUMP DATA (Prior to Start) (Coupled) ...................... 362 Data Sheet 22: MFP 2B RECIRC FLOW AT 2650 GPM (Coupled) ................................. 365 Data Sheet 23: Injection Water Pumps 2A and 2B Performance Data ......................... 368 Figure 1: STANDBY MAIN FEEDWATER PUMP ................................................... 369 Figure 2: MAIN FEEDWATER PUMPS 2A and 2B ................................................. 370 Figure 3:. Injection Water Pumps 2A and 2B .......................................................... 371

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 7 of 371

1.0 INTRODUCTION

1.1 TEST OBJECTIVES A. The minimum flow capability of the Main and Standby Feedwater Pumps meets or exceeds design requirements.

B. Automatic and manual controls, interlocks, and alarms operate properly in accordance with design.

1.2 SCOPE A. Tests are performed utilizing plant equipment under normal and simulated plant conditions.

B. Testing is performed within the normal/design operating parameters of the components covered by this PTI.

2.0 REFERENCES

2.1 Performance References A. 2-TOP-2&3.01, Condensate and Feedwater System B. 2-TOP-46.01, Main Feed Pump Turbine Overspeed Trip Mechanism Test C. N3C-945, Procedure for Evaluation and Qualification of Piping System Vibrations D. SMP-9.0, Conduct of Test E. SMP-15.0, Status and Control of Isolation Devices

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 8 of 371 2.2 Developmental References A. Unit 2 Final Safety Analysis Report - Amendment 109

1. Section 10.4.7
2. Table 14.2-1 Sheet 67 of 89 B. Drawings
1. Flow Diagrams
a. 2-47W801-1, Rev. 9, Main & Reheat Steam
b. 2-47W803-1, Rev. 12, Feedwater
c. 2-47W804-1, Rev. 12, Condensate
d. 2-47W805-2, Rev. 13, Low Pressure Heater Drains & Vents
2. Electrical
a. 2-45B640 Sheet 50, Rev. 0, Contact Development of Control and Instrument Switches
b. 2-45B640 Sheet 51, Rev. 0, Contact Development of Control and Instrument Switches
c. 2-45B640 Sheet 52, Rev. 0, Contact Development of Control and Instrument Switches
d. 2-45B640 Sheet 53, Rev. 0, Contact Development of Selector Switches and Pushbuttons
e. 2-45B640 Sheet 177, Rev. 0, Contact Development of Selector Switches and Pushbuttons
f. 2-45B640 Sheet 178, Rev. 0, Contact Development of Selector Switches and Pushbuttons
g. 2-45B640 Sheet 180, Rev. 0, Contact Development of Selector Switches and Pushbuttons
h. 2-45W721-2, Rev. 3, Wiring Diagrams 6900V Unit BDS 2C, & 2D Single Line, DRA 54026-4, Rev. 0

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 9 of 371 2.2 Developmental References (continued)

i. 2-45W600-3-1, Rev. 1, Wiring Diagrams Main and Auxiliary Feedwater System Schematic Diagram, DRA 53217-249, Rev. 0
j. 2-45W600-3-5, Rev. 1, Wiring Diagrams Main and Auxiliary Feedwater System Schematic Diagrams, DRA 53909-100, Rev. 0
k. 2-45W600-3-6, Rev. 3, Wiring Diagrams Main and Auxiliary Feedwater System Schematic Diagram, DRA 54144-90, Rev. 1 I. 2-45W600-3-7, Rev. 3, Wiring Diagrams Main and Auxiliary Feedwater Schematic Diagram, DRA 54144-91, Rev. I
m. 2-45W600-3-8, Rev. 2, Wiring Diagrams Main and Auxiliary Feedwater Schematic Diagram, DRA 54144-92, Rev. 1
n. 2-45W600-3-9, Rev. 2, Wiring Diagrams Main and Auxiliary Feedwater Schematic Diagram, DRA 54144-93, Rev. 0
o. 2-45W600-6-2, Rev. 2, Wiring Diagrams Heater Drain & Vents Schematic Diagram, DRA 55879-9, Rev. 0, DRA 54847-47, Rev. 0
p. 2-45W600-46-1, Rev. 3, Wiring Diagrams Feedwater Pump &

Turbines Schematic Diagram, DRA 54144-97, Rev. 0, DRA 54144-98, Rev. 0, DRA 53307-51, Rev. 0, DRA 53559-12, Rev. 0

q. 2-45W600-46-2, Rev. 1, Wiring Diagrams Feedwater Pump &

Turbines Schematic Diagram, DRA 53439-62, Rev. 1

r. 2-45W600-46-3, Rev. 4, Wiring Diagrams Feedwater Pump &

Turbines Schematic Diagram, DRA 53439-63, Rev. 2

s. 2-45W600-46-4, Rev. 2, Wiring Diagrams Feedwater Pump &

Turbines Schematic Diagram, DRA 53439-64, Rev. 1

t. 2-45W600-46-5, Rev. 5, Wiring Diagrams Feedwater Pump &

Turbines Schematic Diagram, DRA 53439-65, Rev. 0

u. 2-45W600-46-7, Rev. 5, Wiring Diagrams Feedwater Pump &

Turbines Schematic Diagram, Rev. 0, DRA 53439-66, Rev. 0, DRA 54180-14, Rev. 0

v. 2-45W600-46-8, Rev. 0, Wiring Diagrams Feedwater Pump &

Turbines Schematic Diagram, DRA 53559-14, Rev. 0, DRA 53307-65, Rev. 0, DRA 53439-67, Rev. 0

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 10 of 371 2.2 Developmental References (continued)

w. 2-45W600-47-8, Rev. 1, Wiring Diagram Turbo-Generator Auxiliaries Schematic Diagram, DRA 52378-40, Rev. 0, DRA 53939-155, Rev. 0, DRA 53939-156, Rev. 0, DRA 53939-226, Rev. 0, DRA 55879-6, Rev.

0

x. 2-45W600-57-2, Rev. 4, Wiring Diagram Separation & Misc AUX Relays Schematic Diagram, DRA 53580-492, Rev. 0
y. 2-45W600-57-26, Rev. 1, Wiring Diagram Separation & Misc AUX Relays Schematic Diagram, DRA 55879-5, Rev. 0
z. 2-45W600-57-28, Rev. 2, Wiring Diagrams Separation & Misc AUX Relays Schematic Diagram aa. 2-45W760-2-5, Rev. 5, Wiring Diagram Condensate System Schematic Diagram bb. 2-45W760-3-2, Rev. 4, Wiring Diagrams Main & AUX Feedwater System Schematic Diagram, DRA 53278-128, Rev. 0, DRA 53287-80, Rev. 1, DRA 54144-209, Rev. 0 cc. 2-45W760-3-3, Rev. 4, Wiring Diagrams Main & AUX Feedwater System Schematic Diagram dd. 2-45W760-3-9, Rev. 4, Wiring Diagrams Main & AUX Feedwater System Schematic Diagram ee. 2-45W760-3-10, Rev. 4, Wiring Diagrams Main & AUX Feedwater System Schematic Diagram ff. 2-45W760-3-1 1, Rev. 2, Wiring Diagrams Main & AUX Feedwater System Schematic Diagram gg. 2-45Wi60-6-3, Rev. 4, Wiring Diagram Heater Drains & Vents System Schematic Diagrams hh. 2-45W760-54-1, Rev. 1, Wiring Diagram Injection Water System Schematic Diagram ii. 45N2630-84, Rev. 0, Wiring Diagrams Miscellaneous Valves Connection Diagram, DRA 53876-322, Rev. 0, DRA 53939-118, Rev.

0, DRA 54026-25, Rev. 0, DRA 54144-180, Rev. 0 jj. 45N2691-4, Rev. 0, Wiring Diagrams Separation AUX Relay Panel 2-R-76 Connection Diagram, DRA 54144-122, Rev. 0

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page tI of 371 2.2 Developmental References (continued) kk. 2-45N2635-133, Rev. 0, Turbine Supervisory Panel 2-L-792, DRA-53559-10, Rev. 0 II. 2-45N2635-34, Rev. 0, Wiring Diagrams Local Instrument Panels Connection Diagram mm. 2-45N2635-91, Rev. 3, Wiring Diagrams Local Instrument Panels Connection Diagram nn. 2-45N2635-98, Rev. 0, Wiring Diagrams Local Instrument Panels Connection Diagram oo. 45W2642-1, Rev. 17, Wiring Diagrams Unit Control Board PNL 2-M-3 Connection Diagram, DRA 52360-5, Rev. 0, DRA 52360-6, Rev. 2, DRA 52361-75, Rev. 0, DRA 52343-42, Rev. 0, DRA 52378-21, Rev.

0, DRA 52378-22, Rev. 0, DRA 52690-88, Rev. 0 pp. 2-45N2642-2, Rev. 11, Wiring Diagrams Unit Control Board PNL 2-M-3 Connection Diagram, DRA 52360-7, Rev. 0, DRA 52360-8, Rev. 0, DRA 52360-5, Rev. 0, DRA 52378-23, Rev. 0, DRA 52378-24, Rev. 0 qq. 45W2642-6, Rev. 13, Wiring Diagrams Unit Control Board PNL 2-M-3 Connection Diagram, DRA 52360-15, Rev. 1, DRA 52360-16, Rev. 2, DRA 54928-27, Rev. 0, DRA 52343-45, Rev. 0, DRA 52378-27, Rev.

0, DRA 52690-20, Rev. 0, DRA 54144-173, Rev. 0, DRA 54144-174, Rev. 0 rr. 2-45N2676-5, Rev. 0, Wiring Diagrams Solid State Protection Sys Train A Connection Diagram ss. 45N2676-6, Rev. E, Wiring Diagrams Solid State Protection Sys Train A Connection Diagram tt. 45N2677-5, Rev. M, Wiring Diagrams Solid State Protection Sys Train B Connection Diagram uu. 45N2677-6, Rev. C, Wiring Diagrams Solid State Protection Sys Train B.Connection Diagram vv. 45N2677-7, Rev. M, Wiring Diagrams Solid State Protection Sys Train B Connection Diagram

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 12 of 371 2.2 Developmental References (continued) ww. 45W2673-5, Rev. 6, Wiring Diagram Balance of Plant Instrument Racks NON-DIV Connection Diagram, DRA 54144-177, Rev. 0, DRA 52378-366, Rev. 1 xx. 2-45W2673-6, Rev. 1, Wiring Diagrams BOP INST Racks, NON-DIV Connection Diagram yy. 2-45W2721-1, Rev. 0, Wiring Diagrams 6900V Unit Boards Connection Diagrams zz. 2-45W2721-2, Rev. 0, Wiring Diagrams 6900V Unit Boards Connection Diagrams aaa. 2-45W2721-5, Rev. 1, Wiring Diagrams 6900V Unit Boards Connection Diagrams bbb. 2-45B2752-2D, Rev. 2, Wiring Diagrams 480V TURB MOV BD 2A Conn Diag-COMPT 2D ccc. 2-45B2752-2E, Rev. 2, Wiring Diagrams 480V TURB MOV BD 2A Conn Diag-COMPT 2E ddd. 2-45B2752-3D, Rev. 1, Wiring Diagrams 480V TURB MOV BD 2A Conn Diag - COMPT 3D eee. 2-45B2752-3E, Rev. 1, Wiring Diagrams 480V TURB MOV BD 2A Conn Diag - COMPT 3E fff. 2-45B2752-10A, Rev. 1, Wiring Diagrams 480V TURB MOV BD 2A Conn Diag - COMPT 10A ggg.45W2752-5, Rev. 3, Wiring Diagrams 480V Turbine BLDG MOV BD 2A Connection Diagram, DRA 53336-205, Rev. 0 hhh. 2-45B2752-5C, Rev. 2, Wiring Diagrams 480V TURB MOV BD 2A Conn Diag-COMPT 5C iii. 45W2753-1, Rev. 2, Wiring Diagrams 480V TURB MOV BD 2B Connection Diagram, DRA 53336-208, Rev. 1 jjj. 2-45B2753-4E, Rev. 1, Wiring Diagrams 480V TURB MOV BD 2B Conn Diag-COMPT 4E kkk. 2-45B2753-5C, Rev. 0, Wiring Diagrams 480V TURB MOV BD 2B Conn Diag-COMPT 5C

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 13 of 371 2.2 Developmental References (continued)

III. 2-45B2753-7C, Rev. 1, Wiring Diagrams 480V TURB MOV BD 2B Conn Diag-COMPT 7C mmm. 2-45B2753-8A, Rev. 1, Wiring Diagrams 480V TURB MOV BD 2B Conn Diag-COMPT 8A nnn. 2-45B2753-8B, Rev. 1, Wiring Diagrams 480V TURB MOV BD 2B Conn Diag-COMPT 8B ooo. 2-45B2753-8C, Rev. 1, Wiring Diagrams 480V TURB MOV BD 2B Conn Diag-COMPT 8C ppp. 45W2754-2, Rev. 1, Wiring Diagram 480V TURB MOV BD 2C Connection Diagram, DRA 52866-346, Rev. 1, DRA 53203-32, Rev. 0, DRA 53322-29, Rev. 0, DRA 53336-211, Rev. 0, DRA 53336-212, Rev. 0, DRA 53336-213, Rev. 0, DRA 53336-214, Rev. 0, DRA 53939-147, Rev. 0 qqq. 2-45B2754-3B, Rev. 0, Wiring Diagrams 480V TURB MOV BD 2C Conn Diag-COMPT 3B rrr. 2-45W2614-1, Rev. 0, Wiring Diagram Main Feedwater Pump &

Turbine 2A Connection Diagram sss. 45W2614-2, Rev. 6, Wiring Diagram Main Feedwater Pump & Turbine 2A Connection Diagram, DRA 52322-197, Rev. 0, DRA 53439-21, Rev. 1 ttt. 45W2614-3, Rev. 4, Wiring Diagram Main Feedwater Pump & Turbine 2A Connection Diagram, DRA 52087-19, Rev. 0, DRA 53585-60, Rev.

0, DRA 54187-.11, Rev. 0, DRA 53439-23, Rev. 1 uuu. 45W2614-4, Rev. 3, Wiring Diagram Main Feedwater Pump & Turbine 2A Connection Diagram, DRA 52322-160, Rev. 0, DRA 53559-17, Rev. 0, DRA 53559-33, Rev. 0, DRA 53439-22, Rev. 2 vvv. 2-45W2614-5, Rev. 0, Wiring Diagram Main Feedwater Pump &

Turbine 2B Connection Diagram www. 45W2614-6, Rev. 6, Wiring Diagram Main Feedwater Pump &

Turbine 2B Connection Diagram, DRA 52322-198, Rev. 0, DRA 53439-25, Rev. 1

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 14 of 371 2.2 Developmental References (continued) xxx. 45W2614-7, Rev. 4, Wiring Diagram Main Feedwater Pump & Turbine 2B Connection Diagram, DRA 52322-153, Rev. 0, DRA 53559-115, Rev. 0, DRA 53559-16, Rev. 0, DRA 53439-26, Rev. 2 yyy. 45W2614-8, Rev. 4, Wiring Diagram Main Feedwater Pump & Turbine 2B Connection Diagram, DRA 53585-61, Rev. 0, DRA 54187-12, Rev.

0, DRA 53439-27, Rev. 1 zzz. 45N2687-3, Rev. J, Wiring Diagram Feedwater Aux Relay Panel 2-R-72 Connection Diagram, DCA 52376-12-167, Rev. 0 aaaa. 2-45B655-1, Rev. 0, Main Control Room Annunciator Inputs bbbb. 2-47A615-0, Rev. 1, Plant Computer Termination & I/O List cccc. 45N2635-17, Rev. 5, Wiring Diagrams Local Instrument Panels Connection Diagrams, Sheet 17 dddd. 2-45W753-1, Rev. 4, Wiring Diagram 480V Turbine MOV BD 2A Single Line eeee. 2-45W753-5, Rev. 3, Wiring Diagram 480V Turbine MOV BD 2A Single Line

3. Mechanical None
4. Logic/Control
a. 2-47W610-3-2, Rev. 2, Electrical Control Diagram Main and AUX Feedwater System, DRA 52319-11, Rev. 0, DRA 55180-42, Rev. 0, DRA 55347-60, Rev. 0, DRA 52738-540, Rev. 1
b. 2-47W610-3-4, Rev. 3, Electrical Control Diagram Main and AUX Feedwater System, DRA 53876-307, Rev. 0, DRA 52738-421, Rev. 0, DRA 53876-305, Rev. 0
c. 2-47W610-46-3, Rev. 4, Electrical Control Diagram Feedwater Control System, DRA 53559-155, Rev. 0, DRA 53439-1, Rev. 2
d. 2-47W610-46-4, Rev. 4, Electrical Control Diagram Feedwater Control System, DRA 53559-156, Rev. 0, DRA 53439-2, Rev. 6

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 15 of 371 2.2 Developmental References (continued)

e. 2-47W610-54-1, Rev. 2, Electrical Control Diagram Injection Water System
f. 2-47W611-3-1, Rev. 5, Electrical Logic Diagram Feedwater Pump Turbine AUX
g. 2-47W611-3-2, Rev. 6, Electrical Logic Diagram Feedwater System, DRA 53692-251, Rev. 0, DRA 54144-237, Rev. 0, DRA 54144-238, Rev. 0
h. 2-47W611-3-5, Rev. 3, Electrical Logic Diagram Feedwater System
i. 2-47W611-3-6, Rev. 3, Electrical Logic Diagram Feedwater System, DRA 53600-19, Rev. 0, DRA 53600-20, Rev. 0, DRA 53600-21, Rev.

0, DRA 53600-22, Rev. 0, DRA 53600-23, Rev. 0, DRA 52378-612, Rev. 0, DRA 52378-613, Rev. 0, DRA 53217-21, Rev. 0

5. Vendor Drawings
a. 0126D4010-3, Rev. L, Metal-Clad Switchgear Interconnection Diagram
b. 0126D04654, Rev. 905, Metal-Clad Switchgear Interconnection Diagram
c. 0126D4672-2, Rev. G, Metal-Clad Switchgear Interconnection Diagram
6. Vendor Manuals
a. VTM-W120-2094, Rev. 25, Vendor Manual for Westinghouse Reactor Feedwater Pump Drive Turbine
b. VTM-B580-0010, Rev. 11, Vendor Manual for Byron Jackson Turbine Driven Main Feedwater Pump
c. VTM-B580-0030, Rev. 42, Vendor Manual for Byron Jackson Condensate Booster, Condensate Hotwell, #3 & #7 Heater Drain and Standby Main Feed Pumps

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 16 of 371 2.2 Developmental References (continued)

C. Documents

1. WBN2-3A-4002, Rev. 4, Main Feedwater, Feedwater Control and Injection Water
2. BW/IP International Report GS-1150, Rev. 0, Minimum Flow Calculations Standby Main Feedwater Pump
3. 2-TSD-3A-3, Rev. 2, Main Feedwater System Functional Test

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 17 of 371 3.0 PRECAUTIONS AND LIMITATIONS A. Standard precautions shall be followed for working around energized electrical equipment in accordance with TVA Safety Procedure 1021.

B. Steps may be repeated if all components cannot be tested in a step. However, if the test has been exited, prerequisite steps must be re-verified and a Chronological Test Log (CTL) entry made.

C. Discrepancies between component ID tags and the description in a procedure/instruction do not require a Test Deficiency Notice (TDN), in accordance with SMP-14.0, if the UNIDs match, exclusive of place-keeping zeros and train designators (e.g. 2-HS-31-468 vs. 2-HS-031-0468) and the noun description is sufficient to identify the component. If the component label needs to be changed, a Tag Request Form (TR Card) should be processed in accordance with TI-12.14. Make an entry in the CTL and continue testing.

D. All wires removed/lifted from a terminal shall be identified and taped or covered with an insulator to prevent personnel or equipment hazard and possible spurious initiations. The wires should be grouped together and labeled with the work implementing document number that required them to be lifted if left unattended.

E. All open problems are to be tracked by a corrective action document and entered on the appropriate system punchlist.

F. Problems identified during the test shall be annotated on the CTL from SMP-9.0 including a description of the problem, the procedure step when/where the problem was identified, corrective action steps taken to resolve the problem, and the number of the corrective action document, if one was required.

G. Observe all Radiation Protection (RP) requirements when working in or near contaminated areas.

H. Ensure there are no adverse effects to the operation of Unit 1 structures, systems, or components.

I. Test personnel will coordinate with Unit 1 Operations when manipulating Unit 1 equipment if required.

J. System water chemistry is within system specific parameters especially for fluids supplied from external sources.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 18 of 371 3.0 PRECAUTIONS AND LIMITATIONS (continued)

K. During the performance of this procedure visual observation of piping and components is required. This includes steady state and transient operations with visual confirmation that vibration is not excessive.

L. If the vibration is determined to be excessive the Test Engineer shall initiate a TDN.

M. The Main Feedwater Pump (MFP) discharge pressure must be closely monitored when operating the MFPs under the following conditions which can cause water hammer problems in the feedwater piping:

Feedwater temperature less than 120OF Steam Generator pressure less than 900 PSIG.

Minimum recirculation flow (less than 1500 GPM for Standby Main Feedwater Pump (SMFP) and 2650 GPM at 3300 RPM).

N. The minimum required suction pressure is 46 PSIG for the SMFP and 100 PSIG for MFP 2A and B.

0. Monitor MFP discharge pressure when increasing Main Feedwater Pump Turbine (MFPT) speed. Per 2-TOP-2&3.01, the discharge pressure is to be kept less than or equal to 1185 PSIG. Short durations at pressures up to 1363 PSIG are acceptable, but care must be taken to prevent sudden pressure spikes from lifting #1 Heater Reliefs at 1650 psig.

P. Bearing oil pressure limits are:

SMFP: Normal at 20 PSIG; Alarm at 12 PSIG; Trip at 8 PSIG.

MFPs: Normal at 20 PSIG; Alarm at 12 PSIG; Trip at 10 PSIG.

MFPTs: Normal at 20 PSIG; Alarm at 15 PSIG; Trip at 10 PSIG.

Q. MFPT trips at _ 10 in. Hg vacuum via 2-PS-2-252A or B and the MFPT exhaust shell diaphragms rupture at 5 to 7 PSIG.

R. MFP 2A/2B and MFPT2A/2B Vibration detector range is 0 to .015 in.

displacement. The limits are: MFP alarm at 0.004 in., MFPT alarm at 0.003 in.

If the vibration is determined to be excessive the Test Engineer shall initiate a TDN.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 19 of 371 3.0 PRECAUTIONS AND LIMITATIONS (continued)

S. MFPTs trip if Normal or Reverse Thrust Bearing Wear results in shaft displacement along shaft axis from running zero center position to _ 0.010 in.

wear movement.

T. The MFPTs, MFPs, and SMFP Motor, Gear, and Pump Lubrication systems should be heated to approximately 70°F cold oil to the bearings and 140OF to 160OF hot oil leaving the bearings prior to turning on the cooling water to the bearing coolers. This will help limit startup vibration. Oil temperature alarms at 170 0 F. Oil cooling water inlet temperature should be less than 950 F.

U. Bearing oil circulation shall be maintained following shutdown for a minimum of four hours, to prevent heat damage to the bearings.

V. The Long Cycle Deaeration mode will only be used when the Steam Generator temperature is 200OF or less, the Condensate pressure is less than 350 PSIG, and the Steam Generator pressure is atmospheric or greater.

W. The Chemistry Lab should be notified prior to initiating Short Cycle Operation or Long Cycle Deaeration to ensure personnel are available for sampling.

X. The Condensate Demineralizer Auxiliary Unit Operator should be notified prior to starting any pumps that could affect the differential pressure across the Condensate Demineralizer, so action can be taken to prevent an automatic bypass on high differential pressure.

Y. Short Cycle Operation is not intended for long term operation. Due to high vibration problems its use must be minimized by proceeding to Long Cycle Deaeration as soon as reasonably possible.

Z. 2-PCV-3-40, MFW DEAERATION LINE BACK PRESSURE CONTROL, must be placed in service and 2-FCV-3-195, MFW DEAERATION LINE CONTROL, removed from service, prior to starting any pump in the Condensate/Feedwater Systems other than a Hotwell Pump, to prevent damage to 2-FCV-3-195, MFW DEAERATION LINE CONTROL.

AA. MFPT 2A & 2B critical speed occurs at approximately 2360 RPM. It should be quickly passed through without pausing at the critical speed. MFPT 2A & 2B critical speed occurs at 6500 RPM (calculated in air). It will be approached but not reached during these operations. The overspeed trip is set at 6006 RPM

+120 -0 RPM.

BB. MFP Turbine rotor seal, and/or bearing damage can occur if steam seals are applied with rotor at rest.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 20 of 371 3.0 PRECAUTIONS AND LIMITATIONS (continued)

CC. Admission of steam to seals may cause condenser damage if vacuum has not been established.

DD. Removal of steam seals before condenser vacuum is zero may damage seals due to high air in leakage through the seals.

EE. Damage to the Injection Water Pumps may occur if they are operated over four minutes without at least one MFW Pump receiving seal flow. The Injection Water Pumps do not have recirculation flow capability.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 21 of 371 Date 4.0 PREREQUISITE ACTIONS NOTE Prerequisite steps may be performed in any order unless otherwise stated and should be completed as close in time as practicable to the start of the instruction subsection to which they apply.

4.1 Preliminary Actions

[1] EVALUATE punch list items on Open Watts Bar Integrated Task Equipment List (WITEL), AND ENSURE that they will not adversely affect the test performance.

A. Subsection 6.1 B. Subsection 6.2 C. Subsection 6.3 D. Subsection 6.4 E. Subsection 6.5 F. Subsection 6.6 G. Subsection 6.7 H. Subsection 6.8 I. Subsection 6.9 J. Subsection 6.10 K. Subsection 6.11 L. Subsection 6.12 M. Subsection 6.13 N. Subsection 6.14

0. Subsection 6.15

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 22 of 371 Date 4.1 Preliminary Actions (continued)

P. Subsection 6.16 Q. Subsection 6.17 R. Subsection 6.18 S. Subsection 6.19 T. Subsection 6.20 U. Subsection 6.21 V. Subsection 6.22 W. Subsection 6.23 X. Subsection 6.24 Y. Subsection 6.25 Z. Subsection 6.26 AA. Subsection 6.27 BB. Subsection 6.28 CC. Subsection 6.29 DD. Subsection 6.30 EE. Subsection 6.31 FF. Subsection 6.32 GG. Subsection 6.33 HH. Subsection 6.34 II. Subsection 6.35 JJ. Subsection 6.36

[21 ENSURE changes to the references listed in Appendix A have been reviewed and determined NOT to adversely affect the test performance.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 23 of 371 Date 4.1 Preliminary Actions (continued)

[3] VERIFY current revisions and change paper for referenced drawings has been reviewed and determined NOT to adversely affect the test performance, AND ATTACH documentation of current drawing revision numbers and change paper that were reviewed to the data package.

[4] VERIFY the test/performance copy of this Preoperational Test Instruction (PTI) is the current revision including any change notices and as needed, each test person assisting in this test has the current revision including any change notices.

[5] OBTAIN copies of the applicable forms from the latest revision of SMP-9.0 AND ATTACH to this PTI for use during the performance of this PTI.

[6] ENSURE outstanding Design Change Notices (DCN's),

Engineering Document Construction Releases (EDCR's) or Temporary Alterations (TA's) do NOT adversely impact testing, AND ATTACH documentation of DCN's, EDCR's and TA's that were reviewed to the data package.

[7] ENSURE required Component Testing has been completed prior to start of test.

[8] ENSURE a review of outstanding Clearances has been coordinated with Operations for impact to the test performance, AND RECORD in Appendix B, Temporary Condition Log if required.

[9] VERIFY System cleanness as required for the performance of this test has been completed in accordance with SMP-7.0 for piping systems.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 24 of 371 Date 4.1 Preliminary Actions (continued)

[10] ENSURE the following procedures have been submitted to the Joint Test Group (JTG) for concurrence that they adequately satisfy the requirements of this procedure:

A. 2-TOP-2&3-01, JTG Meeting #

B. N3C-945, JTG Meeting #

C. 2-TOP-46.01, JTG Meeting #

[11] VERIFY plant instruments, listed on Appendix C, Permanent Plant Instrumentation Log, are placed in service and are within their calibration interval for the following: (N/A if not required)

A. Subsection 6.1 B. Subsection 6.2 C. Subsection 6.3 D. Subsection 6.4 E. Subsection 6.5 F. Subsection 6.6 G. Subsection 6.7 H. Subsection 6.8 I. Subsection 6.9 J. Subsection 6.10 K. Subsection 6.11 L. Subsection 6.12 M. Subsection 6.13 N. Subsection 6.14

0. Subsection 6.15 P. Subsection 6.16

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 25 of 371 Date 4.1 Preliminary Actions (continued)

Q. Subsection 6.17 R. Subsection 6.18 S. Subsection 6.19 T. Subsection 6.20 U. Subsection 6.21 V. Subsection 6.22 W. Subsection 6.23 X. Subsection 6.24 Y. Subsection 6.25 Z. Subsection 6.26 AA. Subsection 6.27 BB. Subsection 6.28 CC. Subsection 6.29 DD. Subsection 6.30 EE. Subsection 6.31 FF. Subsection 6.32 GG. Subsection 6.33 HH. Subsection 6.34 II. Subsection 6.35 JJ. Subsection 6.36

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 26 of 371 Date 4.1 Preliminary Actions (continued)

[12] VERIFY Measuring and Test Equipment (M&TE) required for test performance has been (as required) filled, vented, placed in service and recorded on M&TE Log for the following:

A. Subsection 6.2 B. Subsection 6.6 C. Subsection 6.7 D. Subsection 6.8 E. Subsection 6.9 F. Subsection 6.10 G. Subsection 6.11 H. Subsection 6.12 I. Subsection 6.13 J. Subsection 6.16 K. Subsection 6.17 L. Subsection 6.22 M. Subsection 6.26 N. Subsection 6.28

0. Subsection 6.30 P. Subsection 6.31 Q. Subsection 6.32 R. Subsection 6.33 S. Subsection 6.34 T. Subsection 6.35 U. Subsection 6.36

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 27 of 371 Date 4.1 Preliminary Actions (continued)

[13] VERIFY M&TE calibration due dates will support the completion of this test performance.

[14] ENSURE the Plant Computer is available and the computer points listed on Table 1, Computer Point Verification Log, are active and the description and status for each computer point has been verified (as needed).

[15] ENSURE System 55, Annunciator and Sequential Events Recording System applicable TBK switches are ON, the applicable Master Switches are ON, and the window software input(s) are ENABLED for the following Annunciator windows (as needed):

A. 2-XA-55-3A/49-E (SubSections 6.23, 6.27)

B. 2-XA-55-3B/51-A (SubSections 6.23, 6.27)

C. 2-XA-55-3B/51-B (SubSections 6.23, 6.27)

D. 2-XA-55-3B/51-C (SubSections 6.23, 6.27)

E. 2-XA-55-3B/51-D (SubSections 6.23, 6.27)

F. 2-XA-55-3B/52-A (SubSections 6.23, 6.27)

G. 2-XA-55-3B/52-B (SubSections 6.23, 6.27)

H. 2-XA-55-3B/52-C (SubSections 6.23, 6.27)

I. 2-XA-55-3B/53-A (SubSections 6.23, 6.27)

J. 2-XA-55-3B/53-B (SubSections 6.23, 6.27)

K. 2-XA-55-3B/53-C (SubSections 6.23, 6.27)

L. 2-XA-55-3B/53-D (SubSections 6.23, 6.27)

M. 2-XA-55-3B/54-A (SubSections 6.23, 6.27)

N. 2-XA-55-3B/54-B (SubSections 6.23, 6.27)

0. 2-XA-55-3B/54-C (SubSections 6.23, 6.27)

P. 2-XA-55-3B/54-D (SubSections 6.23, 6.27)

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 28 of 371 Date 4.1 Preliminary Actions (continued)

Q. 2-XA-55-3B/55-A (SubSections 6.23, 6.27)

R. 2-XA-55-3B/55-B (SubSections 6.23, 6.27)

S. 2-XA-55-3B/55-C (SubSections 6.23, 6.27)

T. 2-XA-55-3B/55-D (SubSections 6.23, 6.27)

U. 2-XA-55-3B/55-E (SubSection 6.1)

V. 2-XA-55-3B/56-A (SubSections 6.23, 6.27)

W. 2-XA-55-3B/56-B (SubSections 6.23, 6.27)

X. 2-XA-55-3B/56-C (SubSections 6.23, 6.27)

Y. 2-XA-55-2C/36-A (SubSections 6.6, 6.7)

Z. 2-XA-55-2C/37-A (SubSections 6.8, 6.9)

AA. 2-XA-55-2C/38-A (SubSections 6.10, 6.11)

BB. 2-XA-55-3C/57-A (SubSection 6.16)

CC. 2-XA-55-3C/58-A (SubSection 6.17)

DD. 2-XA-55-3C/59-A (SubSection 6.2)

EE. 2-XA-55-3C/59-C (SubSections 6.18, 6.19, 6.20, 6.21)

FF. 2-XA-55-2A/28-E (SubSections 6.23, 6.27)

GG. 2-XA-55-1 B/14-D (SubSection 6.30)

HH. 2-XA-55-1B/14-E (SubSection 6.30)

II. 2-XA-55-2C/41-E (SubSections 6.24, 6.25)

JJ. 2-XA-55-3B/50-E (SubSections 6.24, 6.25)

KK. 2-XA-55-3B/51-E (SubSections 6.24, 6.25)

[16] ENSURE components contained within the boundaries of this test are under the jurisdictional control of Preoperational Startup Engineering (PSE) and/or Plant Operations.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 29 of 371 Date 4.1 Preliminary Actions (continued)

[17] VERIFY the SMFP lube oil system is ready to support testing of the SMFP oil pumps with the oil reservoir filled to normal operation level. (Subsections 6.29, 6.30 and 6.32)

[18] VERIFY the MFPT 2A and 2B Lube Oil Systems are ready to support testing of the MFPT oil pumps with oil reservoirs filled to normal operating level. (Subsections 6.23 thru 6.28 and 6.33 thru 6.36)

[19] VERIFY the following systems are in service, or operable, to the extent necessary to perform this test:

A. System 001, Main Steam - Provide steam for MFPT 2A and 2B. (Subsections 6.33 thru 6.36)

B. System 037, Gland Seal Water - Provide gland seal steam to MFPT 2A and 2B. (Subsections 6.33 thru 6.36)

C. System 002, Condensate System - Provide feedwater.

(Subsections 6.32, 6.34, and 6.36)

D. System 027, Condenser Circulating Water - Provide condenser cooling. (Subsections 6.33 thru 6.36)

E. System 014, Condensate Demineralizer - Provide good water quality.

F. System 054, Injection Water - Provide SMFP, MFP 2A

& 2B injection water. (Subsections 6.31, 6.32, 6.33 thru 6.36)

G. System 032, Control Air - Provide control air to all AOVs.

H. System 055, Plant Annunciator - Feedwater system alarms.

I. System 209, 480V Turbine Building MOV Power.

J. System 235, 120V AC Vital Power.

K. System 236, 125V DC Vital Power.

L. System 237, AC Instrument Power.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 30 of 371 Date 4.1 Preliminary Actions (continued)

[20] PERFORM a pretest walkdown on equipment to be tested to ensure no conditions exist that will impact test performance.

[21] CONDUCT a pretest briefing with Test and Operations personnel in accordance with SMP-9.0.

[22] ENSURE communications are available for areas where testing is to be conducted.

.[23] REVIEW preventive maintenance for system/components covered by this test, AND VERIFY no conditions exist that will impact test performance.

4.2 Special Tools, Measuring and Test Equipment, Parts, and Supplies Test Equipment

[1] ENSURE the following equipment is available. _

  • Jumpers, (Grabber Type with Insulated Boots)
  • Jumpers, (Momentary hand-held contact)

[2] ENSURE the following M&TE or equivalent is available and within their calibration due dates, and RECORD the M&TE data on SMP-9.0, Measuring and Test equipment (M&TE) Log.

A. Ultrasonic Flowmeter, 0-10,000 GPM, (2% of reading). (Subsections 6.32, 6.34 and 6.36)

B. Ultrasonic Flowmeter, 0-1000 GPM, (2% of reading).

C. Three 0-300 PSIG, pressure gage, (+/-0.6 PSIG). (Subsections 6.32, 6.34 and 6.36)

D. Three 0-200 PSIG, pressure gage, (+/-0.6 PSIG). (Subsection 6.31)

E. Three 0-2000 PSIG, pressure gage, (+/-4 PSIG). (Subsections 6.32, 6.34 and 6.36)

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 31 of 371 Date 4.2 Special Tools, Measuring and Test Equipment, Parts, and Supplies (continued)

F. 50-500 0 F, Thermometer, Digital, (+/-2.4 0F). (Subsections 6.31 thru 6.36)

NOTE The vibration M&TE may be substituted as deemed necessary by the Vibration Group.

G. Vibration Analyzer, Frequencies up to 5000Hz, Accuracy +/-2%.

(Subsections 6.31 thru 6.36)

H. Strobe Tachometer, 20Hz-400Hz, RPM, (+/-1.2% of reading).

(Subsections 6.32 thru 6.36)

I. 0-1500 PSIG, pressure gage, (+/-9 PSIG). (Subsection 6.22)

J. 0-100" H20, pressure gage, (+/-1.2% of range). (Subsections 6.2, 6.16 and 6.17)

K. 0-1000 VAC/DC, Multimeter, (+/-2% of reading). (Subsections 6.6 thru 6.13, 6.26, 6.28, 6.30, and 6.32)

[3] The following are available:

A. Test Switch B. Test Rig and Hand Pump C. Nitrogen Bottle - 2500 psi

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 32 of 371 Date 4.3 Field Preparations

[1] ENSURE scaffolding and platforms have been erected, as needed. NA if not necessary.

NOTE The following step will ensure that SSPS trips will not affect the Hot Functional Test.

Several of the tests will send trip signals from the FW pumps.

[2] VERIFY plastic screw and washers at the field terminals listed:

Panel 2-R-48, SOLID STATE PROTECTION SYSTEM TRAIN A OUTPUT CABINET:

TB634-1 MFPT 2A trip CV TB634-2 MFPT 2A trip CV TB634-3 MFPT 2B trip CV TB634-4 MFPT 2B trip CV TB635-1 Cond/CBP/SBFP trip CV TB635-2 Cond/CBP/SBFP trip CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 33 of 371 Date 4.3 Field Preparations (continued)

Panel 2-R-51, SOLID STATE PROTECTION SYSTEM TRAIN B OUTPUT CABINET:

TB634-1 MFPT 2A trip CV TB634-2 MFPT 2A trip CV TB634-3 MFPT 2B trip CV TB634-4 MFPT 2B trip CV TB635-1 Cond/CBP/SBFP trip CV TB635-2 Cond/CBP/SBFP trip CV NOTE The following prerequisites, 4.3[3] and 4.3[4] are applicable for Subsections 6.23 and 6.27.

[3] LIFT lead TTAP (BK) of cable 2SG5, from Terminal Point 196 at Panel 2-L-275 to simulate MFP 2A Suction Valve Open interlock. (Dwg 2-45W2614-1) (Subsection 6.23)

CV

[4] LIFT lead TTBP (BK) of cable 2SG25 from Terminal Point 196 at Panel 2-L-276 to simulate MFP 2B Suction Valve Open interlock. (Dwg 2-45W2614-5) (Subsection 6.27)

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 34 of 371 Date 4.3 Field Preparations (continued)

NOTE The following prerequisites, 4.3[5] thru 4.3181, are applicable for Subsections 6.18 thru 6.21.

[5] LIFT lead 1 BAP (Red) from Terminal AA3, Section A of Panel 2-L-565, Steam Generator Water Hammer Protection.

(Dwg 2-45N2635-98) (Subsection 6.18)

CV

[6] LIFT lead 2BAP (Red) from Terminal CC3, Section A of Panel 2-L-565, Steam Generator Water Hammer Protection.

(Dwg 2-45N2635-98) (Subsection 6.19)

CV

[7] LIFT lead 3BAP (Red) from Terminal CC3, Section B of Panel 2-L-565, Steam Generator Water Hammer Protection.

(Dwg 2-45N2635-98) (Subsection 6.20)

CV

[8] LIFT lead 4BAP (Red) from Terminal AA3, Section C of Panel 2-L-565, Steam Generator Water Hammer Protection.

(Dwg 2-45N2635-98) (Subsection 6.21)

CV

[9] VERIFY 2-TOP-2&3.01 Attachment 2P, Condensate and Feedwater System Long Cycle Power Checklist, or the equivalent in a Work Order, is complete.

[10] VERIFY 2-TOP-2&3.01 Attachment 2V, Condensate and Feedwater System Long Cycle Valve Checklist, or the equivalent in a Work Order, is complete

[11] VERIFY that 2-TOP-2&3.01 Subsection 5.3, Long Cycle Deaeration, or the equivalent in a Work Order, is complete.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 35 of 371 Date 4.3 Field Preparations (continued)

[12] VERIFY the M&TE needed for the SMFP testing has been installed at the locations in Table 2, M&TE HOOKUP LOCATIONS, and is ready to support the SMFP.

[13] VERIFY operations personnel are available to support this test and have been briefed of testing responsibilities.

[14] VERIFY the Main Control Room (MCR) strip charts and computer trends per Table 3, SMFP Computer Trends, are available to monitor SMFP performance.

[15] VERIFY test support personnel are available to support this test section.

[16] NOTIFY the Chemistry Department of pending operation of the SMFP.

[17] VERIFY the Vibration Group has installed monitoring equipment and is standing by to monitor vibrations on the SMFP.

[18] INSTALL a jumper from Terminal 2D7C5 to Terminal 2D7C6 (external side), 2-JB-291-653 Terminal Block TA to simulate 2-FCV-3-205, STANDBY MAIN FEEDWATER PUMP DISCHARGE ISOL, being OPEN to prevent SMFP TRIPPING.

(Dwg 2-45W2721-5)

CV NOTE The following prerequisite is applicable for Subsection 6.32 thru 6.36 (SMFP & MFPT 2A

& 2B Operation).

[19] ENSURE all piping supports required for testing are installed and adjusted as required.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 36 of 371 Date 4.3 Field Preparations (continued)

NOTE The following prerequisites, 4.3[20] thru 4.3[34], are applicable for Subsection 6.33 (MFPT 2A uncoupled operation).

[20] VERIFY that Condensate and Feedwater System Long Cycle Power Checklist 2-TOP-2&3.01-2P, or the equivalent in a Work Order, has been completed.

[21] VERIFY that Condensate and Feedwater System Long Cycle Valve Checklist 2-TOP-2&3.01-2V, or the equivalent in a Work Order, has been completed.

[22] VERIFY that Subsection 5.1 of 2-TOP-2&3.01, Condensate

-and Feedwater System, Short Cycle Operation or the equivalent in a Work Order, has been completed.

[23] VERIFY that Subsection 5.3 of 2-TOP-2&3.01, Condensate and Feedwater System, Long Cycle Deaeration or the equivalent in a Work Order, is complete.

[24] VERIFY Operations personnel have been briefed and are available to support this pump run including performance of 2-TOP-46.01.

[25] VERIFY the MCR computer trends per Table 4, MFPT 2A Computer Trends, are available to monitor MFPT 2A operation.

[26] VERIFY that additional support personnel are available to support this test.

[27] VERIFY the Vibration Group is standing by to monitor vibrations on the MFPT 2A.

[28] VERIFY as a minimum, that communications have been established between the MFPT, the Main Control Room Operator, and the Test Engineer.

[29] VERIFY Chemistry personnel have been notified of impending pump runs and are available for sampling as required.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 37 of 371 Date 4.3 Field Preparations (continued)

[30] VERIFY the MFPT 2A has been on turning gear for at least 45 minutes per Subsection 5.10 of 2-TOP-2&3.01, Condensate and Feedwater System, MFP 2A Operation.

[31] LIFT Lead TTA1 (W) from Terminal 207 of Panel 2-L-275 to simulate MFP 2A Suction Valve 2-FCV-2-221 being OPEN, to prevent MFPT 2A trip. (Dwg 2-45W2614-1)

CV

[32] REMOVE the following fuses to prevent the MFPT 2A from tripping due to a Feedwater Isolation Signal via 2-FSV-46-9A, MFPT 2A TURB TRIP and 2-FSV-46-9B, MFPT 2A TURB TRIP:

A. Fuse Set C31 (0-FU-236-0001/C31A) (2- FSV-46-9A)

Battery Bd. III, Panel 4, Column C. (Dwg 2-45W600-46-7)

CV B. Fuse Set C31 (0-FU-236-0002/C31 B) (2-FSV-46-9B)

Battery Bd. IV, Panel 4, Column C. (Dwg 2-45W600-46-7)

CV

[33] VERIFY MFP 2A is uncoupled from the driver and couplings are protected to allow for uncoupled operation.

[34] VERIFY the MFPT LP and HP governor valves and hydraulic speed controllers have been adjusted prior to testing.

NOTE The following prerequisites are applicable for Subsection 6.31 (Injection Water Pumps 2A/2B Operation).

[35] VERIFY the M&TE has been installed at the locations identified in Table 2, M&TE Hookup Locations, and is ready to support the Injection Water Pumps 2A and 2B runs.

[36] VERIFY that the Injection Water System for the SMFP and MFP's has been put in service per Section 5.5 of 2-TOP-54.01.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 38 of 371 Date 4.3 Field Preparations (continued)

NOTE The following prerequisites, 4.3[37] thru 4.3[51], are applicable for Subsection 6.34 (MFP 2A coupled operation)

[37] LAND lead TTA1 (W) in Panel 2-L-275 to Terminal 207 to remove the simulated OPEN suction valve.

CV

[38] VERIFY that Condensate and Feedwater System Long Cycle Power Checklist 2-TOP-2&3.01-2P, or the equivalent in a Work Order, has been completed.

[39] VERIFY that Condensate and Feedwater System Long Cycle Valve Checklist 2-TOP-2&3.01-2V, or the equivalent in a Work Order, is complete.

[40] VERIFY that Subsection 5.1 of 2-TOP-2&3.01, Condensate and Feedwater System, Short Cycle Operation or the equivalent in a Work Order, is complete.

[41] VERIFY that Subsection 5.3 of 2-TOP-2&3.01, Condensate and Feedwater System, Long Cycle Deaeration or the equivalent in a Work Order, is complete.

[42] VERIFY the M&TE has been installed at the locations identified in Table 2, M&TE Hookup Locations, and is ready to support MFPT 2A run.

[43] VERIFY operations personnel have been briefed and are available to support this pump run.

[44] ENSURE the MCR strip charts and computer trends per Table 4, MFPT 2A Computer Trends, are available to monitor MFPT 2A operation.

[45] ENSURE that additional support personnel are available to support this test.

[46] ENSURE the Vibration Group is standing by to monitor vibrations on the MFPT 2A.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 39 of 371 Date 4.3 Field Preparations (continued)

[47] VERIFY that both Injection Water Pumps have been tested and are aligned for normal operation per 2-TOP-54.01.

[48] ENSURE as a minimum communications have been established between the MFPT, the Main Control Room Operator, and the Test Engineer.

[49] ENSURE Chemistry personnel have been notified of impending pump runs and are available for sampling as required.

[50] VERIFY the Main Feedwater Pump is coupled to the driver and is ready to support the MFPT 2A run. RECORD the work order number.

Work Order #

[51] VERIFY the MFPT 2A has been on turning gear for at least 45 minutes per Subsection 5.10 of 2-TOP-2&3.01, Condensate and Feedwater System, MFP 2A Operation or the equivalent in a Work Order.

NOTE The following prerequisites, 4.3[52] through 4.3166], are applicable for Subsection 6.35 (MFPT 2B uncoupled operation).

[52] ENSURE that Condensate and Feedwater System Long Cycle Power Checklist 2-TOP-2&3.01-2P, or the equivalent in a Work Order, has been completed.

[53] ENSURE that Condensate and Feedwater System Long Cycle Valve Checklist 2-TOP-2&3.01-2V, or the equivalent in a Work Order, has been completed.

[54] ENSURE that Subsection 5.1 of 2-TOP-2&3.01, Condensate and Feedwater System, Short Cycle Operation, or the equivalent in a Work Order, is complete.

[55] ENSURE that Subsection 5.3 of 2-TOP-2&3.01, Condensate and Feedwater System, Long Cycle Deaeration, or the equivalent in a Work Order, is complete.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 40 of 371 Date 4.3 Field Preparations (continued)

[56] ENSURE the MCR strip charts and computer trends per Table 5, MFPT 2B Computer Trends, are available to monitor MFPT 2B operation.

[57] ENSURE that additional support personnel are available to support this test.

[58] ENSURE the Vibration Group is standing by to monitor vibrations on the MFPT 2B.

[59] ENSURE as a minimum communications have been established between the MFPT, the Main Control Room Operator, and the Test Engineer.

[60] ENSURE Chemistry personnel have been notified of impending pump runs and are available for sampling as required.

[61] VERIFY the MFPT 2B has been on turning gear for at least 45 minutes per Subsection 5.10 of 2-TOP-2&3.01, Condensate and Feedwater System, MFP 2B operation.

[62] LIFT Lead TTB1 (W) in Panel 2-L-276 Terminal 207, to simulate MFP 2B Suction Valve 2-FCV-2-224 being OPEN, to prevent MFPT 2B trip. (Dwg 2-45W2614-5)

CV

[63] REMOVE the following fuses to prevent the MFPT 2B from tripping due to a Feedwater Isolation Signal via 2-FSV-46-36A, MFPT 2B TURB TRIP and 2-FSV-46-36B, MFPT 2B TURB TRIP:

A. Fuse Set C33 (0-FU-236-0001/C33A) (2- FSV-46-36A)

Battery Bd. Ill, Panel 4, Column C. (Dwg 2-45W600-46-7)

CV B. Fuse Set C16 (0-FU-236-0002/C16B) (2-FSV-46-36B)

Battery Bd. IV, Panel 4, Column C. (Dwg 2-45W600-46-7)

CV

[64] VERIFY MFP 2B is uncoupled from the driver and couplings are protected to allow for uncoupled operation.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 41 of 371 Date 4.3 Field Preparations (continued)

[65] VERIFY Operations personnel have been briefed and are available to support this turbine run.

[66] VERIFY the MFPT LP and HP governor valves and hydraulic speed controllers have been adjusted prior to testing.

NOTE The following prerequisites, 4.3[67] thru 4.3[80], are applicable for Subsection 6.36 (MFP 2B coupled operation).

[67] LAND lead TTB1 (W) in Panel 2-L-276 to Terminal 207, to remove the simulated OPEN suction valve.

CV

[68] VERIFY that Condensate and Feedwater System Long Cycle Power Checklist 2-TOP-2&3.01-2P, or the equivalent in a Work Order, is complete.

[69] VERIFY that Condensate and Feedwater System Long Cycle Valve Checklist 2-TOP-2&3.01-2V, or the equivalent in a Work Order, is complete.

[70] VERIFY that Subsection 5.1of 2-TOP-2&3.01, Condensate and Feedwater System, Short Cycle Operation, or the equivalent in a Work Order has been completed.

[71] VERIFY that Subsection 5.3 of 2-TOP-2&3.01, Condensate and Feedwater System, Long Cycle Deaeration or the equivalent in a Work Order is complete.

[72] VERIFY the M&TE has been installed at the locations identified in Table 2, M&TE Hookup Locations, and is ready to support MFPT 2B run.

[73] ENSURE Operations personnel have been briefed and are available to support this pump run.

[74] ENSURE the MCR strip charts and computer trends per Table 5, MFPT 2B Computer Trends, are available to monitor MFPT 2B operation.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 42 of 371 Date 4.3 Field Preparations (continued)

[75] ENSURE that additional support personnel are available to support this test.

[76] VERIFY the Main Feedwater Pump is coupled to the driver and is ready to support the MFPT 2B run. RECORD the work order number.

Work Order #

[77] ENSURE the Vibration Group is standing by to monitor vibrations on the MFPT 2B.

[78] ENSURE as a minimum communications have been established between the MFPT, the Main Control Room Operator and the Test Engineer.

.[79] ENSURE Chemistry personnel have been notified of impending pump runs and are available for sampling as required.

[80] VERIFY the MFPT 2B has been on turning gear for at least 45 minutes per Subsection 5.10 of 2-TOP-2&3.01, Condensate and Feedwater System, MFP 2B Operation or the equivalent in a Work Order.

NOTE The following prerequisites 4.3[81] thru 4.3[88], are applicable for Subsection 6.30 (SMFP 2 Breaker Functional).

[81] LIFT Field Wire 282A (BK) at Terminal GG-1 1 located in 6900V Unit Board 2D, Panel 7 to defeat the discharge flow interlock. (Dwg 2-45W760-3-2 or 0126D4672-2)

CV

[82] PLACE 2-HS-30-887, STANDBY MAIN FEEDWATER PUMP AREA COOLER, in the OFF position.

[83] LIFT vendor wire at Terminal 608 located in Panel 2-L-275 to defeat the Main Turbine runback. (Dwg 2-45W2614-3)

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 43 of 371 Date 4.3 Field Preparations (continued)

[84] LIFT vendor wire at Terminal 608 located in Panel 2-L-276 to defeat the Main Turbine runback. (Dwg 2-45W2614-7)

CV

[85] LIFT wire TTAP (BK) at Terminal 196 located in Panel 2-L-275 to defeat the MFWP 2A/2B Condenser Vacuum interlocks. (Dwg 2-45W2614-1)

CV

[86] LIFT wire TTBP (BK) at Terminal 196 located in Panel 2-L-276 to defeat the MFWP 2A/2B Condenser Vacuum interlocks. (Dwg 2-45W2614-5)

CV

[87] INSTALL a jumper across Terminal Board TB 630 Terminal Points 1 (9E04) and 2 (9E03) located in AUX RELAY PANEL 2-R-76 to simulate normal FWP injection water pressure. (Dwg 2-45N2691-4)

CV

[88] INSTALL a jumper across Terminal Board TB 631 Terminal Points 1 (6A04) and 2 (6A03) located in AUX RELAY PANEL 2-R-76 to simulate normal FWP injection water pressure. (Dwg 2-45N2691-4)

CV NOTE The following prerequisite, 4.3[89], is applicable for Subsection 6.1 (SMFP Discharge Isolation valve).

[89] INSTALL a jumper across Terminal Board CC, Terminal Points 1 (3C03) and 2 (3C02) at Panel 2-L-491 (708/1I 5-J) to simulate a normal injection water pressure.

(Dwg 2-45N2635-91)

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 44 of 371 Date 4.4 Approvals and Notifications

[1] OBTAIN permission of the Preoperational Startup Manager to start the test.

Preoperational Startup Manager Signature Date

[2] OBTAIN the Unit 2 Supervisor's (US/SRO) or Shift Manager's (SM) authorization.

U2 US/SROISM Signature Date

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 45 of 371 5.0 ACCEPTANCE CRITERIA NOTE The accuracy of the ultrasonic flowmeter should not be greater than 2%. This is used to calculate the error bands for each acceptance criteria listed below in Section A.

A. The minimum flow capability shall meet or exceed the following requirements:

1. Standby Main Feedwater Pump minimum flow is equal or greater than 1122 GPM (Step 6.32[111).
2. Main Feedwater Pump A minimum flow is equal to or greater than 2703 GPM at approximately 3300 RPM (Step 6.34[15]).
3. Main Feedwater Pump B minimum flow is equal to or greater than 2703 GPM at approximately 3300 RPM (Step 6.36[15]).
4. The Injection Water Pumps 2A and 2B flow are equal to or greater than 150 GPM at 272 feet TDH. (Step 6.31[6], 6.31[17])

B. Controls and Interlocks operate properly per the following:

1. 2-FCV-3-205, STANDBY MAIN FEEDWATER PUMP DISCHARGE ISOL, operates from the handswitches on the Local Control Panel 2-JB-291-653 and the local control lights indicate correct status (6.1[7]B, 6.117]C, 6.1[7]D, 6.1[11]).
2. 2-FCV-3-208, STANDBY MAIN FEEDWATER PUMP MIN FLOW, OPENS on a simulated SMFP Start (Step 6.2[5]), CLOSES on a simulated SMFP Trip (Step 6.2[24]) and will modulate open/closed as the flow changes (Step 6.2[20], 6.2[22]). This valve can also be opened using the local test switch when the SMFP is not in operation (Step 6.2[26]).
3. 2-FCV-3-204, STANDBY MAIN FEEDWATER PUMP NON-RETURN valve can be closed by its local control switch when the SMFP is in operation. It also will open when the SMFP starts. (Steps 6.3[6], 6.3[7])
4. 2-FCV-3-72, MAIN FEEDWATER PUMP A REVERSE FLOW CHECK valve and 2-FCV-3-88, MAIN FEEDWATER PUMP B REVERSE FLOW CHECK valve can be operated by their local test switches if their respective MFPT's are not tripped. Both valves will also close upon a turbine trip. (Steps 6.4[8], 6.4[9], 6.4[11], 6.5[8], 6.5[9], 6.5(11])

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 46 of 371 5.0 ACCEPTANCE CRITERIA (continued)

5. 2-FCV-3-86, MAIN FEEDWATER PUMPS BYPASS ISOL VLV and 2-FCV-3-195, MFW DEAERATION LINE CONTROL VLV can be operated from their respective local control panels. (Step 6.14[4], 6.14[5], 6.15[2], 6.15[3])
6. 2-FCV-3-3, MFW HEATER Al INLET, CLOSES on HIGH-HIGH Level in MFW Heater Al (Step 6.6[29]). This valve also can be operated from the local control station if the MFPT is not tripped (Step 6.6[5], 6.6[6], 6.6[14]).
7. 2-FCV-3-10, MFW HEATER Al OUTLET, CLOSES on HIGH-HIGH Level in MFW Heater Al (Step 6.7[29]). This valve also can be operated from the local control station if the MFPT is not tripped (Step 6.7[5], 6.7[6], 6.7[14]).
8. 2-FCV-3-13, MFW HEATER B1 INLET, CLOSES on HIGH-HIGH Level in MFW Heater B1 (Step 6.8[29]). This valve also can be operated from the local control station if the MFPT is not tripped (Step 6.8[5], 6.8[6], 6.8[14]).
9. 2-FCV-3-20, MFW HEATER B1 OUTLET, CLOSES on HIGH-HIGH Level in MFW Heater B1 (6.9[29]). This valve also can be operate from the local control station if the MFPT is not tripped (Step 6.9[5], 6.9[6], 6.9[14]).
10. 2-FCV-3-23, MFW HEATER C1 INLET, CLOSES on HIGH-HIGH Level in MFW Heater C1 (Step 6.10[29]). This valve also can be operated from the local control station if the MFPT is not tripped (Step 6.10[5], 6.10[6],

6.10[14]).

11. 2-FCV-3-30, MFW HEATER C1 OUTLET, CLOSES on HIGH-HIGH Level in MFW Heater C1 (Step 6.11[29]). This valve also can be operated from the local control station if the MFPT is not tripped (Step 6.11 [5], 6.11 [6],

6.11[14]).

12. 2-FCV-3-67, MAIN FEEDWATER PUMP A DISCHARGE ISOL can be operated from the local control station if the MFPT is not tripped (Step 6.12[19]).
13. 2-FCV-3-81, MAIN FEEDWATER PUMP B DISCHARGE ISOL can be operated from the local control station if the MFPT is not tripped (Step 6.13[19])
14. MFPT 2A Oil Reservoir Heater will start on a low temperature signal and shut off on a low level signal (Steps 6.23[94], 6.23[101], 6.23[103]).
15. MFPT 2A Standby Oil Pumps START on trip of operating pump (Steps 6.23[26] and 6.23134]).

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 47 of 371 5.0 ACCEPTANCE CRITERIA (continued)

16. Annunciator Windows 51-D, OIL FROM COOLER TEMP HI, 55-C #1 BEARING DRAIN OIL TEMP HI, 56-C #2 BEARING DRAIN OIL TEMP HI, and 54-C THRUST BEARING DRAIN OIL TEMP HI annunciate on increasing MFPT 2A bearing oil temperature. (Steps 6.23(169], 6.23[174],

6.23[179], 6.23[184])

17. Annunciator Window 55-B, annunciates on increasing MFPT 2A oil reservoir Hi/Low level and the local panel indicator lights light up. (Steps 6.23[158], 6.23[159], 6.23[164], 6.23[165])
18. MFPT 2A Turning Gear will trip whenever a bearing oil pressure low or turning gear motor temperature high signal is received. (Step 6.23[140],

6.23[144])

19. MFPT 2A Standby Oil Pumps START on low discharge pressure of operating pump and MCR alarm, 54-A MFPT 2A MOP 2 PRESS LO or 53-A MFPT 2A MOP 1 PRESS LO, actuates. (Steps 6.23[41],

6.23[42], 6.23[49], 6.23[50])

20. MFPT 2A Standby Oil Pumps START on high motor temperature of operating pump (Steps 6.23[55] and 6.23[62]).
21. MFPT 2A and B Trip on Train A or Train B Feedwater Isolation Signal (Steps 6.23[260], 6.23[265], 6.27[255], 6.27[260]).
22. MFPT 2A Emergency Oil Pump (EOP) will auto start upon loss of both Main Oil Pumps. MCR alarm will annunciate upon EOP start and the local panel indicator lights will indicate correct EOP status. (Steps 6.23(1 0],

6.23[11])

23. MCR alarm 56-B MFPT 2A EOP CONTROL PWR FAILURE will annunciate upon the loss of DC power to the MFPT 2A EOP. (Step 6.23[7])
24. The loss of 250 VDC control power to the MFPT 2A trip circuit will cause MCR alarm 51-C MFPT 2A TRIP & RESET CIRCUIT POWER FAILURE to annunciate. (Step 6.23(198])
25. MFPT 2A trip will cause MCR alarms 51-A TRIPPED and 28-E TURBINE RUNBACK BOP to annunciate. (Step 6.23(210], 6.23(211])
26. MFPT 2A low pump or turbine bearing oil pressure, low condenser vacuum, thrust bearing wear, injection water differential pressure low, and pump suction valve not fully open will initiate a MCR alarm. (Steps 6.23[217], 6.23[221], 6.23[228], 6.23[233], 6.23[240], 6.23[253], 6.23[255])

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 48 of 371 5.0 ACCEPTANCE CRITERIA (continued)

27. MFPT 2A low suction pressure will cause alarm, 49-E MFWP OR STBY FWP SUCTION NPSH LO (PS-2-129A) to annunciate. (Step 6.23[193])
28. MFPT 2B Oil Reservoir Heater will start on a low temperature signal and shut off on a low level signal. (Steps 6.27[94], 6.27[101], 6.27[103])
29. Annunciator Windows 51-D, OIL FROM COOLER TEMP HI, 55-C #1 BEARING DRAIN OIL TEMP HI, 56-C #2 BEARING DRAIN OIL TEMP HI, and 54-C THRUST BEARING DRAIN OIL TEMP HI annunciate on increasing MFPT 2B bearing oil temperature. (Step 6.27[169], 6.27[174],

6.27[179], 6.27[184])

30. Annunciator Window 55-B, annunciates on increasing MFPT 2B oil reservoir Hi/Low level and the local panel Hi/Lo level lights indicate correctly. (Steps 6.27[158], 6.27[159], 6.27[164], 6.27[165])
31. The loss of 250 VDC control power to the MFPT 2B trip circuit will cause MCR alarm 51-C MFPT 2B TRIP & RESET CIRCUIT POWER FAILURE to annunciate. ( Step 6.27[194])
32. MFPT 2B trip will cause MCR alarm 51-A TRIPPED and 28-E TURBINE RUNBACK BOP to annunciate. (Step 6.27[205], 6.27[206])
33. MFPT 2B low pump or turbine bearing oil pressure, low condenser vacuum, thrust bearing wear, injection water differential pressure low, and pump suction valve not fully open will initiate a MCR alarm. (Steps 6.271212], 6.27[216], 6.27[223], 6.27[228], 6.27[235], 6.27[248])
34. MFPT 2B Turning Gear will trip whenever a bearing oil pressure low or turning gear motor temperature high signal is received. (Steps 6.27[140],

6.271144])

35. MFPT 2B Standby Oil Pumps START on trip of operating pump (Steps 6.27[26]B and 6.27[34]B).
36. MFPT 2B Standby Oil Pumps START on low discharge pressure of operating pump and MCR alarm 54-A MFPT 2B MOP 2 PRESS LO or 53-A MFPT 2B MOP 1 PRESS LO actuate. (Steps 6.27[41], 6.27[42],

6.27[49], 6.27[50])

37. MFPT 2B Standby Main Oil Pumps START on high motor temperature of operating pump (Steps 6.27[55] and 6.27[62]).
38. SMFP Trips on Train A or Train B Feedwater Isolation Signal (Steps 6.30[62] and 6.30[65]).

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 49 of 371 5.0 ACCEPTANCE CRITERIA (continued)

39. MFPT 2B Emergency Oil Pump (EOP) will auto start upon loss of both Main Oil Pumps. MCR alarm will annunciate upon EOP start and the local panel indicator lights will indicate correct EOP status. (Steps 6.27[10],

6.27[11])

40. MCR alarm 56-B MFPT 2B EOP CONTROL PWR FAILURE will annunciate upon the loss of DC power to the MFPT 2B EOP. (Step 6.27[7])
41. MFPT 2A HP and LP Stop valves 2-FCV-1-36 and 2-FCV-1-39 and Control Valves 2-FCV-1 -37 and 2-FCV-1 -38 can be opened and closed from the MCR and the local control panel and position indications at both locations indicate properly. (Steps 6.26[8], 6.26[10], 6.26[11], 6.26[13], 6.26[14],

6.26[16], 6.26[18], 6.26[19], 6.26[34], 6.26[37], 6.26[38], 6.26[39], 6.26[40])

42. MFPT 2B HP and LP Stop valves 2-FCV-1 -43 and 2-FCV-1-46 and Control Valves 2-FCV-1 -44 and 2-FCV-1 -45 can be opened and closed from the MCR and the local control panel and position indications at both locations indicate properly. (Steps 6.28[8], 6.28[10], 6.28[11], 6.28[13], 6.28114],

6.28[16], 6.28[18], 6.28[19], 6.28[34], 6.28[37], 6.28[38], 6.28[39], 6.28[40])

43. SMFP STARTS on MFPT Trip if plant load is above setpoint and pump isolation valves are fully open (Steps 6.30[33] and 6.30[48]).
44. MFPT Emergency Oil Pumps 2A/2B START on low discharge pressure of operating pump, locally. (Steps 6.23[16] and 6.27(16]).
45. The SMFP Auxiliary Oil Pumps 2A and 2B can be started from the handswitches (2-HS-2-210, -211) located on the Local Control Station. The oil pumps will also AUTO start when the SMFP oil pressure is less than the setpoint and will shut off when the SMFP oil pressure is equal to or above the setpoint. (Steps 6.29[4], 6.29[6], 6.29[15], 6.29[19], 6.29[24], 6.29[27])
46. The indicating lights in the Main Control Room provide the correct status for the Main Oil Pumps 2A1/2A2, 2B1/2B2 for each MFPT. (Steps 6.23[12],

6.23[21], 6.27[12], 6.27[21])

47. 2-FCV-3-70, MAIN FEEDWATER PUMP A RECIRC opens at discharge flow less than 4000 GPM, closes at discharge flow greater than 4000 GPM, and modulates as flow moves between these two setpoints. Alarm 57-A, MFP 2A FLOW LO also actuates upon receiving a flow signal less than 4000 GPM. (Steps 6.16[21], 6.16[24], 6.16[25], 6.16[26])

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 50 of 371 5.0 ACCEPTANCE CRITERIA (continued)

48. 2-FCV-3-84, MAIN FEEDWATER PUMP B RECIRC opens at discharge flow less than 4000 GPM, closes at discharge flow greater than 4000 GPM, and modulates as flow moves between these two setpoints. Alarm 58-A, MFP 2B FLOW LO also actuates upon receiving a flow signal less than 4000 GPM. (Steps 6.17[21], 6.17[24], 6.17[25], 6.17[26])
49. 2-PCV-3-40, MFW DEAERATION LINE BACK PRESSURE CONTROL closes when 2-HS-3-45, FW SYSTEM WARMUP CONTROL SWITCH is placed in NORMAL position. (Step 6.22[2])
50. MFPT 2A/2B VAPOR EXTRACTORS can be operated from their Local Control Stations. (Steps 6.23[90], 6.27[90])
51. MFPT 2A/2B TURNING GEAR can be operated from Main Control Room and Local Control Station, including "JOG" operation. (Steps 6.23[114],

6.271114])

52. The Injection Water pumps AUTO start upon MFWP or SBFP seal water differential pressure less than or equal to the setpoint. (Steps 6.24[14],

6.24[23], 6.25[141, 6.25[231)

53. The Injection Water pumps can be operated manually from handswitches in either the MCR or the local panel.

(Steps 6.24[28], 6.24[30], 6.24[32], 6.24[34], 6.24[38], 6.25[28], 6.25[30],

6.25[32], 6.25[34], 6.25[38])

54. The Injection Water Pumps status indication lights on the MCR indicate the correct status for both pumps. (Steps 6.24[11], 6.24[14], 6.25[11], 6.25[14])

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 51 of 371 6.0 PERFORMANCE NOTE The order of subsection performance is as follows:

Subsections 6.1 thru 6.15 and 6.18 thru 6.22 can be performed in any order and/or simultaneously.

Subsections 6.16 and 6.23 can be performed in any order but not simultaneously.

Subsections 6.26, 6.32 and 6.34 must be performed after Subsections 6.16 and 6.23.

Subsections 6.24 and 6.25 must be performed before 6.31.

Subsection 6.29 must be performed before 6.30 and 6.30 before 6.32.

Subsections 6.17 and 6.27 can be performed in any order but not simultaneously.

Subsections 6.28, 6.35 and 6.36 must be performed after Subsections 6.17 and 6.27.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 52 of 371 Date 6.1 2-FCV-3-205, STANDBY MAIN FEEDWATER PUMP DISCHARGE ISOL, Logic Test

[1] VERIFY prerequisites listed in Section 4.3[89] for Subsection 6.1 have been completed.

[2] VERIFY/PLACE 2-HS-3-200A, STANDBY MFWP, at 2-M-4, to the PULL-TO-LOCK position.

[3] DEPRESS 2-HS-3-205, STANDBY MAIN FEEDWATER PUMP DISCHARGE ISOL VLV, CLOSE pushbutton, at Panel 2-JB-291-653, (7291T16J), and VERIFY:

A. 2-FCV-3-205, STANDBY MAIN FEEDWATER PUMP DISCHARGE ISOL, CLOSED (729/T15K).

B. Red Light OFF (2-HS-3-205).

C. Green Light ON (2-HS-3-205).

[4] DEPRESS 2-HS-3-205, STANDBY MAIN FEEDWATER PUMP DISCHARGE VLV, OPEN pushbutton, at Panel 2-JB-291-653, and VERIFY locally that 2-FCV-3-205, STANDBY MAIN FEEDWATER PUMP DISCHARGE ISOL, does not OPEN.

NOTE The next three steps will verify the valve to valve interlock between 2-FCV-2-265 and 2-FCV-3-205. 2-FCV-3-205 will only open after valve 2-FCV-2-265 reaches full open as indicated by light indication.

[5] DEPRESS and HOLD 2-HS-3-205, STANDBY MAIN FEEDWATER PUMP DISCHARGE ISOL VLV, OPEN pushbutton at Panel 2-JB-291-653.

[6] PLACE 2-HS-2-265, STANDBY MAIN FW PUMP SUCTION ISOL VLV, at Panel 2-JB-291-653 to the OPEN position.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 53 of 371 Date 6.1 2-FCV-3-205, STANDBY MAIN FEEDWATER PUMP DISCHARGE ISOL, Logic Test (continued)

[7] VERIFY the following:

A. 2-FCV-2-265, STANDBY MAIN FW PUMP SUCTION ISOL VLV OPENS.

B. 2-FCV-3-205, STANDBY MAIN FEEDWATER PUMP DISCHARGE ISOL, STARTS to OPEN after 2-FCV-2-265 is FULL OPEN. Acc Crit (5.0B.1)

C. Red Light ON (2-HS-3-205). Acc Crit (5.08.1)

D. Green Light OFF (2-HS-3-205). Acc Crit (5.01.1)

[8] RELEASE 2-HS-3-205, STANDBY MAIN FEEDWATER PUMP DISCHARGE ISOL VLV, OPEN pushbutton at Panel 2-JB-291-653.

[9] VERIFY Annunciator Window 55-E, STANDBY MFP DISCH FCV-3-205 NOT FULL OPEN, at 2-XA-55-3B is CLEAR.

NOTE The following two steps will stop 2-FCV-3-205, STANDBY MAIN FEEDWATER PUMP DISCHARGE ISOL, in mid position. The STOP pushbutton should be depressed shortly after dual light indication is obtained at 2-HS-3-205.

[10] DEPRESS 2-HS-3-205, STANDBY MAIN FEEDWATER PUMP DISCHARGE ISOL VLV, CLOSE pushbutton, at Panel 2-JB-291-653.

[11] DEPRESS 2-HS-3-205, STANDBY MAIN FEEDWATER PUMP DISCHARGE ISOL VLV, STOP pushbutton, at Panel 2-JB-291-653 and VERIFY: Acc Crit (5.01.1)

A. 2-FCV-3-205, STANDBY MAIN FEEDWATER PUMP DISCHARGE ISOL, STOPS in MID POSITION (locally).

B. Red Light ON (2-HS-3-205).

C. Green Light ON (2-HS-3-205).

[12] VERIFY Annunciator Window 55-E, STANDBY MFP DISCH FCV-3-205 NOT FULL OPEN, ALARMS.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 54 of 371 Date 6.1 2-FCV-3-205, STANDBY MAIN FEEDWATER PUMP DISCHARGE ISOL, Logic Test (continued)

[13] DEPRESS 2-HS-3-205, STANDBY MAIN FEEDWATER PUMP DISCHARGE ISOL VLV, CLOSE pushbutton, at Panel 2-JB-291-653 and VERIFY 2-FCV-3-205 CLOSES.

NOTE The following two steps will stop 2-FCV-3-205 in mid position. The STOP pushbutton should be depressed shortly after dual light indication is obtained at 2-HS-3-205

[14] DEPRESS 2-HS-3-205, STANDBY MAIN FEEDWATER PUMP DISCHARGE ISOL VLV, OPEN pushbutton, at Panel 2-JB-291-653.

[15] DEPRESS 2-HS-3-205, STANDBY MAIN FEEDWATER PUMP DISCHARGE ISOL VLV, STOP pushbutton, at Panel 2-JB-291-653 and VERIFY:

A. 2-FCV-3-205, STANDBY MAIN FEEDWATER PUMP DISCHARGE ISOL, STOPS in MID POSITION (locally).

B. Red Light ON (2-HS-3-205).

C. Green Light ON (2-HS-3-205).

[16] DEPRESS 2-HS-3-205, STANDBY MAIN FEEDWATER.

PUMP DISCHARGE ISOL VLV, OPEN pushbutton at Panel 2-JB-291-653 and VERIFY 2-FCV-3-205 OPENS.

[17] VERIFY Annunciator Window 55-E, STANDBY MFP DISCH FCV-3-205 NOT FULL OPEN, CLEARS.

[18] DEPRESS 2-HS-3-205, STANDAY MAIN FEEDWATER PUMP DISCHARGE ISOL VLV, CLOSE pushbutton, at Panel 2-JB-291-653 and VERIFY 2-FCV-3-205 CLOSES.

[19] REMOVE the jumper across Terminal Board CC, Terminal Points 1 (3C03) and 2 (3C02) at Panel 2-L-491.

Cv

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 55 of 371 Date 6.2 2-FCV-3-208, STANDBY MAIN FEEDWATER PUMP MIN FLOW, Logic Test

[1] VERIFY prerequisites listed in Section 4.0 for Subsection 6.2 have been completed.

[2] VERIFY/PLACE 2-HS-3-200A, STANDBY MFWP, at 2-M-4 to the PULL-TO-LOCK position.

[3] VERIFY 2-FCV-3-208, STANDBY MAIN FEEDWATER PUMP MIN FLOW is CLOSED by valve stem position indication (729/TI 6J).

[4] LIFT White lead (LFB2) on Terminal Board FF, Terminal Point 6 at Panel 7 of 6900-V Unit Board 2D, to simulate 2-PMP-3-200, STANDBY MAIN FEEDWATER PUMP, running.

(Dwg 0126D4672-2).

CV

[5] VERIFY 2-FCV-3-208, STANDBY MAIN FEEDWATER PUMP MIN FLOW, (729/T16J) OPENS. Acc Crit (5.0B.2)

[6] VERIFY/PLACE 2-FIC-3-208, STANDBY MAIN FW PMP LO FLOW BYPASS CONT, at 2-M-3, in MANUAL with the controller set to 100% OUTPUT and VERIFY:

A. Valve 2-FCV-3-208, STANDBY MAIN FEEDWATER PUMP MIN FLOW, CLOSED (locally).

B. Red Light OFF (2-JB-291-653).

C. Green Light ON (2-JB-291-653).

[7] LOWER the output on Controller 2-FIC-3-208, STANDBY MAIN FW PMP LO FLOW BYPASS CONT, until 0% OUTPUT is obtained and VERIFY:

A. Valve 2-FCV-3-208, STANDBY MAIN FEEDWATER PUMP MIN FLOW, OPENS (locally).

B. Red Light ON (2-JB-291-653).

C. Green Light OFF (2-JB-291-653).

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 56 of 371 Date 6.2 2-FCV-3-208, STANDBY MAIN FEEDWATER PUMP MIN FLOW, Logic Test (continued)

[8] INCREASE the output on Controller 2-FIC-3-208, STANDBY MAIN FW PMP LO FLOW BYPASS CONT, until 100%

OUTPUT is obtained, and VERIFY 2-FCV-3-208 CLOSES.

[9] Using 2-FIC-3-208 jog feature, pulse OPEN 2-FCV-3-208 a few times. VERIFY the valve stops opening when the jogging is stopped. Jog the valve back to completely closed.

[10] PLACE 2-FIC-3-208, STANDBY MAIN FW PMP LO FLOW BYPASS CONT, in AUTO and VERIFY 2-FCV-3-208, STANDBY MAIN FEEDWATER PUMP MIN FLOW, OPENS by light indication at Panel 2-JB-291-653.

NOTE The following steps repeat steps 6.2.6 through 6.2.10 using the DCS workstation screen mimic for 2-FIC-3-208 instead of the controller on 2-M-3.

[11] Using the 2-FIC-3-208 screen mimic in the DCS workstation, VERIFY/PLACE 2-FIC-3-208, STANDBY MAIN FW PMP LO FLOW BYPASS CONT, at 2-M-3, in MANUAL with the controller set to 100% OUTPUT and VERIFY:

A. Valve 2-FCV-3-208, STANDBY MAIN FEEDWATER PUMP MIN FLOW, CLOSED (locally).

B. Red Light OFF (2-JB-291-653).

C. Green Light ON (2-JB-291-653).

[12] LOWER the output on Controller 2-FIC-3-208, STANDBY MAIN FW PMP LO FLOW BYPASS CONT, until 0% OUTPUT is obtained and VERIFY:

A. Valve 2-FCV-3-208, STANDBY MAIN FEEDWATER PUMP MIN FLOW, OPENS (locally).

B. Red Light ON (2-JB-291-653).

C. Green Light OFF (2-JB-291-653).

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 57 of 371 Date 6.2 2-FCV-3-208, STANDBY MAIN FEEDWATER PUMP MIN FLOW, Logic Test (continued)

[13] INCREASE the output on Controller 2-FIC-3-208, STANDBY MAIN FW PMP LO FLOW BYPASS CONT, until 100%

OUTPUT is obtained and VERIFY 2-FCV-3-208 CLOSES.

[14] Using 2-FIC-3-208 jog feature, pulse OPEN 2-FCV-3-208 a few times. VERIFY the valve stops opening when the jogging is stopped. Jog the valve back to completely closed.

[15] PLACE 2-FIC-3-208, STANDBY MAIN FW PMP LO FLOW BYPASS CONT, in AUTO and VERIFY 2-FCV-3-208, STANDBY MAIN FEEDWATER PUMP MIN FLOW, OPENS by light indication at Panel 2-JB-291-653.

[16] CLOSE 2-RTV-3-248A, 2-FT-3-208 ROOT, to isolate the high side of 2-FT-3-208, (729/T'"6J) STANDBY MAIN FEEDWATER PUMP DISCHARGE FLOW.

[17] REMOVE the cap from the calibration tap on the high side of

.2-FT-3-208, STANDBY MAIN FEEDWATER PUMP DISCHARGE FLOW.

[18] INSTALL a 0-100" H20 pressure gage and hand pump/test rig at the calibration tap for 2-FT-3-208, STANDBY MAIN FEEDWATER PUMP DISCHARGE FLOW.

M&TE ID#

CV

[19] INCREASE the simulated pressure between 17 and 20" H 2 0 to simulate a SMFP discharge flow greater than 1500 GPM.

[20] VERIFY 2-FCV-3-208, STANDBY MAIN FEEDWATER PUMP MIN FLOW, CLOSES by light indication at Panel 2-JB-291-653. Acc Crit (5.0B.2)

[21] DECREASE the simulated pressure to below 13" H20 to simulate a SMFP discharge flow less than 1500 GPM.

[22] VERIFY 2-FCV-3-208, STANDBY MAIN FEEDWATER PUMP MIN FLOW, OPENS by light indication at Panel 2-JB-291-653.

Acc Crit (5.0B.2)

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 58 of 371 Date 6.2 2-FCV-3-208, STANDBY MAIN FEEDWATER PUMP MIN FLOW, Logic Test (continued)

[23] LAND White lead (LFB2) on Terminal Board FF, Terminal Point 6 at Panel 7 of 6900-V Unit Board 2D, to clear the 2-PMP-3-200, STANDBY MAIN FEEDWATER PUMP, running simulation(Dwg 0126D4672-2).

CV

[24] VERIFY 2-FCV-3-208, STANDBY MAIN FEEDWATER PUMP MIN FLOW, CLOSES by light indication at Panel 2-JB-291-653. Acc Crit (5.0B.2)

[25] DEPRESS and HOLD 2-HS-3-208, STANDBY MAIN FEEDWATER PUMP RECIRC BYPASS VLV, TEST pushbutton, at Panel 2-JB-291-653.

[26] VERIFY 2-FCV-3-208, STANDBY MAIN FEEDWATER PUMP MIN FLOW, OPENS by light indication at Panel 2-JB-291-653.

Acc Crit (5.0B.2)

[27] RELEASE 2-HS-3-208, STANDBY MAIN FEEDWATER PUMP RECIRC BYPASS VLV, TEST pushbutton, at Panel 2-JB-291-653.

[28] VERIFY 2-FCV-3-208, STANDBY MAIN FEEDWATER PUMP MIN FLOW, CLOSES by light indication at Panel 2-JB-291-653.

[29] INSTALL a jumper at Terminal Board GG across Terminal Points 11 and 12 in Panel 7 of 6900-V Unit Board 2D, to simulate 2-PMP-3-200, STANDBY MAIN FEEDWATER PUMP, running. (Dwg 2-45W760-3-2 or 0126D4672-2)

CV

[30] INSTALL a jumper at Terminal Board TB-C-1 56 across Terminal Points 1 (2M282) and 2 (2NM3C) at Panel 2-R-121, Balance of Plant Instrument Racks, Non-Divisional to simulate 2-PMP-3-200, STANDBY MAIN FEEDWATER PUMP, running.

(Dwg 2-45W2673-5)

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 59 of 371 Date 6.2 2-FCV-3-208, STANDBY MAIN FEEDWATER PUMP MIN FLOW, Logic Test (continued)

[31] VERIFY Annunciator Window 59-A, STANDBY MFP FLOW LO, at 2-XA-55-SC, ALARMS.

[32] REMOVE jumper at Terminal Board TB-C-1 56 across Terminal Points 1 and 2 at Panel 2-R-121.

CV

[33] VERIFY Annunciator Window 59-A, STANDBY MFP FLOW LO, CLEARS.

[34] REMOVE jumper from Terminal Board GG, Terminal Points 11 and 12 of Relay 52STA in Panel 7 of 6900-V Unit Board 2D.

CV

[35] DEPRESSURIZE AND REMOVE the 0-100" H 2 0 pressure gage and hand pump/test rig from the calibration tap of 2-FT-3-208, STANDBY MAIN FEEDWATER PUMP DISCHARGE FLOW.

CV

[36] INSTALL the cap on the calibration tap on the high side of 2-FT-3-208, STANDBY MAIN FEEDWATER PUMP DISCHARGE FLOW.

CV

[37] OPEN 2-RTV-3-248A, FT-3-208 ROOT, to restore the high side of 2-FT-3-208, (729/T1 6J) STANDBY MAIN FEEDWATER PUMP DISCHARGE FLOW.

[38] CLOSE 2-ISV-32-2611 (729/T15J), CONTROL AIR ISOLATION VALVE TO 2-FCV-3-208.

[39] OPEN petcock on 2-PREG-3-208, CONTROL AIR PRESSURE REG FOR 2-FM-3-208D, to bleed control air from 2-FCV-3-208, STANDBY MAIN FEEDWATER PUMP MIN FLOW.

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 60 of 371 Date 6.2 2-FCV-3-208, STANDBY MAIN FEEDWATER PUMP MIN FLOW, Logic Test (continued)

[40] VERIFY locally 2-FCV-3-208, STANDBY MAIN FEEDWATER PUMP MIN FLOW, FAILS to the OPEN position by light indication at Panel 2-JB-291-653.

[41] CLOSE the petcock on 2-PREG-3-208, CONTROL AIR PRESSURE REG FOR 2-FM-3-208D.

CV

[42] OPEN 2-ISV-32-2864, CONTROL AIR ISOLATION VALVE TO 2-FCV-3-208.

[43] VERIFY locally 2-FCV-3-208, STANDBY MAIN FEEDWATER PUMP MIN FLOW, CLOSES by light indication at Panel 2-JB-291-653.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 61 of 371 Date 6.3 2-FCV-3-204, STANDBY MAIN FEEDWATER PUMP NON-RETURN, Logic Test

[1] VERIFY prerequisites listed in Section 4.0 for Subsection 6.3 have been completed..

[2] VERIFYIPLACE 2-HS-3-200A, STANDBY MFWP, at 2-M-4, to the PULL-TO-LOCK position.

[3] VERIFY/OPEN 2-ISV-32-2610, CONTROL AIR ISOLATION VALVE TO 2-FCV-3-204.

CAUTION The counter-weighted swing arm must be verified free of obstructions prior to cycling the non return valve.

[4] DEPRESS 2-HS-3-204, STANDBY MAIN FEEDWATER PUMP REVERSE FLOW VLV, TEST pushbutton, at Panel 2-JB-291-653, (729/T15J), and VERIFY:

A. 2-FCV-3-204, STANDBY MAIN FEEDWATER PUMP NON-RETURN, REMAINS CLOSED (729/T15J).

B. Red Light OFF.

C. Green Light ON.

[5] INSTALL a jumper at Terminal Board FF across Terminal Points 7 (SMFP2) and 8 (SMFP1) at panel 7, 6900-V Unit Board 2D to simulate the SMFP in operation.

(Dwg 0126D4654)

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 62 of 371 Date 6.3 2-FCV-3-204, STANDBY MAIN FEEDWATER PUMP NON-RETURN, Logic Test (continued)

[6] VERIFY the following: Acc Crit (5.0B.3)

A. 2-FCV-3-204, STANDBY MAIN FEEDWATER PUMP NON-RETURN, OPEN (locally).

B. Red Light ON.

C. Green Light OFF.

[7] DEPRESS and HOLD 2-HS-3-204, STANDBY MAIN FEEDWATER PUMP REVERSE FLOW VLV, TEST pushbutton, and VERIFY Valve 2-FCV-3-204, STANDBY MAIN FEEDWATER PUMP NONRETURN, CLOSES by light indication at 2-JB-291-653. Acc Crit (5.0B.3)

[8] RELEASE 2-HS-3-204, STANDBY MAIN FEEDWATER PUMP REVERSE FLOW VLV, TEST pushbutton, and VERIFY Valve 2-FCV-3-204, STANDBY MAIN FEEDWATER PUMP NONRETURN, OPENS by light indication on 2-JB-291-653.

[9] REMOVE jumper across Terminals FF-7 and FF-8 at Panel 7, 6900-V Unit Board 2D.

CV

[10] VERIFY 2-FCV-3-204, STANDBY MAIN FEEDWATER PUMP NON-RETURN, CLOSES by light indication on 2-JB-291-653.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 63 of 371 Date 6.4 2-FCV-3-72, MAIN FEEDWATER PUMP A REVERSE FLOW CHECK, Logic Test

[1] VERIFY prerequisites listed in Section 4.0 for Subsection 6.4 have been completed.

[2] VERIFY 2-FCV-3-72, MAIN FEEDWATER PUMP A REVERSE FLOW CHECK, (729/TI 6H), is CLOSED locally by valve stem position indication.

[3] VERIFY 2-FCV-3-72, MAIN FEEDWATER PUMP A REVERSE FLOW CHECK, is CLOSED by light indication at Panel 2-JB-291-681. (729/T1I6H)

A. Red Light OFF.

B. Green Light ON.

NOTE The following step will load 2-FCV-3-72, MAIN FEEDWATER PUMP A REVERSE FLOW CHECK. The check valve will stroke off its CLOSED limit switch but may not indicate full open. The intent of the step is to verify check valve movement.

[4] LIFT Lead (211) from the normally closed contact of 2-PS-46-13, MFPT 2A LOW OPER OIL PRESS, to simulate MFPT 2A running. (Dwg 2-45W2614-3)

CV

[5] VERIFY 2-FCV-3-72, MAIN FEEDWATER PUMP A REVERSE FLOW CHECK, stroked OPEN or MID POSITION locally.

NOTE If 2-FCV-3-72 strokes full OPEN the green light will be OFF.

[6] VERIFY 2-FCV-3-72, MAIN FEEDWATER PUMP A REVERSE FLOW CHECK, stroked OPEN or MID POSITION by light indication at Panel 2-JB-291-681.

A. Red Light ON.

B. Green Light ON (or OFF).

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 64 of 371 Date 6.4 2.FCV-3-72, MAIN FEEDWATER PUMP A REVERSE FLOW CHECK, Logic Test (continued)

[7] DEPRESS and HOLD 2-HS-3-72, MAIN FEEDWATER PUMP A REVERSE FLOW CHECK VLV, TEST pushbutton at Panel 2-JB-291-681.

[8] VERIFY 2-FCV-3-72, MAIN FEEDWATER PUMP A REVERSE FLOW CHECK, strokes CLOSED by light indication at Panel 2-JB-291-681. Acc Crit (5.0B.4)

[9] RELEASE 2-HS-3-72, MAIN FEEDWATER PUMP A REVERSE FLOW CHECK VLV, TEST pushbutton, at Panel 2-JB-291-681, and VERIFY 2-FCV-3-72 OPENS.

Acc Crit (5.0B.4)

[10] LAND Lead (211) on the normally closed contact of 2-PS-46-13, MFPT 2A LOW OPER OIL PRESS.

CV

[11] VERIFY 2-FCV-3-72, MAIN FEEDWATER PUMP A REVERSE FLOW CHECK, CLOSES. Ace Crit (5.0B.4)

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 65 of 371 Date 6.5 2-FCV-3-88, MAIN FEEDWATER PUMP B REVERSE FLOW CHECK, Logic Test

[1] VERIFY prerequisites listed in Section 4.0 for Subsection 6.5 have been completed.

[2] VERIFY 2-FCV-3-88, MAIN FEEDWATER PUMP B REVERSE FLOW CHECK, (729/T16G), is CLOSED locally by valve stem position indication.

[3] VERIFY 2-FCV-3-88, MAIN FEEDWATER PUMP B REVERSE FLOW CHECK, is CLOSED by light indication at Panel 2-JB-291-682 (729/T16J):

A. Red Light OFF.

B. Green Light ON.

NOTE The following step will load 2-FCV-3-88, MAIN FEEDWATER PUMP B REVERSE FLOW CHECK. The check valve will stroke off its CLOSED limit switch but may not indicate full open. The intent of the step is to verify check valve movement.

[4] LIFT Lead (211) from the normally closed contact of 2-PS-46-40, MFPT 2B LOW OPER OIL PRESS (729/TI 5H), to simulate MFPT 2B running. (Dwg 2-45W2614-7)

CV

[5] VERIFY 2-FCV-3-88, MAIN FEEDWATER PUMP B REVERSE FLOW CHECK, stroked OPEN or MID POSITION locally.

NOTE If 2-FCV-3-88 strokes full OPEN the green light will be OFF.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 66 of 371 Date 6.5 2-FCV-3-88, MAIN FEEDWATER PUMP B REVERSE FLOW CHECK, Logic Test (continued)

[6] VERIFY 2-FCV-3-88, MAIN FEEDWATER PUMP B REVERSE FLOW CHECK, stroked OPEN or MID POSITION by light indication at Panel 2-JB-291-682.

A. Red Light ON.

B. Green Light ON (or OFF).

[7] DEPRESS and HOLD 2-HS-3-88, MAIN FEEDWATER PUMP B REVERSE FLOW CHECK VLV, TEST pushbutton at Panel 2-JB-291-682.

[8] VERIFY 2-FCV-3-88, MAIN FEEDWATER PUMP B REVERSE FLOW CHECK, strokes CLOSED by light indication at Panel 2-JB-291-682. Acc Crit (5.0B.4)

[9] RELEASE 2-HS-3-88, MAIN FEEDWATER PUMP B REVERSE FLOW CHECK VLV, TEST pushbutton, at Panel 2-JB-291-682, and VERIFY 2-FCV-3-88 OPENS.

Acc Crit (5.0B.4)

[10] LAND Lead (211) on the normally closed contact of 2-PS-46-40, MFPT 2B LOW OPER OIL PRESS.

CV

[11] VERIFY 2-FCV-3-88, MAIN FEEDWATER PUMP B REVERSE FLOW CHECK, CLOSES. Acc Crit (5.0B.4)

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 67 of 371 Date 6.6 2-FCV-3-3, MFW HEATER Al INLET, Logic Test

[1] VERIFY prerequisites listed in Section 4.0 for Subsection 6.6 have been completed.

[2] VERIFY Annunciator Window 36-A, HP HEATER Al LEVEL HI/LO, is CLEAR.

[3] VERIFY/PLACE 2-HS-3-3A, Al HEATER INLET, at 2-M-3, in the CLOSE position and VERIFY:

A. 2-FCV-3-3, MFW HEATER Al INLET, CLOSED (708/TI 6G).

B. Red Light OFF (2-HS-3-3A).

C. Green Light ON (2-HS-3-3A).

D. Red Light OFF (2-JB-291-460) (708/T16G).

E. Green Light ON (2-JB-291-460).

F. Continuity across Terminal Points EA3 (BK) and EA4 (W) in SMS MUX Cabinet 2-CMPT-263-R133 (RELAY 2-A214 PWR ON) (Dwg 2-45B2752-2D).

M&TE ID#

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 68 of 371 Date 6.6 2-FCV-3-3, MFW HEATER Al INLET, Logic Test (continued)

[4] PLACE 2-HS-3-3A, Al HEATER INLET, at 2-M-3, in the OPEN position and VERIFY:

A. 2-FCV-3-3, MFW HEATER Al INLET, OPEN (locally).

B. Red Light ON (2-HS-3-3A).

C. Green Light OFF (2-HS-3-3A).

D. Red Light ON (2-JB-291-460).

E. Green Light OFF (2-JB-291-460).

F. No continuity across Terminal Points EA3 (BK) and EA4 (W) in SMS MUX Cabinet 2-CMPT-263-Rl 33 (RELAY 2-A214 PWR OFF)

M&TE ID#

[5] DEPRESS 2-HS-3-3B, MFW HEATER Al INLET VALVE, CLOSE pushbutton, at Panel 2-JB-291-460, and VERIFY 2-FCV-3-3, CLOSES by light indication. Acc Crit (5.0B.6)

[6] DEPRESS 2-HS-3-3B, MFW HEATER Al INLET VALVE, OPEN pushbutton at Panel 2-JB-291-460, and VERIFY 2-FCV-3-3, OPENS by light indication. Acc Crit (5.0B.6)

NOTE The following steps will verify operation of the STOP pushbutton. The valve will be stopped in mid position in both the open and closed directions. The STOP pushbutton shall be depressed shortly after dual light indication is obtained.

[7] PLACE 2-HS-3-3A, Al HEATER INLET, on 2-M-3, to the CLOSE position.

[8] DEPRESS and HOLD 2-HS-3-3B, MFW HEATER Al INLET VALVE, STOP pushbutton at Panel 2-JB-291-460.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 69 of 371 Date 6.6 2-FCV-3-3, MFW HEATER Al INLET, Logic Test (continued)

[9] VERIFY 2-FCV-3-3, MFW HEATER Al INLET, STOPS at MID POSITION by light indication at Panel 2-JB-291-460.

A. 2-FCV-3-3, MFW HEATER Al INLET, Stopped.

B. Red Light ON (2-HS-3-3B).

C. Green Light ON (2-HS-3-3B).

[10] RELEASE 2-HS-3-3B, MFW HEATER Al INLET VALVE, STOP pushbutton, and VERIFY Valve 2-FCV-3-3 does NOT RESTART its travel.

[11] PLACE 2-HS-3-3A, Al HEATER INLET, on 2-M-3, to the CLOSE position to fully close 2-FCV-3-3.

[12] PLACE 2-HS-3-3A, Al HEATER INLET, on 2-M-3 to the OPEN position.

[13] DEPRESS and HOLD 2-HS-3-3B, MFW HEATER Al INLET VALVE, STOP pushbutton, at Panel 2-JB-291-460.

[14] VERIFY 2-FCV-3-3, MFW HEATER Al INLET, STOPS at MID POSITION by light indication at Panel 2-JB-291-460.

Acc Crit (5.0B.6)

A. 2-FCV-3-3, MFW HEATER Al INLET, Stopped.

B. Red Light ON (2-HS-3-3B).

C. Green Light ON (2-HS-3-3B).

[15] RELEASE 2-HS-3-3B, MFW HEATER Al INLET VALVE, STOP pushbutton, and VERIFY 2-FCV-3-3 does NOT RESTART its travel.

[16] PLACE 2-HS-3-3A, Al HEATER INLET, on 2-M-3 to the OPEN position to fully open 2-FCV-3-3.

[17] DEPRESS 2-HS-3-3B, MFW HEATER Al INLET VALVE, CLOSE pushbutton at Panel 2-JB-291-460.

[18] DEPRESS 2-HS-3-3B, MFW HEATER Al INLET VALVE, STOP pushbutton at Panel 2-JB-291-460.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 70 of 371 Date 6.6 2.FCV-3-3, MFW HEATER Al INLET, Logic Test (continued)

[19] VERIFY 2-FCV-3-3, MFW HEATER Al INLET, STOPS at MID POSITION by light indication at Panel 2-JB-291-460.

A. 2-FCV-3-3, MFW HEATER Al INLET, Stopped.

B. Red Light ON (2-HS-3-3B).

C. Green Light ON (2-HS-3-3B).

[20] DEPRESS 2-HS-3-3B, MFW HEATER Al INLET VALVE, CLOSE pushbutton to fully close 2-FCV-3-3.

[21] DEPRESS 2-HS-3-3B, MFW HEATER Al INLET VALVE, OPEN pushbutton, at Panel 2-JB-291-460.

[22] DEPRESS 2-HS-3-3B, MFW HEATER Al INLET VALVE, STOP pushbutton at Panel 2-JB-291-460.

[23] VERIFY 2-FCV-3-3, MFW HEATER Al INLET, STOPS at MID POSITION by light indication at Panel 2-JB-291-460.

A. 2-FCV-3-3, MFW HEATER Al INLET, Stopped.

B. Red Light ON (2-HS-3-3B).

C. Green Light ON (2-HS-3-3B).

[24] DEPRESS 2-HS-3-3B, MFW HEATER Al INLET VALVE, OPEN pushbutton, at Panel 2-JB-291-460, to fully OPEN 2-FCV-3-3.

[25] REMOVE the cover from 2-LS-6-15D, MFW HEATER SHELL SIDE LEVEL HI-HI. (708/TI 6G)

[26] INSTALL a jumper across Terminal Points HAl I (W) and HAIX (BK) at 2-LS-6-15D, MFW HEATER Al SHELL SIDE LEVEL HI-HI to simulate a high level in MFW HEATER Al.

(Dwg 2-45W2752-5)

CV

[27] DEPRESS and HOLD 2-HS-3-3B, MFW HEATER Al INLET VALVE, STOP pushbutton at Panel 2-JB-291-460.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 71 of 371 Date 6.6 2-FCV-3-3, MFW HEATER Al INLET, Logic Test (continued)

[28] VERIFY 2-FCV-3-3, MFW HEATER Al INLET, STOPS at MID POSITION by light indication at Panel 2-JB-291-460.

A. 2-FCV-3-3, MFW HEATER Al INLET, Stopped.

B. Red Light ON (2-HS-3-3B).

C. Green Light ON (2-HS-3-3B).

[29] RELEASE 2-HS-3-3B, MFW HEATER INLET VALVE, STOP pushbutton and VERIFY 2-FCV-3-3 CLOSES by light indication at Panel 2-JB-291-460. Acc Crit (5.0B.6)

[30] REMOVE jumper across Terminal Points HAll (W) and HAIX (BK) at 2-LS-6-15D, MFW HEATER Al SHELL SIDE LEVEL HI-HI.

CV NOTE If Subsection 6.7 is to be performed next the following step may be marked N/A.

[31] INSTALL the cover on 2-LS-6-15D, MFW HEATER SHELL SIDE LEVEL HI-HI.

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 72 of 371 Date 6.7 2-FCV-3-10, MFW HEATER Al OUTLET, Logic Test

[1] VERIFY prerequisites listed in Section 4.0 for Subsection 6.7 have been completed.

[2] VERIFY Annunciator Window 36-A, HP HEATER Al LEVEL HI/LO, is CLEAR.

[3] VERIFY/PLACE 2-HS-3-1OA, Al HEATER OUTLET at 2-M-3, in the CLOSE position and VERIFY:

A. 2-FCV-3-10, MFW HEATER Al OUTLET, CLOSED (708/T16F).

B. Red Light OFF (2-HS-3-10A).

C. Green Light ON (2-HS-3-10A).

D. Red Light OFF (2-JB-291-992) (708/T16F).

E. Green Light ON (2-JB-291-992).

F. Continuity across Terminal Points EA5(BK) and EA6(W) in SMS MUX Cabinet 2-CMPT-263-R133 (Relay 2-A215 PWR ON) (Dwg 2-45B2752-2E)

M&TE ID#

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 73 of 371 Date 6.7 2-FCV-3-10, MFW HEATER Al OUTLET, Logic Test (continued)

[4] PLACE 2-HS-3-10A, Al HEATER OUTLET at 2-M-3, in the OPEN position and VERIFY:

A. 2-FCV-3-10, MFW HEATER Al OUTLET, OPEN (locally).

B. Red Light ON (2-HS-3-10A).

C. Green Light OFF (2-HS-3-10A).

D. Red Light ON (2-JB-291-992).

E. Green Light OFF (2-JB-291-992).

F. No continuity across Terminal Points EA5 (BK) and EA6 (W) in SMS MUX Cabinet 2-CMPT-263-R133 (Relay 2-A215 PWR OFF)

M&TE ID#

[5] DEPRESS 2-HS-3-10B, MFW HEATER Al OUTLET VALVE CLOSE pushbutton at Panel 2-JB-291-992, and VERIFY 2-FCV-3-10 CLOSES by light indication. Acc Crit (5.0B.7)

[6] DEPRESS 2-HS-3-1 0B, MFW HEATER Al OUTLET VALVE, OPEN pushbutton at Panel 2-JB-291-992, and VERIFY by light indication that 2-FCV-3-10 OPENS. Acc Crit (5.0B.7)

NOTE The following steps will verify operation of the STOP pushbutton. The valve will be stopped in mid position in both the open and closed directions. The STOP pushbutton shall be depressed shortly after dual light indication is obtained.

[7] PLACE 2-HS-3-10A, Al HEATER OUTLET, on 2-M-3, to the CLOSE position.

[8] DEPRESS and HOLD 2-HS-3-10B, MFW HEATER Al OUTLET VALVE, STOP pushbutton at Panel 2-JB-291-992.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 74 of 371 Date 6.7 2-FCV-3-10, MFW HEATER Al OUTLET, Logic Test (continued)

[9] VERIFY 2-FCV-3-10, MFW HEATER Al OUTLET, STOPS at MID POSITION by light indication at Panel 2-JB-291-992.

A. 2-FCV-3-10, MFW HEATER Al OUTLET, STOPPED.

B. Red Light ON (2-HS-3-10B).

C. Green Light ON (2-HS-3-10B).

[10] RELEASE 2-HS-3-10B, MFW HEATER Al OUTLET VALVE, STOP pushbutton, and VERIFY 2-FCV-3-10, does NOT RESTART its travel.

[11] PLACE 2-HS-3-1OA, Al HEATER OUTLET, on 2-M-3, to the CLOSE position to fully close 2-FCV-31 0.

[12] PLACE 2-HS-3-10A, Al HEATER OUTLET, on 2-M-3, to the OPEN position.

[13] DEPRESS and HOLD 2-HS-3-1 0B, MFW HEATER Al OUTLET VALVE, STOP pushbutton at Panel 2-JB-291-992.

[14] VERIFY 2-FCV-3-10, MFW HEATER Al OUTLET, STOPS at MID POSITION by light indication at Panel 2-JB-291-992.

Acc Crit (5.0B.7)

A. 2-FCV-3-10, MFW HEATER Al OUTLET, STOPPED.

B. Red Light ON (2-HS-3-10B).

C. Green Light ON (2-HS-3-10B).

[15] RELEASE 2-HS-3-10B, MFW HEATER Al OUTLET VALVE, STOP pushbutton, and VERIFY 2-FCV-3-10, does NOT RESTART its travel.

[16] PLACE 2-HS-3-10A, A-1 HEATER OUTLET, on 2-M-3, to the OPEN position to fully open 2-FCV-3-1 0.

[17] DEPRESS 2-HS-3-10B, MFW HEATER Al OUTLET VALVE, CLOSE pushbutton at Panel 2-JB-291-992.

[18] DEPRESS 2-HS-3-1 0B, MFW HEATER Al OUTLET VALVE, STOP pushbutton at Panel 2-JB-291-992.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 75 of 371 Date 6.7 2-FCV-3-10, MFW HEATER Al OUTLET, Logic Test (continued)

[19] VERIFY 2-FCV-3-10, MFW HEATER Al OUTLET, STOPS at MID POSITION by light indication at Panel 2-JB-291-992.

A. 2-FCV-3-10, MFW HEATER Al OUTLET, STOPPED.

B. Red Light ON (2-HS-3-10B).

C. Green Light ON (2-HS-3-10B).

[20] DEPRESS 2-HS-3-10B, MFW HEATER Al OUTLET VALVE, CLOSE pushbutton to fully close 2-FCV-3-10.

[21] DEPRESS 2-HS-3-10B, MFW HEATER Al OUTLET VALVE, OPEN pushbutton at Panel 2-JB-291-992.

[22] DEPRESS 2-HS-3-10B, MFW HEATER Al OUTLET VALVE, STOP pushbutton at Panel 2-JB-291-992.

[23] VERIFY 2-FCV-3-10, MFW HEATER Al OUTLET, STOPS at MID POSITION by light indication at Panel 2-JB-291-992.

A. 2-FCV-3-10, MFW HEATER Al OUTLET, STOPPED.

B. Red Light ON (2-HS-3-10B).

C. Green Light ON (2-HS-3-10B).

[24] DEPRESS 2-HS-3-1 08, MFW HEATER Al OUTLET VALVE, OPEN pushbutton at Panel 2-JB-291-992 to fully OPEN 2-FCV-3-1 0.

[25] REMOVE the cover from 2-LS-6-15D, MFW HEATER Al SHELL SIDE LEVEL HI-HI (708/T16G).

[26] INSTALL a jumper across Terminal Points HAl 1 (W) and HAlX (BK) at 2-LS-6-15D, MFW HEATER Al SHELL SIDE LEVEL HI-HI, to simulate a high level in MFW HEATER Al.

(Dwg 2-45W2752-5)

CV

[27] DEPRESS and HOLD 2-HS-3-10B, MFW HEATER Al OUTLET VALVE, STOP pushbutton at Panel 2-JB-291-992.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 76 of 371 Date 6.7 2-FCV-3-10, MFW HEATER Al OUTLET, Logic Test (continued)

[28] VERIFY 2-FCV-3-10, MFW HEATER Al OUTLET, STOPS at MID POSITION by light indication at Panel 2-JB-291-992.

A. 2-FCV-3-10, MFW HEATER Al OUTLET, STOPPED.

B. Red Light ON (2-HS-3-10B).

C. Green Light ON (2-HS-3-10B).

[29] RELEASE 2-HS-3-10B, MFW HEATER Al OUTLET VALVE, STOP pushbutton and VERIFY 2-FCV-3-10 CLOSES by light indication at Panel 2-JB-291-992. Acc Crit (5.0B.7)

[30] REMOVE jumper across Terminal HAll (W) and HAI X (BK) at 2-LS-6-15D, MFW HEATER Al SHELL SIDE LEVEL HI-HI.

CV

[31] INSTALL the cover on 2-LS-6-15D, MFW HEATER Al SHELL SIDE LEVEL HI-HI.

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 77 of 371 Date 6.8 2-FCV-3-13, MFW HEATER B1 INLET, Logic Test

[1] VERIFY prerequisites listed in Section 4.0 for Subsection 6.8 have been completed.

[2] VERIFY Annunciator Window 37-A, HP HEATER B1 LEVEL HI/LO is CLEAR.

[3] VERIFY/PLACE 2-HS-3-13A, B1 HEATER INLET, at 2-M-3, in the CLOSE position and VERIFY:

A. 2-FCV-3-13, MFW HEATER B1 INLET, CLOSED (7081T1 5G).

B. Red Light OFF (2-HS-3-13A).

C. Green Light ON (2-HS-3-13A).

D. Red Light OFF (2-JB-291-460) (708/T16G).

E. Green Light ON (2-JB-291-460).

F. Continuity across Terminal Points EAI (BK) and EA2(W) in SMS MUX Cabinet 2-CMPT-263-R134 (Relay 2-B213 PWR ON) (Dwg 2-45B2753-8B)

M&TE ID#

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 78 of 371 Date 6.8 2-FCV-3-13, MFW HEATER BI INLET, Logic Test (continued)

[4] PLACE Handswitch 2-HS-3-13A, B1 HEATER INLET, at 2-M-3, to the OPEN position and VERIFY:

A. Valve 2-FCV-3-13, MFW HEATER B1 INLET, OPEN (locally).

B. Red Light ON (2-HS-3-13A).

C. Green Light OFF (2-HS-3-13A).

D. Red Light ON (2-JB-291-460).

E. Green Light OFF (2-JB-291-460).

F. No continuity across Terminal Points EAI (BK) and EA2(W) in SMS MUX Cabinet 2-CMPT-263-R134 (Relay 2-B213 PWR OFF)

M&TE ID#

[5] DEPRESS 2-HS-3-13B, MFW HEATER B1 INLET VALVE, CLOSE pushbutton at Panel 2-JB-291-460 and VERIFY 2-FCV-3-13 CLOSES by light indication. Acc Crit (5.0B.8)

[6] DEPRESS 2-HS-3-13B, MFW HEATER B1 INLET VALVE, OPEN pushbutton at Panel 2-JB-291-460, and VERIFY 2-FCV-3-13 OPENS by light indication. Acc Crit (5.0B.8)

NOTE The following steps will verify operation of the STOP pushbutton. The valve will be stopped in mid position in both the open and closed directions. The STOP pushbutton shall be depressed shortly after dual light indication is obtained.

[7] PLACE 2-HS-3-13A, B1 HEATER INLET, on 2-M-3, to the CLOSE position.

[8] DEPRESS and HOLD 2-HS-3-13B, MFW HEATER B1 INLET VALVE, STOP pushbutton at Panel 2-JB-291-460.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 79 of 371 Date 6.8 2-FCV-3-13, MFW HEATER B1 INLET, Logic Test (continued)

[9] VERIFY 2-FCV-3-13, MFW HEATER B1 INLET, STOPS at MID POSITION by light indication at Panel 2-JB-291-460.

A. 2-FCV-3-13, MFW HEATER B1 INLET, STOPPED.

B. Red Light ON (2-HS-3-13B).

C. Green Light ON (2-HS-3-13B).

[10] RELEASE 2-HS-3-13B, MFW HEATER B1 INLET VALVE, STOP pushbutton, and VERIFY 2-FCV-3-13, does not RESTART its travel.

[11] PLACE 2-HS-3-13A, B1 HEATER INLET, on 2-M-3, to the CLOSE position to fully close 2-FCV-3-13.

[12] PLACE 2-HS-3-13A, B1 HEATER INLET, on 2-M-3, to the OPEN position.

[13] DEPRESS and HOLD 2-HS-3-13B, MFW HEATER B1 INLET VALVE, STOP pushbutton at Panel 2-JB-291-460.

[14] VERIFY 2-FCV-3-13, MFW HEATER B1 INLET, STOPS at MID POSITION by light indication at Panel 2-JB-291-460.

Acc Crit (5.0B.8)

A. 2-FCV-3-13, MFW HEATER B1 INLET, STOPPED.

B. Red Light ON (2-HS-3-13B).

C. Green Light ON (2-HS-3-13B).

[15] RELEASE 2-HS-3-13B, MFW HEATER B1 INLET VALVE, STOP pushbutton, and VERIFY 2-FCV-3-13, does NOT RESTART its travel.

[16] PLACE 2-HS-3-13A, B1 HEATER INLET, on 2-M-3, to the OPEN position to fully open 2-FCV-3-13.

[17] DEPRESS 2-HS-3-13B, MFW HEATER B1 INLET VALVE, CLOSE pushbutton at Panel 2-JB-291-460.

[18] DEPRESS 2-HS-3-13B, MFW HEATER B1 INLET VALVE, STOP pushbutton at Panel 2-JB-291-460.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 80 of 371 Date 6.8 2-FCV-3-13, MFW HEATER BI INLET, Logic Test (continued)

[19] VERIFY 2-FCV-3-13, MFW HEATER B1 INLET, STOPS at MID POSITION by light indication at Panel 2-JB-291-460.

A. 2-FCV-3-13, MFW HEATER 81 INLET, STOPPED.

B. Red Light ON (2-HS-3-13B).

C. Green Light ON (2-HS-3-13B).

[20] DEPRESS 2-HS-3-13B, MFW HEATER 81 INLET VALVE, CLOSE pushbutton to fully close 2-FCV-3-13.

[21] DEPRESS 2-HS-3-13B, MFW HEATER B1 INLET VALVE, OPEN pushbutton at Panel 2-JB-291-460.

[22] DEPRESS 2-HS-3-13B, MFW HEATER B1 INLET VALVE, STOP pushbutton at Panel 2-JB-291-460.

[23] VERIFY 2-FCV-3-13, MFW HEATER B1 INLET, STOPS at MID POSITION by light indication at Panel 2-JB-291-460.

A. 2-FCV-3-13, MFW HEATER B1 INLET, STOPPED.

B. Red Light ON (2-HS-3-13B).

C. Green Light ON (2-HS-3-13B).

[24] DEPRESS 2-HS-3-13B, MFW HEATER B1 INLET VALVE, OPEN pushbutton at Panel 2-JB-291-460, to fully OPEN 2-FCV-3-13.

[25] REMOVE the cover from 2-LS-6-35D, MFW HEATER 81 SHELL SIDE LEVEL HI-HI (708/T16G).

[26] INSTALL a jumper across Terminal Points HB1X (BK) and HB1 1 (W) at 2-LS-6-35D, MFW HEATER B1 SHELL SIDE LEVEL HI-HI, to simulate a high level in MFW HEATER B1.

(Dwg 2-45W2753-1)

CV

[27] DEPRESS and HOLD 2-HS-3-13B, MFW HEATER 81 INLET VALVE, STOP pushbutton at Panel 2-JB-291-460.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 81 of 371 Date 6.8 2-FCV-3-13, MFW HEATER BI INLET, Logic Test (continued)

[28] VERIFY 2-FCV-3-13, MFW HEATER B1 INLET, STOPS at MID POSITION by light indication at Panel 2-JB-291-460.

A. 2-FCV-3-13, MFW HEATER B1 INLET, STOPPED.

B. Red Light ON (2-HS-3-13B).

C. Green Light ON (2-HS-3-13B).

[29] RELEASE 2-HS-3-13B, MFW HEATER 81 INLET VALVE, STOP pushbutton and VERIFY 2-FCV-3-13 CLOSES by light indication at Panel 2-JB-291-460. Acc Crit (5.0B.8)

[30] REMOVE jumper across Terminals HB1X (BK) and HB1 1 (W) at 2-LS-6-35D, MFW HEATER B1 SHELL SIDE LEVEL HI-HI.

CV NOTE IfSubsection 6.9 is to be performed next the following step may be marked N/A.

[31] INSTALL the cover on 2-LS-6-35D, MFW HEATER B1 SHELL SIDE LEVEL HI-HI.

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 82 of 371 Date 6.9 2-FCV-3-20, MFW HEATER B1 OUTLET, Logic Test

[1] VERIFY prerequisites listed in Section 4.0 for Subsection 6.9 have been completed.

[2] VERIFY Annunciator Window 37-A, HP HEATER B1 LEVEL HI/LO, is CLEAR.

[3] VERIFY/PLACE 2-HS-3-20A, B1 HEATER OUTLET, at 2-M-3, in the CLOSE position and VERIFY:

A. 2-FCV-3-20, MFW HEATER B1 OUTLET, CLOSED (708/T1 5F).

B. Red Light OFF (2-HS-3-20A).

C. Green Light ON (2-HS-3-20A).

D. Red Light OFF (2-JB-291-992) (708/T1 6F).

E. Green Light ON (2-JB-291-992).

F. Continuity across Terminal Points EA3 (BK) and EA4 (W) in SMS MUX Cabinet 2-CMPT-263-R134 (Relay 2-B214 PWR ON) (Dwg 2-45B2753-8C)

M&TE ID#

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 83 of 371 Date 6.9 2-FCV-3-20, MFW HEATER B1 OUTLET, Logic Test (continued)

[4] PLACE 2-HS-3-20A, B1 HEATER OUTLET, at 2-M-3, to the OPEN position and VERIFY:

A. 2-FCV-3-20, MFW HEATER B1 OUTLET, OPEN (locally)

B. Red Light ON (2-HS-3-20A).

C. Green Light OFF (2-HS-3-20A).

D. Red Light ON (2-JB-291-992).

E. Green Light OFF (2-JB-291-992).

F. No continuity across Terminal Points EA3 (BK) and EA4 (W) in SMS MUX Cabinet 2-CMPT-263-R134 (Relay 2-B214 PWR OFF)

M&TE ID#

[5] DEPRESS 2-HS-3-20B, MFW HEATER B1 OUTLET VALVE, CLOSE pushbutton at Panel 2-JB-291-992 and VERIFY 2-FCV-3-20 CLOSES by light indication. Acc Crit (5.0B.9)

[6] DEPRESS 2-HS-3-20B, MFW HEATER B1 OUTLET VALVE, OPEN pushbutton at Panel 2-JB-291-992, and VERIFY 2-FCV-3-20 OPENS by light indication. Acc Crit (5.0B.9)

NOTE The following steps will verify operation of the STOP pushbutton. The valve will be stopped in mid position in both the open and closed directions. The STOP pushbutton shall be depressed shortly after dual light indication is obtained.

[7] PLACE 2-HS-3-20A, B1 HEATER OUTLET, on 2-M-3, to the CLOSE position.

[8] DEPRESS and HOLD 2-HS-3-20B, MFW HEATER B1 OUTLET VALVE, STOP pushbutton at Panel 2-JB-291-992.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 84 of 371 Date 6.9 2-FCV-3-20, MFW HEATER B1 OUTLET, Logic Test (continued)

[9] VERIFY 2-FCV-3-20, MFW HEATER B1 OUTLET, STOPS at MID POSITION by light indication at Panel 2-JB-291-992.

A. 2-FCV-3-20, MFW HEATER B1 OUTLET, STOPPED.

B. Red Light ON (2-HS-3-20B).

C. Green Light ON (2-HS-3-20B)._

[10] RELEASE 2-HS-3-20B, MFW HEATER B1 OUTLET VALVE, STOP pushbutton and VERIFY 2-FCV-3-20, does NOT RESTART its travel.

[11] PLACE 2-HS-3-20A, B1 HEATER OUTLET, on 2-M-3, to the CLOSE position to fully close 2-FCV-3-20.

[12] PLACE 2-HS-3-20A, B1 HEATER OUTLET, on 2-M-3, to the OPEN position.

[13] DEPRESS and HOLD 2-HS-3-20B, MFW HEATER B1 OUTLET VALVE, STOP pushbutton at Panel 2-JB-291-992.

[14] VERIFY 2-FCV-3-20, MFW HEATER B1 OUTLET, STOPS at MID POSITION by light indication at Panel 2-JB-291-992.

Acc Crit (5.0B.9)

A. 2-FCV-3-20, MFW HEATER B1 OUTLET, STOPPED.

B. Red Light ON (2-HS-3-20B).

C. Green Light ON (2-HS-3-20B).

[15] RELEASE 2-HS-3-20B, MFW HEATER 81 OUTLET VALVE, STOP pushbutton, and VERIFY 2-FCV-3-20 does NOT RESTART its travel.

[16] PLACE 2-HS-3-20A, B1 HEATER OUTLET, on 2-M-3, to the OPEN position to fully open 2-FCV-3-20.

[17] DEPRESS 2-HS-3-20B, MFW HEATER B1 OUTLET VALVE, CLOSE pushbutton at Panel 2-JB-291-992.

[18] DEPRESS 2-HS-3-20B, MFW HEATER B1 OUTLET VALVE, STOP pushbutton at Panel 2-JB-291-992.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 85 of 371 Date 6.9 2-FCV-3-20, MFW HEATER BI OUTLET, Logic Test (continued)

[19] VERIFY 2-FCV-3-20, MFW HEATER 81 OUTLET, STOPS at MID POSITION by light indication at Panel 2-JB-291-992.

A. 2-FCV-3-20, MFW HEATER B1 OUTLET, STOPPED.

B. Red Light ON (2-HS-3-20B).

C. Green Light ON (2-HS-3-20B).

[20] DEPRESS 2-HS-3-20B, MFW HEATER B1 INLET VALVE, CLOSE pushbutton to fully close 2-FCV-3-20.

[21] DEPRESS 2-HS-3-20B, MFW HEATER B1 OUTLET VALVE, OPEN pushbutton at Panel 2-JB-291-992.

[22] DEPRESS 2-HS-3-20B, MFW HEATER B1 OUTLET VALVE, STOP pushbutton at Panel 2-JB-291-992.

[23] VERIFY 2-FCV-3-20, MFW HEATER B1 OUTLET, STOPS at MID POSITION by light indication at Panel 2-JB-291-992.

A. 2-FCV-3-20, MFW HEATER 81 OUTLET, STOPPED.

B. Red Light ON (2-HS-3-20B).

C. Green Light ON (2-HS-3-20B).

[24] DEPRESS 2-HS-3-20B, MFW HEATER B1 OUTLET VALVE, OPEN pushbutton at Panel 2-JB-291-992 to fully OPEN 2-FCV-3-20.

[25] REMOVE the cover from 2-LS-6-35D, MFW HEATER B1 SHELL SIDE LEVEL HI-HI (708/T15G).

[26] INSTALL a jumper across Terminal Points HBIX (BK) and HB-11 (W) at 2-LS-6-35D, MFW HEATER 81 SHELL SIDE LEVEL HI-HI, to simulate a high level in MFW HEATER BI.

(Dwg 2-45W2753-1)

CV

[27] DEPRESS and HOLD 2-HS-3-20B, MFW HEATER B1 OUTLET VALVE, STOP pushbutton at Panel 2-JB-291-992.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 86 of 371 Date 6.9 2-FCV-3-20, MFW HEATER B1 OUTLET, Logic Test (continued)

[28] VERIFY 2-FCV-3-20, MFW HEATER B1 OUTLET, STOPS at MID POSITION by light indication at Panel 2-JB-291-992.

A. 2-FCV-3-20, MFW HEATER B1 OUTLET, STOPPED.

B. Red Light ON (2-HS-3-20B).

C. Green Light ON (2-HS-3-20B).

[29] RELEASE 2-HS-3-20B, MFW HEATER B1 OUTLET VALVE, STOP pushbutton and VERIFY 2-FCV-3-20 CLOSES by light indication at Panel 2-JB-291-992. Acc Crit (5.0B.9)

[30] REMOVE jumper across Terminals HB1X (BK) and HB1 1 (W) at 2-LS-6-35D, MFW HEATER B1 SHELL SIDE LEVEL HI-HI.

CV

[31] INSTALL the cover on 2-LS-6-35D, MFW HEATER B1 SHELL SIDE LEVEL HI-HI.

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 87 of 371 Date 6.10 2-FCV-3-23, MFW HEATER Cl INLET, Logic Test

[1] VERIFY prerequisites listed in Section 4.0 for Subsection 6.10 have been completed.

[2] VERIFY Annunciator Window 38-A, HP HEATER C1 LEVEL HI/LO, is CLEAR.

[3] VERIFY/PLACE 2-HS-3-23A, C1 HEATER INLET, at 2-M-3, in the CLOSE position and VERIFY:

A. 2-FCV-3-23, MFW HEATER C1 INLET, is CLOSED (708/TI 5G).

B. Red Light OFF (2-HS-3-23A).

C. Green Light ON (2-HS-3-23A).

D. Red Light OFF (2-JB-291-460) (708/T1I6G).

E. Green Light ON (2-JB-291-460).

F. Continuity across Terminal Points AB1 (BK) and AB2 (W) in SMS MUX Cabinet 2-CMPT-263-R133 (Relay 2-A216 PWR ON) (Dwg 2-45B2752-3D).

M&TE ID#

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 88 of 371 Date 6.10 2-FCV-3-23, MFW HEATER Cl INLET, Logic Test (continued)

[4] PLACE 2-HS-3-23A, Cl HEATER INLET, at 2-M-3, to the OPEN position and VERIFY:

A. Valve 2-FCV-3-23, MFW HEATER C1 INLET, OPEN (locally).

B. Red Light ON (2-HS-3-23A).

C. Green Light OFF (2-HS-3-23A).

D. Red Light ON (2-JB-291-460).

E. Green Light OFF (2-JB-291-460).

F. No continuity across Terminal Points AB1(BK) and AB2 (W) in SMS MUX Cabinet 2-CMPT-263-R133 (Relay 2-A216 PWR OFF)

M&TE ID#

[5] DEPRESS 2-HS-3-23B, MFW HEATER Cl INLET VALVE, CLOSE pushbutton at Panel 2-JB-291-460, and VERIFY 2-FCV-3-23 CLOSES by light indication. Acc Crit (5.0B.10)

[6] DEPRESS 2-HS-3-23B, MFW HEATER Cl INLET VALVE, OPEN pushbutton at Panel 2-JB-291-460, and VERIFY 2-FCV-3-23 OPENS by light indication. Acc Crit (5.0B.10)

NOTE The following steps will verify operation of the STOP pushbutton. The valve will be stopped in mid position in both the open and closed directions. The STOP pushbutton shall be depressed shortly after dual light indication is obtained.

[7] PLACE 2-HS-3-23A, Cl HEATER INLET, on 2-M-3, to the CLOSE position.

[8] DEPRESS and HOLD 2-HS-3-23B, MFW HEATER Cl INLET VALVE, STOP pushbutton at Panel 2-JB-291-460.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 89 of 371 Date 6.10 2-FCV-3-23, MFW HEATER Cl INLET, Logic Test (continued)

[9] VERIFY 2-FCV-3-23, MFW HEATER C1 INLET, STOPS at MID POSITION by light indication at Panel 2-JB-291-460.

A. 2-FCV-3-23, MFW HEATER Cl INLET, STOPPED.

B. Red Light ON (2-HS-3-23B).

C. Green Light ON (2-HS-3-23B).

[10] RELEASE 2-HS-3-23B, MFW HEATER Cl INLET VALVE, STOP pushbutton, and VERIFY 2-FCV-3-23, does NOT RESTART its travel.

[11] PLACE 2-HS-3-23A, C1 HEATER INLET, on 2-M-3, to the CLOSE position to fully CLOSE 2-FCV-3-23.

[12] PLACE 2-HS-3-23A, C1 HEATER INLET, on 2-M-3, to the OPEN position.

[13] DEPRESS and HOLD 2-HS-3-23B, MFW HEATER C1 INLET VALVE, STOP pushbutton at Panel 2-JB-291-460.

[14] VERIFY 2-FCV-3-23, MFW HEATER C1 INLET, STOPS at MID POSITION by light indication at Panel 2-JB-291-460.

Acc Crit (5.0B.10)

A. 2-FCV-3-23, MFW HEATER C1 INLET, STOPPED.

B. Red Light ON (2-HS-3-23B).

C. Green Light ON (2-HS-3-23B).

[15] RELEASE 2-HS-3-23B, MFW HEATER C1 INLET VALVE, STOP pushbutton, and VERIFY 2-FCV-3-23 does NOT RESTART its travel.

[16] PLACE Handswitch 2-HS-3-23A, C1 HEATER INLET, on 2-M-3, to the OPEN position to fully open 2-FCV-3-23.

[17] DEPRESS 2-HS-3-23B, MFW HEATER C1 INLET VALVE, CLOSE pushbutton at Panel 2-JB-291-460.

[18] DEPRESS 2-HS-3-23B, MFW HEATER C1 INLET VALVE, STOP pushbutton at Panel 2-JB-291-460.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 90 of 371 Date 6.10 2-FCV-3-23, MFW HEATER C1 INLET, Logic Test (continued)

[19] VERIFY 2-FCV-3-23, MFW HEATER Cl INLET, STOPS at MID POSITION by light indication at Panel 2-JB-291-460.

A. 2-FCV-3-23, MFW HEATER C1 INLET, STOPPED.

B. Red Light ON (2-HS-3-23B).

C. Green Light ON (2-HS-3-23B).

[20] DEPRESS 2-HS-3-23B, MFW HEATER C1 INLET VALVE, CLOSE pushbutton to fully close 2-FCV-3-23.

[21] DEPRESS 2-HS-3-23B, MFW HEATER C1 INLET VALVE, OPEN pushbutton at Panel 2-JB-291-460.

[22] DEPRESS 2-HS-3-23B, MFW HEATER C1 INLET VALVE, STOP pushbutton at Panel 2-JB-291-460.

[23] VERIFY 2-FCV-3-23, MFW HEATER C1 INLET, STOPS at MID POSITION by light indication at Panel 2-JB-291-460.

A. 2-FCV-3-23, MFW HEATER C1 INLET, STOPPED.

B. Red Light ON (2-HS-3-23B).

C. Green Light ON (2-HS-3-23B).

[24] DEPRESS 2-HS-3-23B, MFW HEATER C1 INLET VALVE, OPEN pushbutton at Panel 2-JB-291-460 to fully OPEN 2-FCV-3-23.

[25] REMOVE the cover from 2-LS-6-58D, MFW HEATER C1 SHELL SIDE LEVEL HI-HI (708/T15G).

[26] INSTALL a jumper across Terminal Points HAI2 (W) and HA1X (BK) at 2-LS-6-58D, MFW HEATER C1 SHELL SIDE LEVEL HI-HI to simulate a high level in MFW HEATER C1.

(Dwg 2-45W2752-5)

CV

[27] DEPRESS and HOLD 2-HS-3-23B, MFW HEATER CI INLET VALVE, STOP pushbutton at Panel 2-JB-291-460.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 91 of 371 Date 6.10 2-FCV-3-23, MFW HEATER Cl INLET, Logic Test (continued)

[28] VERIFY 2-FCV-3-23, MFW HEATER Cl INLET, STOPS at MID POSITION by light indication at Panel 2-JB-291-460.

A. 2-FCV-3-23, MFW HEATER Cl INLET, STOPPED.

B. Red Light ON (2-HS-3-23B).

C. Green Light ON (2-HS-3-23B).

[29] RELEASE 2-HS-3-23B, MFW HEATER Cl INLET VALVE, STOP pushbutton and VERIFY 2-FCV-3-23 CLOSES by light indication at Panel 2-JB-291-460. Acc Crit (5.0B.10)

[30] REMOVE jumper across Terminals HA12 (W) and HAI X (BK) at 2-LS-6-58D, MFW HEATER Cl SHELL SIDE LEVEL HI-HI.-1-1 CV NOTE If Subsection 6.11 is to be performed next the following step may be marked N/A.

[31] INSTALL the cover on 2-LS-6-58D, MFW HEATER C1 SHELL SIDE LEVEL HI-HI.

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 92 of 371 Date 6.11 2-FCV-3-30, MFW HEATER Cl OUTLET, Logic Test

[1] VERIFY prerequisites listed in Section 4.0 for Subsection 6.11 have been completed.

[2] VERIFY Annunciator Window 38-A, HP HEATER C1 LEVEL HI/LO, is CLEAR.

[3] VERIFY/PLACE 2-HS-3-30A, C1 HEATER OUTLET, at 2-M-3, in the CLOSE position and VERIFY:

A. 2-FCV-3-30, MFW HEATER C1 OUTLET, CLOSED (708/TI 5G).

B. Red Light OFF (2-HS-3-30A).

C. Green Light ON (2-HS-3-30A).

D. Red Light OFF (2-JB-291-992) (708/T1I6F).

E. Green Light ON (2-JB-291-992).

F. Continuity across Terminal Points AB3 (BK) and AB4 (W) in SMS MUX Cabinet 2-CMPT-263-R133 (Relay 2-A217 PWR ON) (Dwg 2-45B2752-3E).

M&TE ID#

[4] PLACE 2-HS-3-30A, C1 HEATER OUTLET, at 2-M-3, to the OPEN position and VERIFY:

A. 2-FCV-3-30, MFW HEATER C1 OUTLET, OPEN (locally).

B. Red Light ON (2-HS-3-30A).

C. Green Light OFF (2-HS-3-30A).

D. Red Light ON (2-JB-291-992).

E. Green Light OFF (2-JB-291-992).

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 93 of 371 Date 6.11 2-FCV-3-30, MFW HEATER C1 OUTLET, Logic Test (continued)

F. No continuity across Terminal Points AB3 (BK) and AB4 (W) in SMS MUX Cabinet 2-CMPT-263-R133 (Relay 2-A217 PWR OFF)

M&TE ID#

[5] DEPRESS 2-HS-3-30B, MFW HEATER Cl OUTLET VALVE, CLOSE pushbutton at Panel 2-JB-291-992, and VERIFY 2-FCV-3-30 CLOSES by light indication. Acc Crit (5.0B.11)

[6] DEPRESS 2-HS-3-30B, MFW HEATER Cl OUTLET VALVE, OPEN pushbutton at Panel 2-JB-291-992, and VERIFY 2-FCV-3-30 OPENS by light indication. Acc Crit (5.0B.11)

NOTE The following steps will verify operation of the STOP pushbutton. The valve will be stopped in mid position in both the open and closed directions. The STOP pushbutton shall be depressed shortly after dual light indication is obtained.

[7] PLACE 2-HS-3-30A, Cl HEATER OUTLET, on 2-M-3, to the CLOSE position.

[8] DEPRESS and HOLD 2-HS-3-30B, MFW HEATER Cl OUTLET VALVE, STOP pushbutton at Panel 2-JB-291-992.

[9] VERIFY 2-FCV-3-30, MFW HEATER Cl OUTLET, STOPS at MID POSITION by light indication at Panel 2-JB-291-992.

A. 2-FCV-3-30, MFW HEATER Cl OUTLET, STOPPED.

B. Red Light ON (2-HS-3-30B).

C. Green Light ON (2-HS-3-30B).

[101 RELEASE 2-HS-3-30B, MFW HEATER Cl OUTLET VALVE, STOP pushbutton and VERIFY 2-FCV-3-30 does NOT RESTART its travel.

[11] PLACE 2-HS-3-30A, Cl HEATER OUTLET, on 2-M-3 to the CLOSE position to fully close 2-FCV-3-30.

[12] PLACE 2-HS-3-30A, Cl HEATER OUTLET, on 2-M-3 to the OPEN position.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 94 of 371 Date 6.11 2-FCV-3-30, MFW HEATER C1 OUTLET, Logic Test (continued)

[13] DEPRESS and HOLD 2-HS-3-30B, MFW HEATER C1 OUTLET VALVE, STOP pushbutton at Panel 2-JB-291-992.

[14] VERIFY 2-FCV-3-30, MFW HEATER C1 OUTLET, STOPS at MID POSITION by light indication at Panel 2-JB-291-992.

Acc Crit (5.0B.1 1)

A. 2-FCV-3-30, MFW HEATER C1 OUTLET, STOPPED.

B. Red Light ON (2-HS-3-30B).

C. Green Light ON (2-HS-3-30B).

[15] RELEASE 2-HS-3-30B, MFW HEATER C1 OUTLET VALVE, STOP pushbutton and VERIFY 2-FCV-3-30 does NOT RESTART its travel.

[16] PLACE 2-HS-3-30A, C1 HEATER OUTLET, on 2-M-3 to the OPEN position to fully open 2-FCV-3-30.

[17] DEPRESS 2-HS-3-30B, MFW HEATER C1 OUTLET VALVE, CLOSE pushbutton at Panel 2-JB-291-992.

[18] DEPRESS 2-HS-3-30B, MFW HEATER C1 OUTLET VALVE, STOP pushbutton at Panel 2-JB-291-992.

[19] VERIFY 2-FCV-3-30, MFW HEATER C1 OUTLET, STOPS at MID POSITION by light indication at Panel 2-JB-291-992.

A. 2-FCV-3-30, MFW HEATER C1 OUTLET, STOPPED.

B. Red Light ON (2-HS-3-30B).

C. Green Light ON (2-HS-3-30B).

[20] DEPRESS 2-HS-3-30B, MFW HEATER C1 OUTLET VALVE, CLOSE pushbutton to fully close 2-FCV-3-30.

[21] DEPRESS 2-HS-3-30B, MFW HEATER C1 OUTLET VALVE, OPEN pushbutton at Panel 2-JB-291-992.

[22] DEPRESS 2-HS-3-30B, MFW HEATER C1 OUTLET VALVE, STOP pushbutton at Panel 2-JB-291-992.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 95 of 371 Date 6.11 2-FCV-3-30, MFW HEATER Cl OUTLET, Logic Test (continued)

[23] VERIFY 2-FCV-3-30, MFW HEATER C1 OUTLET, STOPS at MID POSITION by light indication at Panel 2-JB-291-992.

A. 2-FCV-3-30, MFW HEATER C1 OUTLET, STOPPED.

B. Red Light ON (2-HS-3-30B).

C. Green Light ON (2-HS-3-30B).

[24] DEPRESS 2-HS-3-30B, MFW HEATER C1 OUTLET VALVE, OPEN pushbutton at Panel 2-JB-291-992 to fully OPEN 2-FCV-3-30.

[25] REMOVE the cover from 2-LS-6-58D, MFW HEATER C1 SHELL SIDE HI-HI (708/TI'5G).

[26] INSTALL a jumper across Terminal Points HA1 2 (W) and HA1X (BK) at 2-LS-6-58D, MFW HEATER C1 SHELL SIDE HI-HI, to simulate a high level in MFW HEATER C1. (Dwg 2-45W2752-5)

CV (27] DEPRESS and HOLD 2-HS-3-30B MFW HEATER C1 OUTLET VALVE, STOP pushbutton at Panel 2-JB-291-992.

[28] VERIFY 2-FCV-3-30, MFW HEATER C1 INLET, STOPS at MID POSITION by light indication at Panel 2-JB-291-992.

[29] RELEASE 2-HS-3-30B, MEW HEATER C1 OUTLET VALVE, STOP pushbutton and VERIFY 2-FCV-3-30 CLOSES by light indication at Panel 2-JB-291-992. Acc Crit (5.0B.11)

[30] REMOVE jumper across Terminals HA12 (W) and HA1X (BK) at 2-LS-6-58D, MFW HEATER C1 SHELL SIDE HI-HI.

CV

[31] INSTALL the cover on 2-LS-6-58D, MFW HEATER C1 SHELL SIDE HI-HI.

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 96 of 371 Date 6.12 2-FCV-3-67, MAIN FEEDWATER PUMP A DISCHARGE ISOL, Logic Test

[1] VERIFY prerequisites listed in Section 4.0 for Subsection 6.12 have been completed.

[2] VERIFYIPLACE 2-HS-3-67A, MFWP A DISCH ISOL, at 2-M-3 to the CLOSE position and VERIFY:

A. 2-FCV-3-67, MAIN FEEDWATER PUMP A DISCHARGE ISOL, CLOSED (729/T16-H).

B. Red Light OFF (2-HS-3-67A).

C. Green Light ON (2-HS-3-67A).

D. Red Light OFF (2-JB-291-681) (7291T16J).

E. Green Light ON (2-JB-291-681).

F. Continuity across Terminal Points EA1 (BK) and EA2 (W) in SMS MUX Cabinet 2-CMPT-263-R133 (Relay 2-A213 PWR ON) (Dwg 2-45B2754-3B)

M&TE ID#

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 97 of 371 Date 6.12 2-FCV-3-67, MAIN FEEDWATER PUMP A DISCHARGE ISOL, Logic Test (continued)

[3] PLACE 2-HS-3-67A, MFWP A DISCH ISOL, at 2-M-3 in the OPEN position and VERIFY:

A. 2-FCV-3-67, MAIN FEEDWATER PUMP A DISCHARGE ISOL, OPEN (locally).

B. Red Light ON (2-HS-3-67A).

C. Green Light OFF (2-HS-3-67A).

D. Red Light ON (2-JB-291-681).

E. Green Light OFF (2-JB-291-681)

F. No continuity across Terminal Points EA1 (BK) and EA2 (W) in SMS MUX Cabinet 2-CMPT-263-R133 (Relay 2-A213 PWR OFF)

M&TE ID#

[4] DEPRESS 2-HS-3-67B, MAIN FEEDWATER PUMP A DISCHARGE ISOL, CLOSE pushbutton at Panel 2-JB-291-681 and VERIFY 2-FCV-3-67 CLOSES by light indication.

[5] DEPRESS 2-HS-3-67B, MAIN FEEDWATER PUMP A DISCHARGE ISOL, OPEN pushbutton at Panel 2-JB-291-681 and VERIFY 2-FCV-3-67 OPENS by light indication.

NOTE The following steps will verify operation of the STOP pushbutton. The valve will be stopped in mid position for both the open and closed directions. The STOP pushbutton shall be depressed shortly after dual light indication is obtained.

[6] PLACE 2-HS-3-67A, MFWP A DISCH ISOL, at 2-M-3 to the CLOSE position.

[7] DEPRESS and HOLD 2-HS-3-67B, MAIN FEEDWATER PUMP A DISCHARGE ISOL, STOP pushbutton at Panel 2-JB-291-681.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 98 of 371 Date 6.12 2-FCV-3-67, MAIN FEEDWATER PUMP A DISCHARGE ISOL, Logic Test (continued)

[8] VERIFY 2-FCV-3-67, MAIN FEEDWATER PUMP A DISCHARGE ISOL, STOPS at MID POSITION by light indication at Panel 2-JB-291-681.

A. 2-FCV-3-67, MAIN FEEDWATER PUMP A DISCHARGE ISOL, STOPPED.

B. Red Light ON (2-HS-3-67B).

C. Green Light ON (2-HS-3-67B).

[9] RELEASE 2-HS-3-67B, MAIN FEEDWATER PUMP A DISCHARGE ISOL VLV, STOP pushbutton and VERIFY 2-FCV-3-67 does NOT RESTART its travel.

[10] PLACE 2-HS-3-67A, MFWP A DISCH ISOL, at 2-M-3 to the CLOSE position to fully close 2-FCV-3-67.

[11] PLACE 2-HS-3-67A, MFWP A DISCH ISOL, on 2-M-3, to the OPEN position.

[12] DEPRESS and HOLD 2-HS-3-67B, MAIN FEEDWATER PUMP A DISCHARGE ISOL VLV, STOP pushbutton at Panel 2-JB-291-681.

[13] VERIFY 2-FCV-3-67, MAIN FEEDWATER PUMP A DISCH ISOL, STOPS at MID POSITION by light indication at Panel 2-JB-291-681.

A. 2-FCV-3-67, MAIN FEEDWATER PUMP A DISCHARGE ISOL, STOPPED.

B. Red Light ON (2-HS-3-67B).

C. Green Light ON (2-HS-3-67B).

[14] RELEASE 2-HS-3-67B, MAIN FEEDWATER PUMP A DISCHARGE ISOL VLV, STOP pushbutton and VERIFY 2-FCV-3-67 does NOT RESTART its travel.

[15] PLACE 2-HS-3-67A, MFWP A DISCH ISOL, at 2-M-3 to the OPEN position to fully open Valve 2-FCV-3-67.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 99 of 371 Date 6.12 2-FCV-3-67, MAIN FEEDWATER PUMP A DISCHARGE ISOL, Logic Test (continued)

[16] DEPRESS 2-HS-3-67B, MAIN FEEDWATER PUMP A DISCHARGE ISOL VLV, CLOSE pushbutton at Panel 2-JB-291-681.

[17] DEPRESS 2-HS-3-67B, MAIN FEEDWATER PUMP A DISCHARGE ISOL VLV, STOP pushbutton at Panel 2-JB-291-681.

[18] VERIFY 2-FCV-3-67, MAIN FEEDWATER PUMP A DISCHARGE ISOL, STOPS at MID POSITION by light indication, at Panel 2-JB-291-681.

A. 2-FCV-3-67, MAIN FEEDWATER PUMP A DISCHARGE ISOL, STOPPED.

B. Red Light ON (2-HS-3-67B).

C. Green Light ON (2-HS-3-67B).

[19] DEPRESS 2-HS-3-67B, MAIN FEEDWATER PUMP A DISCHARGE ISOL VLV, CLOSE pushbutton at Panel 2-JB-291-681 to fully close 2-FCV-3-67.

Acc Crit (5.0B. 12)

[20] DEPRESS 2-HS-3-67B, MAIN FEEDWATER PUMP A DISCHARGE ISOL VLV, OPEN pushbutton at Panel 2-JB-291-681.

[21] DEPRESS 2-HS-3-67B, MAIN FEEDWATER PUMP A DISCHARGE ISOL VLV, STOP pushbutton at Panel 2-JB-291-681.

[22] VERIFY 2-FCV-3-67, MAIN FEEDWATER PUMP A DISCHARGE ISOL, STOPS at MID POSITION by light indication at Panel 2-JB-291-681.

A. 2-FCV-3-67, MAIN FEEDWATER PUMP A DISCHARGE ISOL, STOPPED.

B. Red Light ON (2-HS-3-67B).

C. Green Light ON (2-HS-3-67B).

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 100 of 371 Date 6.12 2-FCV-3-67, MAIN FEEDWATER PUMP A DISCHARGE ISOL, Logic Test (continued)

[23] DEPRESS 2-HS-3-67B, MAIN FEEDWATER PUMP A DISCHARGE ISOL VLV, CLOSE pushbutton at Panel 2-JB-291-681 and VERIFY 2-FCV-3-67 CLOSES.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 101 of 371 Date 6.13 2-FCV-3-81, MAIN FEEDWATER PUMP B DISCHARGE ISOL, Logic Test

[1] VERIFY prerequisites listed in Section 4.0 for Subsection 6.13 have been completed.

[2] VERIFY/PLACE 2-HS-3-81A, MFWP B DISCH ISOL, at 2-M-3 to the CLOSE position and VERIFY:

A. 2-FCV-3-81, MAIN FEEDWATER PUMP B DISCHARGE ISOL, CLOSED (729/T16J).

B. Red Light OFF (2-HS-3-81A).

C. Green Light ON (2-HS-3-81A)

D. Red Light OFF (2-JB-291-682) (729/TI6H).

E. Green Light ON (2-JB-291-682)._

F. Continuity across Terminal Points DA5 (BK) and DA6 (W) in SMS MUX Cabinet 2-CMPT-263-R134 (Relay 2-8212 PWR ON) (Dwg 2-45B2753-8A).

M&TE ID#

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 102 of 371 Date 6.13 2-FCV-3-81, MAIN FEEDWATER PUMP B DISCHARGE ISOL, Logic Test (continued)

[3] PLACE 2-HS-3-81A, MFWP B DISCH ISOL, at 2-M-3 in the OPEN position and VERIFY:

A. 2-FCV-3-81, MAIN FEEDWATER PUMP B DISCHARGE ISOL, OPEN (locally).

B. Red Light ON (2-HS-3-81A).

C. Green Light OFF (2-HS-3-81A).

D. Red Light ON (2-JB-291-682).

E. Green Light OFF (2-JB-291-682).

F. No continuity across Terminal Points DA5 (BK) and DA6 (W) in SMS MUX Cabinet 2-CMPT-263-Rl 34 (Relay 2-B212 PWR OFF)

M&TE ID#

[4] DEPRESS 2-HS-3-81B MAIN FEEDWATER PUMP B DISCHARGE ISOL VLV, CLOSE pushbutton at Panel 2-JB-291-682 and VERIFY 2-FCV-3-81 CLOSES by light indication.

[5] DEPRESS 2-HS-3-81 B, MAIN FEEDWATER PUMP B DISCHARGE ISOL VLV, OPEN pushbutton at Panel 2-JB-291-682 and VERIFY 2-FCV-3-81 OPENS by light indication.

NOTE The following steps will verify operation of the STOP pushbutton. The valve will be stopped in mid position for both the open and closed directions. The STOP pushbutton shall be depressed shortly after dual light indication is obtained.

[6] PLACE 2-HS-3-81A, MFWP B DISCH ISOL, at 2-M-3 to the CLOSE position.

[7] DEPRESS and HOLD 2-HS-3-81 B, MAIN FEEDWATER PUMP B DISCHARGE ISOL VLV, STOP pushbutton at Panel 2-JB-291-682.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 103 of 371 Date 6.13 2-FCV-3-81, MAIN FEEDWATER PUMP B DISCHARGE ISOL, Logic Test (continued)

[8] VERIFY 2-FCV-3-81, MAIN FEEDWATER PUMP B DISCHARGE ISOL VLV, STOPS at MID POSITION by light indication at Panel 2-JB-291-682.

A. 2-FCV-3-81, MAIN FEEDWATER PUMP B DISCHARGE ISOL, STOPPED.

B. Red Light ON (2-HS-3-81 B).

C. Green Light ON (2-HS-3-81 B).

[9] RELEASE 2-HS-3-81B, MAIN FEEDWATER PUMP B DISCHARGE ISOL VLV, STOP pushbutton and VERIFY 2-FCV-3-81 does NOT RESTART its travel.

[10] PLACE 2-HS-3-81A, MFWP B DISCH ISOL, at 2-M-3 to the CLOSE position to fully close 2-FCV-3-81.

[11] PLACE 2-HS-3-81A, MFWP B DISCH ISOL, on 2-M-3 to the OPEN position.

[12] DEPRESS and HOLD 2-HS-3-81B, MAIN FEEDWATER PUMP B DISCHARGE ISOL VLV, STOP pushbutton at Panel 2-JB-291-682.

[13] VERIFY 2-FCV-3-81, MAIN FEEDWATER PUMP B DISCHARGE ISOL, STOPS at MID POSITION by light indication at Panel 2-JB-291-682.

A. 2-FCV-3-81, MAIN FEEDWATER PUMP B DISCHARGE ISOL, STOPPED.

B. Red Light ON (2-HS-3-81 B).

C. Green Light ON (2-HS-3-81B).

[14] RELEASE 2-HS-3-81B, MAIN FEEDWATER PUMP B DISCHARGE ISOL VLV, STOP pushbutton and VERIFY 2-FCV-3-81 does NOT RESTART its travel.

[15] PLACE 2-HS-3-81A, MFWP B DISCH ISOL, at 2-M-3 to the OPEN position to fully open 2-FCV-3-81.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 104 of 371 Date 6.13 2-FCV-3-81, MAIN FEEDWATER PUMP B DISCHARGE ISOL, Logic Test (continued)

[16] DEPRESS 2-HS-3-81B, MAIN FEEDWATER PUMP B DISCHARGE ISOL VLV, CLOSE pushbutton at Panel 2-JB-291-682.

[17] DEPRESS 2-HS-3-81B, MAIN FEEDWATER PUMP B DISCHARGE ISOL VLV, STOP pushbutton at Panel 2-JB-291-682.

[18] VERIFY 2-FCV-3-81, MAIN FEEDWATER PUMP B DISCHARGE ISOL, STOPS at MID POSITION by light indication at Panel 2-JB-291-682.

A. 2-FCV-3-81, MAIN FEEDWATER PUMP B DISCHARGE ISOL, STOPPED.

B. Red Light ON (2-HS-3-81 B).

C. Green Light ON (2-HS-3-81B).

[19] DEPRESS 2-HS-3-81B, MAIN FEEDWATER PUMP B DISCHARGE ISOL VLV, CLOSE pushbutton at Panel 2-JB-291-682 to fully close 2-FCV-3-81.

Acc Crit (5.0B.13)

[20] DEPRESS 2-HS-3-81B, MAIN FEEDWATER PUMP B DISCHARGE ISOL VLV, OPEN pushbutton at Panel 2-JB-291-682.

[21] DEPRESS 2-HS-3-81B, MAIN FEEDWATER PUMP B DISCHARGE ISOL VLV, STOP pushbutton at Panel 2-JB-291-682.

[22] VERIFY Valve 2-FCV-3-81 MAIN FEEDWATER PUMP B DISCHARGE ISOL, STOPS at MID POSITION by light indication at Panel 2-JB-291-682.

A. 2-FCV-3-81, MAIN FEEDWATER PUMP B DISCHARGE ISOL, STOPPED.

B. Red Light ON (2-HS-3-81 B).

C. Green Light ON (2-HS-3-81B).

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 105 of 371 Date 6.13 2-FCV-3-81, MAIN FEEDWATER PUMP B DISCHARGE ISOL, Logic Test (continued)

[23] DEPRESS 2-HS-3-81B, MAIN FEEDWATER PUMP B DISCHARGE ISOL VLV, CLOSE pushbutton at Panel 2-JB-291-682 and VERIFY 2-FCV-3-81 CLOSES.

6.14 2-FCV-3-86, MAIN FEEDWATER PUMPS BYPASS ISOL, Logic Test

[1] VERIFY prerequisites listed in Section 4.0 for Subsection 6.14 have been completed.

[2] VERIFY/PLACE 2-HS-3-86A, MFW PMPS BYPASS ISOL, at 2-M-3 to the CLOSE position and VERIFY:

A. 2-FCV-3-86, MAIN FEEDWATER PUMPS BYPASS ISOL, CLOSED (729/T15G).

B. Red Light OFF (2-HS-3-86A).

C. Green Light ON (2-HS-3-86A).

D. Red Light OFF (2-JB-291-2868) (729/T15G).

E. Green Light ON (2-JB-291-2868).

[3] PLACE 2-HS-3-86A, MFW PMPS BYPASS ISOL, in the OPEN position and VERIFY:

A. 2-FCV-3-86, MAIN FEEDWATER PUMPS BYPASS ISOL, OPEN (locally).

B. Red Light ON (2-HS-3-86A).

C. Green Light OFF (2-HS-3-86A).

D. Red Light ON (2-JB-291-2868).

E. Green Light OFF (2-JB-291-2868).

.[4] DEPRESS 2-HS-3-86B, MAIN FEEDWATER PUMPS BYPASS ISOL VLV, CLOSE pushbutton at Panel 2-JB-291-2868 and VERIFY 2-FCV-3-86 CLOSES by light indication. Acc Crit (5.0B.5)

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 106 of 371 Date 6.14 2-FCV-3-86, MAIN FEEDWATER PUMPS BYPASS ISOL, Logic Test (continued)

[5] DEPRESS 2-HS-3-86B, MAIN FEEDWATER PUMPS BYPASS ISOL VLV, OPEN pushbutton at Panel 2-JB-291-2868 and VERIFY 2-FCV-3-86 OPENS by light indication. Acc Crit (5.0B.5)

NOTE The following steps will verify operation of the STOP pushbutton. The valve will be stopped in mid position for both the open and closed directions. The STOP pushbutton shall be depressed shortly after dual light indication is obtained.

[6] PLACE 2-HS-3-86A, MFW PMPS BYPASS ISOL, at 2-M-3 to the CLOSE position.

[7] DEPRESS and HOLD 2-HS-3-86B, MAIN FEEDWATER PUMPS BYPASS ISOL VLV, STOP pushbutton at Panel 2-JB-291-2868.

[8] VERIFY 2-FCV-3-86, MAIN FEEDWATER PUMPS BYPASS ISOL, STOPS at MID POSITION by light indication at Panel 2-JB-291-2868.

A. 2-FCV-3-86, MAIN FEEDWATER PUMPS BYPASS ISOL, STOPPED.

B. Red Light ON (2-HS-3-86B).

C. Green Light ON (2-HS-3-86B).

[9] RELEASE 2-HS-3-86B, MAIN FEEDWATER PUMPS BYPASS ISOL VLV, STOP pushbutton and VERIFY 2-FCV-3-86 does NOT RESTART its travel.

[10] PLACE 2-HS-3-86A, MFW PMPS BYPASS ISOL, at 2-M-3 to the CLOSE position to fully close 2-FCV-3-86.

[11] PLACE 2-HS-3-86A, MFW PMPS BYPASS ISOL, at 2-M-3 to the OPEN position.

[12] DEPRESS and HOLD 2-HS-3-86B, MAIN FEEDWATER PUMPS BYPASS ISOL VLV, STOP pushbutton at Panel 2-JB-291-2868.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 107 of 371 Date 6.14 .2-FCV-3-86, MAIN FEEDWATER PUMPS BYPASS ISOL, Logic Test (continued)

[13] VERIFY 2-FCV-3-86, MAIN FEEDWATER PUMPS BYPASS ISOL, STOPS at MID POSITION by light indication at Panel 2-JB-291-2868.

A. 2-FCV-3-86, MAIN FEEDWATER PUMPS BYPASS ISOL, STOPPED.

B. Red Light ON (2-HS-3-86B).

C. Green Light ON (2-HS-3-86B).

[14] RELEASE 2-HS-3-86B, MAIN FEEDWATER PUMPS BYPASS ISOL VLV, STOP pushbutton and VERIFY 2-FCV-3-86 does NOT RESTART its travel.

[15] PLACE 2-HS-3-86A, MFW PMPS BYPASS ISOL, at 2-M-3 to the OPEN position to fully open 2-FCV-3-86.

[16] DEPRESS 2-HS-3-86B, MAIN FEEDWATER PUMPS BYPASS ISOL VLV, CLOSE pushbutton at Panel 2-JB-291-2868.

[17] DEPRESS 2-HS-3-86B, MAIN FEEDWATER PUMPS BYPASS ISOL VLV, STOP pushbutton at Panel 2-JB-291-2868.

[18] VERIFY 2-FCV-3-86, MAIN FEEDWATER PUMPS BYPASS ISOL, STOPS at MID POSITION by light indication at Panel 2-JB-291-2868.

A. 2-FCV-3-86, MAIN FEEDWATER PUMPS BYPASS ISOL, STOPPED.

B. Red Light ON (2-HS-3-86B).

C. Green Light ON (2-HS-3-86B).

[19] DEPRESS 2-HS-3-86B, MAIN FEEDWATER PUMPS BYPASS ISOL VLV, CLOSE pushbutton at Panel 2-JB-291-2868 to fully close 2-FCV-3-86.

[20] DEPRESS 2-HS-3-86B, MAIN FEEDWATER PUMP BYPASS ISOL VLV, OPEN pushbutton at Panel 2-JB-291-2868.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 108 of 371 Date 6.14 2-FCV-3-86, MAIN FEEDWATER PUMPS BYPASS ISOL, Logic Test (continued)

[21] DEPRESS 2-HS-3-86B, MAIN FEEDWATER PUMPS BYPASS ISOL VLV, STOP pushbutton at Panel 2-JB-291-2868.

[22] VERIFY 2-FCV-3-86, MAIN FEEDWATER PUMPS BYPASS ISOL, STOPS at MID POSITION by light indication at Panel 2-JB-291-2868.

A. 2-FCV-3-86, MAIN FEEDWATER PUMPS BYPASS ISOL, STOPPED.

B. Red Light ON (2-HS-3-86B).

C. Green Light ON (2-HS-3-86B).

[23] DEPRESS 2-HS-3-86B, MAIN FEEDWATER PUMPS BYPASS ISOL VLV, CLOSE pushbutton at Panel 2-JB-291-2868 and VERIFY 2-FCV-3-86 CLOSES.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 109 of 371 Date 6.15 2-FCV-3-195, MFW DEAERATION LINE CONTROL, Logic Test

[1] VERIFY prerequisites listed in Section 4.0 for Subsection 6.15 have been completed.

[2] DEPRESS 2-HS-3-195B, MFW DEAERATION LINE CONTROL VLV, CLOSE pushbutton at Panel 2-JB-291-2846, (708/TI 3J) and VERIFY: Acc Crit (5.0B.5)

A. 2-FCV-3-195, MFW DEAERATION LINE CONTROL, CLOSED (708/T13J).

B. Red Light OFF (2-HS-3-195B).

C. Green Light ON (2-HS-3-195B).

[3] DEPRESS 2-HS-3-195B, MFW DEAERATION LINE CONTROL VLV, OPEN pushbutton at Panel 2-JB-291-2846 and VERIFY: Acc Crit (5.0B.5)

A. 2-FCV-3-195, MFW DEAERATION LINE CONTROL VLV, OPEN (locally).

B. Red Light ON (2-HS-3-195B).

C. Green Light OFF (2-HS-3-195B).

NOTE The following steps will verify operation of the STOP pushbutton. The valve will be stopped in mid position for both the open and closed directions. The STOP pushbutton shall be depressed shortly after dual light indication is obtained.

[4] DEPRESS 2-HS-3-195B, MFW DEAERATION LINE CONTROL VLV, CLOSE pushbutton at Panel 2-JB-291-2846.

[5] DEPRESS and HOLD 2-HS-3-195B, MFW DEAERATION LINE CONTROL, STOP pushbutton at Panel 2-JB-291-2846.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 110 of 371 Date 6.15 2-FCV-3-195, MFW DEAERATION LINE CONTROL, Logic Test (continued)

[6] VERIFY 2-FCV-3-195, MFW DEAERATION LINE CONTROL, STOPS at MID POSITION by light indication at Panel 2-JB-291-2846.

A. 2-FCV-3-195, MFW DEAERATION LINE CONTROL, STOPPED.

B. Red Light ON (2-HS-3-195B).

C. Green Light ON (2-HS-3-195B).

[7] RELEASE 2-HS-3-195B, MFW DEAERATION LINE CONTROL VLV, STOP pushbutton and VERIFY 2-FCV-3-195 does NOT RESTART its travel.

[8] DEPRESS 2-HS-3-195B, MFW DEAERATION LINE CONTROL VLV, CLOSE pushbutton at Panel 2-JB-291-2846 to fully close 2-FCV-3-195.

[9] DEPRESS 2-HS-3-195B, MFW DEAERATION LINE CONTROL VLV, OPEN pushbutton at Panel 2-JB-291-2846.

[10] DEPRESS and HOLD 2-HS-3-195B, MFW DEAERATION LINE CONTROL VLV, STOP pushbutton at Panel 2-JB-291-2846.

[11] VERIFY Valve 2-FCV-3-195, MFW DEAERATION LINE CONTROL, STOPS at MID POSITION by light indication at Panel 2-JB-291-2846.

A. 2-FCV-3-195, MFW DEAERATION LINE CONTROL, STOPPED.

B. Red Light ON (2-HS-3-195B).

C. Green Light ON (2-HS-3-195B).

[12] RELEASE 2-HS-3-195B, MFW DEAERATION LINE CONTROL VLV, STOP pushbutton and VERIFY 2-FCV-3-195 does NOT RESTART its travel.

[13] DEPRESS 2-HS-3-195B, MFW DEAERATION LINE CONTROL VLV, CLOSE pushbutton at Panel 2-JB-291-2846 and VERIFY 2-FCV-3-195 CLOSES by light indication.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 111 of 371 Date 6.16 2-FCV-3-70, MAIN FEEDWATER PUMP A RECIRC, Functional Test

[1] VERIFY prerequisites listed in Section 4.0 for Subsection 6.16 have been completed.

[2] VERIFY/PLACE 2-FIC-3-70, MFWP A RECIRC CONTROL, on 2-M-3 in MANUAL with the controller set to 100% and VERIFY:

A. 2-FCV-3-70, MAIN FEEDWATER PUMP A RECIRC, CLOSED (729/T1 5H).

B. Red Light OFF (2-JB-291-1149) (729/T16J).

C. Green Light ON (2-JB-291-1149).

[3] ADJUST controller 2-FIC-3-70, MFWP A RECIRC CONTROL, until 0% output is obtained and VERIFY:

A. 2-FCV-3-70, MAIN FEEDWATER PUMP A RECIRC, OPEN (locally).

B. Red Light ON (2-JB-291-1149).

C. Green Light OFF (2-JB-291-1149).

[4] ADJUST controller 2-FIC-3-70; MFWP A RECIRC CONTROL, until 100% output is obtained and VERIFY 2-FCV-3-70 CLOSES.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 112 of 371 Date 6.16 2-FCV-3-70, MAIN FEEDWATER PUMP A RECIRC, Functional Test (continued)

NOTE The following steps repeat steps 6.16[2] through 6.1614] using the DCS workstation screen mimic for 2-FIC-3-70 instead of the controller on 2-M-3.

[5] VERIFY/PLACE 2-FIC-3-70, MFWP A RECIRC CONTROL, in MANUAL with the controller set to 100% and VERIFY:

A. 2-FCV-3-70, MAIN FEEDWATER PUMP A RECIRC, CLOSED (729/T"5H).

B. Red Light OFF (2-JB-291-1149) (729/T16J).

C. Green Light ON (2-JB-291-1149).

[6] ADJUST controller 2-FIC-3-70, MFWP A RECIRC CONTROL, until 0% output is obtained and VERIFY:

A. 2-FCV-3-70, MAIN FEEDWATER PUMP A RECIRC, OPEN (locally).

B. Red Light ON (2-JB-291-1149).

C. Green Light OFF (2-JB-291-1149).

[7] ADJUST controller 2-FIC-3-70; MFWP A RECIRC CONTROL, until 100% output is obtained and VERIFY 2-FCV-3-70 CLOSES.

[8] CLOSE 2-ISV-32-2602 (729/TI 5H), CONTROL AIR ISOLATION VALVE TO 2-FCV-3-70.

[9] OPEN petcock on 2-PREG-3-70/A2, CONTROL AIR PRESSURE REG FOR 2-FM-3-70E, to bleed off control air to 2-FCV-3-70, MAIN FEEDWATER PUMP A RECIRC.

CV

[10] OPEN petcock on air tank for 2-FCV-3-70, MAIN FEEDWATER PUMP A RECIRC, to bleed OFF control air to 2-FM-3-70E, FW PUMP A I/P.

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 113 of 371 Date 6.16 2-FCV-3-70, MAIN FEEDWATER PUMP A RECIRC, Functional Test (continued)

[11] VERIFY locally 2-FCV-3-70, MAIN FEEDWATER PUMP A RECIRC, FAILS to the OPEN position by valve stem position indication.

[12] CLOSE the petcock on the air tank for 2-FCV-3-70, MAIN FEEDWATER PUMP A RECIRC.

CV

[13] CLOSE the petcock on 2-PREG-3-70/A2, CONTROL AIR PRESSURE REG FOR 2-FM-3-70E.

CV

[14] OPEN 2-ISV-32-2602, CONTROL AIR ISOLATION VALVE TO 2-FCV-3-70.

[15] VERIFY locally 2-FCV-3-70, MAIN FEEDWATER PUMP A RECIRC, CLOSES by valve stem position indication.

[16] CLOSE isolation valve 2-RTV-3-251 A, 2-FT-3-70A/70B/70D ROOT (729/T16H), on the high side of 2-FT-3-70A, MAIN FEEDWATER PUMP A DISCHARGE FLOW.

[17] REMOVE the cap from the calibration tap for the high side of 2-FT-3-70A, MAIN FEEDWATER PUMP A DISCHARGE FLOW.

CV

[18] INSTALL 0-100"H 20 pressure gage and hand pump/test rig at the calibration tap for 2-FT-3-70A, MAIN FEEDWATER PUMP A DISCHARGE FLOW.

M&TE ID#

CV

[19] PLACE 2-FIC-3-70, MFWP A RECIRC CONTROL, on 2-M-3, in AUTO and VERIFY 2-FCV-3-70 OPENS.

[20] INCREASE the simulated pressure between 16" and 18" H 2 0 to simulate a flow greater than 4000 GPM.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 114 of 371 Date 6.16 2-FCV-3-70, MAIN FEEDWATER PUMP A RECIRC, Functional Test (continued)

[21] VERIFY 2-FCV-3-70, MAIN FEEDWATER PUMP A RECIRC, CLOSES by light indication at Panel 2-JB-291-1149.

Acc Crit (5.0B.47)

[22] VERIFY Annunciator Window 57-A, MFP 2A FLOW LO, at 2-XA-55-3C is CLEAR.

[23] DECREASE the simulated pressure between 3" and 5" H 2 0 to simulate a low flow condition.

[24] VERIFY Annunciator Window 57-A, MFP 2A FLOW LO, is in ALARM. Acc Crit (5.0B.47)

[25] VERIFY 2-FCV-3-70, MAIN FEEDWATER PUMP A RECIRC, OPENS by light indication at Panel 2-JB-291-1149.

Acc Crit (5.0B.47)

[26] INCREASE the simulated pressure between 10" and 12" H20 and VERIFY 2-FCV-3-70, MAIN FEEDWATER PUMP A RECIRC, is THROTTLED by light indication at Panel 2-JB-291-1149. Acc Crit (5.08.47)

[27] VERIFY Annunciator Window 57-A, MFP 2A FLOW LO, is CLEAR.

[28] DECREASE the simulated pressure to 0" H20.

[29] DEPRESSURIZE AND REMOVE the 0-100" H20 pressure gage and hand pump/test rig from the calibration tap for 2-FT-3-70A, MAIN FEEDWATER PUMP A DISCHARGE FLOW.

CV

[30] INSTALL the cap on the calibration tap on the high side of 2-FT-3-70A, MAIN FEEDWATER PUMP A DISCHARGE.

CV

[31] OPEN isolation valve 2-RTV-3-251A, 2-FT-3-70A/70B/70D ROOT, on the high side of 2-FT-3-70A, MAIN FEEDWATER PUMP A DISCHARGE FLOW.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 115 of 371 Date 6.16 2-FCV-3-70, MAIN FEEDWATER PUMP A RECIRC, Functional Test (continued)

[32] PLACE 2-FIC-3-70, MFWP A RECIRC CONTROL, in MANUAL and VERIFY Valve 2-FCV-3-70 CLOSES.

6.17 2-FCV-3-84, MAIN FEEDWATER PUMP B RECIRC, Functional Test

[1] VERIFY prerequisites listed in Section 4.0 for Subsection 6.17 have been completed.

[2] VERIFY/PLACE 2-FIC-3-84, MFWP B RECIRC CONTROL, on 2-M-3 in MANUAL with the controller set to 100% output and VERIFY:

A. 2-FCV-3-84, MAIN FEEDWATER PUMP B RECIRC, CLOSED (729/T1 5G).

B. Red Light OFF (2-JB-291-1219) (729/T16H).

C. Green Light ON (2-JB-291-1219).

[3] DEPRESS the (OPEN) pushbutton on controller 2-FIC-3-84, MFWP B RECIRC CONTROL, until 0% output is obtained and VERIFY:

A. 2-FCV-3-84, MAIN FEEDWATER PUMP B RECIRC, OPEN (locally).

B. Red Light ON (2-JB-291-1219).

C. Green Light OFF (2-JB-291-1219).

[4] DEPRESS the (CLOSE) pushbutton on controller 2-FIC-3-84, MFWP B RECIRC CONTROL, until 100% output is obtained and VERIFY 2-FCV-3-84 CLOSES.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 116 of 371 Date 6.17 2-FCV-3-84, MAIN FEEDWATER PUMP B RECIRC, Functional Test (continued)

NOTE The following steps repeat steps 6.17[2] through 6.17[4] using the DCS workstation screen mimic for 2-FIC-3-84 instead of the controller on 2-M-3.

[5] VERIFY/PLACE 2-FIC-3-84, MFWP B RECIRC CONTROL, in MANUAL with the controller set to 100% output and VERIFY:

A. 2-FCV-3-84, MAIN FEEDWATER PUMP B RECIRC, CLOSED (729/T1 5G).

B. Red Light OFF (2-JB-291-1219) (729/T16H).

C. Green Light ON (2-JB-291-1219).

[6] DEPRESS the (OPEN) pushbutton on controller 2-FIC-3-84, MFWP B RECIRC CONTROL, until 0% output is obtained and VERIFY:

A. 2-FCV-3-84, MAIN FEEDWATER PUMP B RECIRC, OPEN (locally).

B. Red Light ON (2-JB-291-1219).

C. Green Light OFF (2-JB-291-1219).

[7] DEPRESS the (CLOSE) pushbutton on controller 2-FIC-3-84, MFWP B RECIRC CONTROL, until 100% output is obtained and VERIFY 2-FCV-3-84 CLOSES.

[8] CLOSE 2-ISV-32-2497 (729/T15-G), CONTROL AIR ISOLATION VALVE TO 2-FCV-3-84.

[9] OPEN petcock on 2-PREG-3-84/A2, CONTROL AIR PRESSURE REG FOR 2-FM-3-84E, to bleed off control air to 2-FCV-3-84, MAIN FEEDWATER PUMP B RECIRC.

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 117 of 371 Date 6.17 2-FCV-3-84, MAIN FEEDWATER PUMP B RECIRC, Functional Test (continued)

[10] OPEN petcock on air tank for 2-FCV-3-84, MAIN FEEDWATER PUMP A RECIRC, to bleed OFF control air to 2-FM-3-84E, FW PUMP B I/P.

CV

[11] VERIFY locally 2-FCV-3-84, MAIN FEEDWATER PUMP B RECIRC, FAILS to the OPEN position by valve stem position indication.

[12] CLOSE the petcock on the air tank for 2-FCV-3-84, MAIN FEEDWATER PUMP B RECIRC.

CV

[13] CLOSE the petcock on 2-PREG-3-84/A2, CONTROL AIR PRESSURE REG FOR 2-FM-3-84E.

CV

[14] OPEN 2-ISV-32-2497, CONTROL AIR ISOLATION VALVE TO 2-PCV-3-84.

[15] VERIFY locally 2-FCV-3-84, MAIN FEEDWATER PUMP B RECIRC, CLOSES by valve stem position indication.

[16] CLOSE isolation valve 2-RTV-3-254A, 2-FT-3-84A/84B/84D ROOT, (729/T1 6-C) to isolate the high side of 2-FT-3-84A, MAIN FEEDWATER PUMP B DISCHARGE FLOW.

[17] REMOVE the cap from the calibration tap for the high side of 2-FT-3-84A, MAIN FEEDWATER PUMP B DISCHARGE FLOW.

CV

[18] INSTALL 0-100"H 20 pressure gage and hand pump/test rig at the calibration tap for 2-FT-3-84A, MAIN FEEDWATER PUMP B DISCHARGE FLOW.

M&TE ID#

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 118 of 371 Date 6.17 2-FCV-3-84, MAIN FEEDWATER PUMP B RECIRC, Functional Test (continued)

[19] PLACE 2-FIC-3-84, MFWP B RECIRC CONTROL, on 2-M-3 in AUTO and VERIFY 2-FCV-3-84 OPENS.

[20] INCREASE the simulated pressure between 16" and 18"H 20 to simulate a flow greater than 4000 GPM.

[21] VERIFY 2-FCV-3-84, MAIN FEEDWATER PUMP B RECIRC, CLOSES by light indication at Panel 2-JB-291-1219.

Acc Crit (5.0B.48)

[22] VERIFY Annunciator Window 58-A, MFP 2B FLOW LO, at 2-XA-55-3C is CLEAR.

[23] DECREASE the simulated pressure between 3" and 5" H 2 0 to simulate a low flow condition.

[24] VERIFY Annunciator Window 58-A, MFP 2B FLOW LO, ALARMS. Acc Crit (5.0B.48)

[25] VERIFY 2-FCV-3-84, MAIN FEEDWATER PUMP B RECIRC, OPENS by light indication at Panel 2-JB-291-1219.

Acc Crit (5.0B.48)

[26] INCREASE the simulated pressure between 10" and 12"H 20 and VERIFY 2-FCV-3-84, MAIN FEEDWATER PUMP B RECIRC, is THROTTLED by light indication at Panel 2-JB-291-1219. Acc Crit (5.0B.48)

[27] VERIFY Annunciator Window 58-A, MFP 2B FLOW LO, is CLEAR.

[28] DECREASE the simulated pressure to 0"H 20.

[29] DEPRESSURIZE AND REMOVE the 0-100"H2 0 pressure gage and hand pump/test rig from the calibration tap for 2-FT-3-84A, MAIN FEEDWATER PUMP B RECIRC.

CV

[30] INSTALL the cap on the calibration tap on the high side of 2-FT-3-84A, MAIN FEEDWATER PUMP B DISCHARGE FLOW.

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 119 of 371 Date 6.17 2-FCV-3-84, MAIN FEEDWATER PUMP B RECIRC, Functional Test (continued)

[31] OPEN isolation valve 2-RTV-3-254A, 2-FT-3-84A/84B/84D ROOT, on the high side of 2-FT-3-84A, MAIN FEEDWATER PUMP B DISCHARGE FLOW.

[32] PLACE 2-FIC-3-84, MFWP B RECIRC CONTROL, in MANUAL and VERIFY 2-FCV-3-84 CLOSES.

6.18 2-FIS-3-11A, Low Feedwater Flow Indicating Switch/Annunciator Test

[1] VERIFY prerequisites listed in Section 4.3[5] for Subsection 6.18 are completed.

[2] VERIFY/PLACE 2-HS-3-45, FW SYSTEM WARMUP CONTROL SWITCH, on 2-M-3 to the BACK FLUSH position.

[3] VERIFY Annunciator Window 59-C, LO FW FLOW WTR HAMMER, is CLEAR.

[4] LAND lead 1 BAP (Red) on Terminal AA3, Section A of Panel 2-L-565, Steam Generator Water Hammer Protection.

(713/A15S) (Dwg 2-45N2635-98)

CV

[5] PLACE 2-HS-3-45, FW SYSTEM WARMUP CONTROL SWITCH, on 2-M-3 to the NORMAL position.

[6] VERIFY Annunciator Window 59-C, LO FW FLOW WTR HAMMER, ALARMS.

[7] PLACE 2-HS-3-45, FW SYSTEM WARMUP CONTROL SWITCH, on 2-M-3 to the BACK FLUSH position.

[8] VERIFY Annunciator Window 59-C, LO FW FLOW WTR HAMMER CLEARS.

[9] PLACE 2-HS-3-45, FW SYSTEM WARMUP CONTROL SWITCH, on 2-M-3 to the NORMAL position.

[10] VERIFY Annunciator Window 59-C, LO FW FLOW WTR HAMMER, ALARMS.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 120 of 371 Date 6.18 2-FIS-3-11A, Low Feedwater Flow Indicating Switch/Annunciator Test (continued)

[11] LIFT lead 1BAP (Red) from Terminal AA3, Section A of Panel 2-L-565, Steam Generator Water Hammer Protection.

CV

[12] VERIFY Annunciator Window 59-C, LO FW FLOW WTR HAMMER, CLEARS.

6.19 2-FIS-3-21A, Low Feedwater Flow Indicating Switch/Annunciator Test

[1] VERIFY prerequisites listed in Section 4.3[6] for Subsection 6.19 are completed.

[2] VERIFY/PLACE 2-HS-3-45, FW SYSTEM WARMUP CONTROL SWITCH, on 2-M-3 to the BACK FLUSH position.

[3] VERIFY Annunciator Window 59-C, LO FW FLOW WTR HAMMER, is CLEAR.

[4] LAND lead 2BAP (Red) on Terminal CC3, Section A of Panel 2-L-565, Steam Generator Water Hammer Protection.

(713/A15S) (Dwg 2-45N2635-98)

CV

[5] PLACE 2-HS-3-45, FW SYSTEM WARMUP CONTROL SWITCH, on 2-M-3 to the NORMAL position.

[6] VERIFY Annunciator Window 59-C, LO FW FLOW WTR HAMMER, ALARMS.

[7] PLACE 2-HS-3-45, FW SYSTEM WARMUP CONTROL SWITCH, on 2-M-3 to the BACK FLUSH position.

[8] VERIFY Annunciator Window 59-C, LO FW FLOW WTR HAMMER, CLEARS.

[9] PLACE 2-HS-3-45, FW SYSTEM WARMUP CONTROL SWITCH, on 2-M-3 to the NORMAL position.

[10] VERIFY Annunciator Window 59-C, LO FW FLOW WTR HAMMER, ALARMS.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 121 of 371 Date 6.19 2-FIS-3-21A, Low Feedwater Flow Indicating Switch/Annunciator Test (continued)

[11] LIFT lead 2BAP (Red) from Terminal CC3, Section A Panel 2-L-565, Steam Generator Water Hammer Protection.

Cv

[12] VERIFY Annunciator Window 59-C, LO FW FLOW WTR HAMMER, CLEARS.

6.20 2-FIS-3-31A, Low Feedwater Flow Indicating Switch/Annunciator Test

[1] VERIFY prerequisites listed in Section 4.3[7] for Subsection 6.20 are completed.

[2] VERIFY/PLACE 2-HS-3-45, FW SYSTEM WARMUP CONTROL SWITCH, on 2-M-3 to the BACK FLUSH position.

[3] VERIFY Annunciator Window 59-C, LO FW FLOW WTR HAMMER, is CLEAR.

[4] LAND lead 3BAP (Red) on Terminal CC3, Section B of Panel 2-L-565, Steam Generator Water Hammer Protection.

(713/A16T) (Dwg 2-45N2635-98)

CV

[5] PLACE 2-HS-3-45, PM SYSTEM WARMUP CONTROL SWITCH, on 2-M-3 to the NORMAL position.

[6] VERIFY Annunciator Window 59-C, LO FW FLOW WTR HAMMER, ALARMS.

[7] PLACE 2-HS-3-45, FW SYSTEM WARMUP CONTROL SWITCH, on 2-M-3 to the BACK FLUSH position.

[8] VERIFY Annunciator Window 59-C, LO FW FLOW W'R HAMMER, CLEARS.

[9] PLACE 2-HS-3-45, FW SYSTEM WARMUP CONTROL SWITCH, on 2-M-3 to the NORMAL position.

[10] VERIFY Annunciator Window 59-C, LO FW FLOW WTR HAMMER, ALARMS.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 122 of 371 Date 6.20 2-FIS-3-31A, Low Feedwater Flow Indicating Switch/Annunciator Test (continued)

[11] LIFT lead 3BAP (Red) from Terminal CC3, Section B Panel 2-L-565, Steam Generator Water Hammer Protection.

CV

[12] VERIFY Annunciator Window 59-C, LO FW FLOW WTR HAMMER, CLEARS.

6.21 2-FIS-3-41A, Low Feedwater Flow Indicating Switch/Annunciator Test

[1] VERIFY prerequisites listed in Section 4.3[8] for Subsection 6.21 are completed.

[2] VERIFY/PLACE 2-HS-3-45, FW SYSTEM WARMUP CONTROL SWITCH, on 2-M-3 to the BACK FLUSH position.

[3] VERIFY Annunciator Window 59-C, LO FW FLOW WTR HAMMER, is CLEAR.

[4] LAND lead 4BAP (Red) on Terminal AA3, Section C of Panel 2-L-565 Steam Generator Water Hammer Protection.

(713/Al 6T) (Dwg 2-45N2635-98)

CV

[5] PLACE 2-HS-3-45, FW SYSTEM WARMUP CONTROL SWITCH, on 2-M-3 to the NORMAL position.

[6] VERIFY Annunciator Window 59-C, LO FW FLOW WTR HAMMER, ALARMS.

[7] PLACE 2-HS-3-45, FW SYSTEM WARMUP CONTROL SWITCH, on 2-M-3 to the BACK FLUSH position.

[8] VERIFY Annunciator Window 59-C, LO FW FLOW WTR HAMMER, CLEARS.

[9] PLACE 2-HS-3-45, FW SYSTEM WARMUP CONTROL SWITCH, on 2-M-3 to the NORMAL position.

[10] VERIFY Annunciator Window 59-C, LO FW FLOW WTR HAMMER, ALARMS.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 123 of 371 Date 6.21 2-FIS-3-41A, Low Feedwater Flow Indicating Switch/Annunciator Test (continued)

[11] LIFT lead 4BAP (Red) from Terminal AA3, Section C of Panel 2-L-565, Steam Generator Water Hammer Protection.

Cv

[12] VERIFY Annunciator Window 59-C, LO FW FLOW WTR HAMMER, CLEARS.

6.22 2-PCV-3-40, Deaeration Line Back Pressure Control

[1] VERIFY prerequisites listed in Section 4.0 for Subsection 6.22 are completed.

[2] VERIFY/PLACE 2-HS-3-45, FW SYSTEM WARMUP CONTROL SWITCH, at 2-M-3 to the NORMAL position and VERIFY: Acc Crit (5.0B.49)

A. 2-PCV-3-40, MFW DEAERATION LINE BACK PRESSURE CONTROL, CLOSED (708/Ti 3J)

[3] PLACE 2-HS-3-45, FW SYSTEM WARMUP CONTROL SWITCH, at 2-M-3 to the BACK FLUSH position and VERIFY:

A. 2-PCV-3-40, MFW DEAERATION LINE BACK PRESSURE CONTROL, remains CLOSED (locally).

[4] CLOSE 2-ISV-3-246A, SENSING LINE SHUTOFF TO PCV-3-40 (71 0/T1 3J).

[5] REMOVE sensing line tubing at 2-PIC-3-40, (708/T1 3-J)

DEAERATION LINE BACK PRESSURE IND CONT.

CV

[6] INSTALL a 0-1500 PSIG gage and nitrogen bottle to the inlet of 2-PIC-3-40, DEAERATION LINE BACK PRESSURE IND CONT, to simulate a deaeration line back pressure.

M&TE ID#

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 124 of 371 Date 6.22 2-PCV-3-40, Deaeration Line Back Pressure Control (continued)

[7] INCREASE simulated pressure above 985 PSIG and VERIFY locally 2-PCV-3-40, MFW DEAERATION LINE BACK PRESSURE CONTROL, moves toward the OPEN position.

[8] PLACE 2-HS-3-45, FW SYSTEM WARMUP CONTROL SWITCH, at 2-M-3 to the NORMAL position and VERIFY 2-PCV-3-40, MFW DEAERATION LINE BACK PRESSURE CONTROL, CLOSED.

[9] PLACE 2-HS-3-45, FW SYSTEM WARMUP CONTROL SWITCH, at 2-M-3 to the FORWARD FLUSH position and VERIFY 2-PCV-3-40, MFW DEAERATION LINE BACK PRESSURE CONTROL, OPENS.

[10] CLOSE 2-ISV-32-3860, (708/TI 3J) CONTROL AIR ISOLATION VALVE TO 2-PCV-3-40.

[11] OPEN the petcock on 2-PREG-3-40/AI, CONTROL AIR VALVE POSITIONER FOR 2-PCV-3-40, to BLEED off control air from 2-PCV-3-40, MFW DEAERATION LINE BACK PRESSURE CONTROL.

CV

[12] VERIFY 2-PCV-3-40, MFW DEAERATION LINE BACK PRESSURE CONTROL, FAILS to the CLOSE position by valve stem position indication.

[13] CLOSE the petcock on 2-PREG-3-40/A1, CONTROL AIR VALVE POSITIONER FOR 2-PCV-3-40.

CV

[14] OPEN 2-ISV-32-3860, CONTROL AIR ISOLATION VALVE TO 2-PCV-3-40, to restore control air to 2-PCV-3-40, MFW DEAERATION LINE BACK PRESSURE CONTROL.

[15] VERIFY 2-PCV-3-40, MFW DEAERATION LINE BACK PRESSURE CONTROL, OPENS by valve stem position indication.

[16] DECREASE the simulated pressure below 800 PSIG and VERIFY 2-PCV-3-40, MFW DEAERATION LINE BACK PRESSURE CONTROL, moves toward the CLOSE position.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 125 of 371 Date 6.22 2-PCV-3-40, Deaeration Line Back Pressure Control (continued)

[17] DECREASE the simulated pressure to 0 PSIG and VERIFY 2-PCV-3-40, MFW DEAERATION LINE BACK PRESSURE CONTROL, goes CLOSED.

[18] DEPRESSURIZE AND REMOVE the pressure gage and pressure source from the inlet of 2-PIC-3-40, DEAERATION LINE BACK PRESSURE IND CONT.

Cv

[19] RECONNECT the sensing line tubing at 2-PIC-3-40, DEAERATION LINE BACK PRESSURE IND CONT.

CV

[20] OPEN 2-ISV-3-246A, SENSING LINE SHUTOFF TO 2-PCV-3-40.

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 126 of 371 Date 6.23 Main Feedwater Pump Turbine 2A Auxiliary Equipment Functional Test

[1] VERIFY prerequisites listed in Section 4.3[3] for Subsection 6.23 are completed.

[2] VERIFY/PLACE 2-HS-46-5AA, MFPT 2A MOP 1, on 2-M-3 to the PULL-TO-LOCK position.

[3] VERIFWPLACE 2-HS-46-5AB, MFPT 2A MOP 2, on 2-M-3 to the PULL-TO-LOCK position.

[4] VERIFWPLACE 2-HS-46-1A, MFPT 2A EMERGENCY OIL PMP, on 2-M-3 in the PULL-TO-LOCK position.

[5] VERIFY/CLOSE 2-SW-46-lA, MFPT 2A EMER OIL PMP DISCONNECT SW, adjacent to Panel 2-JB-291-1149 (729/TI 6J).

[6] OPEN 2-SW-46-1A, MFPT 2A EMER OIL PMP DISCONNECT SW, for Emergency Oil Pump A.

[7] VERIFY Unit 2 Events Display Legend indicates 56-B MFPT 2A EOP CONTROL PWR FAILURE is in ALARM (Red).

Acc Crit (5.0B.23)

[8] CLOSE 2-SW-46-lA, MFPT 2A EMER OIL PMP DISCONNECT SW, for Emergency Oil Pump A.

[9] VERIFY Unit 2 Events Display Legend indicates 56-B MFPT 2A EOP CONTROL PWR FAILURE is NORMAL (Blue).

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 127 of 371 Date 6.23 Main Feedwater Pump Turbine 2A Auxiliary Equipment Functional Test (continued)

[10] PLACE 2-HS-46-1A, MFPT 2A EMERGENCY OIL PMP, on 2-M-3 in the P-AUTO position and VERIFY: Acc Crit (5.0B.22)

A. Red 'ON' Light ON (2-HS-46-1A).

B. Red "RUN" Light ON (2-HS-46-1A).

C. Green Light OFF (2-HS-46-1 A).

D. 2-PMP-46-1A, MFPT 2A EMERG OIL PMP, STARTS (729/TI 6J).

E. "EOP-ON" Red Light ON (2-L-275) (729/TI 5J).

F. "EOP-RUN" Red Light ON (2-L-275).

G. "EOP-OFF" Green Light OFF (2-L-275).

(11] VERIFY Unit 2 Events Display Legend indicates 56-A MFPT 2A EOP RUNNING (PS-46-2) is in ALARM (Red).

Acc Crit (5.0B.22)

[12] PLACE 2-HS-46-5AA, MFPT 2A MOP 1, on 2-M-3 to the START position and VERIFY: Acc Crit (5.0B.46)

A. Red "ON" Light ON (2-HS-46-5AA).

B. Red "RUN" Light ON (2-HS-46-5AA).

C. Green Light OFF (2-HS-46-5AA).

D. 2-PMP-46-5B, MFPT 2A MAIN OIL PUMP 1, STARTS (729/TI 5J).

E. "MOP-1 ON" Red Light ON (2-L-275).

F. "MOP-1 RUN" Red Light ON (2-L-275).

G. "MOP-1 OFF" Green Light OFF (2-L-275).

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 128 of 371 Date 6.23 Main Feedwater Pump Turbine 2A Auxiliary Equipment Functional Test (continued)

[13] PLACE 2-HS-46-1A, MFPT 2A EMERGENCY OIL PMP, on 2-M-3 to the STOP position and VERIFY:

A. Red "ON' Light OFF (2-HS-46-1A).

B. Red "RUN" Light OFF (2-HS-46-IA).

C. Green Light ON (2-HS-46-1 A).

D. 2-PMP-46-1A, MFPT 2A EMERG OIL PMP, STOPS (729/TI 5J).

E. "EOP-ON" Red Light OFF (2-L-275).

F. "EOP-RUN" Red Light OFF (2-L-275).

G. "EOP-OFF" Green Light ON (2-L-275).

[14] VERIFY the Unit 2 Events Display Legend indicates 56-A MFPT 2A EOP RUNNING (PS-46-2) is Normal (Blue).

NOTE The Test Pushbutton creates a low pressure for MOP 1 which will AUTO START the Emergency Oil Pump.

[15] DEPRESS 2-HS-46-2, MFPT 2A EMERG OIL PMP TEST, pushbutton at Panel 2-L-275.

[16] VERIFY 2-PMP-46-1A, MFPT 2A EMERG OIL PMP, STARTS by light indication at Panel 2-L-275. Acc Crit (5.0B.44)

[17] PLACE 2-HS-46-1A, MFPT 2A EMERGENCY OIL PMP, on 2-M-3 to the STOP position.

[18] DEPRESS 2-HS-46-1 B, MFPT 2A EMERG OIL PMP START, pushbutton at Panel 2-L-275 and VERIFY 2-PMP-46-1A, MFPT 2A EMERG OIL PMP, STARTS by light indication.

[19] DEPRESS 2-HS-46-1 D, MFPT 2A EMERG OIL STOP, pushbutton at Panel 2-L-275 and VERIFY 2-PMP-46-1A, MFPT 2A EMERG OIL PMP, STOPS by light indication.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 129 of 371 Date 6.23 Main Feedwater Pump Turbine 2A Auxiliary Equipment Functional Test (continued)

[20] PLACE 2-HS-46-1A, MFPT 2A EMERGENCY OIL PMP, on 2-M-3 to the PULL-TO-LOCK position and VERIFY:

A. Red "ON" Light OFF (2-HS-46-1A).

B. Red "RUN" Light OFF (2-HS-46-1A).

C. Green Light OFF (2-HS-46-1A).

D. "EOP-ON" Red Light OFF (2-L-275).

E. "EOP-RUN" Red Light OFF (2-L-275).

F. "EOP-OFF" Green Light OFF (2-L-275).

[21] PLACE 2-HS-46-5AB, MFPT 2A MOP 2, on 2-M-3 to the START position and VERIFY: Acc Crit (5.0B.46)

A. Red "ON" Light ON (2-HS-46-5AB).

B. Red "RUN" Light ON (2-HS-46-5AB).

C. Green Light OFF (2-HS-46-5AB).

D. 2-PMP-46-5E, MFPT 2A MAIN OIL PMP 2, STARTS (729/TI 4J).

E. "MOP-2 ON" Red Light ON (2-L-275).

F. "MOP-2 RUN" Red Light ON (2-L-275).

G. "MOP-2 OFF" Green Light OFF (2-L-275).

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 130 of 371 Date 6.23 Main Feedwater Pump Turbine 2A Auxiliary Equipment Functional Test (continued)

[22] PLACE 2-HS-46-5AA, MFPT 2A MOP 1, on 2-M-3 to the STOP position and VERIFY:

A. Red "ON" Light OFF (2-HS-46-5AA).

B. Red "RUN" Light OFF (2-HS-46-5AA).

C. Green Light ON (2-HS-46-5AA).

D. 2-PMP-46-5B, MFPT 2A MAIN OIL PMP 1, STOPS (locally).

E. "MOP1 ON" Red Light OFF (2-L-275).

F. "MOP-1 RUN" Red Light OFF (2-L-275).

G. "MOP-1 OFF" Green Light ON (2-L-275).

[23] DEPRESS 2-HS-46-5B, MFPT 2A MOP 1 START, pushbutton at Panel 2-L-275 and VERIFY 2-PMP-46-5B, MFPT 2A MAIN OIL PMP 1, STARTS by light indication.

[24] PLACE 2-HS-46-5AB, MFPT 2A MOP 2, on 2-M-3 to the STOP position and VERIFY:

A. Red "ON" Light OFF (2-HS-46-5AB).

B. Red "RUN" Light OFF (2-HS-46-5AB).

C. Green Light ON (2-HS-46-5AB).

D. 2-PMP-46-5E, MFPT 2A MAIN OIL PMP 2, STOPS (locally).

E. "MOP-2 ON" Red light OFF (2-L-275).

F. "MOP-2 RUN" Red Light OFF (2-L-275).

G. "MOP-2 OFF" Green Light ON (2-L-275).

[25] VERIFY Unit 2 Events Display Legend indicates 53-A MFPT 2A MOP 1 PRESS LO is NORMAL (Blue).

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 131 of 371 Date 6.23 Main Feedwater Pump Turbine 2A Auxiliary Equipment Functional Test (continued)

NOTE The following step will simulate a TRIP of the operating MFPT 2A Main Oil Pump and AUTO-START of the standby oil pump.

[26] PLACE 2-HS-46-5AA, MFPT 2A MOP 1, on 2-M-3 to the STOP position and VERIFY: Acc Crit (5.0B.15)

A. 2-PMP-46-5B, MFPT 2A MAIN OIL PMP 1, STOPS (locally).

B. 2-PMP-46-5E, MFPT 2A MAIN OIL PMP 2, STARTS (locally).

[27] VERIFY Unit 2 Events Display Legend indicates:

A. 52-B MFPT 2A RESERVE MOP RUNNING (HS-46-5A) is in ALARM (Red).

B. 53-A MFPT 2A MOP 1 PRESS is in ALARM (Red).

[28] PLACE 2-HS-46-5AA, MFPT 2A MOP 1, on 2-M-3 to the START position.

[29] PLACE 2-HS-46-5AB, MFPT 2A MOP 2, on 2-M-3 to the STOP position.

[30] VERIFY 2-PMP-46-5E, MFPT 2A MAIN OIL PMP 2, STOPS by light indication at 2-M-3.

[31] VERIFY Unit 2 Events Display Legend indicates:

A. 52-B MFPT 2A RESERVE MOP RUNNING (HS-46-5A) is NORMAL (Blue).

B. 53-A MFPT 2A MOP 1 PRESS LO is NORMAL (Blue).

[32] PLACE 2-HS-46-5AB, MFPT 2A MOP 2, on 2-M-3, to the START position.

[33] PLACE 2-HS-46-5AA, MFPT 2A MOP 1, on 2-M-3 to the STOP position.

WBN MAIN FEEDWATER SYSTEM 2 PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 132 of 371 Date 6.23 Main Feedwater Pump Turbine 2A Auxiliary Equipment Functional Test (continued)

NOTE The following step will simulate a TRIP of the operating MFPT 2A Main Oil Pump and AUTO-START of the standby oil pump.

[34] PLACE 2-HS-46-5AB, MFPT 2A MOP 2, on 2-M-3 to the STOP position and VERIFY: Acc Crit (5.0B.15)

A. 2-PMP-46-5E, MFPT 2A MAIN OIL PMP 2, STOPS (locally).

B. 2-PMP-46-5B, MFPT 2A MAIN OIL PMP 1, STARTS (locally).

[35] VERIFY Unit 2 Events Display Legend indicates:

A. 54-A MFPT 2A MOP 2 PRESS LO is in ALARM (Red).

B. 52-B MFPT 2A RESERVE MOP RUNNING (HS-46-5A) is in ALARM (Red).

[36] PLACE 2-HS-46-5AB, MFPT 2A MOP 2, on 2-M-3 to the START position.

[37] PLACE 2-HS-46-5AA, MFPT 2A MOP 1, on 2-M-3 to the STOP position.

[38] VERIFY Unit 2 Events Display Legend indicates 54-A MFPT 2A MOP 2 PRESS LO is NORMAL (Blue).

[39] VERIFY Unit 2 Events Display Legend indicates 52-B MFPT 2A RESERVE MOP RUNNING (HS-46-5A) is NORMAL (Blue).

NOTE Depressing the MFPT 2A MAIN OIL PUMP 1 TEST, pushbutton will simulate a low pressure on MFPT 2A MAIN OIL PUMP 2 and cause MFPT 2A OIL PUMP 1 to START.

[40] DEPRESS and HOLD 2-HS-46-8, MFPT 2A MOP 1 TEST, pushbutton at Panel 2-L-275.

[41] VERIFY 2-PMP-46-5B, MFPT 2A MAIN OIL PMP 1, STARTS by light indication at Panel 2-L-275. Acc Crit (5.0B.19)

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 133 of 371 Date 6.23 Main Feedwater Pump Turbine 2A Auxiliary Equipment Functional Test (continued)

[42] VERIFY Unit 2 Events Display Legend indicates:

Acc Crit (5.0B.19)

A. 54-A MFPT 2A MOP 2 PRESS LO is in ALARM (Red).

B. 52-B MFPT 2A RESERVE MOP RUNNING (HS-46-5A) is in ALARM (Red).

[43] RELEASE 2-HS-46-8, MFPT 2A MOP 1 TEST, pushbutton at Panel 2-L-275.

[44] PLACE 2-HS-46-5AA, MFPT 2A MOP 1, on 2-M-3 to the STOP position and VERIFY 2-PMP-46-5B, MFPT 2A MAIN OIL PMP 1, STOPS by light indication.

[45] VERIFY Unit 2 Events Display Legend indicates:

A. 54-A MFPT 2A MOP 2 PRESS LO is NORMAL (Blue).

B. 52-B MFPT 2A RESERVE MOP RUNNING (HS-46-5A) is NORMAL (Blue).

[46] PLACE 2-HS-46-5AA, MFPT 2A MOP 1, on 2-M-3 to the START position and VERIFY 2-PMP-46-5B, MFPT 2A MAIN OIL PMP 1, STARTS by light indication.

[47] PLACE 2-HS-46-5AB, MFPT 2A MOP 2, on 2-M-3 to the STOP position and VERIFY 2-PMP-46-5E, MFPT 2A MAIN OIL PMP 2, STOPS by light indication.

NOTE Depressing the MFPT 2A MAIN OIL PUMP 2 TEST, pushbutton will simulate a low pressure on MFPT 2A MAIN OIL PUMP 1 and cause MFPT 2A MAIN OIL PUMP 2 to START.

[48] DEPRESS and HOLD 2-HS-46-7, MFPT 2A MOP 2 TEST, pushbutton at Panel 2-L-275.

[49] VERIFY 2-PMP-46-5E, MFPT 2A MAIN OIL PMP 2 STARTS by light indication at Panel 2-L-275. Acc Crit (5.0B.19)

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 134 of 371 Date 6.23 Main Feedwater Pump Turbine 2A Auxiliary Equipment Functional Test (continued)

[50] VERIFY Unit 2 Events Display Legend indicates:

Acc Crit (5.0B.19)

A. 53-A MFPT 2A MOP 1 PRESS LO is in ALARM (Red).

B. 52-B MFPT 2A RESERVE MOP RUNNING (HS-46-5A) is in ALARM (Red).

[51] RELEASE 2-HS-46-7, MFPT 2A MOP 2 TEST, pushbutton at Panel 2-L-275.

[52] PLACE 2-HS-46-5AB, MFPT 2A MOP 2, on 2-M-3 to the STOP position and VERIFY 2-PMP-46-5E MFPT 2A MAIN OIL PUMP 2, STOPS by light indication.

[53] VERIFY Unit 2 Events Display Legend indicates:

A. 53-A MFPT 2A MOP 2 PRESS LO is NORMAL (Blue).

B. 52-B MFPT 2A RESERVE MOP RUNNING (HS-46-5A) is NORMAL (Blue).

[54] LIFT lead 8FA10 from Terminal 29 of Panel 2-L-275 to simulate a high motor temperature on 2-PMP-46-5E, MFPT 2A MAIN OIL PMP 2. (Dwg 2-45W2614-1)

CV NOTE 2-PMP-46-5E, MFPT 2A MAIN OIL PMP 2, will not stop until 2-PMP-46-5B, MFPT 2A MAIN OIL PMP 1, discharge pressure is adequate.

[55] VERIFY that 2-PMP-46-5B, MFPT 2A MAIN OIL PMP 1, STARTS by light indication at 2-M-3. Acc Crit (5.0B.20)

[56] VERIFY 2-PMP-46-5E, MFPT 2A MAIN OIL PMP 2, STOPS by light indication at 2-M-3.

[57] VERIFY Unit 2 Events Display Legend indicates 51-B MFPT 2A MOP OVERLOAD/CONTROL PWR FAILURE is in ALARM (Red).

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 135 of 371 Date 6.23 Main Feedwater Pump Turbine 2A Auxiliary Equipment Functional Test (continued)

[58] LAND lead 8FA10 on Terminal 29 of Panel 2-L-275.

CV

[59] VERIFY Unit 2 Events Display Legend indicates 51-B MFPT 2A MOP OVERLOAD/CONTROL PWR FAILURE is NORMAL (Blue).

[60] PLACE 2-HS-46-5AB, MFPT 2A MOP 2, on 2-M-3 to the STOP position.

[61] LIFT lead 2AA10 from Terminal 9 of Panel 2-L-275 to simulate high motor temperature on 2-PMP-46-5B, MFPT 2A MAIN OIL PMP 1. (Dwg 2-45W2614-1)

CV NOTE 2-PMP-46-5B, MFPT 2A MAIN OIL PMP 1, will not stop until 2-PMP-46-5E, MFPT 2A MAIN OIL PMP 2, discharge pressure is adequate.

[62] VERIFY that 2-PMP-46-5E, MFPT 2A MAIN OIL PMP 2, STARTS by light indication at 2-M-3. Acc Crit (5.0B.20)

[63] VERIFY 2-PMP-46-5B, MFPT 2A MAIN OIL PMP 1, STOPS by light indication at 2-M-3.

[64] VERIFY Unit 2 Events Display Legend indicates 51-B MFPT 2A MOP OVERLOAD/CONTROL PWR FAILURE is in ALARM (Red).

[65] LAND lead 2AA1 0 on Terminal 9 of Panel 2-L-275.

CV

[66] VERIFY Unit 2 Events Display Legend indicates 51-B MFPT 2A MOP OVERLOAD/CONTROL PWR FAILURE is NORMAL (Blue).

[67] DEPRESS and HOLD 2-HS-46-5F, MFPT 2A MOP 2 STOP, pushbutton at Panel 2-L-275 and VERIFY 2-PMP-46-5E, STOPS by light indication.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 136 of 371 Date 6.23 Main Feedwater Pump Turbine 2A Auxiliary Equipment Functional Test (continued)

[68] VERIFY 2-PMP-46-5B, MFPT 2A MAIN OIL PMP 1, STARTS by light indication at Panel 2-L-275.

[69] RELEASE 2-HS-46-5F, MFPT 2A MOP 2 STOP pushbutton Panel 2-L-275 and VERIFY 2-PMP-46-5E does not START.

[70] DEPRESS and HOLD 2-HS-46-5D, MFPT 2A MOP 1 STOP pushbutton at Panel 2-L-275 and VERIFY 2-PMP-46-5B STOPS by light indication.

[71] VERIFY 2-PMP-46-5E, MFPT 2A MAIN OIL PMP 2, STARTS by light indication at Panel 2-L-275.

[72] RELEASE 2-HS-46-5D, MFPT 2A MOP 1 STOP, pushbutton at Panel 2-L-275 and VERIFY 2-PMP-46-5B does not START.

[73] PLACE and HOLD 2-HS-46-5AB, MFPT 2A MOP 2, on 2-M-3 to the STOP position and VERIFY 2-PMP-46-5E STOPS by light indication.

[74] VERIFY 2-PMP-46-5B, MFPT 2A MAIN OIL PMP 1, STARTS by light indication at Panel 2-L-275.

[75] RELEASE 2-HS-46-5AB, MFPT 2A MOP 2, on 2-M-3 and VERIFY 2-PMP-46-5E does not START.

[76] PLACE and HOLD 2-HS-46-5AA, MFPT 2A MOP 1, on 2-M-3 to the STOP position and VERIFY 2-PMP-46-5B STOPS.

[77] VERIFY 2-PMP-46-5E, MFPT 2A MAIN OIL PMP 2, STARTS by light indication at Panel 2-L-275.

[78] RELEASE 2-HS-46-5AA, MFPT 2A MOP 1, on 2-M-3 and VERIFY 2-PMP-46-5B does not START.

[79] DEPRESS 2-HS-46-5B, MFPT 2A MOP 1 START, pushbutton at Panel 2-L-275 and VERIFY 2-PMP-46-5B, MFPT 2A MAIN OIL PMP 1, STARTS by light indication.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 137 of 371 Date 6.23 Main Feedwater Pump Turbine 2A Auxiliary Equipment Functional Test (continued)

[80] PLACE 2-HS-46-5AB, MFPT 2A MOP 2, on 2-M-3 to the PULL-TO-LOCK position and VERIFY:

A. Red "ON" Light OFF (2-HS-46-5AB).

B. Red "RUN" Light OFF (2-HS-46-5AB).

C. Green Light OFF (2-HS-46-5AB).

D. "MOP-2 ON" Red Light OFF (2-L-275).

E. "MOP-2 RUN" Red Light OFF (2-L-275).

F. "MOP-2 OFF" Green Light OFF (2-L-275).

G. 2-PMP-46-5E, MFPT 2A MAIN OIL PMP 2, STOPS.

[81] PLACE 2-HS-46-5AA, MFPT 2A MOP 1, on 2-M-3 to the PULL-TO-LOCK position and VERIFY:

A. Red "ON" Light OFF (2-HS-46-5AA).

B. Red "RUN" Light OFF (2-HS-46-5AA).

C. Green Light OFF (2-HS-46-5AA).

D. "MOP-1 ON" Red Light OFF (2-L-275).

E. "MOP-1 RUN" Red Light OFF (2-L-275).

F. "MOP-1 OFF" Green Light OFF (2-L-275).

G. 2-PMP-46-5B, MFPT 2A MAIN OIL PMP 1, STOPS.

[82] DEPRESS 2-HS-46-5B; MFPT 2A MOP 1 START, pushbutton at Panel 2-L-275 and VERIFY locally that 2-PMP-46-5B does not START.

[83] DEPRESS 2-HS-46-5E; MFPT 2A MOP 2 START, pushbutton at Panel 2-L-275 and VERIFY locally that 2-PMP-46-5E does not START.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 138 of 371 Date 6.23 Main Feedwater Pump Turbine 2A Auxiliary Equipment Functional Test (continued)

[84] DEPRESS 2-HS-46-1A, MFPT 2A EMERG OIL PMP START, pushbutton at Panel 2-L-275 and VERIFY locally 2-PMP-46-1A does not START.

[851 VERIFY/PLACE 2-HS-46-14, MFPT 2A DRAIN VLVS, on 2-M-3 to the CLOSE position and VERIFY:

A. "2-FCV-46-14A CL." Green Light ON.

B. "2-FCV-46-14A OP" Red Light OFF.

C. "2-FCV-46-14B CL" Green Light ON.

D. "2-FCV-46-14B OP" Red Light OFF.

[86] PLACE 2-HS-46-14, MFPT 2A DRAIN VLVS, on 2-M-3 to the OPEN position and VERIFY:

A. "2-FCV-46-14A CL" Green Light OFF.

B. "2-FCV-46-14A OP" Red Light ON.

C. "2-FCV-46-14B CL" Green Light OFF.

D. "2-FCV-46-14B OP" Red Light ON.

[87] PLACE 2-HS-46-14, MFPT 2A DRAIN VLVS, on 2-M-3 to the CLOSE position.

[88] VERIFY/PLACE 2-HS-46-80, MFPT 2A OIL RES HTR CONT, at Panel 2-JB-291-1149 (729/T16J) to the OFF position and VERIFY:

A. Green Light ON (2-HS-46-80).

B. Red Light OFF (2-HS-46-80).

[89] VERIFY/PLACE 2-HS-46-1 0, MFPT 2A VAPOR EXTRACTOR, at Panel 2-JB-291-1149 to the OFF position and VERIFY:

A. Green Light ON (2-HS-46-10).

B. Red Light OFF (2-HS-46-10).

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 139 of 371 Date 6.23 Main Feedwater Pump Turbine 2A Auxiliary Equipment Functional Test (continued)

[90] PLACE 2-HS-46-10, MFPT 2A VAPOR EXTRACTOR, at Panel 2-JB-291-1149 to the ON position and VERIFY:

A. Green Light OFF (2-HS-46-10).

B. Red Light ON (2-HS-46-10).

C. 2-MTR-46-10 MFPT 2A VAPOR EXTRACTOR is RUNNING (729/T16J). Acc Crit (5.0B.50)

[91] PLACE 2-HS-46-10, MFPT 2A VAPOR EXTRACTOR, at Panel 2-JB-291-1149 to the OFF position.

[92] PLACE 2-HS-46-80, MFPT 2A OIL RES HTR CONT, at Panel 2-JB-291-1149 to the AUTO position.

NOTE The previous step may have energized the Oil Reservoir Heater if the oil temperature was below 70'F. If the Oil Reservoir Heater is ON as indicated by light indication then mark the following step N/A.

[93] INSTALL, a jumper across Terminal Points 45 (23/ORH) and 46 (23/ORH) of Panel 2-L-275, to simulate a low oil reservoir temperature. (Dwg 2-45W2614-1 )

CV

[94] VERIFY the Oil Reservoir Heater is ON by light indication at Panel 2-JB-291-1149: Acc Crit (5.0B.14)

A. Green Light OFF (2-HS-46-80).

B. Red Light ON (2-HS-46-80).

[95] VERIFY 2-VEXT-46-10, MFPT 2A OIL RESERVOIR VAPOR EXTRACTOR, is ON by light indication.

[96] PLACE 2-HS-46-80, MFPT 2A RES HTR CONT, Panel 2-JB-291-1149 to the OFF position.

[97] VERIFY 2-VEXT-46-10, MFPT 2A OIL RESERVOIR VAPOR EXTRACTOR, is OFF by light indication.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 140 of 371 Date 6.23 Main Feedwater Pump Turbine 2A Auxiliary Equipment Functional Test (continued)

[98] PLACE 2-HS-46-80, MFPT 2A OIL RES HTR CONT, at Panel 2-JB-291-1149 to the AUTO position.

[99] VERIFY the Oil Reservoir Heater is ON by light indication at Panel 2-JB-291-1149.

[100] LIFT lead 3C3 from Terminal 43 of Panel 2-L-275 to simulate a low oil level. (Dwg 2-45W2614-1)

CV

[101] VERIFY the Oil Reservoir Heater is OFF by light indication at Panel 2-JB-291-1149. Acc Crit (5.0B.14)

[102] LAND lead 3C3 on Terminal 43 of Panel 2-L-275 to clear the simulated low oil level.

CV

[103] VERIFY the Oil Reservoir Heater is ON by light indication at Panel 2-JB-291-1149. Acc Crit (5.0B.14)

[104] PLACE Handswitch 2-HS-46-80, MFPT 2A OIL RES HTR CONT, at Panel 2-JB-291-1149 to the OFF position.

NOTE This step may be marked N/A if Step 6.23[93] was marked N/A.

[105] REMOVE the jumper across Terminals 45 (23/ORH) and 46 (23/ORH) of Panel 2-L-275.

CV

[106] DEPRESS 2-HS-46-9B, MFPT 2A TURB RESET, pushbutton Panel 2-L-275 to RESET the MFPT 2A.

[107] VERIFYIPLACE 2-HS-46-11B, MFPT 2A TURNING GEAR RESET-SAFE STOP, at Panel 2-L-275 to the JOG position.

[108] VERIFY locally the turning gear is not ENGAGED by observing that the turbine shaft is not rotating.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 141 of 371 Date 6.23 Main Feedwater Pump Turbine 2A Auxiliary Equipment Functional Test (continued)

[109] VERIFY the turning gear is not ENGAGED by light indication at Panel 2-L-275:

A. "TGM RUN" Green Light OFF.

B. "TGM RUN" Red Light OFF.

[110] VERIFY the turning gear is not ENGAGED by light indication on 2-HS-46-1 1A, MFPT 2A TURNING GEAR, at 2-M-3:

A. Green Light OFF.

B. Red Light OFF.

[111] DEPRESS 2-HS-46-11 D, MFPT 2A TURNING GEAR P.B.

START, pushbutton at Panel 2-L-275 and VERIFY locally the turning gear does not START.

[112] PLACE 2-HS-46-1 1A, MFPT 2A TURNING GEAR, on 2-M-3 to the START position and VERIFY by light indication that the turning gear does not START.

[113] PLACE 2-HS-46-5AA, MFPT 2A MOP 1, at 2-M-3 to the START position

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 142 of 371 Date 6.23 Main Feedwater Pump Turbine 2A Auxiliary Equipment Functional Test (continued)

NOTE Position test personnel at Control Board 2-M-3 to observe light indications for the I step.

[114] DEPRESS and HOLD 2-HS-46-1 1E, MFPT 2A TURNING GEAR JOG SW, pushbutton at Panel 2-L-275 and VERIFY:

(Acc Crit 5.0B.51)

A. "TGM RUN" Red Light ON (2-L-275).

B. "TGM OFF" Green Light OFF (2-L-275).

C. Red Light ON (2-HS-46-1 IA).

D. Green Light OFF (2-HS-46-1 IA).

E. Blue Light OFF (2-HS-46-1 1A).

F. Turbine Shaft ROTATING (locally).

[115] RELEASE 2-HS-46-11E, MFPT 2A TURNING GEAR JOG SW, pushbutton at Panel 2-L-275.

[116] VERIFY the turning gear STOPS by light indication at Panel 2-L-275.

[117] PLACE 2-HS-46-1 1B, MFPT 2A TURNING GEAR RESET-SAFE STOP, at Panel 2-L-275 to the NORM position and VERIFY:

A. "TGM RUN" Red Light OFF (2-L-275).

B. "TGM OFF" Green Light ON (2-L-275).

C. Red Light OFF (2-HS-46-1 1A).

D. Green Light ON (2-HS-46-1 1A).

E. Blue Light ON (2-HS-46-11A).

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 143 of 371 Date 6.23 Main Feedwater Pump Turbine 2A Auxiliary Equipment Functional Test (continued)

[118] VERIFY Unit 2 Events Display Legend indicates 53-B MFPT 2A TURNING GEAR FAILURE is in ALARM (Red).

[119] DEPRESS 2-HS-46-1 1 E, MFPT 2A TURNING GEAR JOG SW, pushbutton at Panel 2-L-275 and VERIFY the turning gear will not START.

[120] PLACE 2-HS-46-1 1A, MFPT 2A TURNING GEAR, on 2-M-3 to the START position and VERIFY:

A. Red Light ON (2-HS-46-11A).

B. Green Light OFF (2-HS-46-1 1A).

C. Blue Light OFF (2-HS-46-1IA).

D. "TGM RUN" Red Light ON (2-L-275).

E. "TGM OFF" Green Light OFF (2-L-275).

F. Turbine Shaft ROTATING (locally).

[121] VERIFY Unit 2 Events Display Legend indicates 53-B MFPT TURNING GEAR FAILURE is NORMAL (Blue).

[122] DEPRESS 2-HS-46-9B, MFPT 2A TURB RESET, pushbutton at Panel 2-L-275 to RESET the MFPT 2A.

[123] PLACE 2-HS-46-1 1A, MFPT 2A TURNING GEAR, at 2-M-3 to the STOP position and VERIFY 2-MTR-46-1 1A, MFPT 2A TURNING GEAR, STOPS.

[124] DEPRESS 2-HS-46-11D, MFPT 2A TURNING GEAR P.B.

START, pushbutton at Panel 2-L-275 and VERIFY the turning gear STARTS by light indication.

[125] LIFT lead R/SVCL (LP) from the right side of Terminal 255 of Panel 2-L-275 to simulate an open low pressure stop valve.

(Dwg 2-45W2614-1)

CV

[126] VERIFY locally that the turning gear STOPS.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 144 of 371 Date 6.23 Main Feedwater Pump Turbine 2A Auxiliary Equipment Functional Test (continued)

[127] LAND lead R/SVCL (LP) on the right side of Terminal 255 in Panel 2-L-275.

CV

[128] VERIFY that the turning gear does not RESTART by light indication at Panel 2-L-275.

[129] DEPRESS 2-HS-46-9D, MFPT 2A TURB TRIP, pushbutton at Panel 2-L-275 to TRIP the MFPT.

NOTE The following step will simulate a Main Feedwater Pump Turbine shaft speed of 2 RPM or more.

[130] MOMENTARILY PLACE a jumper between Terminal Points 280 (R/ZSD) AND 282 (R/ZSD) in Panel 2-L-275 and VERIFY locally that the turning gear STARTS.

(Dwg 2-45W2614-1)

CV

[131] LIFT lead 2BA4 on Terminal 258 in Panel 2-L-275 to simulate an open high pressure stop valve. (Dwg 2-45W2614-1)

CV

[132] VERIFY locally that the turning gear STOPS.

[133] LAND lead 2BA4 on Terminal 258 in Panel 2-L-275.

CV

[134] VERIFY locally that the turning gear STARTS.

[135] INSTALL a jumper across Terminal Points 195 and 205 in Panel 2-L-275 to simulate a low turbine bearing oil pressure.

(Dwg 2-45W2614-1)

CV

[136] VERIFY locally that the turning gear STOPS.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 145 of 371 Date 6.23 Main Feedwater Pump Turbine 2A Auxiliary Equipment Functional Test (continued)

[137] REMOVE the jumper across Terminals 195 and 205 in Panel 2-L-275.

Cv

[138] VERIFY locally that the turning gear STARTS.

[139] INSTALL a jumper across Terminal Points 198 (TTAP) and 202 (TTAPO) in Panel 2-L-275 to simulate a low pump bearing oil pressure. (Dwg 2-45W2614-1) _

Cv

[140] VERIFY locally that the turning gear STOPS.

Acc Crit (5.0B.18)

[141] REMOVE the jumper across Terminals 198 (TTAP) and 202 (TTAPO) in Panel 2-L-275.

Cv

[142] VERIFY locally that the turning gear STARTS.

[143] LIFT lead (2BA2) on Terminal 273 in Panel 2-L-275 to simulate a turning gear high motor temperature.

(Dwg 2-45W2614-1)

Cv

[144] VERIFY locally that the turning gear STOPS.

Acc Crit (5.0B.18)

[145] LAND the lifted lead (2BA2) on Terminal 273 in Panel 2-L-275.

Cv

[146] VERIFY locally that the turning gear STARTS.

[147] LIFT lead (R/ZSD) on the right side of Terminal 127 in Panel 2-L-275 to simulate turbine speed greater than 2 RPM.

(Dwg 2-45W2614-1)

Cv

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 146 of 371 Date 6.23 Main Feedwater Pump Turbine 2A Auxiliary Equipment Functional Test (continued)

[148] LIFT lead (R/FT-'la) on the right side of Terminal 251 in Panel 2-L-275 to remove the turbine trip signal from the turning gear logic. (Dwg 2-45W2614-1)

Cv

[149] VERIFY locally that the turning gear CONTINUES to RUN.

[150] PLACE 2-HS-46-1 1A, MFPT 2A TURNING GEAR, on 2-M-3 to the STOP position and VERIFY the turning gear STOPS by light indication.

[151] LAND lead (R/TT-Ila) on the right side of Terminal 251 in Panel 2-L-275.

Cv

[152] VERIFY the turning gear does not RESTART by light indication:

A. Blue Light ON (2-HS-46-1 1A).

B. Green Light ON (2-HS-46-1 1A).

C. TGM OFF Green Light ON (2-L-275).

[153] LAND lead (R/ZSD) on the right side of Terminal 127 in Panel 2-L-275.

Cv

[154] VERIFY locally that the turning gear STARTS.

[155] PLACE 2-HS-46-1 1B, MFPT 2A TURNING GEAR RESET-SAFE STOP, at Panel 2-L-275 to the OFF position and VERIFY the turning gear STOPS by light indication.

[156] VERIFY that only the Blue "Normal Oil Level" indicator light is ON at Panel 2-JB-291-1149.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 147 of 371 Date 6.23 Main Feedwater Pump Turbine 2A Auxiliary Equipment Functional Test (continued)

NOTE Perform the following three steps before releasing 2-HS-46-3B, MFPT 2A ALM TEST HIGH LVL, pushbutton. Position test personnel at 2-M-3 to observe control room indications.

[157] DEPRESS and HOLD 2-HS-46-3B, MFPT 2A ALM TEST HIGH LVL, pushbutton at Panel 2-JB-291-1149.

[158] VERIFY Unit 2 Events Display Legend indicates 55-B MFPT 2A OIL TANK LEVEL HI/LO (LS-46-6AIB) is in ALARM (Red).

Acc Crit (5.0B.17)

[159] VERIFY the following light indications at Panel 2-JB-291-1149:

Acc Crit (5.0B.17)

A. "OIL LEVEL HIGH", White Light ON.

B. "OIL LEVEL NORMAL", Blue Light OFF.

[160] RELEASE 2-HS-46-3B, MFPT 2A ALM TEST HIGH LVL, pushbutton at Panel 2-JB-291-1149.

[161] VERIFY Unit 2 Events Display Legend indicates 55-B MFPT 2A OIL TANK LEVEL HI/LO (LS-46-6AIB) is NORMAL (Blue).

[162] VERIFY that only the Blue "Normal Oil Level" indictor light is ON at Panel 2-JB-291-1149.

NOTE Perform the following three steps before releasing 2-HS-46-3D, MFPT 2A ALM TEST LOW LVL, pushbutton. Position test personnel at 2-M-3 to observe control room indications.

[163] DEPRESS and HOLD 2-HS-46-3D, MFPT 2A ALM TEST LOW LVL, pushbutton at Panel 2-JB-291-1149.

[164] VERIFY Unit 2 Events Display Legend indicates 55-B MFPT 2A OIL TANK LEVEL HI/LO (LS-46-6A/B) is in ALARM (Red).

Acc Crit (5.0B.17)

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 148 of 371 Date 6.23 Main Feedwater Pump Turbine 2A Auxiliary Equipment Functional Test (continued)

[165] VERIFY the following light indications at Panel 2-JB-291-1149:

Acc Crit (5.0B. 17)

A. "OIL LEVEL LOW", White Light ON.

B. "OIL LEVEL NORMAL", Blue Light OFF.

[166] RELEASE 2-HS-46-3D, MFPT 2A ALM TEST LOW LVL, pushbutton at Panel 2-JB-291-1149.

[167] VERIFY Unit 2 Events Display Legend indicates 55-B MFPT 2A OIL TANK LEVEL HI/LO (LS-46-6AIB) is NORMAL (Blue).

[168] VERIFY that only the Blue "Normal Oil Level" indictor light is ON at Panel 2-JB-291-1149.

[169] PLACE and HOLD hand held jumper across Terminal Points 185 (2M268A) and 186 (2NM3B) in Panel 2-L-275 and VERIFY Annunciator Window 51-D, OIL FROM COOLER TEMP HI, ALARMS. (Dwg 2-45W2614-1) Acc Crit (5.0B.16)

CV

[170] VERIFY Unit 2 Events Display Legend indicates 51-D MFPT 2A OIL FROM COOLER TEMP HI is in ALARM (Red).

[171] REMOVE hand held jumper across Terminal Points 185 (2M268A) and 186 (2NM3B) in Panel 2-L-275 and VERIFY Annunciator Window 51-D, OIL FROM COOLER TEMP HI, CLEARS.

CV

[172] VERIFY Unit 2 Events Display Legend indicates 51-D MFPT 2A OIL FROM COOLER TEMP HI is NORMAL (Blue).

[173] PLACE and HOLD hand held jumper across Terminal Points 183 (2M265A) and 184 (2NM3B) in Panel 2-L-275 to simulate a high bearing drain oil temperature.

(Dwg 2-45W2614-1)

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 149 of 371 Date 6.23 Main Feedwater Pump Turbine 2A Auxiliary Equipment Functional Test (continued)

[174] VERIFY DRAIN OILAnnunciator Window 55-C MFPT 2A #1 BEARING TEMP HI, ALARMS. Acc Crit (5.0B.16)

[175] VERIFY Unit 2 Events Display Legend indicates 55-C MFPT 2A #1 BEARING DRAIN OIL TEMP HI (2-TIS-046-0061) is in ALARM (Red).

[1761 REMOVE hand held jumper across Terminal Points 183 (2M265A) and 184 (2NM3B) in Panel 2-L-275 to clear the high bearing drain oil temperature.

CV

[177] VERIFY Unit 2 Events Display Legend indicates 55-C MFPT 2A #1 BEARING DRAIN OIL TEMP HI (2-TIS-046-0061) is NORMAL (Blue).

[178] PLACE and HOLD hand held jumper across Terminal Points 181 (2M266A) and 182 (2NM3B) in Panel 2-L-275, to simulate a high bearing drain oil temperature.

(Dwg 2-45W2614-1)

CV

[179] VERIFY Annunciator Window 56-C MFPT 2A #2 BEARING DRAIN OIL TEMP HI, ALARMS. Acc Crit (5.0B.16)

[180] VERIFY Unit 2 Events Display Legend indicated 56-C MFPT 2A #2 BEARING DRAIN OIL TEMP HI (2-TIS-046-0063) is in ALARM (Red).

[181] REMOVE hand held jumper across Terminal Points 181 (2M266A) and 182 (2NM3B) in Panel 2-L-275, to clear the simulated high bearing oil temp.

CV

[1821 VERIFY Unit 2 Events Display Legend indicates 56-C MFPT 2A #2 BEARING DRAIN OIL TEMP HI (2-TIS-046-0063) is NORMAL (Blue).

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 150 of 371 Date 6.23 Main Feedwater Pump Turbine 2A Auxiliary Equipment Functional Test (continued)

[183] PLACE and HOLD hand held jumper across Terminal Points 179 (2M264A) and 180 (2NM3B) in Panel 2-L-275, to simulate a high thrust bearing drain oil temperature.

(Dwg 2-45W2614-1)

Cv

[184] VERIFY Annunciator Window 54-C MFPT 2A THRUST BEARING DRAIN OIL TEMP HI, ALARMS Acc Crit (5.0B.16)

[185] VERIFY Unit 2 Events Display Legend indicates 54-C MFPT 2A THRUST BEARING DRAIN OIL TEMP HI (2-TIS-046-0065) is in ALARM (Red).

[186] REMOVE hand held jumper across Terminal Points 179 (2M264A) and 180 (2NM3B) in Panel 2-L-275, and to clear the high thrust bearing drain oil temperature.

Cv

[187] VERIFY Unit 2 Events Display Legend indicates 54-C MFPT 2A THRUST BEARING DRAIN OIL TEMP HI (2-TIS-046-0065) is NORMAL (Blue).

[188] LIFT lead TMAX (BK) from Terminal Board TB203, Terminal point 9 in Panel 2-R-72 (708/T10H) to simulate a loss of AC control power. (Dwg 2-45N2687-3)

CV

[189] VERIFY Unit 2 Events Display Legend indicates 52-C MFPT 2A CONTROL BUS UNDERVOLTAGE is in ALARM (Red).

[190] LAND lead TMAX (BK) on Terminal Board TB203, Terminal Point 9 in panel 2-R-72.

CV

[191] VERIFY Unit 2 Events Display Legend indicates 52-C MFPT 2A AC CONTROL BUS UNDERVOLTAGE is NORMAL (Blue).

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 151 of 371 Date 6.23 Main Feedwater Pump Turbine 2A Auxiliary Equipment Functional Test (continued)

[192] PLACE and HOLD hand held jumper across Terminal Points 76 (2NM3A) and 78 (2M239) in Panel 2-R-141 (717/A13U) to simulate a low FWP Suction NPSH.

(Dwg 2-45W2673-6)

Cv

[193] VERIFY Unit 2 Events Display Legend indicates 49-E MFWP OR STBY FWP SUCTION NPSH LO (2-PS-2-129A) is in ALARM (Red). Acc Crit (5.0B.27)

[194] REMOVE hand held jumper across Terminal Points 76 (2NM3A) and 78 (2M239) in Panel 2-R-141 to clear the low FWP Suction NPSH.

Cv

[195] VERIFY Unit 2 Events Display Legend indicates 49-E MFWP OR STBY FWP SUCTION NPSH LO (2-PS-2-129A) is NORMAL (Blue).

[196] VERIFY the Amber "LOSS OF 250 VDC" Light is ON at Panel 2-JB-291-1149.

[197] PLACE Breaker 320 at 250V DC Battery Board 2 to the OFF position. (692/C7P)

[198] VERIFY Unit 2 Events Display Legend indicates 51-C MFPT 2A TRIP & RESET CIRCUIT POWER FAILURE is in ALARM (Red). Acc Crit (5.0B.24)

[199] VERIFY the Amber "LOSS OF 250 VDC" light is OFF at Panel 2-JB-291-1149.

[200] PLACE Breaker 320 at the 250 VDC Battery Board 2 to the ON position.

[201] VERIFY Unit 2 Events Display Legend indicates 51-C MFPT 2A TRIP & RESET CIRCUIT POWER FAILURE is NORMAL (Blue).

[202] VERIFY the Amber "LOSS OF 250 VDC" light is ON at Panel 2-JB-291-1149.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 152 of 371 Date 6.23 Main Feedwater Pump Turbine 2A Auxiliary Equipment Functional Test (continued)

NOTE The following steps simulate interlocks for testing the MFPT trips. Simulations which are not required may be marked N/A.

[203] LIFT lead TTAP (BK) from the left side of Terminal Board TB-AA, Terminal 1 in Section B of Panel 2-L-69 (708/T1 5-G),

to simulate a normal MFPT condenser vacuum. (N/A if normal condenser vacuum is established). (Dwg 2-45N2635-34)

CV

[204] INSTALL an OPEN test switch between Terminal Board TB-AA, Terminal 1 and the lifted lead TTAP (BK) in Section B of Panel 2-L-69. (N/A if normal condenser vacuum is established) (Dwg 2-45N2635-34)

CV

[205] INSTALL a jumper at Terminal Board TB630 across Terminal Points 1 (9E04) and 2 (9E03) at Panel 2-R-76 to simulate a normal FWP seal water pressure. (N/A if MFP Seal Injection is in service.) (Dwg 2-45N2691-4)

CV

[206] INSTALL a jumper across contact at points 1 and 2 on relay 2-PIS-47-13RLY1 in 2-L-262 to simulate the main turbine at full load.

CV

[207] DEPRESS 2-HS-46-5B, MFPT 2A MOP 1 START, pushbutton at Panel 2-L-275 to START 2-PMP-46-5B.

[208] PLACE 2-HS-46-9A, TRIP RESET MFPT 2A, on 2-M-3 to the RESET position and VERIFY:

A. Red Light ON (2-HS-46-9A).

B. Green Light OFF (2-HS-46-9A).

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 153 of 371 Date 6.23 Main Feedwater Pump Turbine 2A Auxiliary Equipment Functional Test (continued)

[209] PLACE 2-HS-46-9A, TRIP RESET MFPT 2A, on 2-M-3 to the TRIP position and VERIFY:

A. Red Light OFF (2-HS-46-9A).

B. Green Light ON (2-HS-46-9A.)

[210] VERIFY Unit 2 MCR alarm 51-A TRIPPED and Events Display Legend indicates 51-A MFPT 2ATRIPPED is in ALARM (Red).

Acc Crit (5.0B.25)

[211] VERIFY Unit 2 MCR alarm 28-E TURBINE RUNBACK BOP and Events Display Legend indicates 28-E TURBINE RUNBACK BOP (PIS-47-13RLY4) is in ALARM (Red).

Acc Crit (5.0B.25)

[212] PLACE 2-HS-46-9A, TRIP RESET MFPT 2A, on 2-M-3 to the RESET position.

[213] VERIFY Unit 2 Events Display Legends indicates 51-A MFPT 2A TRIPPED and 28-E TURBINE RUNBACK BOP (PIS 13RLY4) are NORMAL (Blue) and the MCR alarms clear.

[214] DEPRESS 2-HS-46-9D, MFPT 2A TURB TRIP, pushbutton at Panel 2-L-275 and VERIFY:

A. "TURBINE TRIP" Green Light ON.

B. "RESET" Red Light OFF.

[215] DEPRESS 2-HS-46-9B, MFPT 2A TURB RESET, pushbutton at Panel 2-L-275 and VERIFY:

A. "TURBINE TRIP" Green Light OFF.

B. "RESET" Red Light ON.

[216] LIFT one lead of the jumper installed at Terminal Board TB630 across Terminal Points 1 (9E04) and 2 (9E03) at Panel 2-R-76 to simulate low FWP seal water pressure.

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 154 of 371 Date 6.23 Main Feedwater Pump Turbine 2A Auxiliary Equipment Functional Test (continued)

[217] VERIFY Unit 2 Events Display Legend indicates 50-E MFP 2A INJ WATER DP LO is in ALARM (Red). Acc Crit (5.0B.26)

[218] LAND the lead of the jumper installed in step 6.23[205] and lifted in step 6.23[216] to simulate normal FWP seal water pressure.

CV

[219] VERIFY Unit 2 Events Display Legend indicates 51-E MFP 2B INJ WATER DP LO is NORMAL (Blue).

[220] INSTALL a jumper across Terminal Points 198 (TTAP [BK])

and Terminal 202 (TTAPO [W]) at Panel 2-L-275 to simulate a low pump bearing oil pressure. (Dwg 2-45W2614-1)

CV

[221] VERIFY Unit 2 Events Display-Legend indicates 52-A MFPT 2A BEARING OIL PRESS LO (PS-46-12B) is in ALARM (Red).

Acc Crit (5.08.26)

(222] VERIFY MFPT 2A is TRIPPED by light indication at 2-HS-46-9A, TRIP RESET MFPT 2A.

[223] REMOVE jumper across Terminals 198 (TTAP [BK]) and 202 (TTAPO [W]) at Panel 2-L-275 to clear the simulated low pump bearing oil pressure.

CV

[224] VERIFY Unit 2 Events Display Legend indicates 52-A MFPT 2A BEARING OIL PRESS LO (PS-46-12B) is NORMAL (Blue).

[225] PLACE 2-HS-46-9A, TRIP RESET MFPT 2A, on 2-M-3 to the RESET position.

[226] INSTALL a jumper across Terminal Points 195 (63/LBOT) and 205 (63/LBOT) at Panel 2-L-275 to simulate a low turbine bearing oil pressure. (Dwg 2-45W2614-1)

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 155 of 371 Date 6.23 Main Feedwater Pump Turbine 2A Auxiliary Equipment Functional Test (continued)

[227] VERIFY MFPT 2A is TRIPPED by light indication at 2-HS-46-9A, TRIP RESET MFPT 2A.

[228] VERIFY Unit 2 Events Display Legend indicates 52-A MFPT 2A BEARING OIL PRESS LO (PS-46-12B) is in ALARM (Red).

Acc Crit (5.0B.26)

[229] REMOVE jumper across Terminals 195 (63/LBOT) and (63/LBOT) at Panel 2-L-275 to clear the simulated low turbine bearing oil pressure CV

[230] PLACE 2-HS-46-9A, TRIP RESET MFPT 2A, on 2-M-3 to the RESET position.

NOTE If a normal condenser vacuum was established the following two steps are required to simulate a low condenser vacuum. If a normal condenser vacuum was not established the following step may be marked N/A.

[231] INSTALL a jumper at Terminal Board AA across Terminal Points 1 (TTAP [BK]) and 2 (TTA1 [W]) in Section B of Panel 2-L-69, to simulate a loss of condenser vacuum. (Dwg 2-45N2635-34)

CV

[232] CLOSE test switch (installed in step 6.23[204]) to establish a loss of normal condenser vacuum. (N/A if step 6.231231] was marked N/A.)

[233] VERIFY Unit 2 Events Display Legend indicates 55-D MFPT 2A CONDENSER VACUUM LO (2-PS-2-252D) is in ALARM (Red). Acc Crit (5.0B.26)

[234] VERIFY MFPT 2A is TRIPPED by light indication at 2-HS-46-9A, TRIP RESET MFPT 2A.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 156 of 371 Date 6.23 Main Feedwater Pump Turbine 2A Auxiliary Equipment Functional Test (continued)

[235] REMOVE jumper from Terminals AA-1 (TTAP [BK]) and AA-2 (TTA1 [W]) at Section B of Panel 2-L-69. (N/A if step 6.23[231]

was marked N/A.)

CV

[236] OPEN test switch to establish a normal condenser vacuum.

(N/A if step 6.23[204] was N/A)

[237] VERIFY Unit 2 Events Display Legend indicates 55-D MFPT 2A CONDENSER VACUUM LO (2-PS-2-252D) is NORMAL (Blue).

[238] PLACE 2-HS-46-9A, TRIP RESET MFPT 2A, to the RESET position.

[239] INSTALL a jumper at Terminal Board TB-2 across Terminal Points 119 (2M257A) and 120 (2NM3B) in 2-L-792, TURBINE SUPERVISORY CABINET to simulate a normal thrust bearing wear (Dwg 2-45W600-46-8).

CV

[240] VERIFY Unit 2 Events Display Legend indicates 54-B MFPT 2A THRUST BEARING WEAR is in ALARM (Red).

Acc Crit (5.0B.26)

[241] INSTALL a jumper at Terminal Points TB9-3 and TB9-4 on 2-RLY-046-450A in 2-L-792, TURBINE SUPERVISORY CABINET to simulate a normal thrust bearing wear (Dwg 2-45N2635-133).

CV

[242] VERIFY MFPT 2A is TRIPPED by light indication at 2-HS-46-9A, TRIP RESET MFPT 2A.

[243] REMOVE the jumper installed in step 6.23[239] across Terminal Board TB-2 across Terminal Points 119 (2M257A) and 120 (2NM3B) in 2-L-792, TURBINE SUPERVISORY CABINET (Dwg 2-45W600-46-8).

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 157 of 371 Date 6.23 Main Feedwater Pump Turbine 2A Auxiliary Equipment Functional Test (continued)

[244] VERIFY Unit 2 Events Display Legend indicates 54-B MFPT 2A THRUST BEARING WEAR is NORMAL (Blue).

[245] REMOVE the jumper across Terminal Points TB9-3 and TB9-4 on 2-RLY-046-450A in 2-L-792, TURBINE SUPERVISORY CABINET that was installed in Step 6.23[241]

(Dwg 2-45N2635-133).

CV

[246] PLACE 2-HS-46-9A, TRIP RESET MFPT 2A, on 2-M-3 to the RESET position.

[247] INSTALL a jumper across TB9-9 and TB9-1 0 on 2-RLY-046-450A in 2-L-792, TURBINE SUPERVISORY CABINET to simulate a reverse thrust bearing wear (Dwg 2-45N2635-133).

CV

[248] VERIFY MFPT 2A is TRIPPED by light indication at 2-HS-46-9A, TRIP RESET MFPT 2A.

[249] REMOVE the jumper installed in step 6.23[235] across TB9-9 and TB9-10 on 2-RLY-046-450A in 2-L-792, TURBINE SUPERVISORY CABINET (Dwg 2-45N2635-133).

CV

[250] LAND lead TTAP (BK) on Terminal Point 196 at Panel 2-L-275 to clear the MFP 2A Suction Valve Open Interlock. (Lifted by prerequisite 4.3[3])

CV

[251] PLACE 2-HS-2-221A, MFWP A SUCTION ISOL, on 2-M-3 to the OPEN position and VERIFY 2-FCV-2-221 OPENS by light indication.

[252] PLACE 2-HS-46-9A, TRIP RESET MFPT 2A, on 2-M-3 to the RESET position.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 158 of 371 Date 6.23 Main Feedwater Pump Turbine 2A Auxiliary Equipment Functional Test (continued)

[253] PLACE 2-HS-2-221A, MFPT 2A SUCTION ISOL, on 2-M-3 to the CLOSE position and VERIFY Annunciator Window 53-C, MFP SUCTION VLV NOT FULL OPEN, ALARMS before 2-FCV-2-221 is CLOSED. Acc Crit (5.0B.26)

[254] VERIFY MFPT 2A is TRIPPED by light indication at 2-HS-46-9A, TRIP RESET MFPT 2A.

[255] VERIFY Unit 2 Events Display Legend indicates 53-C MFP 2A SUCTION VLV NOT FULL OPEN is in ALARM (Red).

Acc Crit (5.0B.26)

[256] PLACE 2-HS-2-221A, MFPT 2A SUCTION ISOL, on 2-M-3 to the OPEN position and VERIFY Annunciator Window 53-C, MFP SUCTION VLV NOT FULL OPEN, is CLEAR.

[257] VERIFY Unit 2 Events Display Legend indicates 53-C MFP 2A SUCTION VLV NOT FULL OPEN is NORMAL (Blue).

[258] PLACE 2-HS-46-9A, TRIP RESET MFPT 2A, on 2-M-3 to the RESET position.

[259] INSTALL a jumper at Terminal Board TB634 across the field side of Terminal Points 1 (TVAA1) and 2 (TVAA2) in Panel 2-R-48 to simulate a Train A Feedwater Isolation Signal.

(Dwg 2-45N2676-5)

CV

[260] VERIFY MFPT 2A is TRIPPED by light indication at 2-HS-46-9A, TRIP RESET MFPT 2A. Acc Crit (5.0B.21)

[261] REMOVE jumper across Terminals TB634-1 (TVAA1) and TB634-2 (TVAA2) at 2-R-48.

CV

[262] VERIFY MFPT 2A REMAINS TRIPPED by light indication at 2-HS-46-9A, TRIP RESET MFPT 2A.

[263] PLACE 2-HS-46-9A, TRIP RESET MFPT 2A, on 2-M-3, to the RESET position.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 159 of 371 Date 6.23 Main Feedwater Pump Turbine 2A Auxiliary Equipment Functional Test (continued)

[264] INSTALL a jumper at Terminal Board TB634 across the field side of Terminal Points 1 (TVAB1) and 2 (TVAB2) in Panel 2-R-51 to simulate a Train B Feedwater Isolation Signal.

(Dwg 2-45N2677-5)

CV

[265] VERIFY MFPT 2A is TRIPPED by light indication at 2-HS-46-9A, TRIP RESET MFPT 2A. Acc Crit (5.0B.21)

[266] REMOVE jumper across Terminals TB634-1 (TVAB1) and TB634-2 (TVAB2) at 2-R-51.

CV (2671 VERIFY MFPT 2A remains TRIPPED by light indication at 2-HS-46-9A, TRIP RESET MFPT 2A.

[268] PLACE 2-HS-46-9A, TRIP RESET MFPT 2A, on 2-M-3 to the RESET position.

[269] REMOVE the jumper across contact at points 1 and 2 on relay 2-PIS-47-13RLY1 in 2-L-262.

CV

[270] REMOVE the OPEN test switch between Terminal Board TB-AA, Terminal 1 and the lifted lead TTAP (BK) in Panel 2-L-69. (N/A if normal condenser vacuum was established)

CV

[271] LAND lead THAP on Terminal Board TB-AA, Terminal 1 in Panel 2-L-69. (N/A if normal condenser vacuum was established)

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 160 of 371 Date 6.23 Main Feedwater Pump Turbine 2A Auxiliary Equipment Functional Test (continued)

[272] LIFT lead (2NM3B) from Terminal OL2 of 2-STR-46-1A, (729/T16J) MFPT 2A EMERG OIL PMP STARTER, to simulate EOP 1A overload. (Dwg 2-45W600-46-4)

CV

[273] VERIFY Unit 2 Events Display Legend indicates 55-A MFPT 2A EOP OVERLOAD is in ALARM (Red).

[274] LAND lead (2NM3B) on Terminal OL2 of 2-STR-46-1A, MFPT 2A EMERG OIL PMP STARTER.

CV

[275] VERIFY Unit 2 Events Display Legend indicates 55-A MFPT 2A EOP OVERLOAD is NORMAL (Blue).

[276] INSTALL a jumper at Terminal Board TB2 across Terminal Points 137 (2M270A) and 108 (2NM3B) at 2-L-792, TURBINE SUPERVISORY CABINET, to simulate a high turbine vibration (2-45N2635-133).

CV

[277] VERIFY Unit 2 Events Display Legend indicates 53-D, MFPT 2A TURBINE VIBRATION HI is in ALARM (Red).

[278] REMOVE jumper across Terminals TB2-137 (2M270A) and TB2-108 (2NM3B) at 2-L-792, TURBINE SUPERVISORY CABINET.

CV

[279] VERIFY Unit 2 Events Display Legend indicates 53-D, MFPT 2A TURBINE VIBRATION HI is NORMAL (Blue).

[280] INSTALL a jumper at Terminal Board TB2 across Terminal Points 113 (2M271A) and 114 (2NM3B) at 2-L-792, TURBINE SUPERVISORY CABINET, to simulate a pump bearing #2 high vibration (2-45N2635-133).

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 161 of 371 Date 6.23 Main Feedwater Pump Turbine 2A Auxiliary Equipment Functional Test (continued)

[281] VERIFY Unit 2 Events Display Legend indicates 54-D MFPT 2A PUMP VIBRATION HI is in ALARM (Red).

[282] REMOVE jumper across Terminals TB2-113 (2M271A) and TB2-114 (2NM3B) at 2-L-792, TURBINE SUPERVISORY CABINET.

CV

[283] VERIFY Unit 2 Events Display Legend indicates 54-D MFPT 2A PUMP VIBRATION HI is NORMAL (Blue).

[284] INSTALL a jumper at Terminal Board TB2 across Terminal Points 107 (2M270A) and 108 (2NM3B) at 2-L-792, TURBINE SUPERVISORY CABINET, to simulate a turbine high vibration (2-45N2635-133).

CV

[285] VERIFY Unit 2 Events Display Legend indicates 54-D MFPT 2A PUMP VIBRATION HI is in ALARM. (Red).

[286] REMOVE jumper across Terminals TB2-107 (2M270A) and TB2-108 (2NM3B) at 2-L-792, TURBINE SUPERVISORY CABINET.

CV

[287] VERIFY Unit 2 Events Display Legend indicates 54-D MFPT 2A PUMP VIBRATION HI is NORMAL (Blue).

[288] DEPRESS 2-HS-46-5D, MFPT 2A MOP 1 STOP, pushbutton at Panel 2-L-275.

NOTE The following steps may be marked N/A if Subsection 6.24 is to be performed next or if the simulations are not required.

[289] REMOVE jumper across Terminals TB630-1 (9E04) and TB630-2 (9E03) in Panel 2-R-76. (N/A it Step 6.23[205] was marked N/A)

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 162 of 371 Date 6.24 Injection Water Pump 2A Control Logic Test

[1] ENSURE that handswitch 2-HS-54-9A1 (2-M-2) is in Pull-To-Lock (P-T-L) position.

[2] ENSURE that breaker 2-BKR-54-9A, 480V Turbine Building MOV Control Board 2A, is OFF. (Dwg 2-45W753-1)

[3] REMOVE the Overload heaters.

Cv

[4] ENSURE the control power fuses are installed.

[5] PLACE breaker 2-BKR-54-9A, 480V Turbine Building MOV Control Board 2A, to the ON position.

[6] INSTALL a jumper at Terminal Board TB630 across Terminal Points 1 (9E04) and 2 (9E03) at Panel 2-R-76 to simulate a normal FWP seal water pressure. (Dwg 2-45N2691-4)

Cv

[7] VERIFY that Annunciator Window Box 2-XA-55-2C, Alarm 41-E, INJ WATER PMPS DISCH HDR PRESS LO, CLEARS.

[8] VERIFY the following:

A. The Red light for 2-HS-54-9A1 (2-M-2) is OFF.

B. The Green light for 2-HS-54-9A1 (2-M-2) is ON.

[9] PRESS the RESET pushbutton on handswitch 2-HS-54-9A2 on panel 2-JB-291-860 (T15J/708).

[10] MOVE handswitch 2-HS-54-9A1 from Pull-To-Lock (P-T-L) to P-AUTO.

[11] VERIFY the following: Acc Crit (5.OB.54)

A. The Red light for 2-HS-54-9A1 (2-M-2) is OFF.

B. The Green light for 2-HS-54-9A1 (2-M-2) is ON.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 163 of 371 Date 6.24 Injection Water Pump 2A Control Logic Test (continued)

[12] INSTALL a jumper at Terminal Board AA, Section C across Terminal Points 1 (10A3) and 2 (10A2) at Panel 2-L-33 to simulate low FWP 2A seal water differential pressure. (Dwg 45N2635-17)

Cv

[13] VERIFY that Annunciator Window Box 2-XA-55-3B, Alarm 50-E, MFP 2A INJ WATER AP LO, ALARMS.

[14] VERIFY the following: Acc Crit (5.OB.54)

A. The Red light for 2-HS-54-9A1 (2-M-2) is ON.

B. The Green light for 2-HS-54-9A1 (2-M-2) is OFF.

[15] MOVE handswitch 2-HS-54-9A1 from P-AUTO to Pull-To-Lock (P-T-L).

[16] VERIFY the following:

A. The Red light for 2-HS-54-9A1 (2-M-2) is OFF.

B. The Green light for 2-HS-54-9A1 (2-M-2) is ON.

[17] REMOVE the jumper installed in Step 6.24[12].

Cv

[18] VERIFY that Annunciator Window Box XA-55-3B, Alarm 50-E, MFP 2A INJ WATER AP LO, CLEARS.

[19] MOVE handswitch 2-HS-54-9A1 from Pull-To-Lock (P-T-L) to P-AUTO.

[20] VERIFY the following:

A. The Red light for 2-HS-54-9A1 (2-M-2) is OFF.

B. The Green light for 2-HS-54-9A1 (2-M-2) is ON.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 164 of 371 Date 6.24 Injection Water Pump 2A Control Logic Test (continued)

[21] INSTALL a jumper at Terminal Board BB, Section C across Terminal Points 1 (4E3) and 2 (4E2) at Panel 2-L-33 to simulate low FWP 2B seal water differential pressure. (Dwg 45N2635-17)

Cv

[22] VERIFY that Annunciator Window Box XA-55-3B, Alarm 51-E, MFP 2B INJ WATER AP LO, ALARMS.

[23] VERIFY the following: Acc Crit (5.0B.54)

A. The Red light for 2-HS-54-9A1 (2-M-2) is ON.

B. The Green light for 2-HS-54-9A1 (2-M-2) is OFF.

[24] REMOVE the jumper installed in Step 6.24[21]

Cv

[25] VERIFY that Annunciator Window Box XA-55-3B, Alarm 51-E, MFP 2B INJ WATER AP LO, CLEARS.

[26] VERIFY the following:

A. The Red light for 2-HS-54-9A1 (2-M-2) is OFF.

B. The Green light for 2-HS-54-9A1 (2-M-2) is ON.

[27] PLACE handswitch 2-HS-54-9A1 to START and spring return to P-AUTO.

[28] VERIFY the following: Acc Crit (5.OB.53)

A. The Red light for 2-HS-54-9A1 (2-M-2) is ON.

B. The Green light for 2-HS-54-9A1 (2-M-2) is OFF.

[29] PLACE handswitch 2-HS-54-9A1 to STOP then spring return to P-AUTO.

[30] VERIFY the following: Acc Crit (5.0B.53)

A. The Red light for 2-HS-54-9A1 (2-M-2) is OFF.

B. The Green light for 2-HS-54-9A1 (2-M-2) is ON.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 165 of 371 Date 6.24 Injection Water Pump 2A Control Logic Test (continued)

[31] PRESS and HOLD the TEST pushbutton on handswitch 2-HS-54-9B2 on panel 2-JB-291-860 (T15J/708).

[32] VERIFY the following: Acc Crit (5.0B.53)

A. The Red light for 2-HS-54-9A1 (2-M-2) is ON.

B. The Green light for 2-HS-54-9A1 (2-M-2) is OFF.

[33] RELEASE the TEST pushbutton.

[34] VERIFY the following: Acc Crit (5.0B.53)

A. The Red light for 2-HS-54-9A1 (2-M-2) is OFF.

B. The Green light for 2-HS-54-9A1 (2-M-2) is ON.

[35] PRESS and HOLD the TEST pushbutton on handswitch 2-HS-54-9A2 on panel 2-JB-291-860 (T15J1/708).

[36] VERIFY the following:

A. The Red light for 2-HS-54-9A1 (2-M-2) is ON.

B. The Green light for 2-HS-54-9A1 (2-M-2) is OFF.

[37] PRESS the SAFE STOP pushbutton on handswitch 2-HS-54-9A2 on panel 2-JB-291-860 (T15J/708).

[38] VERIFY the following: Acc Crit (5.0B.53)

A. The Red light for 2-HS-54-9A1 (2-M-2) is OFF.

B. The Green light for 2-HS-54-9A1 (2-M-2) is ON.

[39] RELEASE the TEST pushbutton.

A. The Red light for 2-HS-54-9A1 (2-M-2) is OFF.

B. The Green light for 2-HS-54-9A1 (2-M-2) is ON.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 166 of 371 Date 6.24 Injection Water Pump 2A Control Logic Test (continued)

[40] REMOVE the jumper installed in step 6.24[6] at Terminal Board TB630 across Terminal Points 1 (9E04) and 2 (9E03) at Panel 2-R-76.

(Dwg 2-45N2691-4)

Cv

[41] PLACE breaker 2-BKR-54-9A, 480V Turbine Building MOV Control Board 2A, to the OFF position.

[42] PRESS the RESET pushbutton on handswitch 2-HS-54-9A2 on panel 2-JB-291-860 (T15J/708).

[43] RE-INSTALL the Overload heaters.

Cv 6.25 Injection Water Pump 2B Control Logic Test

[1] ENSURE that handswitch 2-HS-54-9B1 (2-M-2) is in Pull-To-Lock (P-T-L) position.

[2] ENSURE that breaker 2-BKR-54-9B, 480V Turbine Building MOV Control Board 2B is OFF. (Dwg 2-45W753-5)

(3] REMOVE the Overload heaters.

Cv

[4] ENSURE the control power fuses are installed.

[5] PLACE breaker 2-BKR-54-9B, 480V Turbine Building MOV Control Board 2B to the ON position.

[6] INSTALL a jumper at Terminal Board TB630 across Terminal Points 1 (9E04) and 2 (9E03) at Panel 2-R-76 to simulate a normal FWP seal water pressure. (Dwg 2-45N2691-4)

Cv

[7] VERIFY that Annunciator Window Box XA-55-2C, Alarm 41-E, INJ WATER PMPS DISCH HDR PRESS LO, CLEARS.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 167 of 371 Date 6.25 Injection Water Pump 2B Control Logic Test (continued)

[8] VERIFY the following:

A. The Red light for 2-HS-54-9B1 (2-M-2) is OFF.

B. The Green light for 2-HS-54-9B1 (2-M-2) is ON.

[9] PRESS the RESET pushbutton on handswitch 2-HS-54-9B2 on panel 2-JB-291-860 (T1 5J/708).

[10] MOVE handswitch 2-HS-54-9B1 from Pull-To-Lock (P-T-L) to P-AUTO.

[11] VERIFY the following: Acc Crit (5.0B.54)

A. The Red light for 2-HS-54-9B1 (2-M-2) is OFF.

B. The Green light for 2-HS-54-9B1 (2-M-2) is ON.

[12] INSTALL a jumper at Terminal Board BB, Section C across Terminal Points 1 (4E3) and 2 (4E2) at Panel 2-L-33 to simulate low FWP 2B seal water differential pressure. (Dwg 45N2635-17)

Cv

[13] VERIFY that Annunciator Window Box XA-55-3B, Alarm 51-E, MFP 2B INJ WATER AP LO, ALARMS.

[14] VERIFY the following: Acc Crit (5.0B.54)

A. The Red light for 2-HS-54-9B1 (2-M-2) is ON.

B. The Green light for 2-HS-54-9B1 (2-M-2) is OFF.

[15] MOVE handswitch 2-HS-54-9B1 from P-AUTO to Pull-To-Lock (P-T-L).

[16] VERIFY the following:

A. The Red light for 2-HS-54-9B1 (2-M-2) is OFF.

B. The Green light for 2-HS-54-9B1 (2-M-2) is ON.

[17] REMOVE the jumper installed in Step 6.25[12]

Cv

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 168 of 371 Date 6.25 Injection Water Pump 2B Control Logic Test (continued)

[18] VERIFY that Annunciator Window Box XA-55-3B, Alarm 51-E, MFP 2B INJ WATER AP LO, CLEARS.

[19] MOVE handswitch 2-HS-54-9B1 from Pull-To-Lock (P-T-L) to P-AUTO.

[20] VERIFY the following:

A. The Red light for 2-HS-54-9B1 (2-M-2) is OFF.

B. The Green light for 2-HS-54-9B1 (2-M-2) is ON.

[21] INSTALL a jumper at Terminal Board AA, Section C across Terminal Points 1 (10A3) and 2 (10A2) at Panel 2-L-33 to simulate low FWP 2A seal water differential pressure.

(Dwg 45N2635-17)

Cv

[22] VERIFY that Annunciator Window Box XA-55-3B, Alarm 50-E, MFP 2A INJ WATER AP LO, ALARMS.

[23] VERIFY the following: Acc Crit (5.OB.54)

A. The Red light for 2-HS-54-9B1 (2-M-2) is ON.

B. The Green light for 2-HS-54-9B1 (2-M-2) is OFF.

[24] REMOVE the jumper installed in Step 6.25[21].

Cv

[25] VERIFY that Annunciator Window Box XA-55-3B, Alarm 50-E, MFP 2A INJ WATER AP LO, CLEARS.

[26] VERIFY the following:

A. The Red light for 2-HS-54-9B1 (2-M-2) is OFF.

B. The Green light for 2-HS-54-9B1 (2-M-2) is ON.

[27] PLACE handswitch 2-HS-54-9B1 to START and spring return to P-AUTO.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 169 of 371 Date 6.25 Injection Water Pump 2B Control Logic Test (continued)

[28] VERIFY the following: Acc Crit (5.0B.53)

A. The Red light for 2-HS-54-9B1 (2-M-2) is ON.

B. The Green light for 2-HS-54-9B1 (2-M-2) is OFF.

[29] PLACE handswitch 2-HS-54-9B1 to STOP then spring return to P-AUTO.

[30] VERIFY the following: Acc Crit (5.0B.53)

A. The Red light for 2-HS-54-9B1 (2-M-2) is OFF.

B. The Green light for 2-HS-54-9B1 (2-M-2) is ON.

[31] PRESS and HOLD the TEST pushbutton on handswitch 2-HS-54-9B2 on panel 2-JB-291-860 (T15J1/708).

[32] VERIFY the following: Acc Crit (5.0B.53)

A. The Red light for 2-HS-54-9B1 (2-M-2) is ON.

B. The Green light for 2-HS-54-9B1 (2-M-2) is OFF.

[33] RELEASE the TEST pushbutton.

[34] VERIFY the following: Acc Crit (5.0B.53)

A. The Red light for 2-HS-54-9B1 (2-M-2) is OFF.

B. The Green light for 2-HS-54-9B1 (2-M-2) is ON.

[35] PRESS and HOLD the TEST pushbutton on handswitch 2-HS-54-9B2 on panel 2-JB-291-860 (T15J1/708).

[36] VERIFY the following:

A. The Red light for 2-HS-54-9B1 (2-M-2) is ON.

B. The Green light for 2-HS-54-9B1 (2-M-2) is OFF.

[37] PRESS the SAFE STOP pushbutton on handswitch 2-HS-54-9B2 on panel 2-JB-291-860 (T15J/708).

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 170 of 371 Date 6.25 Injection Water Pump 2B Control Logic Test (continued)

[38] VERIFY the following: Acc Crit (5.0B.53)

A. The Red light for 2-HS-54-9B1 (2-M-2) is OFF.

B. The Green light for 2-HS-54-9B1 (2-M-2) is ON.

[39] RELEASE the TEST pushbutton.

A. The Red light for 2-HS-54-9B1 (2-M-2) is OFF.

B. The Green light for 2-HS-54-9B1 (2-M-2) is ON.

[40] REMOVE the jumper installed in step 6.25[6] at Terminal Board TB630 across Terminal Points 1 (9E04) and 2 (9E03) at Panel 2-R-76. (Dwg 2-45N2691-4)

Cv

[41] PLACE breaker 2-BKR-54-9B, 480V Turbine Building MOV Control Board 2B to the OFF position.

[42] PRESS the RESET pushbutton on handswitch 2-HS-54-9B2 on panel 2-JB-291-860 (T15J/708).

[43] RE-INSTALL the Overload heaters.

Cv

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 171 of 371 Date 6.26 MFPT 2A High Pressure, Low Pressure and Governor Valve Logic Test

[1] VERIFY prerequisites listed in Section 4.0 for Subsection 6.26 have been completed.

NOTE The following steps satisfy interlocks for stroking the HP, LP, and GOV valves. Simulations which are not required or were installed in Subsection 6.23 may be marked N/A.

[2] LIFT lead TTAP (BK) from the left side of Terminal Board TB-AA, Terminal Point I in Section B of Panel 2-L-69, (708/T1 5G) to simulate a normal MFPT condenser vacuum.

(N/A it normal condenser vacuum is established)

(Dwg 2-45N2635-34)

CV

[3] INSTALL a jumper at Terminal Board TB630 across Terminal Points 1 (9E04) and 2 (9E03) at Panel 2-R-76 to simulate a normal FWP seal water pressure. (N/A if MFP Seal Injection is in service.) (Dwg 2-45N2691-4)

CV NOTE The following step may be marked N/A it MFPT 2A is running.

[4] DEPRESS 2-HS-46-5B, MFPT 2A MOP 1 START, pushbutton at Panel 2-L-275 (729/T15J) to START 2-PMP-46-5B.

[5] PLACE 2-HS-2-221A, MFWP A SUCTION ISOL, on 2-M-3 to the OPEN position and VERIFY 2-FCV-2-221 OPENS by light indication.

[6] PLACE 2-HS-46-9A, TRIP RESET MFPT 2A, on 2-M-3 to the RESET position.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 .

Page 172 of 371 Date 6.26 MFPT 2A High Pressure, Low Pressure and Governor Valve Logic Test (continued)

[7] VERIFY the following:

A. 2-FCV-1-36, MFPT 2A HP STEAM STOP VLV, CLOSED (729 /T15J).

B. Green Light ON (2-HS-46-15B) (2-JB-291-1149).

C. Red Light OFF (2-HS-46-15B).

D. Green Light ON (2-HS-46-15A) (2-M-3)

E. Red Light OFF (2-HS-46-15A)

F. 2-FCV-1-39, MFPT 2A LP STEAM STOP VLV, CLOSED (729/T1 6J).

G. Green Light ON (2-HS-46-16B) (729/TI 5J).

H. Red Light OFF (2-HS-46-16B).

I. Green Light ON (2-HS-46-16A) (2-M-3).

J. Red Light OFF (2-HS-46-16A).

K. No continuity across Terminal Points 581 (AB-5) and 582 (AB-6) in Panel 2-L-275. (Dwg 2-45W2614-3)

M&TE ID#

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 173 of 371 Date 6.26 MFPT 2A High Pressure, Low Pressure and Governor Valve Logic Test (continued)

[8] PLACE 2-HS-46-15A, MFPT 2A HP STOP VLV, at 2-M-3 to the RAISE position and VERIFY:

A. Red Light ON (2-HS-46-15A). Acc Crit (5.0B.41)

B. Green Light OFF (2-HS-46-15A). Acc Crit (5.0B.41)

C. 2-FCV-1-36 OPEN (locally). Acc Crit (5.OB.41)

D. Red Light ON (2-HS-46-15B). Acc Crit (5.0B.41)

E. Green Light OFF (2-HS-46-15B). Acc Crit (5.OB.41)

F. Red Light ON (2-HS-46-16A). Acc Crit (5.0B.41)

G. Green Light OFF (2-HS-46-16A). Acc Crit (5.0B.41)

H. 2-FCV-1-39 OPEN (locally). Acc Crit (5.0B.41)

I. Red Light ON (2-HS-46-16B) Acc Crit (5.OB.41)

J. Green Light OFF (2-HS-46-16B). Acc Crit (5.0B.41)

K. Continuity across Terminal Points 581 (AB-5) and 582 (AB-6) in Panel 2-L-275.

M&TE ID#

[9] PLACE Handswitch 2-HS-46-9A, TRIP RESET MFPT 2A, on 2-M-3 to the TRIP position.

[10] VERIFY 2-FCV-1-36, MFPT 2A HP STEAM STOP VLV, CLOSES by light indication on 2-HS-46-15A, MFPT 2A HP STOP VLV. Acc Crit (5.0B.41)

[11] VERIFY 2-FCV-1-39, MFPT 2A LP STEAM STOP VLV, CLOSES by light indication on 2-HS-46-16A, MFPT 2A LP STOP VLV. Acc Crit (5.0B.41)

[12] PLACE 2-HS-46-9A, TRIP RESET MFPT 2A, on 2-M-3 to the RESET position

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 174 of 371 Date 6.26 MFPT 2A High Pressure, Low Pressure and Governor Valve Logic Test (continued)

[13] PLACE 2-HS-46-15B, MFPT 2A HP STOP VLV, Panel 2-JB-291-1149 (729/T16J) to the RAISE position and VERIFY: Acc Crit (5.0B.41)

A. 2-FCV-1-36 OPEN.

B. 2-FCV-1-39 OPEN.

[14] PLACE 2-HS-46-9A, TRIP RESET MFPT 2A, on 2-M-3 to the TRIP position and VERIFY: Acc Crit (5.0B.41)

A. 2-FCV-1-36 CLOSED.

B. 2-FCV-1-39 CLOSED

[15] PLACE 2-HS-46-9A, TRIP RESET MFPT 2A, on 2-M-3 to the RESET position.

[16] PLACE 2-HS-46-16A, MFPT 2A LP STOP VLV, 2-M-3 to the RAISE position and VERIFY: Acc Crit (5.0B.41)

A. Red Light ON (2-HS-46-16A).

B. Green Light OFF (2-HS-46-16A).

C. 2-FCV-1-39 OPEN (locally).

D. Red Light ON (2-HS-46-16B).

E. Green Light OFF (2-HS-46-16B).

F. Red Light ON (2-HS-46-15A).

G. Green Light OFF (2-HS-46-15A).

H. 2-FCV-1-36 OPEN (locally).

I. Red Light ON (2-HS-46-15B).

J. Green Light OFF (2-HS-46-15B).

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 175 of 371 Date 6.26 MFPT 2A High Pressure, Low Pressure and Governor Valve Logic Test (continued)

[17] PLACE 2-HS-46-9A, TRIP RESET MFPT 2A, on 2-M-3 to the TRIP position.

[18] VERIFY 2-FCV-1-39, MFPT 2A LP STEAM STOP VLV, CLOSES by light indication on 2-HS-46-16A, MFPT 2A LP STOP VLV. Acc Crit (5.0B.41)

[19] VERIFY 2-FCV-1-36, MFPT 2A HP STEAM STOP VLV, CLOSES by light indication on 2-HS-46-15A, MFPT 2A HP STOP VLV. Acc Crit (5.0B.41)

[20] PLACE 2-HS-46-15A, MFPT 2A HP STOP VLV, at 2-M-3 to the TEST position and VERIFY:

A. 2-FCV-1-36 does not STROKE by light indication.

B. 2-FCV-1-39 does not STROKE by light indication.

[21] PLACE 2-HS-46-16A, MFPT 2A LP STOP VLV, at 2-M-3 to the TEST position and VERIFY:

A. 2-FCV-1-36 does not STROKE by light indication.

B. 2-FCV-1-39 does not STROKE by light indication.

[22] PLACE 2-HS-46-15B, MFPT 2A HP STOP VLV, at Panel 2-JB-291-1149 to the TEST position and VERIFY:

A. 2-FCV-1-36 does not STROKE by light indication.

B. 2-FCV-1-39 does not STROKE by light indication.

[23] PLACE 2-HS-46-16B, MFPT 2A LP STOP VLV, at Panel 2-JB-291-1149 to the TEST position and VERIFY:

A. 2-FCV-1 -36 does not STROKE by light indication.

B. 2-FCV-1-39 does not STROKE by light indication.

[24] PLACE 2-HS-46-9A, TRIP RESET MFPT 2A, on 2-M-3 to the RESET position.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 176 of 371 Date 6.26 MFPT 2A High Pressure, Low Pressure and Governor Valve Logic Test (continued)

[25] PLACE 2-HS-46-16B MFPT 2A LP STOP VLV, at Panel 2-JB-291-1149 to the RAISE position and VERIFY:

A. 2-FCV-1-36 OPEN.

B. 2-FCV-1-39 OPEN.

[26] VERIFY locally 2-FCV-1-37 (729/Ti 5), MFPT 2A HP STEAM CONTROL VLV, is CLOSED by valve stem position indication.

[27] VERIFY locally 2-FCV-1 -38 (729/TI 6J), MFPT 2A LP STEAM CONTROL VLV, is CLOSED by valve stem position indication.

[28] VERIFY 2-FCV-1-37, MFPT 2A HP STEAM CONTROL VLV, and 2-FCV-1-38, MFPT 2A LP STEAM CONTROL VLV, are CLOSED by light indication at Panel 2-L-275.

A. Green Light ON.

B. Red Light OFF.

[29] VERIFY 2-FCV-1-38, MFPT 2A LP STEAM CONTROL VLV, is at a MINIMUM position as indicated on 2-ZI-46-13D, MFPT 2A LOW PRESS GOV VLV POSITION, at 2-L-275 and RECORD the indicated position.

LP GV % OPEN  % (0-6.5%)

[30] VERIFY 2-FCV-1-37, MFPT 2A HP STEAM CONTROL VLV, is at a MINIMUM position as indicated on 2-ZI-46-13E, MFPT 2A HIGH PRESS GOV VLV POSITION, at 2-L-275 and RECORD the indicated position.

HP GV % OPEN  % (0-6.5%)

[31] VERIFY 2-FCV-1-37, MFPT 2A. HP STEAM CONTROL VLV, and 2-FCV-1 -38, MFPT 2A LP STEAM CONTROL VLV, are CLOSED by light indication at 2-HS-46-13A, MFPT 2A GOVERNOR VLV, on 2-M-3.

A. Green Light ON.

B. Red Light OFF.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 177 of 371 Date 6.26 MFPT 2A High Pressure, Low Pressure and Governor Valve Logic Test (continued)

[32] VERIFY 2-FCV-1 -38, MFPT 2A LP STEAM CONTROL VLV, is at a MINIMUM position as indicated on 2-ZI-46-13A, MFPT 2A LP GOV VLV POS, on 2-M-3 and RECORD the indicated position.

MFPT LP GOV VLV  % (0-6.5%)

[331 VERIFY 2-FCV-1-37, MFPT 2A HP STEAM CONTROL VLV, is at a MINIMUM position as indicated on 2-ZI-46-13B, MFPT 2A HP GOV VLV POS, on 2-M-3 and RECORD the indicated position.

MFPT HP GOV VLV  % (0-6.5%)

[34] PLACE and HOLD 2-HS-46-13A, MFPT 2A GOVERNOR VLV, on 2-M-3 to the RAISE position until FULL OPEN indication is obtained and VERIFY: Acc Crit (5.0B.41)

A. Green Light OFF (2-HS-46-13A).

B. Red Light ON (2-HS-46-13A).

C. Green Light OFF (2-L-275).

D. Red Light ON (2-L-275).

[35] VERIFY 2-FCV-1-37, MFPT 2A HP STEAM CONTROL VLV, is at a MAXIMUM position as indicated at 2-ZI-46-13B, MFPT 2A HP GOV VLV on 2-M-3 and RECORD the position indication.

MFPT 2A HP GOV VLV  % (93.5-100%)

[36] VERIFY 2-FCV-1-38, MFPT 2A LP STEAM CONTROL VLV, is at a MAXIMUM position as indicated on 2-ZI-46-13A, MFPT 2A LP GOV VLV, on 2-M-3 and RECORD the position indication.

MFPT 2A LP GOV VLV  % (93.5-100%)

[37] PLACE 2-HS-46-13A, MFPT 2A GOVERNOR VLV, on 2-M-3 to the LOWER position to close 2-FCV-1-37, MFPT 2A HP STEAM CONTROL VLV, and 2-FCV-1-38, MFPT 2A LP STEAM CONTROL VLV. Acc Crit (5.0B.41)

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 178 of 371 Date 6.26 MFPT 2A High Pressure, Low Pressure and Governor Valve Logic Test (continued)

[38] DEPRESS and HOLD 2-HS-46-13B, MFPT 2A GOV VLV POSITION, RAISE pushbutton at Panel 2-L-275 until 2-FCV-1-37, MFPT 2A HP STEAM CONTROL VLV, and 2-FCV-1-38, MFPT 2A LP STEAM CONTROL VLV are OPEN. Acc Crit (5.0B.41)

[39] VERIFY 2-FCV-1-37, MFPT 2A HP STEAM CONTROL VLV, is at a MAXIMUM position as indicated at 2-ZI-46-13E, MFPT 2A HIGH PRESS GOV VLV POSITION, at Panel 2-L-275 and RECORD the indicated position. Acc Crit (5.0B.41)

HP GV % OPEN  % (93.5-100%)

[40] VERIFY 2-FCV-1-38, MFPT 2A LP STEAM CONTROL VLV, is at a MAXIMUM position as indicated on 2-ZI-46-13D, MFPT 2A LOW PRESS GOV VLV POSITION, at Panel 2-L-275 and RECORD the indicated position. Acc Crit (5.0B.41)

LP GV % OPEN  % (93.5-100%)

NOTE The next two steps will occur simultaneously. Position test support personnel at 2-FCV-1-39, MFPT 2A LP STEAM STOP VLV, to verify a partial valve stroke and amber light actuation. The amber light is ON when 2-FCV-1-39, MFPT 2A LP STEAM STOP VLV, reaches 25% closed and is OFF when the valve starts to reopen.

[41] PLACE 2-HS-46-16B, MFPT 2A LP STOP VLV, at Panel 2-JB-291-1149 to the TEST position and VERIFY the Amber light flashes ON, then OFF.

[42] VERIFY 2-FCV-1-39, MFPT 2A LP STEAM STOP VLV, partial stroke CLOSED, then returned to the OPEN position.

[43] PLACE 2-HS-46-16A, MFPT 2A LP STOP VLV, on 2-M-3 to the TEST position and VERIFY the Amber light flashes ON, then OFF to indicate 2-FCV-1-39 movement.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 179 of 371 Date 6.26 MFPT 2A High Pressure, Low Pressure and Governor Valve Logic Test (continued)

NOTE Position test personnel at 2-FCV-1-36, MFPT 2A HP STEAM STOP VLV, to observe valve stem movement.

[44] PLACE 2-HS-46-15A, MFPT 2A HP STOP VLV, 2-M-3 to the TEST position and VERIFY the Amber Light does not flash ON and OFF.

[45] VERIFY 2-FCV-1-36, MFPT 2A HP STEAM STOP VLV did not STROKE by observing the valve stem for movement.

[46] PLACE 2-HS-46-9A, TRIP RESET MFPT 2A, on 2-M-3 to the TRIP position.

[47] VERIFY locally the following valves are CLOSED:

A. 2-FCV-1-36, MFPT 2A HP STEAM STOP VLV.

B. 2-FCV-1-39, MFPT 2A LP STEAM STOP VLV.

C. 2-FCV-1-37, MFPT 2A HP STEAM CONTROL VLV.

D. 2-FCV-1-38, MFPT 2A LP STEAM CONTROL VLV.

[48] PLACE 2-HS-46-9A, TRIP RESET MFPT 2A, on 2-M-3 to the RESET position.

[49] PLACE 2-HS-46-15A, MFPT 2A HP STOP VLV, to the RAISE position.

[50] PLACE 2-HS-46-15A, MFPT 2A HP STOP VLV, on 2-M-3 to the TEST position and VERIFY the Amber Light flashes ON, then OFF to indicate 2-FCV-1 -36 stroke.

[51] VERIFY locally 2-FCV-1-36, MFPT 2A HP STEAM STOP VLV, stroked CLOSED by observing the valve stem for movement.

[52] PLACE 2-HS-46-15B, MFPT 2A HP STOP VLV, Panel 2-JB-291-1149 to the TEST position and VERIFY the Amber light is ON, then OFF to indicate valve stroke.

[53] DEPRESS 2-HS-46-9D, MFPT 2A TURB TRIP PB, at Panel 2-L-275 to TRIP MFPT 2A.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 180 of 371 Date 6.26 MFPT 2A High Pressure, Low Pressure and Governor Valve Logic Test (continued)

[54] PLACE 2-HS-46-15A, MFPT 2A HP STOP VLV, 2-M-3 to the RAISE position and VERIFY by light indication that 2-FCV-1-36 REMAINS CLOSED.

[55] PLACE 2-HS-46-16A, MFPT 2A LP STOP VLV, 2-M-3 to the RAISE position and VERIFY by light indication that 2-FCV-1-39 REMAINS CLOSED.

[56] PLACE 2-HS-46-13A, MFPT 2A GOVERNOR VLV, on 2-M-3 to the RAISE position and VERIFY by light indication that 2-FCV-1 -37 and 2-FCV-1 -38 REMAIN CLOSED.

[57] REMOVE jumper across Terminal Board TB630 across Terminal Points 1 and 2 in Panel 2-R-76. (N/A if Step 6.23[205] and/or 6.26[3] were marked N/A)

CV

[58] LAND lead TTAP (BK) on Terminal Board TB-AA, Terminal Point 1 in Panel 2-L-69. (N/A if Step 6.26[2] was marked N/A)

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 181 of 371 Date 6.27 Main Feedwater Pump Turbine 2B Auxiliary Equipment Functional Test

[1] VERIFY prerequisites listed in Section 4.3[4] for Subsection 6.27 are completed.

[2] VERIFY/PLACE 2-HS-46-30AA, MFPT 2B MOP 1 on 2-M-3 to the PULL-TO-LOCK position.

[3] VERIFY/PLACE 2-HS-46-30AB, MFPT 2B MOP 2, on 2-M-3 to the PULL-TO-LOCK position.

[4] VERIFY/PLACE 2-HS-46-27A, MFPT 2B EMERGENCY OIL PMP, on 2-M-3 in the PULL-TO-LOCK position.

[5] VERIFY/CLOSE 2-SW-46-27A, MFPT 2B EMER OIL PMP DISCONNECT SW, adjacent to Panel 2-JB-291-1219 (729/TI 6H).

[6] OPEN local disconnect 2-SW-46-27A, MFPT 2B EMER OIL PUMP DISCONNECT SW, for Emergency Oil Pump A.

[7] VERIFY Unit 2 Events Display Legend indicates 56-B MFPT 2B EOP CONTROL PWR FAILURE is in ALARM (Red).

Acc Crit (5.0B.40)

[8] CLOSE local disconnect 2-SW-46-27A, MFPT 2B EMER OIL PMP DISCONNECT SW, for Emergency Oil Pump A.

[9] VERIFY Unit 2 Events Display Legend indicates 56-B MFPT 2B EOP CONTROL PWR FAILURE is NORMAL (Blue).

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 182 of 371 Date 6.27 Main Feedwater Pump Turbine 2B Auxiliary Equipment Functional Test (continued)

[10] PLACE 2-HS-46-27A, MFPT 2B EMERGENCY OIL PMP, on 2-M-3 in the P-AUTO position and VERIFY: Acc Crit (5.0B.39)

A. Red "ON" Light ON (2-HS-46-27A).

B. Red "RUN" Light ON (2-HS-46-27A).

C. Green Light OFF (2-HS-46-27A).

D. 2-PMP-46-27A, MFPT 2B EMERG OIL PMP, STARTS (729/TI 5H)

E. "EOP-ON" Red Light ON (2-L-276) (729/T1 5H)

F. "EOP-RUN" Red light ON (2-L-276).

G. "EOP-OFF" Green Light OFF (2-L-276).

[11] VERIFY Unit 2 Events Display Legend indicates 56-A MFPT 2B EOP RUNNING (PS-46-28) is in ALARM (Red).

Acc Crit (5.0B.39)

[12] PLACE 2-HS-46-30AA, MFPT 2B MOP 1, 2-M-3 to the START position and VERIFY: Acc Crit (5.08.46)

A. Red "ON" Light ON (2-HS-46-30AA).

B. Red "RUN" Light ON (2-HS-46-30AA).

C. Green Light OFF (2-HS-46-30AA).

D. 2-PMP-46-30B, MFPT 2B MAIN OIL PMP 1, STARTS (729/TI 6H).

E. "MOP-1 ON" Red Light ON (2-L-276).

F. "MOP-1 RUN" Red Light ON (2-L-276).

G. "MOP-1 OFF" Green Light OFF (2-L-276).

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 183 of 371 Date 6.27 Main Feedwater Pump Turbine 2B Auxiliary Equipment Functional Test (continued)

[13] PLACE 2-HS-46-27A, MFPT 2B EMERGENCY OIL PMP, on 2-M-3 to the STOP position and VERIFY:

A. Red "ON" Light OFF (2-HS-46-27A).

B. Red "RUN" Light OFF (2-HS-46-27A).

C. Green Light ON (2-HS-46-27A).

D. 2-PMP-46-27A, MFPT 2B EMERG OIL PMP, STOPS (729/Ti 6H).

E. "EOP-ON" Red Light OFF (2-L-276).

F. "EOP-RUN" Red Light OFF (2-L-276).

G. "EOP-OFF" Green Light ON (2-L-276).

[14] VERIFY the Unit 2 Events Display Legend Indicates 56-A MFPT 2B EOP RUNNING (PS-46-28) is NORMAL (Blue).

NOTE The Test pushbutton creates a low pressure for MOP 1 which will AUTO START the Emergency Oil Pump.

[15] DEPRESS 2-HS-46-28, MFPT 2B EMERG OIL PMP TEST, pushbutton at Panel 2-L-276.

[16] VERIFY 2-PMP-46-27A, MFPT 2B EMERG OIL PMP, STARTS by light indication at Panel 2-L-276.

Acc Crit (5.0B.44)

[17] PLACE 2-HS-46-27A, MFPT 2B EMERGENCY OIL PMP, on 2-M-3 to the STOP position.

[18] DEPRESS 2-HS-46-27B, MFPT 2B EMERG OIL PMP START, pushbutton at Panel 2-L-276 and VERIFY 2-PMP-46-27A, MFPT 2B EMERG OIL PMP, STARTS by light indication.

[19] DEPRESS 2-HS-46-27D, MFPT 2B EMERG OIL STOP, pushbutton at Panel 2-L-276 and VERIFY 2-PMP-46-27A, MFPT 2B EMERG OIL PMP, STOPS by light indication.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 184 of 371 Date 6.27 Main Feedwater Pump Turbine 2B Auxiliary Equipment Functional Test (continued)

[20] PLACE 2-HS-46-27A, MFPT 2B EMERGENCY OIL PMP, on 2-M-3 to the PULL-TO-LOCK position and VERIFY:

A. Red "ON" Light OFF (2-HS-46-27A).

B. Red "RUN" Light OFF (2-HS-46-27A).

C. Green Light OFF (2-HS-46-27A).

D. "EOP-ON" Red Light OFF (2-L-276).

E. "EOP-RUN" Red Light OFF (2-L-276).

F. "EOP-OFF" Green Light OFF (2-L-276).

[21] PLACE 2-HS-46-30AB, MFPT 2B MOP 2, on 2-M-3 to the START position and VERIFY: Acc Crit (5.0B.46)

A. Red "ON" Light ON (2-HS-46-30AB).

B. Red "RUN" Light ON (2-HS-46-30AB).

C. Green Light OFF (2-HS-46-30AB).

D. 2-PMP-46-30E, MFPT 2B MAIN OIL PMP 2, STARTS (729/Ti 5H).

E. "MOP-2 ON" Red Light ON (2-L-276).

F. "MOP-2 RUN" Red Light ON (2-L-276).

G. "MOP-2 OFF" Green Light OFF (2-L-276).

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 185 of 371 Date 6.27 Main Feedwater Pump Turbine 2B Auxiliary Equipment Functional Test (continued)

[22] PLACE 2-HS-46-30AA, MFPT 2B MOP 1, on 2-M-3 to the STOP position and VERIFY:

A. Red "ON" Light OFF (2-HS-46-30AA).

B. Red "RUN" Light OFF (2-HS-46-30AA).

C. Green Light ON (2-HS-46-30AA).

D. 2-PMP-46-30B, MFPT 2B MAIN OIL PMP 1, STOPS (locally).

E. "MOP-1 ON" Red Light OFF (2-L-276).

F. "MOP-1 RUN" Red Light OFF (2-L-276).

G. "MOP-1 OFF" Green Light ON (1-L--276).

[23] DEPRESS 2-HS-46-30B, MFPT 2B MOP 1 START, pushbutton at Panel 2-L-276 and VERIFY 2-PMP-46-30B, MFPT 2B MAIN OIL PMP 1, STARTS by light indication.

[24] PLACE 2-HS-46-30AB, MFPT 2B MOP 2, on 2-M-3 to the STOP position and VERIFY:

A. Red "ON" Light OFF (2-HS-46-30AB).

B. Red "RUN" Light OFF (2-HS-46-30AB).

C. Green Light ON (2-HS-46-30AB).

D. 2-PMP-46-30E, MFPT 2B MAIN OIL PMP 2, STOPS (locally).

E. "MOP-2 ON" Red Light OFF (2-L-276).

F. "MOP-2 RUN" Red Light OFF (2-L-276).

G. "MOP-2 OFF" Green Light ON (2-L-276).

[25] VERIFY Unit 2 Events Display Legend indicates 53-A MFPT MOP 1 PRESS LO is NORMAL (Blue).

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 186 of 371 Date 6.27 Main Feedwater Pump Turbine 2B Auxiliary Equipment Functional Test (continued)

NOTE The following step will simulate TRIP of the operating MFPT 2B Main Oil Pump and AUTO-START of standby oil pump.

[26] PLACE 2-HS-46-30AA, MFPT 2B MOP 1, on 2-M-3 to the STOP position and VERIFY:

A. 2-PMP-46-30B, MFPT 2B MAIN OIL PMP 1, STOPS (locally).

B. 2-PMP-46-30E, MFPT 2B MAIN OIL PMP 2, STARTS (locally). Acc Crit (5.0B.35)

[27] VERIFY Unit 2 Events Display Legend indicates:

A. 52-B MFPT 2B RESERVE MOP RUNNING (HS-46-30A) is in ALARM (Red).

B. 53-A MFPT 2B MOP 1 PRESS LO is in ALARM (Red).

[28] PLACE 2-HS-46-30AA, MFPT 2B MOP 1, on 2-M-3 to the START position.

[29] PLACE 2-HS-46-30AB, MFPT 2B MOP 2, on 2-M-3 to the STOP position.

[30] VERIFY 2-PMP-46-30E, MFPT 2B MAIN OIL PMP 2, STOPS by light indication at 2-M-3.

[31] VERIFY Unit 2 Events Display Legend indicates:

A. 52-B MFPT 2B RESERVE MOP RUNNING (HS-46-30A) is NORMAL (Blue).

B. 53-A MFPT 2B MOP 1 PRESS LO is NORMAL (Blue).

[32] PLACE 2-HS-46-30AB, MFPT 2B MOP 2, on 2-M-3 to the START position.

[33] PLACE 2-HS-46-30AA, MFPT 2B MOP 1, on 2-M-3 to the STOP position.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 187 of 371 Date 6.27 Main Feedwater Pump Turbine 2B Auxiliary Equipment Functional Test (continued)

NOTE The following step will simulate a TRIP of the operating MFPT 2B Main Pump and AUTO-START of the standby oil pump.

[34] PLACE 2-HS-46-30AB, MFPT 2B MOP 2, on 2-M-3 to the STOP position and VERIFY:

A. 2-PMP-46-30E, MFPT 2B MAIN OIL PMP 2, STOPS (locally).

B. 2-PMP-46-30B, MFPT 2B MAIN OIL PMP 1, STARTS (locally). Acc Crit (5.0B.35)

[35] VERIFY Unit 2 Events Display Legend indicates:

A. 54-A MFPT 2B MOP 2 PRESS LO is in ALARM (Red).

B. 52-B MFPT 2B RESERVE MOP RUNNING (HS-46-30A) is in ALARM (Red)

[36] PLACE 2-HS-46-30AB, MFPT 2B MOP 2, on 2-M-3 to the START position.

[37] PLACE 2-HS-46-30AA, MFPT 2B MOP 1, on 2-M-3 to the STOP position.

[38] VERIFY Unit 2 Events Display Legend indicates 54-A MFPT 2B MOP 2 PRESS LO is NORMAL (Blue).

[39] VERIFY Unit 2 Events Display Legend indicates 52-B MFPT 2B RESERVE MOP RUNNING (HS-46-30A) is NORMAL (Blue).

NOTE Depressing the MFPT 2B MAIN OIL PUMP 1 TEST, pushbutton will simulate a low pressure on MFPT 2B MAIN OIL PUMP 2 and cause MFPT 2B MAIN OIL PUMP 1 to START.

[40] DEPRESS and HOLD 2-HS-46-34, MFPT 2B MOP 1 TEST, pushbutton at Panel 2-L-276.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 188 of 371 Date 6.27 Main Feedwater Pump Turbine 2B Auxiliary Equipment Functional Test (continued)

[41] VERIFY 2-PMP-46-30B, MFPT 2B MAIN OIL PMP 1, STARTS by light indication at Panel 2-L-276. Acc Crit (5.0B.36)

[42] VERIFY Unit 2 Events Display Legend indicates:

Acc Crit (5.0B.36)

A. 54-A MFPT 2B MOP 2 PRESS LO is in ALARM (Red).

B. 52-B MFPT 2B RESERVE MOP RUNNING (HS-46-30A) is in ALARM (Red).

[43] RELEASE 2-HS-46-34, MFPT 2B MOP 1 TEST, pushbutton Panel 2-L-276.

[44] PLACE 2-HS-46-30AA, MFPT 2B MOP 1, on 2-M-3 to the STOP position and VERIFY 2-PMP-46-30B STOPS by light indication.

[45] VERIFY Unit 2 Events Display Legend indicates:

A. 54-A MFPT 2B MOP 2 PRESS LO is NORMAL (Blue).

B. 52-B MFPT 2B RESERVE MOP RUNNING (HS-46-30A) is NORMAL (Blue).

[46] PLACE 2-HS-46-30AA, MFPT 2B MOP 1, on 2-M-3 to the START position and VERIFY 2-PMP-46-30B, MFPT 2B MAIN OIL PMP 1, STARTS by light indication.

[47] PLACE 2-HS-46-30AB, MFPT 2B MOP 2, on 2-M-3 to the STOP position and VERIFY 2-PMP-46-30E, MFPT 2B MAIN OIL PMP 2, STOPS by light indication.

NOTE Depressing the MFPT 2B MAIN OIL PUMP 2 Test, pushbutton will simulate a low pressure on MFPT 2B MAIN OIL PUMP 1 and cause MFPT 2B MAIN OIL PUMP 2 to START.

[48] DEPRESS and HOLD 2-HS-46-33, MFPT 2B MOP 2 TEST, pushbutton at Panel 2-L-276.

[49] VERIFY 2-PMP-46-30E, MFPT 2B MAIN OIL PMP 2, STARTS by light indication at Panel 2-L-276. Acc Crit (5.0B.36)

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 189 of 371 Date 6.27 Main Feedwater Pump Turbine 2B Auxiliary Equipment Functional Test (continued)

[50] VERIFY Unit 2 Events Display Legend indicates:

Acc Crit (5,0B.36)

A. 53-A MFPT 2B MOP 1 PRESS LO is in ALARM (Red).

B. 52-B MFPT 2B RESERVE MOP RUNNING (HS-46-30A) is in ALARM (Red).

[51] RELEASE 2-HS-46-33, MFPT 2B MOP 1 TEST, pushbutton at Panel 2-L-276.

.[52] PLACE 2-HS-46-30AB, MFPT 2B MOP 2, on 2-M-3 to the STOP position and VERIFY 2-PMP-46-30E MFPT 2B MAIN OIL PUMP 2, STOPS by light indication.

[53] VERIFY Unit 2 Events Display Legend indicates:

A. 53-A MFPT 2B MOP 2 PRESS LO is NORMAL, (Blue).

B. 52-B MFPT 2B RESERVE MOP RUNNING (HS-46-30A) is NORMAL (Blue).

[54] LIFT lead 3AB10 from Terminal 29 of Panel 2-L-276 to simulate a high motor temperature on 2-PMP-46-30E, MFPT 2B MAIN OIL PMP 2. (Dwg 2-45W2614-5)

CV NOTE 2-PMP-46-30E, MFPT 2B MAIN OIL PMP 2, will not stop until 2-PMP-46-30B, MFPT 2B MAIN OIL PMP 1, discharge pressure is adequate.

[55] VERIFY that 2-PMP-46-30B, MFPT 2B MAIN OIL PMP 1, STARTS by light indication at 2-M-3. Acc Crit (5.0B.37)

[56] VERIFY 2-PMP-46-30E, MFPT 2B MAIN OIL PMP 2, STOPS by light indication at 2-M-3.

[57] VERIFY Unit 2 Events Display Legend indicates 51-B MFPT 2B MOP OVERLOAD/CONTROL PWR FAILURE is in ALARM (Red).

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 190 of 371 Date 6.27 Main Feedwater Pump Turbine 2B Auxiliary Equipment Functional Test (continued)

[58) LAND lead 3AB10 on Terminal 29 of Panel 2-L-276.

CV

[59] VERIFY Unit 2 Events Display Legend indicates 51-B MFPT 2B MOP OVERLOAD/CONTROL PWR FAILURE is NORMAL (Blue).

[60] PLACE 2-HS-46-30AB, MFPT 2B MOP 2, on 2-M-3 to the STOP position.

[61] LIFT lead 9FB10 from Terminal 9 of Panel 2-L-276 to simulate a high motor temperature on 2-PMP-46-30B, MFPT 2B MAIN OIL PMP 1. (Dwg 2-45W2614-5)

CV NOTE 2-PMP-46-30B, MFPT 2B MAIN OIL PMP 1, will not STOP until 2-PMP-46-30E, MFPT 2B MAIN OIL PMP 2, discharge pressure is adequate.

[62] VERIFY that 2-PMP-46-30E MFPT 2B, MAIN OIL PMP 2, STARTS by light indication at 2-M-3. Acc Crit (5.0B.37)

[63] VERIFY 2-PMP-46-30B, MFPT 2B MAIN OIL PMP 1, STOPS by light indication at 2-M-3.

[64] VERIFY Unit 2 Events Display Legend indicates 51-B MFPT 2B MOP OVERLOAD/CONTROL PWR FAILURE is in ALARM (Red).

[65] LAND lead 9FB10 on the right side of Terminal 9 of Panel 2-L-276.

CV

[66] VERIFY Unit 2 Events Display Legend indicates 51-B MFPT 2B MOP OVERLOAD/CONTROL PWR FAILURE is NORMAL (Blue).

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 191 of 371 Date 6.27 Main Feedwater Pump Turbine 2B Auxiliary Equipment Functional Test (continued)

[67] DEPRESS and HOLD 2-HS-46-30F, MFPT 2B MOP 2 STOP, pushbutton at Panel 2-L-276 and VERIFY 2-PMP-46-30E STOPS by light indication.

[68] VERIFY 2-PMP-46-30B, MFPT 2B MAIN OIL PMP 1, STARTS by light indication at Panel 2-L-276.

[69] RELEASE 2-HS-46-30F, MFPT 2B MOP 2 STOP pushbutton at Panel 2-L-276 and VERIFY 2-PMP-46-30E does not START.

[70] DEPRESS and HOLD 2-HS-46-30D, MFPT 2B MOP 1 STOP pushbutton at Panel 2-L-276 and VERIFY 2-PMP-46-30B STOPS by light indication.

[71] VERIFY 2-PMP-46-30E, MFPT 2B MAIN OIL PMP 2, STARTS by light indication at Panel 2-L-276.

[72] RELEASE 2-HS-46-30D, MFPT 2B MOP 1 STOP pushbutton at Panel 2-L-276 and VERIFY 2-PMP-46-30B does not START.

[73] PLACE and HOLD 2-HS-46-30AB, MFPT 2B MOP 2, on 2-M-3 to the STOP position and VERIFY 2-PMP-46-30E STOPS by light indication.

[74] VERIFY 2-PMP-46-30B, MFPT 2B MAIN OIL PMP 1, STARTS by light indication at Panel 2-L-276.

[75] RELEASE 2-HS-46-30AB, MFPT 2B MOP 2, on 2-M-3 and VERIFY 2-PMP-46-30B does not START.

[76] PLACE and HOLD 2-HS-46-30AA, MFPT 2B MOP 1, on 2-M-3 to the STOP position and VERIFY 2-PMP-46-30B STOPS.

[77] VERIFY 2-PMP-46-30E, MFPT 2B MAIN OIL PMP 2, STARTS, by light indication at Panel 2-L-276.

[78] RELEASE 2-HS-46-30AA, MFPT 2B MOP 1, on 2-M-3 and VERIFY 2-PMP-46-30B does not START.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 192 of 371 Date 6.27 Main Feedwater Pump Turbine 2B Auxiliary Equipment Functional Test (continued)

[79] DEPRESS 2-HS-46-30B, MFPT 2B MOP 1 START, pushbutton at Panel 2-L-276 and VERIFY 2-PMP-46-30B, MFPT 2B MAIN OIL PMP 1, STARTS by light indication.

[80] PLACE 2-HS-46-30AB, MFPT 2B MOP 2, 2-M-3 to the PULL-TO-LOCK position and VERIFY:

A. Red "ON" Light OFF (2-HS-46-30AB).

B. Red "RUN" Light OFF (2-HS-46-30AB).

C. Green Light OFF (2-HS-46-30AB).

D. "MOP-2 ON" Red Light OFF (2-L-276).

E. "MOP-2 RUN" Red Light OFF (2-L-276).

F. "MOP-2 OFF" Green Light OFF (2-L-276).

G. 2-PMP-46-30E, MFPT 2B MAIN OIL PMP 2, STOPS.

[81] PLACE 2-HS-46-30AA, MFPT 2B MOP 1, on 2-M-3 to the PULL-TO-LOCK position and VERIFY:

A. Red "ON" Light OFF (2-HS-46-30AA).

B. Red "RUN" Light OFF (2-HS-46-30AA).

C. Green Light OFF (2-HS-46-30AA).

D. "MOP-1 ON" Red Light OFF (2-L-276).

E. "MOP-1 RUN" Red Light OFF (2-L-276).

F. "MOP-1 OFF" Green Light OFF (2-L-276).

G. 2-PMP-46-30B, MFPT 2B MAIN OIL PMP 1, STOPS.

[82] DEPRESS 2-HS-46-30B, MFPT 2B MOP 1 START, pushbutton at Panel 2-L-276 and VERIFY locally that 2-PMP-46-30B does not START.

[83] DEPRESS 2-HS-46-30E, MFPT 2B MOP 2 START, pushbutton at Panel 2-L-276 and VERIFY locally that 2-PMP-46-30E does not START.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 193 of 371 Date 6.27 Main Feedwater Pump Turbine 2B Auxiliary Equipment Functional Test (continued)

[84] DEPRESS 2-HS-46-27B, MFPT 2B EMERG OIL PMP START, pushbutton at Panel 2-L-276 and VERIFY locally that 2-PMP-46-28 does not START.

[85] VERIFY/PLACE 2-HS-46-41, MFPT 2B DRAIN VLVS, on 2-M-3 to the CLOSE position and VERIFY:

A. "2-FCV-46-41A CL" Green Light ON.

B. "2-FCV-46-41A OP" Red Light OFF.

C. "2-FCV-46-41B CL" Green Light ON.

D. "2-FCV-46-41 B OP" Red Light OFF.

[86] PLACE 2-HS-46-41, MFPT 2B DRAIN VLVS, on 2-M-3 to the OPEN position and VERIFY:

A. "2-FCV-46-41A CL" Green Light OFF.

B. "2-FCV-46-41A OP" Red Light ON.

C. "2-FCV-46-41 B CL" Green Light OFF.

D. "2-FCV-46-41B OP" Red Light ON.

[87] PLACE 2-HS-46-41, MFPT 2B DRAIN VLVS, on 2-M-3 to the CLOSE position.

[88] VERIFY/PLACE 2-HS-46-81, MFPT 2B OIL RES HTR CONT, at Panel 2-JB-291-1219 (729/T16J) to the OFF position and VERIFY:

A. Green Light ON (2-HS-46-81).

B. Red Light OFF (2-HS-46-81).

[89] VERIFY/PLACE 2-HS-46-37, MFPT 2B VAPOR EXTRACTOR, at Panel 2-JB-291-1219 to the OFF position and VERIFY:

A. Green Light ON (2-HS-46-37).

B. Red Light OFF (2-HS-46-37).

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 194 of 371 Date 6.27 Main Feedwater Pump Turbine 2B Auxiliary Equipment Functional Test (continued)

[90] PLACE 2-HS-46-37, MFPT 2B VAPOR EXTRACTOR, at Panel 2-JB-291-1219 to the ON position and VERIFY:

A. Green Light OFF (2-HS-46-37).

B. Red Light ON (2-HS-46-37).

C. 2-MTR-46-37, MFPT 2B VAPOR EXTRACTOR, is RUNNING (729/T1i6H). Acc Crit (5.0B.50)

[91] PLACE 2-HS-46-37, MFPT 2B VAPOR EXTRACTOR, at Panel 2-JB-291-1219 to the OFF position.

[92] PLACE 2-HS-46-81, MFPT 2B OIL RES HTR CONT, at Panel 2-JB-291-1219 to the AUTO position.

NOTE The previous step may have energized the Oil Reservoir Heater if the oil temperature was below 70 0 F. If the Oil Reservoir Heater is ON as indicated by light indication then mark the following step N/A.

[93] INSTALL a jumper across Terminal Points 45 (23/ORH) and 46 (23/ORH) of Panel 2-L-276 to simulate a low oil reservoir temperature. (Dwg 2-45W2614-5)

CV

[94] VERIFY the Oil Reservoir Heater is ON by light indication at Panel 2-JB-91-1219: Acc Crit (5.0B.28)

A. Green Light OFF (2-HS-46-81).

B. Red Light ON (2-HS-46-81).

[95] VERIFY the 2-VEXT-46-37, MFPT 2B OIL RESERVOIR VAPOR EXTRACTOR, is ON by light indication.

[96] PLACE 2-HS-46-81, MFPT 2B OIL RES HTR CONT, at Panel 2-JB-291-1219 to the OFF position.

[97] VERIFY the 2-VEXT-46-37, MFPT 2B OIL RESERVOIR VAPOR EXTRACTOR, is OFF by light indication.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 195 of 371 Date 6.27 Main Feedwater Pump Turbine 2B Auxiliary Equipment Functional Test (continued)

[98] PLACE 2-HS-46-81, MFPT 2B OIL RES HTR CONT, at Panel 2-JB-291-1219 to the AUTO position.

[99] VERIFY the Oil Reservoir Heater is ON by light indication at Panel 2-JB-291-1219.

[100] LIFT lead 903 from Terminal 43 of Panel 2-L-276 to simulate a low oil level. (Dwg 2-45W2614-5)

CV

[101] VERIFY the Oil Reservoir Heater is OFF by light indication at Panel 2-JB-291-1219. Acc Crit (5.0B.28)

[102] LAND lead 903 on Terminal 43 of Panel 2-L-276 to clear the simulated low oil level.

CV

[103] VERIFY the Oil Reservoir Heater is ON by light indication at Panel 2-JB-291-1219. Acc Crit (5.0B.28)

[104] PLACE 2-HS-46-81, MFPT 2B OIL RES HTR CONT, at Panel 2-JB-291-1219 to the OFF position.

NOTE This step may be marked N/A if Step 6.27[93] was marked N/A.

[105] REMOVE the jumper across Terminals 45 (23/ORH) and 46 (23/ORH) of Panel 2-L-276.

CV

[106] DEPRESS 2-HS-46-36B, MFPT 2B TURB RESET, pushbutton at Panel 2-L-276 to RESET the MFPT 2B.

[107] VERIFY/PLACE 2-HS-46-38B, MFPT 2B TURNING GEAR RESET-SAFE STOP, at Panel 2-L-276 to the JOG position.

[108] VERIFY locally the turning gear is not ENGAGED by observing that the turbine shaft is not rotating.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 196 of 371 Date 6.27 Main Feedwater Pump Turbine 2B Auxiliary Equipment Functional Test (continued)

[109] VERIFY the turning gear is not ENGAGED by light indication at Panel 2-L-276.

A. "TGM RUN" Green Light OFF.

B. "TGM RUN" Red Light OFF.

[110] VERIFY the turning gear is not ENGAGED by light indication on Handswitch 2-HS-46-38A, MFPT 2B TURNING GEAR, at 2-M-3:

A. Green Light OFF.

B. Red Light OFF.

[111] DEPRESS 2-HS-46-38D, MFPT 2B TURNING GEAR P.B.

START, pushbutton at Panel 2-L-276 and VERIFY locally turning gear does not START.

[112] PLACE 2-HS-46-38A, MFPT 2B TURNING GEAR, on 2-M-3 to the START position and VERIFY by light indication that the turning gear does not START.

[113] PLACE 2-HS-46-30AA, MFPT 2B MOP 1, on 2-M-3 to the START position.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 197 of 371 Date 6.27 Main Feedwater Pump Turbine 2B Auxiliary Equipment Functional Test (continued)

NOTE Position test personnel at Control Board 2-M-3 to observe light indications for the following step.

[114] DEPRESS and HOLD 2-HS-46-38E, MFPT 2B TURNING GEAR JOG SW, pushbutton at Panel 2-L-276 and VERIFY:

(Acc Crit 5.0B.51)

A. "TGM RUN" Red Light ON (2-L-276).

B. "TGM OFF" Green Light OFF (2-L-276).

C. Red Light ON (2-HS-46-38A).

D. Green Light OFF (2-HS-46-38A).

E. Blue Light OFF (2-HS-46-38A).

F. Turbine Shaft ROTATING (locally).

[115] RELEASE 2-HS-46-38E, MFPT 2B TURNING GEAR JOG SW, pushbutton at Panel 2-L-276.

[116] VERIFY the turning gear STOPS by light indication at Panel 2-L-276.

[117] PLACE 2-HS-46-38B, MFPT 2B TURNING GEAR RESET-SAFE STOP, at Panel 2-L-276 to the NORM position and VERIFY:

A. "TGM RUN" Red Light OFF (2-L-276).

B. "TGM OFF" Green Light ON (2-L-276).

C. Red Light OFF (2-HS-46-38A).

D. Green Light ON (2-HS-46-38A).

E. Blue Light ON (2-HS-46-38A).

[118] VERIFY Unit 2 Events Display Legend indicates 53-B MFPT 2B TURNING GEAR FAILURE is in ALARM (Red).

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 198 of 371 Date 6.27 Main Feedwater Pump Turbine 2B Auxiliary Equipment Functional Test (continued)

[119] DEPRESS 2-HS-46-38E, MFPT 2B TURNING GEAR JOG SW, pushbutton at Panel 2-L-276 and VERIFY the turning gear will not START.

[120] PLACE 2-HS-46-38A, MFPT 2B TURNING GEAR, on 2-M-3 to the START position and VERIFY:

A. Red Light ON (2-HS-46-38A).

B. Green Light OFF (2-HS-46-38A).

C. Blue Light OFF (2-HS-46-38A).

D. "TGM RUN" Red Light ON (2-L-276).

E. "TGM OFF" Green Light OFF (2-L-276).

F. Turbine Shaft ROTATING (locally).

[121] VERIFY Unit 2 Events Display Legend indicates 53-B MFPT 2B TURNING GEAR FAILURE is NORMAL (Blue).

[122] DEPRESS 2-HS-46-36B, MFPT 2B TURB RESET, pushbutton at Panel 2-L-276 to RESET the MFPT 2B.

[123] PLACE 2-HS-46-38A, MFPT 2B TURNING GEAR at 2-M-3 to the STOP position and VERIFY 2-MTR-46-38D, MFPT 2B TURNING GEAR, STOPS.

[124] DEPRESS 2-HS-46-38D, MFPT 2B TURNING GEAR P.B.

START, pushbutton at Panel 2-L-276 and VERIFY the turning gear STARTS by light indication.

[125] LIFT lead RISVCL [LP] from the right side of Terminal 255 of Panel 2-L-276 to simulate an open low pressure stop valve.

(Dwg 2-45W2614-5)

CV

[126] VERIFY locally that the turning gear STOPS.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 199 of 371 Date 6.27 Main Feedwater Pump Turbine 2B Auxiliary Equipment Functional Test (continued)

[127] LAND lead RISVCL [LP] on the right side of Terminal 255 in Panel 2-L-276.

CV

[128] VERIFY that the turning gear does not RESTART by light indication at Panel 2-L-276.

[129] DEPRESS 2-HS-46-36D, MFPT 2B TURB TRIP, pushbutton Panel 2-L-276 to TRIP the MFPT.

NOTE The following step will simulate a Main Feedwater Pump Turbine shaft speed of 2 RPM or more.

[130] MOMENTARILY PLACE a jumper between Terminal Points 280 (R/ZSD) and 282 (R/ZSD) in Panel 2-L-276 and VERIFY locally that the turning gear STARTS.

(Dwg 2-45W2614-5)

CV

[1311 LIFT lead 9E4 on Terminal 258 in Panel 2-L-276 to simulate an open high pressure stop valve. (Dwg. 2-45W2614-5)

CV

[132] VERIFY locally that the turning gear STOPS.

[133] LAND lead 9E4 on Terminal 258 in Panel 2-L-276.

CV

[134] VERIFY locally that the turning gear STARTS.

[135] INSTALL a jumper across Terminal Points 195 and 205 (TTBTO) in Panel 2-L-276 to simulate a low turbine bearing oil pressure. (Dwg 2-45W2614-5)

CV

[136] VERIFY locally that the turning gear STOPS.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 200 of 371 Date 6.27 Main Feedwater Pump Turbine 2B Auxiliary Equipment Functional Test (continued)

[137] REMOVE the jumper across Terminals 195 and 205 (TTBTO) in Panel 2-L-276.

Cv

[138] VERIFY locally that the turning gear STARTS.

[139] INSTALL jumper across Terminal Points 198 (TTBP [BK])

and 202 (TTBPO [W]) in Panel 2-L-276 to simulate a low pump bearing oil pressure. (Dwg 2-45W2614-5)

Cv

[140] VERIFY locally that the turning gear STOPS.

Acc Crit (5.0B.34)

[141] REMOVE the jumper across Terminals 198 (TTBP [BK])

and 202 (TTBPO [WM) in Panel 2-L-276.

Cv

[142] VERIFY locally that the turning gear STARTS.

[143] LIFT lead (9E2) on Terminal 273 in Panel 2-L-276 to simulate a turning gear high motor temperature. (Dwg 2-45W2614-5)

Cv

[144] VERIFY locally that the turning gear STOPS.

Acc Crit (5.0B.34)

[145] LAND the lifted lead (9E2) on Terminal 273 in Panel 2-L-276.

Cv

[146] VERIFY locally that the turning gear STARTS.

[147] LIFT lead (R/ZSD) on the right side of Terminal 127 in Panel 2-L-276 to simulate turbine speed greater than 2 RPM.

(Dwg 2-45W2614-5)

Cv

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 201 of 371 Date 6.27 Main Feedwater Pump Turbine 2B Auxiliary Equipment Functional Test (continued)

[148] LIFT lead (R/TT-1) on the right side of Terminal 251 in Panel 2-L-276 to remove the turbine trip signal from the turning gear logic. (Dwg 2-45W2614-5)

Cv

[149] VERIFY locally that the turning gear CONTINUES to RUN.

[150] PLACE 2-HS-46-38A, MFPT 2B TURNING GEAR, on 2-M-3 to the STOP position and VERIFY the turning gear STOPS by light indication.

[151] LAND lead (R/TT-1) on the right side of Terminal 251 in Panel 2-L-276.

Cv

[152] VERIFY the turning gear does not RESTART by light indication:

A. Blue Light ON (2-HS-46-38A).

B. Green Light ON (2-HS-46-38A).

C. "TGM OFF" Green Light ON (2-L-276).

[153] LAND lead (RPZSD) on the right side of Terminal 127 in Panel 2-L-276.

Cv

[154] VERIFY locally that the turning gear STARTS.

[155] PLACE 2-HS-46-38B, MFPT 2B TURNING GEAR RESET-SAFE STOP, at Panel 2-L-276 to the OFF position and VERIFY the turning gear STOPS by light indication.

[156] VERIFY that only the Blue "Normal Oil Level" indicator light is ON at Panel 2-JB-291-1219.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 202 of 371 Date 6.27 Main Feedwater Pump Turbine 2B Auxiliary Equipment Functional Test (continued)

NOTE Perform the following three steps before releasing 2-HS-46-29B, MFPT 2B ALM TEST HIGH LVL, pushbutton. Position test personnel at 2-M-3 to observe control room indications.

[157] DEPRESS and HOLD 2-HS-46-29B, MFPT 2B ALM TEST HIGH LVL, pushbutton at Panel 2-JB-291-1219.

[158] VERIFY Unit 2 Events Display Legend indicates 55-B MFPT 2B OIL TANK LEVEL HI/LO (LS-46-32ANB) is in ALARM (Red).

Acc Crit (5.0B.30)

[159] VERIFY the following light indications at Panel 2-JB-291-1219:

Acc Crit (5.0B.30)

A. "OIL LEVEL HIGH", White Light ON.

B. "OIL LEVEL NORMAL", Blue Light OFF.

[160] RELEASE 2-HS-46-29B, MFPT 2B ALM TEST HIGH LVL, pushbutton at Panel 2-JB-291-1219.

[161] VERIFY Unit 2 Events Display Legend indicates 55-B MFPT 2B OIL TANK LEVEL HI/LO (LS-46-32ANB) is NORMAL (Blue).

[162] VERIFY that only the Blue "Normal Oil Level" indictor light is ON at Panel 2-JB-291-1219.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 203 of 371 Date 6.27 Main Feedwater Pump Turbine 2B Auxiliary Equipment Functional Test (continued)

NOTE Perform the following three steps before releasing 2-HS-46-29D, MFPT 2B ALM TEST LOW LVL, pushbutton. Position test personnel at 2-M-3 to observe control room indications.

[163] DEPRESS and HOLD 2-HS-46-29D, MFPT 2B ALM TEST LOW LVL, pushbutton at Panel 2-JB-291-1219.

[164] VERIFY Unit 2 Events Display Legend indicates 55-B MFPT 2B OIL TANK LEVEL HI/LO (LS-46-32NB) is in ALARM (Red).

Acc Crit (5.0B.30)

[165] VERIFY the following light indications at Panel 2-JB-291-1219:

Acc Crit (5.0B.30)

A. "OIL LEVEL LOW", White Light ON.

B. "OIL LEVEL NORMAL', Blue Light OFF.

[166] RELEASE 2-HS-46-29D, MFPT 2B ALM TEST LOW LVL, pushbutton at Panel 2-JB-291-1219.

[167] VERIFY Unit 2 Events Display Legend indicates 55-B MFPT 2B OIL TANK LEVEL HI/LO (LS-46-32A/B) is NORMAL (Blue).

[168] VERIFY that only the Blue "Normal Oil Level" indictor light is ON at Panel 2-JB-291-1219.

[169] PLACE and HOLD hand held jumper across Terminal Points 185 (2M268B) and 186 (2NM3B) in Panel 2-L-276 and VERIFY Annunciator Window 51-D, OIL FROM COOLER TEMP HI, ALARMS. (Dwg 2-45W2614-5) Acc Crit (5.0B.29)

CV

[170] VERIFY Unit 2 Events Display Legend indicates 51-D; MFPT 2B OIL FROM COOLER TEMP HI is in ALARM (Red).

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 204 of 371 Date 6.27 Main Feedwater Pump Turbine 2B Auxiliary Equipment Functional Test (continued)

[171] REMOVE hand held jumper across Terminal Points 185 (2M268B) and 186 (2NM3B) in Panel 2-L-276 and VERIFY Annunciator Window 51-D OIL FROM COOLER TEMP HI, CLEARS.

Cv

[172] VERIFY Unit 2 Events Display Legend indicates 51-D MFPT 2B OIL FROM COOLER TEMP HI is NORMAL (Blue).

[173] PLACE and HOLD hand held jumper across Terminal Points 183 (2M265B) and 184 (2NM3B) in Panel 2-L-276 to simulate a high bearing drain oil temperature.

(Dwg 2-45W2614-5)

CV

[174] VERIFY Annunciator Window 55-C MFPT 2B #1 BEARING DRAIN OIL TEMP HI, ALARMS. Acc Crit (5.0B.29)

[175] VERIFY Unit 2. Events Display Legend indicates 55-C MFPT 2B #1 BEARING DRAIN OIL TEMP HI (2-TIS-046-0062) is in ALARM (Red).

[176] REMOVE hand held jumper across Terminal Points 183 (2M265B) and 184 (2NM3B) in Panel 2-L-276 to clear the high bearing drain oil temperature.

CV

[177] VERIFY Unit 2 Events Display Legend indicates 55-C MFPT 2B #1 BEARING DRAIN OIL TEMP HI (2-TIS-046-0062) is NORMAL (Blue)

[178] PLACE and HOLD hand held jumper across Terminal Points 181 (2M266B) and 182 (2NM3B) in Panel 2-L-276, to simulate a high bearing drain oil temperature.

(Dwg 2-45W2614-5)

CV

[179] VERIFY Annunciator Window 56-C MFPT 2B #2 BEARING DRAIN OIL TEMP HI, ALARMS. Acc Crit (5.0B.29)

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 205 of 371 Date 6.27 Main Feedwater Pump Turbine 2B Auxiliary Equipment Functional Test (continued)

[180] VERIFY Unit 2 Events Display Legend indicates 56-C MFPT 2B #2 BEARING DRAIN OIL TEMP HI (2-TIS-046-0064) is in ALARM (Red).

[181] REMOVE hand held jumper across Terminal Points 181 (2M266B) and 182 (2NM3B) in Panel 2-L-276, to clear the simulated high bearing oil temp.

CV

[182] VERIFY Unit 2 Events Display Legend indicates 56-C MFPT 2B #2 BEARING DRAIN OIL TEMP HI (2-TIS-046-0064) is NORMAL (Blue).

[183] PLACE and HOLD hand held jumper across Terminal Points 179 (2M264B) and 180 (2NM3B) in Panel 2-L-276, to simulate a high thrust bearing drain oil temperature.

(Dwg 2-45W2614-5)

CV

[184] VERIFY Annunciator Window 54-C MFPT 2B THRUST BEARING DRAIN OIL TEMP HI, ALARMS. Acc Crit (5.OB.29)

[185] VERIFY Unit 2 Events Display Legend indicates 54-C MFPT 2B THRUST BEARING DRAIN OIL TEMP HI (2-TIS-046-0066) is in ALARM (Red).

[186] REMOVE hand held jumper across Terminal Points 179 (2M264B) and 180 (2NM3B) in Panel 2-L-276, to clear the high thrust bearing drain oil temperature.

CV

[187] VERIFY Unit 2 Events Display Legend indicates 54-C MFPT 2B THRUST BEARING DRAIN OIL TEMP HI (2-TIS-046-0066) is NORMAL (Blue).

[188] LIFT lead TMBX (BK) from Terminal Board TB203, Terminal point 11 in Panel 2-R-72 (708/TI 0-H) to simulate a loss of AC control power. (Dwg 2-45N2687-3)

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 206 of 371 Date 6.27 Main Feedwater Pump Turbine 2B Auxiliary Equipment Functional Test (continued)

[189] VERIFY Unit 2 Events Display Legend indicates 52-C MFPT 2B AC CONTROL BUS UNDERVOLTAGE is in ALARM (Red).

[190] LAND lead TMBX (BK) on Terminal Board TB203, Terminal Point 11 in Panel 2-R-72.

Cv

[191] VERIFY Unit 2 Events Display Legend indicates 52-C MFPT 2B AC CONTROL BUS UNDERVOLTAGE is NORMAL (Blue).

[192] VERIFY the Amber "LOSS OF 250 VDC" Light is ON at Panel 2-JB-291-1219.

[193] PLACE Breaker 321 at 250V DC Battery Board 2, to the OFF position.

[194] VERIFY Unit 2 Events Display Legend indicates 51-C MFPT 2B TRIP & RESET CIRCUIT PWR FAILURE is in ALARM (Red). Acc Crit (5.0B.31)

[195] VERIFY the Amber "LOSS OF 250 VDC" light is OFF at Panel 2-JB-291-1219.

[196] PLACE Breaker 321 at the 250V DC Battery Board 2 to the ON position.

[197] VERIFY Unit 2 Events Display Legend indicates 51-C MFPT 2B TRIP & RESET CIRCUIT POWER FAILURE is NORMAL (Blue).

[198] VERIFY the Amber "LOSS OF 250 VDC" light is ON at Panel 2-JB-291-1219.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 207 of 371 Date 6.27 Main Feedwater Pump Turbine 2B Auxiliary Equipment Functional Test (continued)

NOTE The following steps simulate interlocks for testing the MFPT trips. Simulations which are not required may be marked N/A.

[199] LIFT lead TTBP (BK) from the left side of Terminal Board TB AA, Terminal 4 in Section B of Panel 2-L-69, (708/T1 5G) to simulate a normal MFPT condenser vacuum. (N/A if normal condenser vacuum is established) (Dwg 2-45N2635-34)

CV

[200] INSTALL an open test switch between Terminal Board TB AA, Terminal 4 and the lifted lead TTBP (BK) in Section B of Panel 2-L-69. (N/A if normal condenser vacuum is established) (Dwg 2-45N2635-34)

CV

[201] INSTALL a jumper at Terminal Board TB631 across Terminal Points 1 (6A04) and 2 (6A03) at Panel 2-R-76 to simulate a normal FWP seal water pressure. (N/A if MFP Seal Injection is in service) (Dwg 2-45N2691-4)

CV NOTE The following step may be marked N/A if MFPT 2B MOP 1 is running.

[202] DEPRESS 2-HS-46-30B, MFPT 2B MOP 1 START, pushbutton at Panel 2-L-276 to START 2-PMP-46-30B.

[203] PLACE 2-HS-46-36A, TRIP RESET MFPT 2B, on 2-M-3 to the RESET position and VERIFY:

A. Red Light ON (2-HS-46-36A).

B. Green Light OFF (2-HS-46-36A).

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 208 of 371 Date 6.27 Main Feedwater Pump Turbine 2B Auxiliary Equipment Functional Test (continued)

[204] PLACE 2-HS-46-36A, TRIP RESET MFPT 2B, on 2-M-3 to the TRIP position and VERIFY:

A. Red Light OFF (2-HS-46-36A).

B. Green Light ON (2-HS-46-36A).

[205] VERIFY Unit 2 MCR alarm 51-A TRIPPED and Events Display Legend indicates 51-A MFPT 2B TRIPPED is in ALARM (Red).

Acc Crit (5.0B.32)

[206] VERIFY Unit 2 MCR alarm 28-E TURBINE RUNBACK BOP and Events Display Legend indicates 28-E TURBINE RUNBACK BOP (PIS-47-13RLY4) is in ALARM (Red).

Acc Crit (5.0B.32)

[207] PLACE 2-HS-46-36A, TRIP RESET MFPT 2B, on 2-M-3 to the RESET position.

[208] VERIFY Unit 2 Events Display Legends indicate 51-A MFPT 2B TRIPPED and 28-E TURBINE RUNBACK BOP (PIS 13RLY4) are NORMAL (Blue) and the MCR alarms clear.

[209] DEPRESS 2-HS-46-36D, MFPT 2B TURB TRIP, pushbutton Panel 2-L-276 and VERIFY:

A. "TURBINE TRIP" Green Light ON.

B. "RESET" Red Light OFF.

[210] DEPRESS 2-HS-46-36B, MFPT 2B TURB RESET, pushbutton at Panel 2-L-276 and VERIFY:

A. "TURBINE TRIP" Green Light OFF.

B. "RESET" Red Light ON.

[211] LIFT one lead of the jumper installed at Terminal Board TB631 across Terminal Points 1 (6A04) and 2 (6A03) at Panel 2-R-76 to simulate low FWP seal water pressure.

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 209 of 371 Date 6.27 Main Feedwater Pump Turbine 2B Auxiliary Equipment Functional Test (continued)

[212] VERIFY Unit 2 Events Display Legend indicates 51-E MFP 2B INJ WATER DP LO is in ALARM (Red). Acc Crit (5.0B.33)

[213] LAND the lead of the jumper installed lifted in step 6.27[211]

to simulate normal FWP seal water pressure.

CV

[214] VERIFY Unit 2 Events Display Legend indicates 51-E MFP 2B INJ WATER DP LO is NORMAL (Blue).

[215] INSTALL a jumper across Terminal Points 198 (TTBP [BK])

and Terminal 202 (TTBPO [W]) at Panel 2-L-276 to simulate a low pump bearing oil pressure. (Dwg 2-45W2614-5)

CV

[216] VERIFY Unit 2 Events Display Legend indicates 52-A MFPT 2B BEARING OIL PRESS LO (PS-46-39B) is in ALARM (Red).

Acc Crit (5.0B.33)

[217] VERIFY MFPT 2B is TRIPPED by light indication at 2-HS-46-36A, TRIP RESET MFPT 2B.

[218] REMOVE jumper across Terminals 198 (TTBP [BK)) and 202 (TTBPO [W]) at Panel 2-L-276 to clear the simulated low pump bearing oil pressure.

CV

[219] VERIFY Unit 2 Events Display Legend indicates 52-A MFPT 2B BEARING OIL PRESS LO (PS-46-39B) is NORMAL (Blue).

[220] PLACE 2-HS-46-36A, TRIP RESET MFPT 2B, to the RESET position.

[221] INSTALL a jumper across Terminal Points 195 (63/LBOT) and 205 (63/LBOT) at Panel 2-L-276 to simulate a low turbine bearing oil pressure. (Dwg 2-45W2614-5)

CV

[222] VERIFY MFPT 2B is TRIPPED by light indication at 2-HS-46-36A, TRIP RESET MFPT 2B.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 210 of 371 Date 6.27 Main Feedwater Pump Turbine 2B Auxiliary Equipment Functional Test (continued)

[223] VERIFY Unit 2 Events Display Legend indicates 52-A MFPT 2B BEARING OIL PRESS LO (PS-46-39B) is in ALARM (Red).

Acc Crit (5.0B.33)

[224] REMOVE jumper across Terminals 195 (63/LBOT) and 205 (63/LBOT) at Panel 2-L-276 to clear the simulated low turbine bearing oil pressure.

CV

[225] PLACE 2-HS-46-36A, TRIP RESET MFPT 2B, on 2-M-3 to the RESET position.

NOTE If a normal condenser vacuum was established the following two steps are required to simulate a low condenser vacuum. If a normal condenser vacuum was not established the following step may be marked N/A.

[226] INSTALL a jumper at Terminal Board AA across Terminal Points 4 (TTBP [BK]) and 5 (TTB1 [W]) in Section B of Panel 2-L-69, to simulate a loss of condenser vacuum.

(Dwg 2-45N2635-34)

CV

[227] CLOSE test switch (installed in step 6.27[200] to establish a loss of normal condenser vacuum.

[228] VERIFY Unit 2 Events Display Legend indicates 55-D MFPT 2B CONDENSER VACUUM LO (PS-2-252E) is in ALARM (Red). Acc Crit (5.0B.33)

[229] VERIFY MFPT 2B is TRIPPED by light indication at 2-HS-46-36A, TRIP RESET MFPT 2B.

[230] REMOVE jumper from Terminals AA-4 (TTBP [BK]) and AA-5 (TTB1 [W]) at Section B of Panel 2-L-69. (N/A if step 6.27[226]

was marked N/A.)

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 211 of 371 Date 6.27 Main Feedwater Pump Turbine 2B Auxiliary Equipment Functional Test (continued)

[231] OPEN test switch to establish a normal condenser vacuum.

(N/A if step 6.27[227] was N/A)

[232] VERIFY Unit 2 Events Display Legend indicates 55-D MFPT 2B CONDENSER VACUUM LO (PS-2-252E) is NORMAL (Blue).

[233] PLACE 2-HS-46-36A, TRIP RESET MFPT 2B, to the RESET position.

[234] INSTALL a jumper at across TB2-122 (2M257B) and TB2-123 (2NM3B) in 2-L-792, TURBINE SUPERVISORY CABINET to simulate a normal thrust bearing wear (Dwg 2-45W600-46-8).

CV

[235] VERIFY Unit 2 Events Display Legend indicates 54-B MFPT 2B THRUST BEARING WEAR is in ALARM (Red).

Acc Crit (5.0B.33)

[236] INSTALL a jumper across TB9-5 and TB9-6 on 2-RLY-046-450B in 2-L-792, TURBINE SUPERVISORY CABINET to simulate a normal thrust bearing wear (Dwg 2-45W2635-133).

CV

[237] VERIFY MFPT 2B is TRIPPED by light indication at 2-HS-46-36A, TRIP RESET MFPT 2B.

[238] REMOVE the jumper across TB2-122 (2M257B) and TB2-123 (2NM3B) in 2-L-792, TURBINE SUPERVISORY CABINET that was installed in step 6.27[234] (Dwg 2-45W600-46-8).

CV

[239] VERIFY Unit 2 Events Display Legend indicates 54-B MFPT 2B THRUST BEARING WEAR is NORMAL (Blue).

[240] REMOVE jumper across TB9-5 and TB9-6 in 2-L-792, TURBINE SUPERVISORY CABINET that was installed in step 6.27[236] (Dwg 2-45W2635-133).

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 212 of 371 Date 6.27 Main Feedwater Pump Turbine 2B Auxiliary Equipment Functional Test (continued)

[241] PLACE 2-HS-46-36A, TRIP RESET MFPT 2B, on 2-M-3 to the RESET position.

[242] INSTALL a jumper across TB9-11 and TB9-12 on 2-RLY-046-450D in 2-L-792, TURBINE SUPERVISORY CABINET to simulate a reverse thrust bearing wear (Dwg 2-45W2635-133).

CV

[243] VERIFY MFPT 2B is TRIPPED by light indication at 2-HS-46-36A, TRIP RESET MFPT 2B.

[244] REMOVE jumper across TB9-11 and TB9-112 in 2-L-792, TURBINE SUPERVISORY CABINET installed in step 6.27[234] (Dwg 2-45W2635-133).

CV

[245] LAND lead TTBP (BK) on Terminal Point 196 at Panel 2-L-276 to clear the MFP 2B Suction Valve Open Interlock. (Lifted by prerequisite 4.3[4])

CV

[246] PLACE 2-HS-2-224A, MFWP B SUCTION ISOL, on 2-M-3 to the OPEN position and VERIFY 2-FCV-2-224 OPENS by light indication.

[247] PLACE 2-HS-46-36A, TRIP RESET MFPT 2B, on 2-M-3 to the RESET position.

[248] PLACE 2-HS-2-224A, MFPT 2B SUCTION ISOL, on 2-M-3 to the CLOSE position and VERIFY Annunciator Window 53-C, MFP SUCTION VLV NOT FULL OPEN, ALARMS before 2-FCV-2-224 is CLOSED. Acc Crit (5.0B.33)

[249] VERIFY MFPT 2B is TRIPPED by light indication at 21-HS-46-36A, TRIP RESET MFPT 2B.

[250] VERIFY Unit 2 Events Display Legend indicates 53-C MFP 2B SUCTION VLV NOT FULL OPEN is in ALARM (Red).

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 213 of 371 Date 6.27 Main Feedwater Pump Turbine 2B Auxiliary Equipment Functional Test (continued)

[251] PLACE 2-HS-2-224A, MFPT 2B SUCTION ISOL, on 2-M-3 to the OPEN position and VERIFY Annunciator Window 53-C, MFP SUCTION VLV NOT FULL OPEN, is CLEAR.

[252] VERIFY Unit 2 Events Display Legend indicates 53-C MFP 2B SUCTION VLV NOT FULL OPEN is NORMAL (Blue).

[253] PLACE 2-HS-46-36A, TRIP RESET MFPT 2B, on 2-M-3 to the RESET position.

[254] INSTALL a jumper at Terminal Board TB634 across the field side of Terminal Points 3 (TVBA1) and 4 (TVBA2) in Panel 2-R-48, to simulate a Train A Feedwater Isolation Signal. (Dwg 2-45N2676-5)

CV

[255] VERIFY MFPT 2B is TRIPPED by light indication at Handswitch 2-HS-46-36A, TRIP RESET MFPT 2B.

Acc Crit (5.0B.21)

[256] REMOVE jumper across Terminals TB634-3 (TVBA1) and TB634-4 (TVBA2) at 2-R-48.

CV

[257] VERIFY MFPT 2B remains TRIPPED by light indication at 2-HS-46-36A, TRIP RESET MFPT 2B.

[258] PLACE 2-HS-46-36A, TRIP RESET MFPT 2B, on 2-M-3 to the RESET position.

[259] INSTALL a jumper at Terminal Board TB634 across the field side of Terminal Points 3 (TVBB1) and 4 (TVBB2) in Panel 2-R-51, to simulate a Train B Feedwater Isolation Signal. (Dwg 2-45N2677-5)

CV

[260] VERIFY MFPT 2B is TRIPPED by light indication at 2-HS-46-36A, TRIP RESET MFPT 2B. Acc Crit (5.0B.21)

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 214 of 371 Date 6.27 Main Feedwater Pump Turbine 2B Auxiliary Equipment Functional Test (continued)

[261] REMOVE the jumper installed in step 6.27[259] across Terminals TB634-3 (TVBB1) and TB634-4 (TVBB2) at 2-R-51.

CV

[262] VERIFY MFPT 2B remains TRIPPED by light indication at Handswitch 2-HS-46-36A, TRIP RESET MFPT 2B.

[263] PLACE 2-HS-46-36A, TRIP RESET MFPT 2B, on 2-M-3 to the RESET position.

[264] REMOVE OPEN test switch between Terminal Board TB-AA, Terminal 4 and the lifted lead TTBP (BK) in Panel 2-L-69. (N/A if normal condenser vacuum was established)

CV

[265] LAND lead TTBP (BK) on Terminal Board TB-AA, Terminal 4 in Panel 2-L-69.

CV

[266] LIFT lead (2NM3B) from Terminal OL2 of 2-STR-46-27A (729/T16H) MFPT 2B EMERG OIL PMP STARTER, to simulate EOP 2B overload. (Dwg 2-45W600-46-4)

CV

[2671 VERIFY Unit 2 Events Display Legend indicates 55-A MFPT 2B EOP OVERLOAD is in ALARM (Red).

[268] LAND lead (2NM3B) on Terminal OL2 of 2-STR-46--27A, MFPT 2B EMERG OIL PMP STARTER.

CV

[269] VERIFY Unit 2 Events Display Legend indicates 55-A MFPT 2B EOP OVERLOAD is NORMAL (Blue).

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 215 of 371 Date 6.27 Main Feedwater Pump Turbine 2B Auxiliary Equipment Functional Test (continued)

[270] INSTALL a jumper at Terminal Board TB2 across Terminal Points 140 (2M270B) and 141 (2NM3B) at 2-L-792, TURBINE SUPERVISORY CABINET, to simulate a high turbine vibration (2-45N2635-133).

CV

[271] VERIFY Unit 2 Events Display Legend indicates 53-D MFPT 2B TURBINE VIBRATION HI is in ALARM (Red).

[272] REMOVE the jumper installed in step 6.27[270] across Terminals TB2-140 (2M270B) and TB2-141 (2NM3B) at 2-L-792, TURBINE SUPERVISORY CABINET.

CV

[273] VERIFY Unit 2 Events Display Legend indicates 53-D MFPT 2B TURBINE VIBRATION HI is NORMAL (Blue).

[274] INSTALL a jumper at Terminal Board TB2 across Terminal Points 116 (2M271B) and 117 (2NM3B) at 2-L-792, TURBINE SUPERVISORY CABINET, to simulate a pump bearing #2 high vibration (2-45N2635-133).

CV

[275] VERIFY Unit 2 Events Display Legend indicates 54-D MFPT 2B PUMP VIBRATION HI is in ALARM (Red).

[276] REMOVE the jumper installed in step 6.27[274] across Terminals TB2-116 (2M271B) and TB2-117 (2NM3B) at 2-L-792, TURBINE SUPERVISORY CABINET.

CV

[277] VERIFY Unit 2 Events Display Legend indicates 54-D MFPT 2B PUMP VIBRATION HI is NORMAL (Blue).

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 216 of 371 Date 6.27 Main Feedwater Pump Turbine 2B Auxiliary Equipment Functional Test (continued)

[278] INSTALL a jumper at Terminal Board TB2 across Terminal Points 110 (2M270B) and 111 (2NM3B) at 2-L-792, TURBINE SUPERVISORY CABINET, to simulate a turbine high vibration (2-45N2635-133).

CV

[279] VERIFY Unit 2 Events Display Legend indicates 54-D MFPT 2B PUMP VIBRATION HI is in ALARM (Red).

[280] REMOVE the jumper across contact at points 1 and 2 on relay 2-PIS-47-13RLY1 in 2-L-262.

CV

[281] REMOVE the jumper installed in step 6.27[278] across Terminals TB2-110 (2M270B) and TB2-111 (2NM3B) at 2-L-792, TURBINE SUPERVISORY CABINET.

CV

[282] VERIFY Unit 2. Events Display Legend indicates 54-D MFPT 2B PUMP VIBRATION HI is NORMAL (Blue).

[283] DEPRESS 2-HS-46-30D, MFPT 2B MOP 1 STOP, pushbutton at Panel 2-L-276.

NOTE The following steps may be marked N/A if Subsection 6.28 is to be performed next or if the simulations are not required.

[284] REMOVE jumper across Terminal Board TB 631, Terminal Points 1 (6A04) and 2 (6A03) in Panel 2-R-76. (N/A if Step 6.27[201] was marked N/A)

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 217 of 371 Date 6.28 MFPT 2B High Pressure, Low Pressure and Governor Valve Logic Test

[1] VERIFY prerequisites listed in Section 4.0 for Subsection 6.28 have been completed.

NOTE The following steps satisfy interlocks for stroking the HP and LP Stop and Governor (control) valves. Simulations which are not required or were installed in Subsection 6.25 may be marked N/A.

[2] LIFT lead TTBP (BK) from the left side of Terminal Board TB-AA, Terminal Point 4 in Section B of Panel 2-L-69, (709/TI 5G) to simulate a normal MFPT condenser vacuum.

(N/A if normal condenser vacuum is established.)

(Dwg 2-45N2635-34)

Cv

[3] INSTALL a jumper at Terminal Board TB631 across Terminal Points 1 (6A04) and 2 (6A03) at Panel 2-R-76 to simulate a normal FWP seal water pressure. (N/A if MFP Seal Injection is in service). (Dwg 2-45N2691-4)

Cv NOTE The following step may be marked N/A if MFPT 2B MOP 1 is running.

[4] DEPRESS 2-HS-46-30B, MFPT 2B MOP 1 START, pushbutton at Panel 2-L-276 (729/T1 5H) to START 2-PMP-46-30B.

[5] PLACE 2-HS-2-224A, MFWP B SUCTION ISOL, on 2-M-3 to the OPEN position and VERIFY 2-FCV-2-224 OPENS by light indication.

[6] PLACE 2-HS-46-36A, TRIP RESET MFPT 2B, on 2-M-3 to the RESET position.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 218 of 371 Date 6.28 MFPT 2B High Pressure, Low Pressure and Governor Valve Logic Test (continued)

[7] VERIFY the following:

A. 2-FCV-1-43, MFPT 2B HP STEAM STOP VLV, CLOSED (729/T16-H)

B. Green Light ON (2-HS-46-43B) (2-JB-291-1219).

C. Red Light OFF (2-HS-46-43B).

D. Green Light ON (2-HS-46-43A) (2-M-3)

E. Red Light OFF (2-HS-46-43A).

F. 2-FCV-1-46, MFPT 2B LP STEAM STOP VLV, CLOSED (729/Ti 6J).

G. Green Light ON (2-HS-46-44B) (729/T16H).

H. Red Light OFF (2-HS-46-44B).

I. Green Light ON (2-HS-46-44B) (2-M-3).

J. Red Light OFF (2-HS-46-44A).

K. No continuity across Terminal Points 581 (EA5) and 582 (EA6) in Panel 2-L-276. (Dwg 2-45W2614-7)

M&TE ID#

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 219 of 371 Date 6.28 MFPT 2B High Pressure, Low Pressure and Governor Valve Logic Test (continued)

[8] PLACE 2-HS-46-43A, MFPT 2B HP STOP VLV, on 2-M-3 to the RAISE position and VERIFY:

A. Red Light ON (2-HS-46-43A). Acc Crit (5.0B.42)

B. Green Light OFF (2-HS-46-43A). Acc Crit (5.OB.42)

C. 2-FCV-1-43 OPEN (locally). Acc Crit (5.0B.42)

D. Red Light ON (2-H3-46-43B). Acc Crit (5.0B.42)

E. Green Light OFF (2-HS-46-43B). Acc Crit (5.0B.42)

F. Red Light ON (2-HS-46-44A). Acc Crit (5.0B.42)

G. Green Light OFF (2-HS-46-44A). Acc Crit (5.0B.42)

H. 2-FCV-1 -46 OPEN (locally). Acc Crit (5.0B.42)

I. Red Light ON (2-HS-46-44B). Acc Crit (5.0B.42)

J. Green Light OFF (2-HS-46--44A). Acc Crit (5.083.42)

K. Continuity across Terminal Points 581 (EA5) and 582 (EA6) in Panel 2-L-276.

M&TE ID#

[9] PLACE 2-HS-46-36A, TRIP RESET MFPT 2B, 2-M-3 to the TRIP position.

[10] VERIFY Valve 2-FCV-1-43, MFPT 2B HP STEAM STOP VLV, CLOSES by light indication on Handswitch 2-HS-46-43A, MFPT 2B HP STOP VLV. Acc Crit (5.0B.42)

[11] VERIFY 2-FCV-1-46, MFPT 2B LP STEAM STOP VLV, CLOSES by light indication on 2-HS-46-44A, MFPT 2B LP STOP VLV. Acc Crit (5.0B.42)

[12] PLACE 2-HS-46-36A, TRIP RESET MFPT 2B, on 2-M-3 to the RESET position.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 220 of 371 Date 6.28 MFPT 2B High Pressure, Low Pressure and Governor Valve Logic Test (continued)

[13] PLACE 2-HS-46-43B, MFPT 2B HP STOP VLV, at Panel 2-JB-291-1149 (729/T16H) to the RAISE position and VERIFY: Acc Crit (5.0B.42)

A. 2-FCV-1-43 OPEN.

B. 2-FCV-1-46 OPEN.

[14] PLACE 2-HS-46-36A, TRIP RESET MFPT 2B on 2-M-3 to the TRIP position and VERIFY: Acc Crit (5.0B.42)

A. 2-FCV-1-43 CLOSED.

B. 2-FCV-1-46 CLOSED.

[15] PLACE 2-HS-46-36A, TRIP RESET MFPT 2B on 2-M-3 to the RESET position.

[16] PLACE 2-HS-46-44A, MFPT 2B LP STOP VLV, on 2-M-3 to the RAISE position and VERIFY: Acc Crit (5.0B.42)

A. Red Light ON (2-HS-46-44A).

B. Green Light OFF (2-HS-46-44A).

C. 2-FCV-1-46 OPEN (locally).

D. Red Light ON (2-HS-46-44B).

E. Green Light OFF (2-HS-46-44B).

F. Red Light ON (2-HS-46-43A).

G. Green Light OFF (2-HS-46-43A).

H. Valve 2-FCV-1-43 OPEN (locally).

I. Red Light ON (2-HS-46-43B).

J. Green Light OFF (2-HS-46-43B).

[17] PLACE 2-HS-46-36A, TRIP RESET MFPT 2B on 2-M-3 to the TRIP position.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 221 of 371 Date 6.28 MFPT 2B High Pressure, Low Pressure and Governor Valve Logic Test (continued)

[18] VERIFY 2-FCV-1-46, MFPT 2B LP STEAM STOP VLV, CLOSES by light indication on 2-HS-46-44A, MFPT 2B LP STOP VLV. Acc Crit (5.0B.42)

[19] VERIFY 2-FCV-1 -43, MFPT 2B HP STEAM STOP VLV, CLOSES by light indication on 2-HS-46-43A, MFPT 2B HP STOP VLV. Acc Crit (5.0B.42)

[20] PLACE 2-HS-46-43A, MFPT 2B HP STOP VLV, at 2-M-3 to the TEST position and VERIFY:

A. 2-FCV-1-43 Does Not STROKE by light indication.

B. 2-FCV-1-46 Does Not STROKE by light indication.

[21] PLACE 2-HS-46-44A, MFPT 2B LP STOP VLV, at 2-M-3 to the TEST position and VERIFY:

A. 2-FCV-1-43 Does Not STROKE by light indication.

B. 2-FCV-1-46 Does Not STROKE by light indication.

[22] PLACE 2-HS-46-43B, MFPT 2B HP STOP VLV, at Panel 2-JB-291-1219 to the TEST position and VERIFY:

A. 2-FCV-1-43 Does Not STROKE by light indication.

B. 2-FCV-1-46 Does Not STROKE by light indication.

[23] PLACE 2-HS-46-44B, MFPT 2B LP STOP VLV, at Panel 2-JB-291-1219 to the TEST position and VERIFY:

A. 2-FCV-1-43 Does Not STROKE by light indication.

B. 2-FCV-1-46 Does Not STROKE by light indication.

[24] PLACE 2-HS-46-36A, TRIP RESET MFPT 2B on 2-M-3 to the RESET position.

[25] PLACE 2-HS-46-44B, MFPT 2B LP STOP VLV, at Panel 2-JB-291-1219 to the RAISE position and VERIFY:

A. 2-FCV-1-43 OPEN.

B. 2-FCV-1-46 OPEN.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 222 of 371 Date 6.28 MFPT 2B High Pressure, Low Pressure and Governor Valve Logic Test (continued)

[26] VERIFY locally 2-FCV-1-44, (729/T1 5H), MFPT 2B HP STEAM CONTROL VLV, is CLOSED by valve stem position indication.

[27] VERIFY locally 2-FCV-1 -45, (729/TI 6H), MFPT 2B LP STEAM CONTROL VLV, is CLOSED by valve stem position indication.

[28] VERIFY 2-FCV-1-44, MFPT 2B HP STEAM CONTROL VLV, and 2-FCV-1-45, MFPT 2B LP STEAM CONTROL VLV, are CLOSED by light indication at Panel 2-L-276.

A. Green Light ON.

B. Red Light OFF.

[29] VERIFY 2-FCV-1-45, MFPT 2B LP STEAM CONTROL VLV, is at a MINIMUM position as indicated on 2-ZI-46-40D, MFPT 2B LOW PRESS GOV VLV POSITION, (2-L-276) and RECORD the indicated position.

LP GV % OPEN  % (0 - 6.5%)

[30] VERIFY 2-FCV-1-44, MFPT 2B HP STEAM CONTROL VLV, is at a MINIMUM position as indicated on 2-ZI-46-40E, MFPT 2B HIGH PRESS GOV VLV POSITION, (2-L-276) and RECORD the indicated position.

HP GV % OPEN  %(0-6.5%)

[31] VERIFY 2-FCV-1-44, MFPT 2B HP STEAM CONTROL VLV, and 2-FCV-1-45, MFPT 2B LP STEAM CONTROL VLV, are CLOSED by light indication at 2-HS-46-40A, MFPT 2B GOVERNOR VLV, on 2-M-3:

A. Green Light ON.

B. Red Light OFF.

[32] VERIFY 2-FCV-1-45, MFPT 2B LP STEAM CONTROL VLV, is at a MINIMUM position as indicated on 2-ZI-46-40A, MFPT 2B LP GOV VLV POS, on 2-M-3 and RECORD the indicated position.

MFPT LP GOV VLV  %(0-6.5%)

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 223 of 371 Date 6.28 MFPT 2B High Pressure, Low Pressure and Governor Valve Logic Test (continued)

[33] VERIFY 2-FCV-1-44, MFPT 2B HP STEAM CONTROL VLV, is at a MINIMUM position as indicated on 2-ZI-46-40B, MFPT 2B HP GOV VLV POS, on 2-M-3 and RECORD the indicated position.

MFPT HP GOV VLV_% (0-6.5%)

[34] PLACE and HOLD 2-HS-46-40A, MFPT 2B HP GOVERNOR VLV, on 2-M-3 to the RAISE position until FULL OPEN indication is obtained and VERIFY: Acc Crit (5.0B.42)

A. Red Light ON (2-HS-46-40A).

B. Green Light OFF (2-HS-46-40A).

C. Green Light OFF (2-L-276).

D. Red Light ON (2-L-276).

[35] VERIFY 2-FCV-1-44, MFPT 2B HP STEAM CONTROL VLV, is at a MAXIMUM position as indicated at 2-ZI-46-40B, MFPT 2B HP GOV VLV, on 2-M-3 and RECORD the position indication.

MFPT 2B HP GOV VLV  % (93.5-100%)

[36] VERIFY 2-FCV-1-45, MFPT 2B LP STEAM CONTROL VLV, is at a MAXIMUM position as indicated at 2-ZI-46-40A, MFPT 2B LP GOV VLV, on 2-M-3 and RECORD the position indication.

MFPT 2B LP GOV VLV  % (93.5-100%)

[37] PLACE 2-HS-46-40A, MFPT 2B GOVERNOR VLV, on 2-M-3 to the LOWER position to close 2-FCV-1-44, MFPT 2B HP STEAM CONTROL VLV, and 2-FCV-1-45, MFPT 2B LP STEAM CONTROL VLV. Acc Crit (5.0B.42)

[38] DEPRESS and HOLD 2-HS-46-40B, MFPT 2B GOVERNOR VLV, RAISE pushbutton at Panel 2-L-276 until 2-FCV-1-44, MFPT 2B HP STEAM CONTROL VLV, and 2-FCV-1-45, MFPT 2B LP STEAM CONTROL VLV, are OPEN.

Acc Crit (5.0B.42)

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 224 of 371 Date 6.28 MFPT 2B High Pressure, Low Pressure and Governor Valve Logic Test (continued)

[391 VERIFY 2-FCV-1-44, MFPT 2B HP STEAM CONTROL VLV, is at a MAXIMUM position as indicated at 2-ZI-46-40E, MFPT 2B HIGH PRESS GOV VLV POSITION, at Panel 2-L-276, and RECORD the position indication. Acc Crit (5.0B.42)

HP GV % OPEN  % (93.5-100%)

[40] VERIFY 2-FCV-1-45, MFPT 2B LP STEAM CONTROL VLV, is at a MAXIMUM position as indicated at 2-ZI-46-40D, MFPT 2B LOW PRESS GOV VLV POSITION, on 2-L-276 and RECORD the position indication. Acc Crit (5.08.42)

LP GV % OPEN  % (93.5-100%)

NOTE The next two steps will occur simultaneously. Position test support personnel at 2-FCV-1-46, MFPT 2B LP STEAM STOP VLV, to verify a partial valve stroke and amber light actuation. The Amber light is ON when Valve 2-FCV-1-46, MFPT 2B LP STEAM STOP VLV, reaches 25% closed and is OFF when the valve starts to reopen.

[41] PLACE 2-HS-46-44B, MFPT 2B LP STOP VLV, at Panel 2-JB-291-1219 to the TEST position and VERIFY the Amber Light flashes ON, then OFF.

[42] VERIFY 2-FCV-1-46, MFPT 2B LP STEAM STOP VLV, partial stroke CLOSED, then returned to the OPEN position.

[43] PLACE 2-HS-46-44A, MFPT 2B LP STOP VLV, on 2-M-3 to the TEST position and VERIFY the Amber Light flashes ON, then OFF to indicate Valve 2-FCV-1-46 movement.

NOTE Position test personnel at Valve 2-FCV-1-43, MFPT in HP STEAM STOP VLV, to observe valve stem movement.

[44] PLACE 2-HS-46-43A, MFPT 2B HP STOP VLV, on 2-M-3 to the TEST position and VERIFY the Amber Light does not flash ON and OFF.

[45] VERIFY 2-FCV-1-43, MFPT 2B HP STEAM STOP VLV, did not STROKE by observing the valve stem for movement.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 225 of 371 Date 6.28 MFPT 2B High Pressure, Low Pressure and Governor Valve Logic Test (continued)

[46] PLACE 2-HS-46-36A, TRIP RESET MFPT 2B, on 2-M-3 to the TRIP position.

[47] VERIFY locally the following valves are CLOSED:

A. 2-FCV-1-43, MFPT 2B HP STEAM STOP VLV.

B. 2-FCV-1-46, MFPT 2B LP STEAM STOP VLV.

C. 2-FCV-1-44, MFPT 2B HP STEAM CONTROL VLV.

D. 2-FCV-1-45, MFPT 2B LP STEAM CONTROL VLV.

[48] PLACE 2-HS-46-36A, TRIP RESET MFPT 2B, on 2-M-3 to the RESET position.

[49] PLACE 2-HS-46-43A, MFPT 2B HP STOP VLV, on 2-M-3 to the RAISE position.

[50] PLACE 2-HS-46-43A, MFPT 2B HP STOP VLV, on 2-M-3 to the TEST position and VERIFY the Amber Light flashes ON, then OFF to indicate 2-FCV-1-43 stroke.

[51] VERIFY locally 2-FCV-1-43, MFPT 2B HP STEAM STOP VLV, stroked CLOSED by observing the valve stem for movement.

[52] PLACE 2-HS-46-43B, MFPT 2B LP STEAM STOP VLV, at Panel 2-JB-291-1219 to the TEST position and VERIFY the Amber Light is ON, then OFF to indicate valve stroke.

[53] DEPRESS 2-HS-46-36D, MFPT 2B TURB TRIP PB, at Panel 2-L-276 to TRIP MFPT 2B.

[54] PLACE 2-HS-46-43A, MFPT 2B HP STOP VLV, at 2-M-3 to the RAISE position and VERIFY by light indication that 2-FCV-1-43 REMAINS CLOSED.

[55] PLACE 2-HS-46-44A, MFPT 2B LP STOP VLV, at 2-M-3 to the RAISE position and VERIFY by light indication that 2-FCV-1-46 REMAINS CLOSED.

[56] PLACE 2-HS-46-40A, MFPT 2B GOVERNOR VLV, at 2-M-3 to the RAISE position and VERIFY by light indication that 2-FCV-1-44 and 2-FCV-1-45 REMAIN CLOSED.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 226 of 371 Date 6.28 MFPT 2B High Pressure, Low Pressure and Governor Valve Logic Test (continued)

[57] REMOVE jumper across Terminals TB631-1 (6A04) and TB631-2 (6A03) in Panel 2-R-76. (N/A if Steps 6.27[201]

and/or 6.28[3] were marked N/A.)

CV

[58] LAND lead TTBP (BK) on the left side of Terminal Board TB-AA, Terminal Point 4 in Section B of Panel 2-L-69. (N/A if Step 6.28[2] was marked N/A)

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 227 of 371 Date 6.29 SMFP Auxiliary Oil Pump 2A & 2B Logic Test

[1] VERIFY prerequisites listed in Section 4.0 for Subsection 6.29 have been completed.

[2] VERIFY/PLACE 2-HS-3-210, STANDBY MAIN FEEDWATER PUMP AUX OIL PMP A, at Panel 2-JB-291-653 (729/T16J) in the OFF (LOCK) position and VERIFY:

A. Red Light OFF (2-HS-3-210).

B. Green Light ON (2-HS-3-21 0).

C. 2-PMP-3-210, STANDBY MAIN FW PMP AUX OIL PMP A, STOPPED (729/T15J).

[3] VERIFY/PLACE 2-HS-3-21 1, STANDBY MAIN FEEDWATER PUMP AUX OIL PMP B, at Panel 2-JB-291-653 (729/T16J) in the OFF (LOCK) position and VERIFY:

A. Red Light OFF (2-HS-3-21 1).

B. Green Light ON (2-HS-3-21 1).

C. 2-PMP-3-21 1, STANDBY MAIN FW PMP AUX OIL PMP B, STOPPED (729/T15J).

[4] PLACE 2-HS-3-210, STANDBY MAIN FEEDWATER PUMP AUX OIL PMP A, at Panel 2-JB-291-653 in the ON position and VERIFY: Acc Crit (5.0B.45)

A. Red Light ON (2-HS-3-210).

B. Green Light OFF (2-HS-3-210).

C. 2-PMP-3-210, STANDBY MAIN FW PMP AUX OIL PMP A, STARTS (locally).

[5] PLACE 2-HS-3-210, STANDBY MAIN FEEDWATER PUMP AUX OIL PMP A, at Panel 2-JB-291-653 in the OFF (LOCK) position and VERIFY 2-PMP-3-210, STANDBY MAIN FW PMP AUX OIL PMP A, STOPS.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 228 of 371 Date 6.29 SMFP Auxiliary Oil Pump 2A & 2B Logic Test (continued)

[6] PLACE 2-HS-3-21 1, STANDBY MAIN FEEDWATER PUMP AUX OIL PMP B, at Panel 2-JB-291-653 in the ON position and VERIFY: Acc Crit (5.0B.45)

A. Red Light ON (2-HS-3-21 1).

B. Green Light OFF (2-HS-3-21 1).

C. 2-PMP-3-211, STANDBY MAIN FW PMP AUX OIL PMP B, STARTS (locally).

[7] REMOVE the cover from Pressure Switch 2-PS-3-212B, STANDBY MAIN FW PMP OIL PRESS.

CV NOTE The following two steps will simulate a NORMAL lube oil pressure.

[8] INSTALL a jumper labeled J-1 across switch contacts 2D2 (BK) and 2D3 (W) of cable 2PL2002 in Pressure Switch 2-PS-3-212B, STANDBY MAIN FW PUMP OIL PRESS.

(Dwg 2-45W2721-5)

CV

[9] INSTALL a jumper labeled J-2 across switch contacts 2E2 (BK) and 2E3 (W) of cable 2PL2008 in Pressure Switch 2-PS-3-212B, STANDBY MAIN FW PUMP OIL PRESS.

(Dwg 2-45W2721-5)

CV

[10] PLACE 2-HS-3-210, STANDBY MAIN FEEDWATER PUMP AUX OIL PMP A, at Panel 2-JB-291-653 in the AUTO position and VERIFY 2-PMP-3-210 does not START.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 229 of 371 Date 6.29 SMFP Auxiliary Oil Pump 2A & 2B Logic Test (continued)

[11] PLACE 2-HS-3-211, STANDBY MAIN FEEDWATER PUMP AUX OIL PMP B, at Panel 2-JB-291-653 to the OFF (LOCK) position and VERIFY:

A. 2-PMP-3-210, STANDBY MAIN FW PMP AUX OIL PMP A, STARTS (locally).

B. 2-PMP-3-211, STANDBY MAIN FW PMP AUX OIL PMP B, STOPS (locally).

[12] REMOVE cover from Pressure Switch 2-PS-3-212A, STANDBY MAIN FW PMP OIL PRESS.

Cv

[13] INSTALL a jumper labeled J-3 across switch contacts 5CI (BK) and 5C2(W) of cable 2PL2015 in Pressure Switch 2-PS-3-212A, STANDBY MAIN FW PUMP OIL PRESS, to simulate a normal lube oil pressure. (Dwg 2-45W2721-5)

Cv

[14] PLACE 2-HS-3-21 1, STANDBY MAIN FEEDWATER PUMP AUX OIL PMP B, at Panel 2-JB-291-653 to the AUTO position and VERIFY 2-PMP-3-211 does not START by light indication.

[15] PLACE 2-HS-3-210, STANDBY MAIN FEEDWATER PUMP AUX OIL PMP A, at Panel 2-JB-291-653 to the OFF (LOCK) position and VERIFY: Acc Crit (5.0B.45)

A. 2-PMP-3-210, STANDBY MAIN FW PMP AUX OIL PMP A, STOPS (locally).

B. 2-PMP-3-21 1, STANDBY MAIN FW PMP AUX OIL PMP B, does not START (locally).

[16] REMOVE jumper labeled J-3 across switch contacts 5C1 (BK) and 5C2 (W) of cable 2PL2015 in 2-PS-3-212, STANDBY MAIN FW PUMP OIL PRESS.

Cv

[17] VERIFY locally 2-PMP-3-211 STANDBY MAIN FW PMP AUX OIL PMP B, STARTS.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 230 of 371 Date 6.29 SMFP Auxiliary Oil Pump 2A & 2B Logic Test (continued)

[18] PLACE 2-HS-3-211, STANDBY MAIN FEEDWATER PUMP AUX OIL PMP B, at Panel 2-JB-291-653 to the OFF (LOCK) position and VERIFY 2-PMP-3-211 STOPS by light indication.

[19] PLACE 2-HS-3-210, STANDBY MAIN FEEDWATER PUMP AUX OIL PMP A, at Panel 2-JB-291-653 to the AUTO position and VERIFY 2-PMP-3-210 STARTS by light indication.

Acc Crit (5.0B.45)

[20] INSTALL a jumper labeled J-3 across switch contacts 5C1 (BK) and 5C2 (W) of cable 2PL2015 in Pressure Switch 2-PS-3-212A, STANDBY MAIN FW PUMP OIL PRESS.

CV

[21] LIFT lead 2D2 from Terminal Board EE, Terminal Point 5 in 6900-V Unit Board 2D, Panel 7 to simulate SMFP RUNNING.

(Dwg 0126D4654)

CV

[22] VERIFY 2-PMP-3-210, STANDBY MAIN FW PMP AUX OIL PMP A, does not TRIP by light indication at Panel 2-JB-291-653.

[23] REMOVE jumper labeled J-1 across switch contacts 2D2 (BK) and 2D3 (W) of cable 2PL2002 in Pressure Switch 2-PS-3-212B, STANDBY MAIN FW PUMP OIL PRESS.

CV

[24] VERIFY locally 2-PMP-3-210, STANDBY MAIN FW PMP AUX OIL PMP A, TRIPS. Acc Crit (5.0B.45)

[25] PLACE 2-HS-3-210, STANDBY MAIN FEEDWATER PUMP AUX OIL PMP A, at Panel 2-JB-291-653 in the ON position and VERIFY 2-PMP-3-210 STARTS then STOPS after RELEASING 2-HS-3-210, STANDBY MAIN FEEDWATER PUMP AUX OIL PMP A.

[26] LAND lead 2D2 on Terminal Board EE, Terminal Point 5 in 6900-V Unit Board 2D, Panel 7.

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 231 of 371 Date 6.29 SMFP Auxiliary Oil Pump 2A & 2B Logic Test (continued)

[27] PLACE 2-HS-3-21 1, STANDBY MAIN FEEDWATER PUMP AUX OIL PMP B, at Panel 2-JB-291-653 in the ON position and VERIFY 2-PMP-3-211 STARTS by light indication.

Acc Crit (5.0B.45)

[28] LIFT lead 2E2 from Terminal Board EE, Terminal 9 in 6900-V Unit Board 2D, Panel 7 to simulate SMFP RUNNING. (Ref Dwg 0126D4654)

CV

[29] VERIFY 2-PMP-3-21 1, STANDBY MAIN FW PMP AUX OIL PMP B, does not TRIP by light indication at Panel 2-JB-291-653.

[30] REMOVE jumper labeled J-2 from switch contacts 2E2 (BK) and 2E3 (W) of cable 2PL2008 in Pressure Switch 2-PS-3-212B, STANDBY MAIN FW PUMP OIL PRESS.

CV

[31] VERIFY 2-PMP-3-21 1, STANDBY MAIN FW PMP AUX OIL PMP B, TRIPS by light indication at Panel 2-JB-291-653.

[32] PLACE 2-HS-3-21 1, STANDBY MAIN FEEDWATER PUMP AUX OIL PMP B, at Panel 2-JB-291-653 to the ON position and VERIFY 2-PMP-3-211 STARTS then STOPS after RELEASING 2-HS-3-211, STANDBY MAIN FEEDWATER PUMP AUX OIL PMP B.

[33] LAND lead 2E2 on Terminal Board EE, Terminal Point 9 in 6900-V Unit Board 2D, Panel 7.

CV

[34] PLACE 2-HS-3-21 1, STANDBY MAIN FW PMP AUX OIL PMP B, at Panel 2-JB-291-653 in the OFF (LOCK) position.

[35] PLACE 2-HS-3-210, STANDBY MAIN FEEDWATER PUMP AUX OIL PMP A, at Panel 2-JB-291-653 in the OFF (LOCK) position.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 232 of 371 Date 6.29 SMFP Auxiliary Oil Pump 2A & 2B Logic Test (continued)

[36] REMOVE jumper labeled J3 across switch contacts 5C1 (BK) and 5C2 (W) of cable 2PL2015 in Pressure Switch 2-PS-3-212A, STANDBY MAIN FW PUMP OIL PRESS.

CV

[37] REPLACE cover on Pressure Switch 2-PS-3-212A, STANDBY MAIN FW PMP OIL PRESS.

CV

[38] REPLACE cover on Pressure Switch 2-PS-3-212B, STANDBY MAIN FW PMP OIL PRESS.

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 233 of 371 Date 6.30 Standby Main Feedwater Pump Breaker Logic and Functional Test

[1] VERIFY prerequisites listed in Subsections 4.3[81] through 4.3[88] for Subsection 6.30 have been completed.

[2] VERIFY/PLACE 2-HS-3-200A, STANDBY MAIN PMP, on 2-M-4 in the STOP/PULL-TO-LOCK position.

[3] DEPRESS 2-HS-3-200B, STANDBY MAIN FEEDWATER PUMP, SAFE-STOP pushbutton at Panel 2-JB-291-653 (729/T1 6J).

[4] INSTALL a jumper across Terminal B-1i1 and G-1 2 in 6900-V Unit Board 2D, Panel 7 to simulate 52HL closed contacts.

(Dwg 012604654)

CV

[5] INSTALL a jumper across Terminal A-17 and G-14 in 6900-V Unit Board 2D, Panel 7 to simulate 52HL closed contacts.

(Dwg 0126D4654)

CV

[6] VERIFY/RACK OUT/DOWN 2-BKR-3-200, STANDBY MAIN FEEDWATER PUMP (2-PMP-3-200), at Panel 7, of 6900-V Unit Board 2D (724/T15A).

CV

[7] RACK IN 2-BKR-3-200, STANDBY MAIN FEEDWATER PUMP (2-PMP-3 -200), at Panel 7 of 6900-V Unit Board 2D to the TEST position.

CV

[8] INSTALL the umbilical cord test device on the 6900-V Unit Board 2D, Panel 7, to provide breaker control power.

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 234 of 371 Date 6.30 Standby Main Feedwater Pump Breaker Logic and Functional Test (continued)

[9] INSTALL the test link on the 6900-V Unit Board 2D, Panel 7, to defeat the 52STA device.

CV

[10] PLACE 2-HS-3-210, STANDBY MAIN FEEDWATER PUMP AUX OIL PMP A, at 2-JB-291-653, in the ON position, and VERIFY 2-PMP-3-210 STARTS with Red Light indication ON (2-HS-3-21 0).

[11] INSTALL a jumper across Terminal Board CC, Terminal Points 1 (3C03) and 2 (3C02) at Panel 2-L-491 (708/T15J) to simulate a normal injection water pressure.

(Dwg 2-45N2635-91).

CV

[12] DEPRESS 2-HS-3-200B, STANDBY MAIN FEEDWATER PUMP, RESET pushbutton at Panel 2-JB-291-653.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 235 of 371 Date 6.30 Standby Main Feedwater Pump Breaker Logic and Functional Test (continued)

[13] PLACE Handswitch 2-HS-3-200A, STANDBY MAIN FW PMP, on 2-M-4 to P-AUTO and VERIFY:

A. 2-BKR-3-200, STANDBY MAIN FEEDWATER PUMP (2-PMP-3-200) OPEN (Green Flag).

B. Red Light OFF (2-HS-3-200A).

C. Green Light ON (2-HS-3-200A).

D. White Light OFF (2-HS-3-200A).

E. Red Light OFF (6900-V Unit Board 2D, Panel 7).

F. Green Light ON 6900-V Unit Board 2D, Panel 7).

G. Computer point Y2401 D indicates OPEN.

H. No continuity across Terminal Points GG-1 1 and GG-12 in 6900-V Unit Board 2D, Panel 7.

M&TE ID#

I. 0 VAC (Nominal) across Terminal Points EE-5 and EE-6 in 6900-V Unit Board 2D, Panel 7.

M&TE ID#

J. Continuity across Terminal Points EE-9 and EE-10 in 6900-V Unit Board 2D, Panel 7.

M&TE ID#

K. No continuity across Terminal Points EE-1 1 and EE-12 in 6900-V Unit Board 2D, Panel 7.

M&TE ID#

L. 0 VAC (Nominal) across Terminal Points FF-5 and FF-6 in 6900-V Unit Board 2D, Panel 7.

M&TE ID#

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 236 of 371 Date 6.30 Standby Main Feedwater Pump Breaker Logic and Functional Test (continued)

M. 120 VDC (Nominal) across Terminal Points FF-7 and FF-8 in 6900-V Unit Board 2D, Panel 7.

M&TE ID#

[14] INSTALL a jumper across switch contacts 2D2 (BK) and 2D3 (W) of cable 2PL2002 in Pressure Switch 2-PS-3-212B (Dwg 2-45W2721-5).

CV

[15] DEPRESS the TEST CLOSE pushbutton at 6900-V Unit Board 2D, Panel 7, and VERIFY:

A. 2-BKR-3-200, STANDBY MAIN FEEDWATER PUMP (2-PMP-3-200), CLOSED (RED flag).

B. Red Light ON (2-HS-3-200A).

C. Green Light OFF (2-HS-3-200A).

D. White Light OFF (2-HS-3-200A).

E. Red Light ON (6900-V Unit Board 2D, Panel 7).

F. Green Light OFF (6900-V Unit Board 2D, Panel 7).

G. Computer point Y2401 D indicates CLOSED.

H. Continuity across Terminal Points GG-1 1 and GG-12 in 6900-V Unit Board 2D, Panel 7.

M&TE ID#

I. 120 VAC (Nominal) across Terminal Points EE-5 and EE-6 in 6900-V Unit Board 2D, Panel 7.

M&TE ID#

J. No continuity across Terminal Points EE-9 and EE-10 in 6900-V Unit Board 2D, Panel 7.

M&TE ID#

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 237 of 371 Date 6.30 Standby Main Feedwater Pump Breaker Logic and Functional Test (continued)

K. Continuity across Terminal Points EE-1 1 and EE-12 in 6900-V Unit Board 2D, Panel 7.

M&TE ID#

L. 120 VAC (Nominal) across Terminal Points FF-5 and FF-6 in 6900-V Unit Board 2D, Panel 7.

M&TE ID#

M. 0 VDC (Nominal) across Terminal Points FF-7 and FF-8 in 6900-V Unit Board 2D, Panel 7.

M&TE ID#

[16] DEPRESS the TRIP TEST pushbutton at 6900-V Unit Board 2D, Panel 7, and VERIFY 2-BKR-3-200, STANDBY MAIN FEEDWATER PUMP (2-PMP-3-200), OPENS.

[17] DEPRESS 2-HS-3-200B, STANDBY MAIN FEEDWATER PUMP, START pushbutton at Panel 2-JB-291-653 and VERIFY that 2-BKR-3-200, STANDBY MAIN FEEDWATER PUMP (2-PMP-3-200), does not CLOSE.

[18] PLACE 2-HS-2-265, STANDBY MAIN FW PUMP SUCTION ISOL VLV, at Panel 2-JB-291-653 to the OPEN position and VERIFY 2-FCV-2-265 OPENS.

[19] DEPRESS 2-HS-3-200B, STANDBY MAIN FEEDWATER PUMP, START pushbutton at Panel 2-JB-291-653 and VERIFY that 2-BKR-3-200, STANDBY MAIN FEEDWATER PUMP (2-PMP-3-200), does not CLOSE.

[20] PLACE 2-HS-3-205, STANDBY MAIN FEEDWATER PUMP DISCHARGE ISOL VLV, at Panel 2-JB-291-653 to the OPEN position and VERIFY 2-FCV-3-205 OPENS.

[21] PLACE 2-HS-3-200A, STANDBY MAIN FEEDWATER PUMP, 2-M-4 to STOP/PULL-TO-LOCK position.

[22] PLACE 2-HS-2-265, STANDBY MAIN FW PUMP SUCTION ISOL VLV, at Panel 2-JB-291-653 to the CLOSE position and VERIFY 2-FCV-2-265 CLOSES.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 238 of 371 Date 6.30 Standby Main Feedwater Pump Breaker Logic and Functional Test (continued)

[23] PLACE 2-HS-3-200A, STANDBY MAIN FW PMP, on 2-M-4 to P-AUTO position.

[24] DEPRESS 2-HS-3-200B, STANDBY MAIN FEEDWATER PUMP, START pushbutton at Panel 2-JB-291-653 and VERIFY that 2-BKR-3-200, STANDBY MAIN FEEDWATER PUMP, does not CLOSE.

[25] PLACE 2-HS-2-265, STANDBY MAIN FW PUMP SUCTION ISOL VLV, at Panel 2-JB-291-653 to the OPEN position and VERIFY 2-FCV-2-265 OPENS.

[26] DEPRESS 2-HS-3-200B, STANDBY MAIN FEEDWATER PUMP, START pushbutton at Panel 2-JB-291-653 and VERIFY that 2-BKR-3-200, STANDBY MAIN FEEDWATER PUMP, CLOSES.

[27] DEPRESS 2-HS-3-200B, STANDBY MAIN FEEDWATER PUMP, SAFE-STOP pushbutton and VERIFY that 2-BKR-3-200 STANDBY MAIN FEEDWATER PUMP, OPENS.

[28] PLACE 2-HS-3-200A, STANDBY MAIN FW PMP, on 2-M4 in the START position and VERIFY 2-BKR-3-200, STANDBY MAIN FEEDWATER PUMP, remains OPEN.

[29] DEPRESS 2-HS-3-200B, STANDBY MAIN FEEDWATER PUMP, RESET pushbutton.

[30] INSTALL a jumper across Terminal Points 607 and 608 at Panel 2-L-275 to simulate MFPT 2A TRIPPED.

(Dwg 2-45W600-57-26)

CV

[31] VERIFY 2-BKR-3-200, STANDBY MAIN FEEDWATER PUMP (2-PMP-3-200), DOES NOT CLOSE.

[32] INSTALL a jumper at Terminal Board TB545 across Terminal Points 1 (TTC1) and 6 (TTC6) in Auxiliary Relay Panel 2-R-75 (711/T11 D) to simulate plant load greater than setpoint. (Dwg 2-45N2690-4)

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 239 of 371 Date 6.30 Standby Main Feedwater Pump Breaker Logic and Functional Test (continued)

[33] VERIFY 2-BKR-3-200, STANDBY MAIN FEEDWATER PUMP (2-PMP-3-200), CLOSES. ACC CRIT (5.08.43)

[34] REMOVE jumper across Terminals 607 and 608 at Panel 2-L-275.

CV

[35] LIFT Lead (2D7C1) from Terminal 5 of Relay 27-2DX2, MAIN BUS UNDERVOLTAGE RELAY, at 6900-V Unit Board 2D, Panel 9 (Dwg 2-45W760-201-2) to simulate the SMFP breaker close interlock.

CV

[36] PLACE 2-HS-3-200A, STANDBY MAIN FW PMP, on 2-M-4 in the STOP position.

[37] INSTALL a jumper across Terminal Points 607 and 608 at Panel 2-L-275 to simulate MFPT 2A is TRIPPED (Dwg 2-45W600-57-26).

CV

[38] VERIFY 2-BKR-3-200, STANDBY MAIN FEEDWATER PUMP (2-PMP-3-200), DOES NOT CLOSE.

[39] REMOVE jumper across Terminal 607 and 608 at Panel 2-L-275.

CV

[40] LAND Lead (2D7C1) on Terminal 5 of Relay 27-2DX2, MAIN BUS UNDERVOLTAGE RELAY, at 6900-V Unit Board 2D, Panel 9.

CV

[41] PLACE 2-HS-3-200A, STANDBY MAIN FW PMP, on 2-M-4 to the START position and VERIFY that 2-BKR-3-200, STANDBY MAIN FEEDWATER PUMP (2-PMP-3-200), CLOSES.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 240 of 371 Date 6.30 Standby Main Feedwater Pump Breaker Logic and Functional Test (continued)

[42] DEPRESS 2-HS-3-200B, STANDBY MAIN FEEDWATER PUMP, SAFE-STOP pushbutton and VERIFY that 2-BKR-3-200, STANDBY MAIN FEEDWATER PUMP (2-PMP-3-200), OPENS.

[43] REMOVE jumper across Terminals TB 545-1 and TB 545-6 in Panel 2-R-75.

Cv

[44] INSTALL a jumper across Terminal Points 607 and 608 at Panel 2-L-276 to simulate MFPT 2B is TRIPPED.

(Dwg 2-45W600-57-26)

Cv

[45] VERIFY 2-BKR-3-200, STANDBY MAIN FEEDWATER PUMP (2-PMP-3-200), DOES NOT CLOSE.

[46] DEPRESS 2-HS-3-200B, STANDBY MAIN FEEDWATER PUMP, RESET pushbutton.

[47] INSTALL a jumper at Terminal Board TB 545 across Terminal Points 1 (TTCl) and 6 (TTC6) in Auxiliary Relay Panel 2-R-75 (71 1/T1 1 D) to simulate plant load greater than setpoint. (Dwg 2-45N2690-4)

Cv

[48] VERIFY 2-BKR-3-200, STANDBY MAIN FEEDWATER PUMP (2-PMP-3-200) CLOSES. ACC CRIT (5.0B.43)

[49] PLACE 2-HS-3-205, STANDBY MAIN FEEDWATER PUMP DISCHARGE ISOL VLV, at Panel 2-JB-291-653 to the CLOSE position and VERIFY that 2-BKR-3-200, STANDBY MAIN FEEDWATER PUMP (2-PMP-3-200), does not OPEN.

[50] PLACE 2-HS-3-205, STANDBY MAIN FEEDWATER PUMP DISCHARGE ISOL VLV, at Panel 2-JB-291-653 to the OPEN position and VERIFY 2-FCV-3-205 OPENS.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 241 of 371 Date 6.30 Standby Main Feedwater Pump Breaker Logic and Functional Test (continued)

[51] PLACE 2-HS-2-265, STANDBY MAIN FW PUMP SUCTION ISOL VLV, at Panel 2-JB-291-653 to the CLOSE position and VERIFY:

A. 2-BKR-3-200, STANDBY MAIN FEEDWATER PUMP (2-PMP-3-200), DOES NOT OPEN.

B. 2-FCV-2-265, STANDBY MAIN FW PUMP SUCTION ISOL VLV, DOES NOT CLOSE.

[52] PLACE 2-HS-3-200A, STANDBY MAIN FW PMP, on 2-M-4 in the STOP/PULL-TO-LOCK position and VERIFY 2-BKR-3-200, STANDBY MAIN FEEDWATER PUMP (2-PMP-3-200),

OPENS.

[53] REMOVE the jumper across Terminal Points 607 and 608 at Panel 2-L-276.

CV

[54] REMOVE the jumper across Terminals TB545-1 (TTCI) and TB545-6 (TTC6) in Auxiliary Relay Panel 2-R-75.

CV

[55] PLACE 2-HS-3-200A, STANDBY MAIN FW PUMP, on 2-M-4 in the P-AUTO position.

[56] PLACE 2-HS-3-200A, STANDBY MAIN FW PUMP, on 2-M-4 in the START position.

[57] PLACE 2-HS-3-210, STANDBY MAIN FEEDWATER PUMP AUX OIL PMP A, at Panel 2-JB-291-653 in the OFF position and VERIFY that 2-BKR-3-200, STANDBY MAIN FEEDWATER PUMP (2-PMP-3-200), OPENS on low lube oil pressure.

[58] PLACE 2-HS-3-210, STANDBY MAIN FEEDWATER PUMP AUX OIL PMP A, at Panel 2-JB-291-653 in the ON position and VERIFY that 2-PMP-3-210, STARTS.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 242 of 371 Date 6.30 Standby Main Feedwater Pump Breaker Logic and Functional Test (continued)

[59] PLACE 2-HS-3-200A, STANDBY MAIN FW PMP, on 2-M-4 to the STOP position then START position and VERIFY 2-BKR-3-200, STANDBY MAIN FEEDWATER PUMP (2-PMP-3-200), CLOSES.

[60] LIFT lead FW1 from Terminal 1 of relay HWPA at BOP AUX Relay Panel 2-R-75 to prevent tripping of the Condensate Booster Pumps on a feedwater isolation signal.

(Dwg 2-45W600-57-28)

Cv

[61] LIFT lead FW1 from Terminal 1 of relay HWPB at BOP AUX Relay Panel 2-R-75 to prevent tripping of the Condensate Booster Pumps on a feedwater isolation signal.

(Dwg 2-45W600-57-28)

Cv

[62] INSTALL a jumper at Terminal Board TB635 across the field side of Terminal Points 1 (HWPA1) and 2 (HWPA2) in SSPS TRAIN A OUTPUT CABINET 2-R-48 and VERIFY 2-BKR-3-200, STANDBY MAIN FEEDWATER PUMP (2-PMP-3-200), OPENS on a feedwater isolation signal.

Acc Crit (5.0B.38) (Dwg 2-45N2676-5)

Cv

[63] REMOVE the jumper across Terminals TB635-1 (HWPA1) and TB635-2 (HWPA2) in Panel 2-R-48.

Cv

[64] PLACE 2-HS-3-200A, STANDBY MAIN FW PMP, on 2-M4 to the STOP, then START position and VERIFY 2-BKR-3-200, STANDBY MAIN FEEDWATER PUMP (2-PMP-3-200),

CLOSES.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 243 of 371 Date 6.30 Standby Main Feedwater Pump Breaker Logic and Functional Test (continued)

[65) INSTALL a jumper at Terminal Board TB635 across the field side of Terminal Points 1 (HWPB1) and 2 (HWPB2) in SSPS TRAIN B OUTPUT CABINET 2-R-51 and VERIFY 2-BKR-3-200, STANDBY MAIN FEEDWATER PUMP (2-PMP-3-200), OPENS on a feedwater isolation signal.

Acc Crit (5.0B.38) (Dwg 2-45N2677-5)

CV

[66] REMOVE the jumper across Terminal TB635-1 (HWPB1) and TB635-2 (HWPB2) in Panel 2-R-51.

CV

[67] PLACE 2-HS-3-200A, STANDBY MAIN FW PMP, on 2-M-4 to the STOP, then START position and VERIFY 2-BKR-3-200, STANDBY MAIN FEEDWATER PUMP (2-PMP-3-200),

CLOSES.

[68] VERIFY the breaker overload and trip indications are as follows:

A. Annunciator Window 14-D, M-1 THRU M-6 MOTOR OVERLOAD, at 2-XA-SS-1B is CLEAR.

B. Annunciator Window 14-E, M-1 THRU M-6 MOTOR TRIPOUT, at 2-XA-55-1B is CLEAR.

C. Motor Breaker Trip Audible Buzzer at Panel 2-M-2 OFF.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 244 of 371 Date 6.30 Standby Main Feedwater Pump Breaker Logic and Functional Test (continued)

[69] MANUALLY ACTUATE the instantaneous portion (50) of A-PHASE OVERCURRENT RELAY 50/51/83 at 6900-V Unit 2D, Panel 7, and VERIFY:

A. 2-BKR-3-200, STANDBY MAIN FEEDWATER PUMP (2-PMP-3-200), OPEN.

B. INST target is ACTUATED on A-PHASE OVERCURRENT RELAY 50/51/83 at 6900-V Unit Board 2D, Panel 7.

C. White Light ON (2-HS-3-200A).

D. Annunciator Window 14-E, M-1 THRU M-6 MOTOR TRIPOUT, ALARMS.

E. Audible Motor Breaker Trip Buzzer ON.

[70] VERIFY the Unit 2 Events Display Legend indicates 14-E M-1 THRU M-6 MOTOR TRIPOUT is in ALARM (Red).

[71] RESET instantaneous target on A-PHASE OVERCURRENT RELAY 50/51/83 at 6900-V Unit Board 2D, Panel 7.

[72] PLACE 2-HS-3-200A, STANDBY MAIN FW PMP, on 2-M-4 to the START position, and VERIFY 2-BKR-3-200, STANDBY MAIN FEEDWATER PUMP (2-PMP-3-200), DOES NOT CLOSE.

[73] PLACE 2-HS-3-200A, STANDBY MAIN FW PMP, on 2-M-4 to the STOP position and VERIFY:

A. White Light OFF (2-HS-3-200A).

B. Annunciator Window 14E, M-1 THRU M-6 MOTOR TRIPOUT, is CLEAR.

C. Audible Motor Trip Breaker Buzzer OFF.

[74] VERIFY the Unit 2 Events Display Legend indicates 14-E M-1.

THRU M-6 MOTOR TRIPOUT is NORMAL (Blue).

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 245 of 371 Date 6.30 Standby Main Feedwater Pump Breaker Logic and Functional Test (continued)

[75] PLACE 2-HS-3-200A, STANDBY MAIN FW PMP, on 2-M-4 to the START position and VERIFY that 2-BKR-3-200, STANDBY MAIN FEEDWATER PUMP (2-PMP-3-200), is CLOSED.

[76] INSTALL a jumper across Terminals 1 and 2 on the back of Relay 27-2DX2, MAIN BUS UNDERVOLTAGE RELAY, at 6900-V Unit Board 2D, Panel 9. (Dwg 2-45W760-201-2)

CV

[77] VERIFY the following:

A. 2-BKR-3-200, STANDBY MAIN FEEDWATER PUMP (2-PMP-3-200) OPEN.

B. White Light ON (2-HS-3-200A).

C. Annunciator Window 14-E, M-1 THRU M-6 MOTOR TRIPOUT, ALARMS.

D. Audible Motor Breaker Buzzer ON.

[78] VERIFY the Unit 2 Events Display Legend indicates 14-E M-1 THRU M-6 MOTOR TRIPOUT is in ALARM (Red).

[79] REMOVE jumper across Terminals 1 and 2 of Relay 27-2DX2, MAIN BUS UNDERVOLTAGE RELAY, at 6900-V Unit Board 2D, Panel 9.

CV

[80] PLACE 2-HS-3-200A, STANDBY MAIN FW PMP, on 2-M-4 to the STOP position and VERIFY:

A. White Light Off (2-HS-3-200A).

B. Annunciator Window 14-E, 2-M-1 THRU M-6 MOTOR TRIPOUT, is CLEAR.

C. Audible Motor Trip Breaker Buzzer OFF.

[81] PLACE 2-HS-3-200A, STANDBY MAIN FW PMP, on 2-M-4 to the START position and VERIFY that 2-BKR-3-200, STANDBY MAIN FEEDWATER PUMP (2-PMP-3-200) is CLOSED.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 246 of 371 Date 6.30 Standby Main Feedwater Pump Breaker Logic and Functional Test (continued)

[82] MANUALLY ACTUATE the instantaneous portion (50) of C-PHASE OVERCURRENT Relay 50/51/83 at 6900-V Unit Board 2D, Panel 7, and VERIFY:

A. 2-BKR-3-200 STANDBY MAIN FEEDWATER PUMP (2-PMP-3-200), OPEN.

B. INST target is ACTUATED on C-PHASE OVERCURRENT RELAY 50/51/83 at 6900-V Unit Board 2D, Panel 7.

C. White Light ON (2-HS-3-200A).

D. Annunciator Window 14-E, M-1 THRU M-6 MOTOR TRIPOUT, ALARMS.

E. Audible Motor Trip Breaker Buzzer ON.

[83] VERIFY the Unit 2 Events Display Legend indicates 14-E M-1 THRU M-6 MOTOR TRIPOUT is in Alarm (Red).

[84] RESET INST target on C-PHASE OVERCURRENT RELAY 50/51/83 at 6900-V Unit Board 2D, Panel 7.

[85] PLACE 2-HS-3-200A, STANDBY MAIN FW PMP, on 2-M--4 to the STOP position and VERIFY:

A. White Light OFF (2-HS-3-200A).

B. Annunciator Window 14-E, 2-M-1 THRU M-6 MOTOR TRIPOUT, is CLEAR.

C. Audible Motor Trip Breaker Buzzer OFF.

[86] PLACE 2-HS-3-200A, STANDBY MAIN FW PMP, on 2-M-4 to the START position, and VERIFY that 2-BKR-3-200, STNDBY MAIN FEEDWATER PUMP (2-PMP-3-200), is CLOSED.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 247 of 371 Date 6.30 Standby Main Feedwater Pump Breaker Logic and Functional Test (continued)

[87] ROTATE and HOLD disc on time PORTION (51) OF A-PHASE OVERCURRENT RELAY 50/51/83 at 6900-V Unit Board 2D, Panel 7, and VERIFY:

A. White Light ON (2-HS-3-200A).

B. Annunciator Window 14-D, M-1 THRU M-6 MOTOR OVERLOAD, ALARMS.

[88] VERIFY Unit 2 Events Display Legend indicates 14-D M-1 THRU M-6 MOTOR OVERLOAD is in Alarm (Red).

[89] MOMENTARILY PLACE jumper across Terminals 9 and 10 on back of A-PHASE OVERCURRENT RELAY 50/51/83, at 6900-V Board 2D, Panel 7.

CV A. VERIFY 2-BRK-3-200, STANDBY MAIN FEEDWATER PUMP (2-PMP-3-200), OPEN.

B. VERIFY TIME target is ACTUATED on A-PHASE OVERCURRENT RELAY 50/51/83 at 6900-V Unit Board 2D, Panel 7.

[90] RELEASE disc on A-PHASE OVERCURRENT RELAY 50/51/83 and VERIFY:

A. White Light OFF (2-HS-3-200A).

B. Annunciator Window 14-D, M-1 THRU M-6 MOTOR OVERLOAD, is CLEAR.

[91] VERIFY Unit 2 Events Display Legend indicates 14-D M-1 THRU M-6 MOTOR OVERLOAD, is NORMAL (Blue).

[92] RESET the target on A-PHASE OVERCURRENT RELAY 50/51/83, at 6900-V Unit Board 2D, Panel 7.

[93] PLACE 2-HS-3-200A, STANDBY MAIN FW PMP, to STOP position.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 248 of 371 Date 6.30 Standby Main Feedwater Pump Breaker Logic and Functional Test (continued)

[94] PLACE 2-HS-3-200A, STANDBY MAIN FW PMP, on 2-M-4 to the START position, and VERIFY 2-BKR-3-200, STANDBY MAIN FEEDWATER PUMP (2-PMP-3-200), is CLOSED.

[95] ROTATE and HOLD disc on time PORTION (51) of C-PHASE OVERCURRENT RELAY 50/51/83 at 6900-V Unit Board 2D, Panel 7, and VERIFY:

A. White Light ON (2-HS-3-200A).

B. Annunciator Window 14-D, M-1 THRU M-6 MOTOR OVERLOAD, ALARMS.

[96] VERIFY the Unit 2 Events Display Legend indicates 14-D M-1 THRU M-6 MOTOR OVERLOAD is in ALARM (Red).

[97] MOMENTARILY PLACE jumper across Terminals 9 and 10 on back of C-PHASE OVERCURRENT RELAY 50/51/83 at 6900-V Unit Board 2D, Panel 7.

CV A. VERIFY 2-BKR-3-200, STANDBY MAIN FEEDWATER PUMP (2-PMP-3-200), OPEN.

B. VERIFY TIME target is ACTUATED on C-PHASE OVERCURRENT RELAY 50/51/83 at 6900-V Unit Board 2D, Panel 7.

[98] RELEASE disc on C-PHASE OVERCURRENT RELAY 50/51/83 and VERIFY:

A. White Light OFF (2-HS-3-200A).

B. Annunciator Window 14-D, M-1 THRU M-6 MOTOR OVERLOAD, is CLEAR.

[99] RESET the time target on C-PHASE OVERCURRENT RELAY 50/51/83, at 6900-V Unit Board 2D, Panel 7.

[100] PLACE 2-HS-3-200A, STANDBY MAIN FW PMP, on 2-M-4, to STOP position.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 249 of 371 Date 6.30 Standby Main Feedwater Pump Breaker Logic and Functional Test (continued)

[101] PLACE 2-HS-3-200A, STANDBY MAIN FW PMP, on 2-M-4 to the START position and VERIFY that 2-BRK-3-200, STANDBY MAIN FEEDWATER PUMP (2-PMP-3-200), is CLOSED.

[102] MANUALLY ACTUATE GROUND OVERCURRENT RELAY 50G at 6900-V Unit Board 2D, Panel 7, and VERIFY:

A. 2-BKR-3-200, STANDBY MAIN FEEDWATER PUMP (2-PMP-3-200), is OPEN.

B. GROUND OVERCURRENT RELAY 50G target is ACTUATED at 6900-V Unit Board 2D, Panel 7.

[103] RESET the GROUND OVERCURRENT RELAY 5OG target at 6900-V Unit Board 2D, Panel 7.

[104] PLACE 2-HS-3-200A, STANDBY MAIN FW PMP, in the STOP position.

[105] MANUALLY ACTUATE the instantaneous portion (50) of C-PHASE OVERCURRENT Relay 50/51 at 6900-V Board 2D, Panel 7 and VERIFY:

A. 2-BKR-3-200 STANDY MAIN FEEDWATER PUMP (2-PMP-3-200) is OPEN.

B. INST target is ACTUATE on C-PHASE OVERCURRENT RELAY 50/51 at 6900-V Unit Board 2D, Panel 7.

C. White Light ON (2-HS-3-200A).

D. Annunciator Window 14-E, M-1 THRU M-6 MOTOR TRIPOUT, ALARMS.

E. Audible Motor Trip Breaker Buzzer ON.

[106] RESET INST target on C-PHASE OVERCURRENT RELAY 50/51 at 6900-V Unit Board 2D, Panel 7.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 250 of 371 Date 6.30 Standby Main Feedwater Pump Breaker Logic and Functional Test (continued)

[107] PLACE 2-HS-3-200A, STANDBY MAIN FW PMP, on 2-M-4 to the STOP position and VERIFY:

A. White Light OFF (2-HS-3-200A).

B. Annunciator Window 14-E, 2-M-1 THRU M-6 MOTOR TRIPOUT, is CLEAR.

C. Audible Motor Trip Breaker Buzzer OFF.

[108] PLACE 2-HS-3-200A, STANDBY MAIN FW PMP, on 2-M-4 to the START position and VERIFY that 2-BKR-3-200 is CLOSED.

[109] MANUALLY ACTUATE time PORTION (51) of C-PHASE OVERCURRENT RELAY 50/51 at 6900-V Unit Board 2D, Panel 7, and VERIFY:

A. 2-BKR-3-200, STANDBY MAIN FEEDWATER PUMP (2-PMP-3-200), is OPEN.

B. TIME target is ACTUATE On C-PHASE OVERCURRENT RELAY 50/51 at 6900-V Unit Board 2D, Panel 7.

C. White Light ON (2-HS-3-200A).

D. Annunciator Window 14-E, M-1 THRU M-6 MOTOR TRIPOUT, ALARMS.

E. Audible Motor Breaker Trip Buzzer ON.

[110] RESET TIME target on C-PHASE OVERCURRENT RELAY 50/51 at 6900-V Unit Board 2D, Panel 7.

[111] PLACE 2-HS-3-200A, STANDBY MAIN FW PMP, on 2-M-4 to the STOP position and VERIFY:

A. White Light OFF (2-HS-3-200A).

B. Annunciator Window 14-E, 2-M-1 THRU M-6 MOTOR TRIPOUT, is CLEAR.

C. Audible Motor Trip Breaker Buzzer OFF.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 251 of 371 Date 6.30 Standby Main Feedwater Pump Breaker Logic and Functional Test (continued)

[112] PLACE 2-HS-3-200A, STANDBY MAIN FW PMP, on 2-M-4 to the START position and VERIFY that 2-BKR-3-200 is CLOSED.

[113] MANUALLY ACTUATE the instantaneous portion (50) of A-PHASE OVERCURRENT Relay 50/51 at 6900-V Unit Board 2D, Panel 7, and VERIFY:

A. 2-BKR-3-200 STANDBY MAIN FEEDWATER PUMP (2-PMP-3-200) is OPEN.

B. INST target is ACTUATE on A-PHASE OVERCURRENT RELAY 50/51 at 6900-V Unit Board 2D, Panel 7.

C. White Light ON (2-HS-3-200A).

D. Annunciator Window 14-E, M-1 THRU M-6 MOTOR TRIPOUT, ALARMS.

E. Audible Motor Trip Breaker Buzzer ON.

[114] RESET INST target on A-PHASE OVERCURRENT RELAY 50-51 at 6900-V Unit Board 2D, Panel 7.

[115] PLACE 2-HS-3-200A, STANDBY MAIN FW PMP, on 2-M-4 to the STOP position and VERIFY:

A. White Light OFF (2-HS-3-200A).

B. Annunciator Window 14-E, 2-M-1 THRU M-6 MOTOR TRIPOUT, is CLEAR.

C. Audible Motor trip Breaker Buzzer OFF.

[116] PLACE 2-HS-3-200A, STANDBY MAIN FW PMP, on 2-M-4 to the START position and VERIFY that 2-BKR-3-200 is CLOSED.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 252 of 371 Date 6.30 Standby Main Feedwater Pump Breaker Logic and Functional Test (continued)

[117] MANUALLY ACTUATE time PORTION (51) of A-PHASE OVERCURRENT RELAY 50/51 at 6900-V Unit Board 2D, Panel 7, and VERIFY:

A. 2-BKR-3-200, STANDBY MAIN FEEDWATER PUMP (2-PMP-3-200), is OPEN.

B. TIME target is ACTUATE on A-PHASE OVERCURRENT RELAY 50/51 at 6900-V Unit Board 2D, Panel 7.

C. White Light ON (2-HS-3-200A).

D. Annunciator Window 14-E, M-1 THRU M-6 MOTOR TRIPOUT, ALARMS.

E. Audible Motor Breaker Trip Buzzer ON.

[118] RESET TIME target on A-PHASE OVERCURRENT RELAY 50/51 at 6900-V Unit Board 2D, Panel 7.

[119] PLACE 2-HS-3-200A, STANDBY MAIN FW PMP, on 2-M-4 to the STOP position and VERIFY:

A. White Light OFF (2-HS-3-200A).

B. Annunciator Window 14-E, 2-M-1 THRU M-6 MOTOR TRIPOUT, is CLEAR.

C. Audible Motor Trip Breaker Buzzer OFF.

[120] PLACE 2-HS-3-205, STANDBY MAIN FW PMP DISH ISOL VLV, at Panel 2-JB-291-653 to the CLOSE position.

[121] PLACE 2-HS-2-265, STANDBY MAIN FW PUMP SUCTION ISOL VLV, at Panel 2-JB-291-653 to the CLOSE position.

[122] REMOVE jumper across Terminal B-11 and G-1 2 in 6900-V Unit Board 2D, Panel 7.

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 253 of 371 Date 6.30 Standby Main Feedwater Pump Breaker Logic and Functional Test (continued)

[123] REMOVE jumper across Terminal A-17 and G-14 in 6900-V Unit Board 2D, Panel 7.

CV

[124] REMOVE jumper across, Terminal Points CC-1 and CC-2 in Panel 2-L-491.

CV

[125] LAND lead FW1 on Terminal 1 of relay HWPA in Panel 2-R-75.

CV

[126] LAND lead FW1 on Terminal 1 of relay HWPB in Panel 2-R-75.

CV

[127] PLACE 2-HS-3-210, STANDBY MAIN FEED PUMP AUX OIL PMP A, at Panel 2-JB-291-653 to the OFF (LOCK) position.

CV

[128] REMOVE jumper across switch contacts 2D2 (BK) and 2D3 (W) in Pressure Switch 2-PS-3-212B installed in Step 6.30[141.

CV

[129] REMOVE the test link on the 6900-V Unit Board 2D, Panel 7.

CV

[130] REMOVE the umbilical cord test device on the 6900-V Unit Board 2D, Panel 7.

CV

[131] PLACE 2-HS-46-5AA, MFPT 2A MOP 1, on 2-M-3 to the start position and VERIFY 2-PMP-46-5B (729/T15J), MFPT 2A MAIN OIL PUMP 1, is RUNNING.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 254 of 371 Date 6.30 Standby Main Feedwater Pump Breaker Logic and Functional Test (continued)

[132] PLACE 2-HS-2-221A, MAIN FW PUMP A SUCTION ISOL VLV, on 2-M-3 to the OPEN position.

[133] VERIFY no continuity across Terminal 196 and lifted wire TTAP (BK) in Panel 2-L-275. (Lifted in Step 4.3[85])

M&TE ID#

[134] PLACE 2-HS-2-221A to the CLOSE position and VERIFY continuity exist across Terminal 196 and lifted wire TTAP (BK) in Panel 2-L-275 when 2-FCV-2-221 travels from the FULL OPEN position.

M&TE ID#

[135] PLACE 2-HS-46-30AA, MFPT 2B MOP 1, on 2-M-3 to the START position and VERIFY 2-PMP-46-30B (729/T16H),

MFPT 2B MAIN OIL PMP 1, is RUNNING.

[136] PLACE 2-HS-2-224A, MAIN FW PUMP B SUCTION ISOL VLV, on (2-M-3) to the OPEN position.

[137] VERIFY no continuity across Terminal 196 and lifted wire TTBP (BK) in Panel 2-L-276. (Lifted in Step 4.3[86])

M&TE ID#

[138] PLACE 2-HS-2-224A, to the CLOSE position and VERIFY continuity exist across Terminal 196 and lifted wire TTBP (BK) in Panel 2-L-276 when 2-FCV-2-224 travels from the FULL OPEN position.

M&TE ID#

[139] LAND vendor wire at Terminal 608 located in Panel 2-L-275.

CV

[140] LAND vendor wire at Terminal 608 located in Panel 2-L-276.

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 255 of 371 Date 6.30 Standby Main Feedwater Pump Breaker Logic and Functional Test (continued)

[141] LAND wire TTAP (BK) at Terminal 196 located in Panel 2-L-275.

CV

[142] LAND wire TTBP (BK) at Terminal 196 located in Panel 2-L-276.

CV

[143] REMOVE jumper installed across Terminals TB630-1 and TB630-2 located in AUX RELAY PANEL 2-R-76.

Cv

[144] REMOVE jumper installed across Terminal TB631-1 and TB631-2 located in AUX RELAY PANEL 2-R-76.

Cv

[145] LAND Wire 282A (BK) at Terminal GG-1 1 located in 6900-V Unit Board 2D, Panel 7.

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 256 of 371 Date 6.31 Injection Water Pumps 2A and 2B Operation The primary objective of this Subsection is to check the operational performance of the Injection Water Pumps 2A and 2B by gathering enough data to verify the Vendor pump curve.

CAUTION The minimum flow per pump is 45 GPM and there is no provision for a minimum flow line.

DO NOT isolate any of the three flow paths before starting either pump.

[1] VERIFY the prerequisites listed in 4.3[35] and 4.3[36] have been completed.

[2] VERIFY that both pumps have been aligned for normal operation per 2-TOP-54.01, Section 5.5.

[3] VERIFY the hotwell pumps are in operation and supplying water to the Injection Water System.

[4] VERIFY differential pressure control valves controllers 2-PDIC-54-1 MAIN FEEDWATER PUMP 2A SEAL WTR DIFF PRESS, 2-PDIC-54-5, MAIN FEEDWATER PUMP 2B SEAL WTR DIFF PRESS, and 2-PDIC-54-33, STANDBY MFW PUMP SEAL WTR DIFF PRESS control stations are in service and set to approximately 25 PSID and not pegged in either direction.

[5] START Injection Water Pump 2A using handswitch 2-HS-54-9A1 (2-M-2).

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 257 of 371 Date 6.31 Injection Water Pumps 2A and 2B Operation (continued)

NOTE The following steps will vary the flow rate to gather performance data on the pumps. The Test Engineer may have to use one or both of the other differential pressure controllers, 2-PDIC-54-5 or 2-PDIC-54-33, to achieve the desired flowrates. Note the usage of the other controllers in the CTL.

[6] MOVE the 2-PDIC-54-1, MAIN FEEDWATER PUMP 2A SEAL WTR DIFF PRESS (2-PNL-276-L33/C, T16H/729) PB ADJ dial adjust pressure until the flow from the ultrasonic flow meter reads 150 GPM. Acc Crit (5.OA.4)

Total Developed Head (TDH) (@150 GPM):

[discharge pressure _ PSIG- suction pressure PSIG]

X 2.307 = ft.

[7] RECORD the data for pump 2A on Data Sheet 23.

[8] ADJUST 2-PDIC-54-1, MAIN FEEDWATER PUMP 2A SEAL WTR DIFF PRESS to obtain approximately 160 GPM and RECORD the data on Data Sheet 23.

[9] ADJUST 2-PDIC-54-1, MAIN FEEDWATER PUMP 2A SEAL WTR DIFF PRESS to obtain approximately 180 GPM and record the data on Data Sheet 23.

[10] ADJUST 2-PDIC-54-1, MAIN FEEDWATER PUMP 2A SEAL WTR DIFF PRESS to obtain approximately 120 GPM and record the data on Data Sheet 23.

[11] ADJUST 2-PDIC-54-1, MAIN FEEDWATER PUMP 2A SEAL WTR DIFF PRESS to obtain approximately 100 GPM and RECORD the data on Data Sheet 23.

[12] ADJUST 2-PDIC-54-1, MAIN FEEDWATER PUMP 2A SEAL WTR DIFF PRESS to obtain approximately 80 GPM and RECORD the data on Data Sheet 23.

[13] ADJUST 2-PDIC-54-1, MAIN FEEDWATER PUMP 2A SEAL WTR DIFF PRESS to obtain approximately 60 GPM and RECORD the data on Data Sheet 23.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 258 of 371 Date 6.31 Injection Water Pumps 2A and 2B Operation (continued)

[14] MOVE the PB ADJ dial for 2-PDIC-54-1, MAIN FEEDWATER PUMP 2A SEAL WTR DIFF PRESS back to approximately 15 PSID.

[15] STOP Injection Water Pump 2A using handswitch 2-HS-54-9A1 (2-M-2).

[16] START Injection Water Pump 2B using handswitch 2-HS-54-9B1 (2-M-2).

[17] REPEAT Steps 6.31 [6] through 6.31[14] using Data Sheet 23, adjusting the flow with 2-PIC-54-1. Acc Crit (5.OA.4)

Total Developed Head (TDH) (@150 GPM):

[discharge pressure _ PSIG - suction pressure PSIG]

X 2.307 = ft.

[18] STOP Injection Water Pump 2B using handswitch 2-HS-54-9B1 (2-M-2).

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 259 of 371 Date 6.32 Standby Main Feedwater Pump (SMFP) Operation NOTE During the performance of this Subsection, piping vibration data will be collected. The TE is responsible for performance of piping vibration activities in accordance with N3C-945 and shall make an entry in the CTL.

[1] VERIFY prerequisites listed in Subsection 4.3[9] through 4.3[18] and 4.3[19] for Subsection 6.32 have been completed.

[2] RACK-IN the SMFP Breaker into 6900-V Unit Board 2D, Panel 7.

[3] RAISE the Breaker Elevator to the FULL-UP/OPERATE position for 6900-V Unit Board 2D, Panel 7.

[4] RECORD SMFP initial pump run data on Data Sheet 1, SMFP Initial Pump Run (Prior to Start).

NOTE If SMFP NPSH is less than 46 PSIG an additional Hotwell Pump shall be started.

[5] VERIFY the SMFP suction pressure is equal to or greater than 46 PSIG as was recorded from the suction gage 2-PI-2-273, STANDBY MAIN FW PMP SUCTION PRESS, on Data Sheet 1.

[6] VERIFY 0 VAC (Nominal) across Terminal Points EE-5 and EE-6 in 6900-V Unit Board 2D, Panel 7. (Dwg 0126D4672-2)

M&TE ID#

[7] ENSURE the Piping Vibration Test Engineer has test equipment and personnel in place to support vibration testing.

VIB. ENGR.

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 260 of 371 Date 6.32 Standby Main Feedwater Pump (SMFP) Operation (continued)

[8] NOTIFY TE responsible for N3C-945 that conditions have been established for transient event for the Standby Main Feedwater Pump START.

VIB. ENGR.

Cv CAUTIONS

1) The primary objective of this Section is to check the operational performance of the SMFP while operating at minimum flow conditions. Operation of the SMFP 2A at minimum flow conditions with the discharge valve closed may result in excessive vibrations, excessive pump discharge pressure, excessive bearing temperatures, or other adverse conditions. Close monitoring of MCR and local indications for adverse conditions is required.
2) Upon start of the SMFP, 2-FCV-3-208, STANDBY MAIN FEEDWATER PUMP MIN FLOW, needs to gradually open initially to prevent water hammer, and then maintain minimum flow to protect the pump. If auto operation fails to respond properly, manual operation will be required to OPEN 2-FCV-3-208 following pump start.

NOTE An operator should be stationed at the local control panel and be prepared to STOP the SMFP using 2-HS-3-200B, STANDBY MAIN FEEDWATER PUMP, if necessary.

[9] START the computer trends per Table 3, SMFP Computer Trends, to monitor SMFP performance.

[10] START the Standby Main Feedwater Pump on recirc per Subsection 5.9 of 2-TOP-2&3.01, Condensate and Feedwater System.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 261 of 371 Date 6.32 Standby Main Feedwater Pump (SMFP) Operation (continued)

CAUTION If the automatic controller fails to respond properly, the recirculation flow will need to be established manually at > 1122 GPM, to protect the SMFP from damage.

[11] RECORD the indicated recirc flow and VERIFY 2-FCV-3-208, STANDBY MAIN FEEDWATER PUMP MIN FLOW, gradually OPENS to provide a minimum flow of 1122 GPM.

Acc Crit (5.OA.1)

GPM _Ž1122 GPM M&TE ID#

[12] PERFORM vibration testing in accordance with N3C-945.

VIB. ENGR.

CV

[13] RECORD SMFP operational data on Data Sheet 2, SMFP Recirc Flow for recirc flow equal to or greater than 1122 GPM.

[14] REVIEW Data Sheet 2 and VERIFY SMFP NPSH is equal to or greater than 46 PSIG.

[15] VERIFY 120 VAC (Nominal) across Terminal Points EE-5 and EE-6 in 6900-V Unit Board 2D, Panel 7.

M&TE ID#

[16] OBTAIN SMFP vibration data per N3C-945.

[17] STOP computer trends and MCR strip charts as applicable and attach to this procedure.

[18] DEPRESS 2-HS-3-200B, STANDBY MAIN FEEDWATER PUMP, SAFE STOP pushbutton to STOP SMFP AND VERIFY 2-FCV-3-208, STANDBY MAIN FEEDWATER PUMP MIN FLOW, CLOSES. (This step may be marked N/A if SMFP operation is to continue).

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 262 of 371 Date 6.32 Standby Main Feedwater Pump (SMFP) Operation (continued)

[19] REMOVE jumper across Terminal 2D7C5 and 2D7C6 at Terminal Block TA in Panel 2-JB-291-653 installed in step 4.3[18]

CV

[201 OBTAIN a copy of the SMFP vibration data and attach to this procedure.

[211 VERIFY SMFP vibration data is acceptable.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 263 of 371 Date 6.33 Main Feedwater Pump Turbine (MFPT) 2A Uncoupled Operation

[1] VERIFY prerequisites listed in Subsections 4.1[18] through 4.1[19]and 4.3[19] through 4.3[34] for Subsection 6.33 have been completed.

[2] START the computer trends per Table 4, MFPT 2A Computer Trends to support this test.

[3] VERIFY/PLACE 2-SIC-46-20A, MFPT 2A SPEED CONTROL, on 2-M-3 in MANUAL and SET to minimum RPM.

NOTES

1) Hand knob on top of the Hand Speed Changer (HSC) is turned clockwise to increase speed. A decrease in control oil pressure increases speed. The HSC is the middle controller at the MFPT control block.
2) The Governor Valve Positioner (GVP) has control from zero speed to the minimum speed (2700 RPM) setting of the HSC. From minimum speed to rated speeds the HSC has control of speed.

[4] DEPRESS 2-HS-46-13D, MFPT 2A GOV VLV POS LOWER pushbutton at Panel 2-L-275 (729/Ti 5-J) until the governor is at a minimum position as indicated by light indication.

A. Red Light OFF.

B. Green Light ON.

[5] VERIFY/ADJUST 2-SC-46-13B, MFPT 2A HAND SPEED CHANGER, at Panel 2-L-275 to obtain a pressure between 70 and 80 PSIG as indicated on 2-PI-46-5001, HAND SPEED CHANGER PRESS MFPT 2A 0-160 PSIG.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 264 of 371 Date 6.33 Main Feedwater Pump Turbine (MFPT) 2A Uncoupled Operation (continued)

CAUTION The primary objective of this subsection is to check the operational performance of MFPT 2A while uncoupled from MFP 2A and to checkout operation of the governor and overspeed trip mechanism. The governor control system may need additional adjustment and may not control properly. Excessive vibration and bearing temperatures may be experienced. Close monitoring of MCR and local indications for adverse conditions is required.

NOTE Position an operator near the MFPT 2A manual trip and direct the operator to trip the MFPT 2A should the speed exceed 6126 RPM, or should excessive vibration, excessive bearing temperature, or other adverse condition arise or when directed to do so by the direction of the Test Engineer, or Unit Supervisor.

[6] RECORD MFPT 2A initial test data on Data Sheet 3, MFPT 2A Initial Pump Data (Prior to Start) (Uncoupled).

NOTE Close observation of MFPT 2A speed during reset and opening of the steam valves is required to observe for MFPT speed increasing too rapidly. Make a test log entry if the turbine rolls off turning gear and speed increases upon reset of MFPT 2A.

[7] DEPRESS 2-HS-46-9B, MFPT 2A TURB RESET, pushbutton at Panel 2-L-275 to RESET the MFPT 2A.

[8] DEPRESS 2-HS-46-9D, MFPT 2A TURB TRIP, pushbutton at Panel 2-L-275 and TRIP MFPT 2A.

[9] VERIFY MFPT 2A is TRIPPED by the Green Trip Light at Panel 2-L-275.

[10] DEPRESS 2-HS-46-9B, MFPT 2A TURB RESET, pushbutton at Panel 2-L-275 to RESET the MFPT 2A.

[11] VERIFY MFPT 2A is RESET by the Red Reset Light indication at Panel 2-L-275.

[12] DEPRESS the MANUAL TRIP PLUNGER located adjacent to the overspeed trip device to TRIP the MFPT 2A.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 265 of 371 Date 6.33 Main Feedwater Pump Turbine (MFPT) 2A Uncoupled Operation (continued)

[13] VERIFY MFPT 2A is TRIPPED by the Green Trip Light at Panel 2-L-275.

[14] DEPRESS 2-HS-46-9B, MFPT 2A TURB RESET, pushbutton at Panel 2-L-275 to RESET the MFPT 2A.

[15] VERIFY MFPT 2A is RESET by Red Reset Light indication at Panel 2-L-275.

CAUTION Manually trip the MFPT 2A if speed increases uncontrollably when the HP and LP stop and governor valves are open.

[16] Simultaneously PLACE the following handswitches located at Panel 2-JB-291-1149 (729/TI 6-J) to the RAISE position:

  • 2-HS-46-15B, MFPT 2A HP STOP VLV.

" 2-HS-46-16B, MFPT 2A LP STOP VLV.

NOTE If the MFPT 2A GOV VLV POSITION (2-HS-46-13B) does not function properly, the governor valve can be manually adjusted by the hand knob on top of the governor valve positioner.

[17] DEPRESS 2-HS-46-13B, MFPT 2A GOV VLV POSITION RAISE pushbutton at Panel 2-L-275 to OPEN the governor valve and ROLL the turbine to approximately 900 RPM as indicated on 2-SI-46-20D, MFPT 2A SPEED.

[18] RECORD MFPT 2A operational test data at a speed of 900 RPM on Data Sheet 4, MFPT 2A @ 900 RPM (Uncoupled).

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 266 of 371 Date 6.33 Main Feedwater Pump Turbine (MFPT) 2A Uncoupled Operation (continued)

NOTE The Vibration Group should monitor MFPT 2A vibration continuously through overspeed trip.

[19] DEPRESS 2-HS-46-13B, MFPT 2A GOV VLV POSITION RAISE pushbutton at Panel 2-L-275 INTERMITTENTLY to increase MFPT 2A speed to 1800 RPM as indicated on 2-SI-46-20D, MFPT 2A SPEED.

[20] RECORD MFPT 2A operational test data at a speed of 1800 RPM on Data Sheet 5, MFPT 2A @ 1800 RPM (Uncoupled).

CAUTION During spin up of the MFPT, critical speeds may cause vibration alert lights to come on briefly.

MFPT 2A critical speed occurs at approximately 2360 RPM. Vibration will be high through this speed. It should be quickly passed through without pausing at the critical speed.

Sustained excessive vibration may indicate the need to shutdown and balance the turbine.

[21] DEPRESS 2-HS-46-13B, MFPT 2A GOV VLV POSITION RAISE pushbutton at Panel 2-L-275 INTERMITTENTLY to increase MFPT 2A to 2700 RPM as indicated on 2-SI-46-20D, MFPT 2A SPEED.

[22] VERIFY the MFPT2 A Governor Valve is controlling speed at approximately 2700 RPM.

[23] RECORD MFPT 2A operational data at 2700 RPM on Data Sheet 6, MFPT 2A @ 2700 RPM (Uncoupled).

[24] ADJUST the RCW to MFPT 2A oil coolers to maintain hot oil temperature (leaving the bearings) between 140OF and 1601F, per Subsection 5.10 of 2-TOP-2&3.01 if necessary.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 267 of 371 Date 6.33 Main Feedwater Pump Turbine (MFPT) 2A Uncoupled Operation (continued)

[25] VERIFY the MFPT Condenser Drain Tank level is being maintained by 2-LCV-6-209, MFPT COND DRAIN TANK BYPASS TO CONDENSER, as indicated on 2-LG-6-206A, MFPT COND DRAIN TANK LEVEL (685/T14H), (i.e., level is not increasing).

[26] CONSULT the Vibration Group and VERIFY that MFPT 2A vibrations are within acceptable limits.

[27] PERFORM 2-TOP-46.01, MFPT Overspeed Trip Mechanism Test SBMFP Aux Oil Pump Test and MFPT Oil Tank Level Test, Subsection 6.2.1 NOTE The following steps will verify that the Hand Speed Changer (2-SC-46-13B) is adjusted properly. The lower oil pressure has control.

[28] DETERMINE whether the Governor Valve Positioner or the Hand Speed Changer has control of MFPT 2A speed by observing and RECORDING the pressures below:

Governor Valve Positioner (2-IPI-46-5003)

PSIG Hand Speed Changer (2-IPI-46-5001)

PSIG Control Oil Pressure (2-IPI-46-5005)

PSIG MFPT 2A Speed Control (GVPorHSC)

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 268 of 371 Date 6.33 Main Feedwater Pump Turbine (MFPT) 2A Uncoupled Operation (continued)

NOTE The Governor Valve Positioner and Hand Speed Changer are adjusted using the hand control knobs until the Hand Speed Changer has control, readjustments may be necessary.

Hand knobs on top of the HSC and GVP are turned clockwise to increase speed.

A decrease in control oil pressure increases speed. The HSC is the middle controller at the MFPT control block. The HSC and GVP hand knobs are very sensitive, only fractional turns are necessary. The GVP has control from zero speed to the minimum speed setting of the HSC. From minimum speed to rated speed, the HSC or Electric-Hydraulic Convertor (EHC) has control of speed. If the GVP has not automatically run to its maximum speed setting then control has not transferred to the hand speed controller.

[29] VERIFY/SET the MFPT 2A speed at 2700 RPM using GVP hand knob and RECORD pressure as indicated on 2-IPI-46-5003, GOV VALVE POSITION PRESS MFPT 2A 0-100 PSIG.

PSIG

[30] TURN Hand Speed Changer hand knob in the clockwise direction to match the pressure of the Governor Valve Positioner and RECORD the pressure as indicated on 2-IPI-46-5001, HAND SPEED CHANGER PRESS MFPT 2A 0-160 PSIG.

PSIG NOTE The following step will cause the valve positioner to run to its maximum control pressure (speed) position.

[31] TURN the GVP hand knob in the counter clockwise to INCREASE control oil pressure above the hand speed changer pressure.

[32] VERIFY the MFPT 2A speed is between 2700 and 2800 RPM with the Hand Speed Changer in control as indicated by the LOWER PRESSURE on 2-IPI-46-5001, HAND SPEED CHANGER PRESS MFPT 2A 0-160 PSIG.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 269 of 371 Date 6.33 Main Feedwater Pump Turbine (MFPT) 2A Uncoupled Operation (continued)

[33] DEPRESS 2-HS-46-13D, MFPT 2A GOV VLV POS LOWER pushbutton at Panel 2-L-275 to lower MFPT 2A speed to 2000 RPM as indicated on 2-SI-46-20D, MFPT 2A SPEED.

CAUTION MFPT 2A critical speed occurs at approximately 2360 RPM. It should be quickly passed through without pausing at the critical speed.

[34] DEPRESS 2-HS-46-13B, MFPT 2A GOV VLV POSITION RAISE pushbutton at Panel 2-L-275 until the GOV VLV POS MAX Red light is ON.

[35] VERIFY MFPT 2A speed increased to between 2700 and 2800 RPM as indicated on 2-SI-46-20D, MFPT 2A SPEED.

[36] SLOWLY INCREASE MFPT 2A speed to 3300 RPM using the Hand Speed Changer control knob.

[37] RECORD MFPT 2A operational data at 3300 RPM on Data Sheet 7, MFPT 2A @ 3300 RPM (Uncoupled).

[38] SLOWLY INCREASE MFPT 2A speed to 4500 RPM as indicated on 2-SI-46-20D, MFPT 2A SPEED, using the Hand Speed Changer control knob.

[39] RECORD MFPT 2A operational data at 4500 RPM on Data Sheet 8, MFPT 2A @ 4500 RPM (Uncoupled).

[40] SLOWLY INCREASE MFPT 2A speed to 5000 RPM using the Hand Speed Changer control knob.

[41] RECORD MFPT 2A operational data at 5000 RPM on Data Sheet 9, MFPT 2A @ 5000 RPM (Uncoupled).

[42] SLOWLY INCREASE MFPT 2A speed to 5625 RPM using the Hand Speed Changer control knob.

[43] RECORD MFPT 2A operational data at the normal operating speed on Data Sheet 10, MFPT 2A @ 5625 RPM (Uncoupled).

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 270 of 371 Date 6.33 Main Feedwater Pump Turbine (MFPT) 2A Uncoupled Operation (continued)

NOTE The following step will trip the MFPT. The turbine speed should not be increased above 6126 RPM. Increase speed in very small increments to allow accurate observation of the overspeed trip setpoint. Ifthe MFPT does not trip, lower the speed to 5000 RPM and repeat the following step before any overspeed trip adjustments are made.

[44] SLOWLY INCREASE speed to the overspeed trip setpoint of 6126 RPM using the hand speed control knob. RECORD the trip setpoint as indicated on the temporary speed indicator.

RPM [6006 to 6126 RPM]

M&TE ID#

NOTE The following two steps may be marked N/A if the MFPT is tripped. If the overspeed trip did not occur, adjustments to the overspeed trip mechanism are required.

[45] If the overspeed trip does not occur after the second attempt, REDUCE MFPT speed to 2700 RPM using 2-HS-46-13D, MFPT 2A GOV VLV POS LOWER pushbutton.

[46] TRIP the MFPT 2A using the MANUAL TRIP on the side the MFPT 2A.

[47] VERIFY locally the following steam valves CLOSED upon MFPT 2A TRIP:

A. 2-FCV-1-39, MFPT 2A LP STEAM STOP VLV.

B. 2-FCV-1-36, MFPT 2A HP STEAM STOP VLV.

C. 2-FCV-1-37, MFPT 2A HP STEAM CONTROL VLV.

D. 2-FCV-1-38, MFPT 2A LP STEAM CONTROL VLV

[48] VERIFY MFPT 2A speed decreases to zero and the turbine goes on turning gear.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 271 of 371 Date 6.33 Main Feedwater Pump Turbine (MFPT) 2A Uncoupled Operation (continued)

NOTE If the overspeed trip did not occur within 6006 to 6126 RPM re-perform applicable portions of this Subsection.

[49] OBTAIN copies of all vibration signatures taken on MFPT 2A and ATTACH to this procedure.

[50] STOP computer trending and ATTACH this information to this procedure.

[51] DEPRESS 2-HS-46-9B, MFPT 2A TURB RESET, pushbutton at Panel 2-L-275 to RESET MFPT 2A.

[52] PLACE 2-HS-46-15B, MFPT 2A HP STOP VLV, at 2-JB-291-1149 to the RAISE position.

[53] DEPRESS 2-HS-46-1 3B, MFPT 2A GOV VLV POSITION RAISE pushbutton at Panel 2-L-275 until the GOV VLV POS MIN Green Light is EXTINGUISHED.

[54] SLOWLY INCREASE MFPT 2A speed to approximately to 5850 RPM using the HAND SPEED CHANGER Control Knob.

[55] ADJUST HSC high speed stop to limit speed to approximately 5850 RPM.

[56] TRIP MFPT 2A using the MANUAL TRIP on the side of MFPT 2A.

[57] NOTIFY the Shift Manager of the test completion or pending retest.

[58] BRIEF test support personnel of test status, next planned operation and/or MFPT 2A coupled operation schedule.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 272 of 371 Date 6.34 Main Feedwater Pump (MFP) 2A Coupled Operation CAUTION The primary objective of this Subsection is to get the turbine and pump to a speed between 2700 RPM and 3300 RPM to checkout governor control and MFP operational performance at 2703 GPM at 3300 RPM. Operation of the MFP 2A at minimum flow with the discharge valve closed may result in excessive vibration, excessive pump discharge pressure, excessive bearing temperature, or other adverse condition. Do not exceed minimum speed except as directed by the Test Engineer. Close monitoring of MCR and local indications for adverse conditions is required.

NOTE During the performance of this Subsection, piping vibration data will be collected. The TE is responsible for performance of piping vibration activities in accordance with N3C-945 and shall make an entry in the CTL.

Continued operation of the MFP may lower steam generator pressure and temperature.

The operation of the MFPT may be terminated if directed to do so by the Shift Manager.

[1] VERIFY prerequisites listed in Subsections 4.1[18] through 4.1[19], 4.3[19] and 4.3[37] through 4.3[51] for Subsection 6.34 have been completed.

NOTE If the MFP 2A Suction pressure is less than 100 PSIG start any idle Hotwell Pump.

[2] VERIFY/PLACE 2-FIC-3-70, FW PMP A FLOW CONTROLLER, on 2-M-3 is in AUTO with setpoint set at 65%.

[3] ENSURE the Piping Vibration Test Engineer has test equipment and personnel are in place to support vibration testing.

VIB. ENGR.

CV

[4] VERIFYIPLACE 2-HS-3-195B, MFW DEAERATION LINE CONTROL VLV, at Panel 2-JB-291-2846, (708/T1 4-J), to the CLOSE position.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 273 of 371 Date 6.34 Main Feedwater Pump (MFP) 2A Coupled Operation (continued)

[5] VERIFY 2-FCV-3-195, MFW DEAERATION LINE CONTROL, is CLOSED by light indication at Panel 2-JB-291-2846.

A. Red Light OFF (2-HS-3-195B).

B. Green Light ON (2-HS-3-195B).

[6] VERIFY/PLACE 2-HS-3-86B, MAIN FEEDWATER PUMPS BYPASS ISOL VLV, at Panel 2-JB-291-2868 (729/TI 5-G) to the CLOSE position.

[7] VERIFY 2-FCV-3-86, MAIN FEEDWATER PUMPS BYPASS ISOL, is CLOSED by light indication at Panel 2-JB-291-2868.

A. Red Light OFF (2-HS-3-86B).

B. Green Light ON (2-HS-3-86B).

[8] VERIFY MFP 2A suction pressure is greater than 100 PSIG as indicated on 2-PI-2-207, MAIN FEEDWATER PUMP 2A SUCTION PRESS, at Panel 2-L-33.

[9] START computer trends per Table 4, MFPT 2A Computer Trends, to support this test.

[10] RECORD initial pump data on Data Sheet 11, MFP 2A Initial Pump Data (Prior to Start) (Coupled).

[11] NOTIFY TE responsible for N3C-945 that conditions have been established for transient event for MFP 2A Start.

VIB. ENGR.

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 274 of 371 Date 6.34 Main Feedwater Pump (MFP) 2A Coupled Operation (continued)

NOTES

1) Position an operator near the MFPT 2A manual trip and direct the operator to trip the MFPT 2A should the speed exceed 6126 RPM or discharge pressure exceed 1250 PSIG.
2) The following two steps will be performed simultaneously and will be signed off when both steps are complete.

[12] PERFORM vibration testing in accordance with N3C-945.

VIB. ENGR.

Cv

[13] START MFP 2A per applicable steps of Subsection 5.10 of 2-TOP-2&3.01, Condensate and Feedwater System.

NOTE MFP 2A recirculation 2-FCV-3-70, MAIN FEEDWATER PUMP A RECIRC, will gradually open to provide minimum flow pump protection of 2703 GPM at 3300 RPM.

[14] If necessary, ADJUST MFPT 2A speed using 2-SIC-46-20A, MFPT 2A SPEED CONTROL, to obtain approximately 2703 GPM as indicated on the temporary flow meter installed on the recirc line.

CAUTION If the automatic controller fails to respond properly, the recirculation flow will need to be established manually at 2703 GPM. If recirculation flow cannot be established, trip the MFPT 2A.

[15] VERIFY 2-FCV-3-70, MAIN FEEDWATER PUMP A RECIRC, OPENS and is MAINTAINING at least 2703 GPM at approximately 3300 RPM. ACC CRIT (5.OA.2)

GPM (_Ž2703 GPM)

M&TE ID#

[16] ADJUST cooling water to MFPT 2A and MFP 2A oil coolers to maintain hot oil temperature (leaving the bearings) between 140OF and 160°F per Subsection 5.10 of 2-TOP-2&3.01.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 275 of 371 Date 6.34 Main Feedwater Pump (MFP) 2A Coupled Operation (continued)

[17] VERIFY the MFPT 2A Condenser Drain Tank level is being maintained by 2-LCV-6-209, MFPT COND DRAIN TANK BYPASS TO CONDENSER, as indicated on 2-LG-6-206A, MFPT COND DRAIN TANK LEVEL. (685/T14H). (i.e., level is not increasing)

[18] RECORD MFP 2A recirc flow data at 3300 RPM on Data Sheet 12, MFP 2A Recirc Flow at 2703 GPM (Coupled).

[19] OBTAIN vibration signatures for the MFP 2A on recirc flow.

[20] VERIFY MFP 2A suction pressure is greater than 100 PSIG as indicated on 2-PI-2-207, MAIN FEEDWATER PUMP 2A SUCTION PRESS, at Panel 2-L-33.

[211 CONSULT the Vibration Group and VERIFY MFP 2A vibration signatures are within acceptable limits.

[22] REQUEST a hot oil sample be collected for analysis immediately following shutdown of the MFP 2A. (This step may be marked N/A if an oil sample has already been taken)

[23] SHUTDOWN MFPT 2A per applicable steps of Subsection 7.3.1 of 2-TOP-2 & 3.01.

[24] VERIFY locally the following steam valves CLOSED, upon MFP 2A TRIP:

A. 2-FCV-1-39, MFPT 2A LP STEAM STOP VLV.

B. 2-FCV-1-36, MFPT 2A HP STEAM STOP VLV.

C. 2-FCV-1-37, MFPT 2A HP STEAM CONTROL VLV.

D. 2-FCV-1-38, MFPT 2A LP STEAM CONTROL VLV.

[25] VERIFY MFPT 2A speed decreases to zero and the turbine goes on turning gear.

[26] VERIFY/PLACE 2-FIC-3-70, FW PMP A FLOW CONTROLLER, on 2-M-3 to AUTO and setpoint at 65%.

[27] STOP computer trending and ATTACH this information to the procedure.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 276 of 371 Date 6.34 Main Feedwater Pump (MFP) 2A Coupled Operation (continued)

[28] OBTAIN copies of all vibration signatures taken on MFP 2A and ATTACH to this procedure.

[29] NOTIFY the Shift Manager of test completion or pending retest.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 277 of 371 Date 6.35 Main Feedwater Pump Turbine (MFPT) 2B Uncoupled Operation

[1] VERIFY prerequisites listed in Subsections 4.1[18] through 4.1[19], 4.3119] and 4.3[52] through 4.3[66] for Subsection6.35 have been completed.

[2] START the computer trends per Table 5, MFPT 2B Computer Trends to support this test.

[3] VERIFY/PLACE 2-SIC-46-20B, MFPT 2B SPEED CONTROL, on 2-M-3 in MANUAL and SET to minimum RPM.

NOTES

1) Hand knob on top of the Hand Speed Changer (HSC) is turned clockwise to increase speed. A decrease in control oil pressure increases speed. The HSC is the middle controller at the MFPT control block.
2) The Governor Valve Positioner (GVP) has control from zero speed to the minimum speed (2700 RPM) setting of the HSC. From minimum speed to rated speed, the HSC has control of speed.

[4] DEPRESS 2-HS-46-40D, MFPT 2B GOV VLV POS, LOWER pushbutton at Panel 2-L-276 (729/T15H) until the governor is at a minimum position as indicated by light Indication.

A. Red Light OFF.

B. Green Light ON.

[5] VERIFY/ADJUST 2-SC-46-40B, MFPT 2B HAND SPEED CHANGER, Panel 2-L-276 to obtain a pressure between 70 and 80 PSIG as indicated on 2-IPI-46-5006, HAND SPEED CHANGER PRESS MFPT 2B 0-160 PSIG.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 278 of 371 Date 6.35 Main Feedwater Pump Turbine (MFPT) 2B Uncoupled Operation (continued)

CAUTION The primary objective of this Subsection is to check the operational performance of MFPT 2B while uncoupled from MFP 2B and to checkout operation of the governor and overspeed trip mechanism. The governor control system may need additional adjustment and may not control properly. Excessive vibration and bearing temperatures may be experienced. Close monitoring of MCR and local indications for adverse conditions is required.

NOTE Position an operator near the MFPT 2B manual trip and direct the operator to trip the MFPT 2B should the speed exceed 6126 RPM, or should excessive vibration, excessive bearing temperature, or other adverse condition arise or when directed to do so by the Test Engineer, or Unit Supervisor.

[6] RECORD MFPT 2B initial test data on Data Sheet 13, MFPT 2B Initial Pump Data (Prior to Start) (Uncoupled).

NOTE Close observation of MFPT 2B speed during reset and opening of the steam valves is required to observe for MFPT speed increasing too rapidly. Make a test log entry if the turbine rolls off turning gear and speed increases upon reset of MFPT 2B.

[7] DEPRESS 2-HS-46-36B, MFPT 2B TURB RESET, pushbutton at Panel 2-L-276 to RESET the MFPT 2B.

[8] DEPRESS 2-HS-46-36D, MFPT 2B TURB TRIP, pushbutton at Panel 2-L-276 and TRIP MFPT 2B.

[9] VERIFY MFPT 2B is TRIPPED by the Green Trip Light at Panel 2-L-276.

[10] DEPRESS 2-HS-46-36B, MFPT 2B TURB RESET, pushbutton at Panel 2-L-276 to RESET the MFPT 2B.

[11] VERIFY MFPT 2B is RESET by the Red Reset Light indication at Panel 2-L-276.

[12] DEPRESS the MANUAL TRIP PLUNGER located adjacent to the overspeed trip device to trip the MFPT 2B.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 279 of 371 Date 6.35 Main Feedwater Pump Turbine (MFPT) 2B Uncoupled Operation (continued)

[13] VERIFY MFPT 2B is TRIPPED by the Green Trip Light at Panel 2-L-276.

[14] DEPRESS 2-HS-46-36B, MFPT 2B TURB RESET, pushbutton at Panel 2-L-276 to RESET the MFPT 2B.

[15] VERIFY MFPT 2B is RESET by Green Reset Light indication at Panel 2-L-276.

CAUTION Manually trip the MFPT 2B if speed increases uncontrollably when the HP and LP stop and governor valves are open.

[16] Simultaneously PLACE the following handswitches located at Panel 2-JB-291-1219 (729/T16H) to the RAISE position.

  • 2-HS-46-43B, MFPT 2B HP STOP VLV.
  • 2-HS-46-44B, MFPT 2B LP STOP VLV.

NOTE If the MFPT 2B GOV VLV POSITION (2-HS-46-40B) does not function properly, the governor valve can be manually adjusted by the hand knob on top of the governor valve positioner.

[17] DEPRESS 2-HS-46-40B, MFPT 2B GOV VLV POSITION, RAISE pushbutton at Panel 2-L-276 to OPEN the governor valve and ROLL the turbine to approximately 900 RPM as indicated on 2-SI-46-20E, MFPT 2B SPEED.

[18] RECORD MFPT 2B operational test data at 900 RPM on Data Sheet 14, MFPT 2B @ 900 RPM (Uncoupled).

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 280 of 371 Date 6.35 Main Feedwater Pump Turbine (MFPT) 2B Uncoupled Operation (continued)

NOTE The Vibration Group should monitor MFPT 2B vibration continuously through overspeed trip.

[19] DEPRESS 2-HS-46-40B, MFPT 2B GOV VLV POSITION, RAISE pushbutton at Panel 2-L-276 INTERMITTENTLY to increase MFPT 2B speed to 1800 RPM as indicated on 2-SI-46-20E, MFPT 2B SPEED.

[20] RECORD MFPT 2B operational test data at a speed of 1800 RPM on Data Sheet 15, MFPT 2B @ 1800 RPM (Uncoupled).

CAUTION During spin up of MFPT critical speeds may cause vibration alert lights to come on briefly.

MFPT 2B critical speed occurs at approximately 2360 RPM. Vibration will be high through this speed. It should be quickly passed through without pausing at the critical speed.

Sustained excessive vibration may indicate the need to shutdown and balance the turbine.

[21] DEPRESS 2-HS-46-40B, MFPT 2B GOV VLV POSITION, RAISE pushbutton at Panel 2-L-276 INTERMITTENTLY to increase MFPT 2B speed to 2700 RPM as indicated on 2-SI-46-20E, MFPT 2B SPEED.

[22] VERIFY the MFPT 2B Governor Valve is controlling speed at approximately 2700 RPM.

[23] RECORD MFPT 2B operational data at 2700 RPM on Data Sheet 16, MFPT 2B @ 2700 RPM (Uncoupled).

[24] ADJUST the RCW to MFPT 2B oil coolers to maintain hot oil temperature (leaving the bearings) between 140OF and 160 0 F, per Subsection 5.11 of 2-TOP-2&3.01, if necessary.

[25] VERIFY the MFPT Condenser Drain Tank level is being maintained by Valve 2-LCV-6-209, MFPT COND DRAIN TANK BYPASS TO CONDENSER as indicated on 2-LG-6-206A, MFPT COND DRAIN TANK LEVEL. (685/T14H) (i.e., level is not increasing.)

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 281 of 371 Date 6.35 Main Feedwater Pump Turbine (MFPT) 2B Uncoupled Operation (continued)

[26] CONSULT the Vibration Group and VERIFY that MFPT 2B vibrations are within acceptable limits.

[27] PERFORM 2-TOP-46.01, MFPT Overspeed Trip Mechanism Test SBMFP Aux Oil Pump Test and MFPT Oil Tank Level Test, Subsection 6.3.1.

NOTE The following steps will verify that the Rand Speed Changer (2-SC-46-40B) is adjusted properly. The lower oil pressure has control.

[28] DETERMINE whether the Governor Valve Positioner or the Hand Speed Changer has control of MFPT speed by observing and RECORDING the pressure below:

Governor Valve Positioner (2-IPI-46-5008)

PSIG Hand Speed Changer (2-IPI-46-5006)

PSIG Control Oil Pressure (2-IPI-46-5010)

PSIG MFPT 2B Speed Control (GVP or HSC)

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 282 of 371 Date 6.35 Main Feedwater Pump Turbine (MFPT) 2B Uncoupled Operation (continued)

NOTE The Governor Valve Positioner and Hand Speed Changer are adjusted using the hand control knobs until the Hand Speed Changer has control, readjustments may be necessary.

Hand knobs on top of the HSC and GVP are turned clockwise to increase speed.

A decrease in control oil pressure increases speed. The HSC is the middle controller at the MFPT control block. The HSC and GVP hand knobs are very sensitive. Only fractional turns are necessary. The GVP has control from zero speed to the minimum speed setting of the HSC. From minimum speed to rated speed, the HSC or Electric-Hydraulic Convertor (EHC) has control of speed. If the GVP has not automatically run to its maximum speed setting then control has not transferred to the hand speed control.

[29] VERIFYISET the MFPT 2B speed at 2700 RPM using GVP hand knob and RECORD pressure as indicated on 2-IPI-46-5008, GOV VLV POSITION PRESS MFPT 2B 0-100 PSIG.

PSIG

[30] TURN Hand Speed Changer hand knob in the clockwise direction to match the pressure of the Governor Valve Positioner and RECORD the pressure as indicated on 2-IPI-46-5006, HAND SPEED CHANGER PRESS MFPT 2B 0-160 PSIG.

PSIG NOTE The following step will cause the valve positioner to run to its maximum control pressure (speed) position.

[31] TURN the GVP hand knob in the counter-clockwise to INCREASE control oil pressure above the hand speed changer pressure.

[32] VERIFY the MFPT 2B speed is between 2700 and 2800 RPM with the Hand Speed Changer in control as indicated by the lower pressure on 2-IPI-46-5006, HAND SPEED CHANGER PRESS MFPT 2B, 0-160 PSIG.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 283 of 371 Date 6.35 Main Feedwater Pump Turbine (MFPT) 2B Uncoupled Operation (continued)

[33] DEPRESS 2-HS-46-40D, MFPT 2B GOV VLV POS LOWER pushbutton at Panel 2-L-276 to lower MFPT 2B speed to 2000 RPM as indicated on 2-SI-46-20E, MFPT 2B SPEED.

CAUTION MFPT 2B critical speed occurs at approximately 2360 RPM. It should be quickly passed through without pausing at the critical speed.

[34] DEPRESS 2-HS-46-40B, MFPT 2B GOV VLV POSITION RAISE pushbutton at Panel 2-L-276 until the GOV VLV POS MAX Red Light is ON.

[35] VERIFY MFPT 2B speed increased to between 2700 and 2800 RPM as indicated on 2-SI-46-20E, MFPT 2B SPEED.

[36] SLOWLY INCREASE MFPT 2B speed to 3300 RPM as indicated on 2-SI-46-20E using the Hand Speed Changer control knob.

[37] RECORD MFPT 2B operational data at 3300 RPM on Data Sheet 17, MFPT 2B @ 3300 RPM (Uncoupled).

[38] SLOWLY INCREASE MFPT 2B speed to 4500 RPM as indicated on 2-SI-46-20E, MFPT 2B SPEED, using the Hand Speed Changer control knob.

[39] RECORD MFPT 2B operational data at 4500 RPM on Data Sheet 18, MFPT 2B @ 4500 RPM (Uncoupled).

[40] SLOWLY INCREASE MFPT 2B speed to 5000 RPM as indicated on 2-SI-46-20E using the Hand Speed Changer control knob.

[41] RECORD MFPT 2B operational data at 5000 RPM on Data Sheet 19, MFPT 2B @ 5000 RPM (Uncoupled).

[42] SLOWLY INCREASE MFPT 2B speed to 5625 RPM as indicated on 2-SI-46-20E using the Hand Speed Changer control knob.

[43] RECORD MFPT 2B operational data at the normal operating speed on Data Sheet 20, MFPT 2B @ 5625 RPM (Uncoupled).

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 284 of 371 Date 6.35 Main Feedwater Pump Turbine (MFPT) 2B Uncoupled Operation (continued)

NOTE The following step will trip the MFPT. The turbine speed should not be increased above 6126 RPM. Increase speed in very small increments to allow accurate observation of the overspeed trip setpoint. Ifthe MFPT does not trip, lower the speed to 5000 RPM and repeat the following step before any overspeed trip adjustments are made.

[44] SLOWLY INCREASE speed to the overspeed trip setpoint of 6126 RPM using the Hand Speed Changer control knob and RECORD the trip setpoint as indicated on the temporary speed indicator.

RPM [6006 to 6126 RPM]

M&TE ID#

NOTE The following two steps may be marked N/A if the MFPT is tripped. Ifthe overspeed trip did not occur, adjustments to the overspeed trip mechanism are required.

[451 Ifthe overspeed trip does not occur after the second attempt, REDUCE MFPT speed to 2700 RPM using 2-HS-46-40B, MFPT 2B GOV VLV POS, LOWER pushbutton.

[46] TRIP the MFPT 2B using the MANUAL TRIP on the side of the MFPT 2B.

[47] VERIFY locally the following steam valves CLOSED, upon MFPT 2B trip:

A. 2-FCV-1-46, MFPT 2B LP STEAM STOP VLV.

B. 2-FCV-1-43, MFPT 2B HP STEAM STOP VLV.

C. 2-FCV-1-44, MFPT 2B HP STEAM CONTROL VLV.

D. 2-FCV-1-45, MFPT 2B LP STEAM CONTROL VLV.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 285 of 371 Date 6.35 Main Feedwater Pump Turbine (MFPT) 2B Uncoupled Operation (continued)

[48] VERIFY MFPT 2B speed decreases to zero and the turbine goes on turning gear.

NOTE If the overspeed trip did not occur within the 6006 to 6126 RPM re-perform applicable portions of this Subsection.

[49] OBTAIN copies of all vibration signatures taken on MFPT 2B and ATTACH to this procedure.

[50] STOP computer trending and ATTACH this information to this procedure.

[51] DEPRESS 2-HS-46-36B, MFPT 2B TURB RESET, pushbutton at Panel 2-L-276 to RESET MFPT 2B.

[52] PLACE 2-HS-46-43B, MFPT 2B HP STOP VLV, at 2-JB-291-1219 to the RAISE position.

[53] DEPRESS 2-HS-46-40B, MFPT 2B GOV VLV POSITION, RAISE pushbutton at Panel 2-L-276 until the GOV VLV POS MIN Green Light is EXTINGUISHED.

(54] SLOWLY INCREASE MFPT 2B speed to approximately to 5850 RPM using the HAND SPEED CHANGER Control Knob.

[55] ADJUST HSC high speed stop to limit speed to approximately 5850 RPM.

[56] TRIP MFPT 2B using the MANUAL TRIP on the side of MFPT 2B.

[57] NOTIFY the Shift Manager of the test completion schedule or pending retest.

[58] BRIEF test support personnel of test status, next planned operation and/or MFPT 2B coupled operation schedule.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 286 of 371 Date 6.36 Main Feedwater Pump (MFP) 2B Coupled Operation CAUTION The primary objective of this Subsection is to get the turbine and pump to a speed between 2700 RPM and 3300 RPM to checkout governor control and MFP operational performance at 2703 GPM at 3300 RPM. Operation of the MFP 2B at minimum flow with the discharge valve closed may result in excessive vibration, excessive pump discharge pressure, excessive bearing temperature, or other adverse condition. Do not exceed minimum speed except as directed by the Test Engineer. Close monitoring of MCR and local indications for adverse conditions is required.

NOTE During the performance of this Subsection, piping vibration data will be collected. The TE is responsible for performance of piping vibration activities in accordance with N3C-945 and shall make an entry in the CTL.

Continued operation of the MFP may lower steam generator pressure and temperature.

The operation of the MFPT may be terminated it directed to do so by the Shift Manager.

[1] VERIFY prerequisites listed in Subsections 4.1 [18] through 4.1[19], 4.3[19] and 4.3[67] through 4.3[80] for Subsection 6.36 have been completed.

I NOTE If MFP 2B suction pressure is less than 100 PSIG start any idle Hotwell Pump.

[2] VERIFYIPLACE 2-FIC-3-84, FW PMP B FLOW CONTROLLER, is in AUTO with setpoint set at 65%.

[3] ENSURE the Piping Vibration Test Engineer has test equipment and personnel are in place to support vibration testing.

VIB. ENGR.

CV

[4] VERIFYIPLACE 2-HS-3-195B, MFW DEAERATION LINE CONTROL VLV, at Panel 2-JB-291-2850 (708/T14J) to the CLOSE position.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 287 of 371 Date 6.36 Main Feedwater Pump (MFP) 2B Coupled Operation (continued)

[5] VERIFY 2-FCV-3-195, MFW DEAERATION LINE CONTROL, is CLOSED by light indication at Panel 2-JB-291-2846.

A. Red Light OFF (2-HS-3-195B).

B. Green Light ON (2-HS-3-195B).

[6] VERIFY/PLACE 2-HS-3-86B, MAIN FEEDWATER PUMPS BYPASS ISOL VLV, at Panel 2-JB-291-2868 (729/T15C) to the CLOSE position.

A. Red Light OFF (2-HS-3-86B).

B. Green Light ON (2-HS-3-86B).

[7] VERIFY 2-FCV-3-86, MAIN FEEDWATER PUMPS BYPASS ISOL, is CLOSED by light indication at Panel 2-JB-291-2868.

[8] VERIFY MFP 2B suction pressure is greater than 100 PSIG as indicated on 2-PI-2-213, MAIN FEEDWATER PUMP 2B SUCTION PRESS, at Panel 2-L-34.

[9] START computer trends per Table 5, MFPT 2B Computer Trends to support this test.

[10] RECORD initial pump data on Data Sheet 21, MFP 2B Initial Pump Data (Prior to Start) (Coupled).

[11] NOTIFY TE responsible for N3C-945 that conditions have been established for transient event MFP start.

VIB. ENGR.

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 288 of 371 Date 6.36 Main Feedwater Pump (MFP) 2B Coupled Operation (continued)

NOTES

1) Position an operator near the MFPT 2B manual trip and direct the operator to trip the MFPT 2B should the speed exceed 6126 RPM or discharge pressure exceed 1250 PSIG.
2) The following two steps will be performed simultaneously and will be signed off when both steps are complete.

[12] PERFORM vibration testing in accordance with N3C-945.

VIB. ENGR.

CV

[13] START MFP 2B per applicable steps of Subsection 5.11 of 2-TOP-2&3.01, Condensate and Feedwater System.

NOTE MFP 2B Recirculation 2-FCV-3-84, MAIN FEEDWATER PUMP B RECIRC, will gradually open to provide minimum flow pump protection of 2703 GPM at 3300 RPM.

[14] If necessary, ADJUST MFPT 2B speed using 2-SIC-46-20E, MFPT 2B SPEED CONTROL, to obtain approximately 2703 GPM as indicated on the temporary flow meter installed on the recirc line.

CAUTION If the automatic controller fails to respond properly, the recirculation flow will need to be established manually > 2703 GPM. If recirculation flow cannot be established, trip the MFPT 2B.

[15] VERIFY 2-FCV-3-84, MAIN FEEDWATEP PUMP B RECIRC, OPENS and is MAINTAINING --2703 GPM at approximately 3300 RPM. ACC CRIT (5.OA.3)

GPM (>2703 GPM)

M&TE ID#

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 289 of 371 Date 6.36 Main Feedwater Pump (MFP) 2B Coupled Operation (continued)

[16] ADJUST cooling water to MFPT 2B and MFP 2B oil coolers to maintain hot oil temperature (leaving the bearings) between 140OF and 160°F per Subsection 5.11 of 2-TOP-2&3.01.

[17] VERIFY the MFPT 2B Condenser Drain Tank Level is being maintained by 2-LCV-6-209, MFPT COND DRAIN TANK BYPASS TO CONDENSER, as indicated on 2-LG-6-206A, MFPT COND DRAIN TANK LEVEL. (685rTI4H) (i.e., level is not increasing).

.[18] RECORD MFP 2B recirc flow at 2703 GPM data on Data Sheet 22, MFP 2B Recirc Flow at 2703 GPM (Coupled).

[19] OBTAIN vibration signatures for the MFP 2B on recirc flow.

[20] VERIFY MFP 2B suction pressure is greater than 100 PSIG as indicated on 2-PI-2-213, MAIN FEEDWATER PUMP 2B SUCTION PRESS, at Panel 2-L-34.

[21] CONSULT the Vibration Group and VERIFY MFP 2B vibration signatures are within acceptable limits.

[22] REQUEST a hot oil sample be collected for analysis immediately following shutdown of the MFP 2B. (This step may be marked N/A if an oil sample has already been taken)

[23] SHUTDOWN MFPT 2B per applicable steps of Subsection 7.3.1 of 2-TOP-2&3.01.

[24] VERIFY locally the following steam valves CLOSED, upon MFP 2B TRIP:

A. 2-FCV-1-46, MFPT 2B LP STEAM STOP VLV.

B. 2-FCV-1-43, MFPT 2B HP STEAM STOP VLV.

C. 2-FCV-1-44, MFPT 2B HP STEAM CONTROL VLV.

D. 2-FCV-1-45, MFPT 2B LP STEAM CONTROL VLV.

[25] VERIFY MFPT 2B speed decreases to zero and the turbine goes on turning gear.

[26] VERIFY/PLACE 2-FIC-3-84, FW PMP B FLOW CONTROLLER, on 2-M-3 to AUTO and setpoint at 65%.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 290 of 371 Date 6.36 Main Feedwater Pump (MFP) 2B Coupled Operation (continued)

[27] STOP computer trending and ATTACH this information to the procedure.

[28] OBTAIN copies of all vibration signatures taken on MFP 2B and ATTACH to this procedure.

[29] NOTIFY the Shift Manager of test completion or pending retest.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 291 of 371 Date 7.0 POST PERFORMANCE ACTIVITIES

[1] VERIFY that Post-test calibration of the M&TE used to record quantitative acceptance criteria has been satisfactorily performed and the results RECORDED on M&TE Log.

[2] VERIFY that Post-test calibration of permanent plant instruments used to record quantitative acceptance criteria has been satisfactorily performed and the results RECORDED on Appendix C, Permanent Plant Instrumentation Log.

[3] INSTALL the following fuses:

A. Fuse Set C31 (0-FU-236-0001/C31A) (2- FSV-46-9A)

Battery Bd. Ill, Panel 4, Column C.

CV B. Fuse Set C31 (0-FU-236-0002/C31 B) (2-FSV-46-9B)

Battery Bd. IV, Panel 4, Column C.

CV

[4] INSTALL the following fuses:

A. Fuse Set C33 (0-FU-236-0001/C33A) (2- FSV-46-36A)

Battery Bd. III, Panel 4, Column C.

CV B. Fuse Set C16 (0-FU-236-0002/C16B) (2-FSV-46-36B)

Battery Bd. IV, Panel 4, Column C.

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 292 of 371 Date 7.0 POST PERFORMANCE ACTIVITIES (continued)

[5] LAND the following leads:

A. Lead 1BAP (Red) to Terminal AA3, Section A of Panel 2-L-565, Steam Generator Water Hammer Protection.

Cv B. Lead 2BAP (Red) to Terminal CC3, Section A of Panel 2-L-565, Steam Generator Water Hammer Protection.

Cv C. Lead 3BAP (Red) to Terminal CC3, Section B of Panel 2-L-565, Steam Generator Water Hammer Protection.

Cv D. Lead 4BAP (Red) to Terminal AA3, Section C of Panel 2-L-565, Steam Generator Water Hammer Protection.

Cv

[6] REMOVE the following:

A. SMFP suction pressure gage installed on the calibration tap of 2-PT-2-273, STANDBY MAIN FW PUMP SUCTION HDR PRESS, (729/T1I6-J).

Cv B. SMFP 4" RECIRC flow ultrasonic flowmeter installed on the recirc line upstream of 2-FCV-3-208, STANDBY MAIN FEEDWATER PUMP MIN FLOW, (729/T16-J).

Cv

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 293 of 371 Date 7.0 POST PERFORMANCE ACTIVITIES (continued)

C. MFPT 2A 8" RECIRC flow ultrasonic flowmeter installed on the recirc line upstream of 2-FCV-3-70, MAIN FEEDWATER PUMP A RECIRC, (729/T15-H).

CV D. MFPT 2B 8" RECIRC flow ultrasonic flowmeter installed on the recirc line upstream of 2-FCV-3-84, MAIN FEEDWATER PUMP B RECIRC, (729/T15-G).

CV E. SMFP discharge pressure gage installed on the calibration tap of 2-PI-3-203B, STANDBY MAIN FW PMP DISCH PRESSURE, (729/T16-J).

CV F. MFPT 2A suction pressure gage installed on the calibration tap of 2-PI-2-207, MAIN FEEDWATER PUMP 2A SUCTION PRESS, (729/T16-J).

CV G. MFPT 2A discharge pressure gage installed on the calibration tap of 2-PI-3-66B, MAIN FEEDWATER PUMP A DISCHARGE PRESSURE (729/T16-H).

CV H. MFPT 2B suction pressure gage installed on the calibration tap of 2-PI-2-213, MAIN FEEDWATER PUMP 2B SUCTION PRESS, (729/T16-G).

CV

1. MFPT 2B discharge gage installed on the calibration tap of 2-PI-3-80B, FW PUMP B OUTLET PRESS IND, (729 /T16-G)

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 294 of 371 Date 7.0 POST PERFORMANCE ACTIVITIES (continued)

[7] VERIFY no excessive vibration of piping (or ductwork, as applicable) and components was observed or Engineering has evaluated the vibration and found it acceptable or has initiated corrective action.

[8] NOTIFY the Unit 2 US/SRO of the test completion and system alignment.

8.0 RECORDS A. QA Records Completed Test Package B. Non QA Records None

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 295 of 371 Appendix A (Page 1 of 1)

TEST PROCEDURES/INSTRUCTIONS REFERENCE REVIEW NOTES

1) Additional copies of this table may be made as necessary.
2) Initial and date indicates review has been completed for impact PROCEDURE/ IMPACT INITIAL AND DATE.

INSTRUCTION Yes/No (N/A for no change) 2-TSD-3A-3 BW/IP International Report GS-1 150 WBN2-3A-4002 VTM-B580-0030 VTM-B580-00 10 VTM-W120-2094 Unit 2 Final Safety Analysis Report Section 10.4.7 Table 14.2-1 Sheet 67 of 89

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 296 of 371 Appendix B (Page 1 of 1)

TEMPORARY CONDITION LOG Date_____

NOTE These steps will be N/A if no temporary condition exists. Additional copies of this Appendix may be made as necessary.

ITEM TEMPORARY CONDITION PERFORMED RETURNED TO NORMAL No. DESCRIPTION Step Performed By/Date Step Returned By/Date No. CV/Date. No. CV /Date

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 297 of 371 Appendix C (Page 1 of 9)

PERMANENT PLANT INSTRUMENTATION LOG INSTRUMENT OR CAL DUE FILLED AND PLACED IN USED FOR POST-TEST POST-TEST INSTRUMENT LOOP # DATE VENTED' SERVICE 1 QUANTITATIVE CAL DATE 2 CALIBRATION 2 ACC CRIT ACCEPTABLE NO IN ITIAL/DATE INITIAL/DATE YES INITIALIDATE 2-PIC-54-2 (2-L-33) 2-PDIC-54-1 (2-L-33) 2-TI-3-71D (Local) 2-PI-2-21 (2-L-95) 2-PI-2-27 (2-L-95) 2-PI-2-34 (2-L-95) 2-PIC-54-6 (2-L-34) 2-SI-46-20E (2-L-276) 2-PI-46-31 (2-L-276)

These items may be initialed and dated by personnel performing the task. Instrumentation not required to be filled and vented may be identified as Not Applicable.

(N/A).

2 May be identified as Not Applicable (N/A) if instrument was not used to verify/record quantitative acceptance criteria data.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 298 of 371 Appendix C (Page 2 of 9)

PERMANENT PLANT INSTRUMENTATION LOG INSTRUMENT OR CAL DUE FILLED AND PLACED IN USED FOR POST-TEST POST-TEST INSTRUMENT LOOP # DATE VENTED1 SERVICE 1 QUANTITATIVE CAL DATE 2 CALIBRATION 2 ACC CRIT ACCEPTABLE NO INITIALIDATE INITIALIDATE YES INITIAL/DATE 2-TI-24-57B (2-L-258) 2-TIS-46-60 (2-L-276) 2-TIS-46-62 (2-L-276) 2-TIS-46-64 (2-L-276) 2-TIS-46-66 (2-L-276) 2-PDIC-54-5 (2-L-34) 2-PI-46-52A (2-L-276) 2-PI-46-52B (2-L-276) 2-TIS-46-59 (2-L-275) 1 These items may be initialed and dated by personnel performing the task. Instrumentation not required to be filled and vented may be identified as Not Applicable.

(N/A).

2 May be identified as Not Applicable (N/A) if instrument was not used to verify/record quantitative acceptance criteria data.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 299 of 371 Appendix C (Page 3 of 9)

PERMANENT PLANT INSTRUMENTATION LOG INSTRUMENT OR CAL DUE FILLED AND PLACED IN USED FOR POST-TEST2 POST-TEST CALIBRATION INSTRUMENT LOOP # DATE VENTED' SERVICE1 QUANTITATIVE CAL DATE ACCEPTABLE 2 ACC CRIT INITIAL/DATE INITIAL/DATE INITIAL/DATE YES NO 2-TIS-46-61 (2-L-275) 2-TIS-46-63 (2-L-275) 2-TIS-46-65 (2-L-275) 2-1PI-46-5001 (2-L-275) 2-IPI-46-5002 (2-L-275) 2-IPI-46-5003 (2-L-275) 2-PDIC-54-33 (2-L-490) 2-PIC-54-35 (2-L-490) 2-IPI-46-5004 (2-L-275) 2-IPI-46-5005 (2-L-275)

These items may be initialed and dated by personnel performing the task. Instrumentation not required to be filled and vented may be identified as Not Applicable.

(N/A).

2 May be identified as Not Applicable (N/A) if instrument was not used to verify/record quantitative acceptance criteria data.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 300 of 371 Appendix C (Page 4 of 9)

PERMANENT PLANT INSTRUMENTATION LOG INSTRUMENT OR CAL DUE FILLED AND PLACED IN USED FOR POST-TEST POST-TEST INSTRUMENT LOOP # DATE VENTED1 SERVICE 1 QUANTITATIVE CAL DATE 2 CALIBRATION 2 ACC CRIT ACCEPTABLE INITIALIDATE INITIAL/DATE YES NO INITIALIDATE 2-TI-24-57A (2-L-258) 2-TI-3-71 A (Local) 2-PI-3-73A (Local) 2-TI-3-71 B (Local) 2-PI-3-73B (Local) 2-PI-2-207 (2-L-33) 2-PI-3-66B (2-L-33) 2-IPI-46-5006 (2-L-276) 2-IPI-46-5007 (2-L-276) 2-IPI-46-5008 (2-L-276)

These items may be initialed and dated by personnel performing the task. Instrumentation not required to be filled and vented may be identified as Not Applicable.

(N/A).

2 May be Identified as Not Applicable (N/A) if instrument was not used to verify/record quantitative acceptance criteda data.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 301 of 371 Appendix C (Page 5 of 9)

PERMANENT PLANT INSTRUMENTATION LOG INSTRUMENT OR CAL DUE FILLED AND PLACED IN USED FOR POST-TEST POST-TEST INSTRUMENT LOOP # DATE VENTED 1 SERVICE 1 QUANTITATIVE CAL DATE 2 CALIBRATION 2 ACC CRIT ACCEPTABLE INITIAL/DATE INITIAL/DATE YES NO INITIAL/DATE 2-1PI-46-5009 (2-L-276) 2-IPI-46-5010 (2-L-276) 2-TI-3-85A (Local) 2-PI-3-89A (Local) 2-TI-3-85D (Local) 2-PI-3-89B (Local) 2-TI-24-57A (2-L-258) 2-TI-3-71A (Local) 2-PI-3-73A (Local) 2-TI-3-71 B (Local)

These items may be initialed and dated by personnel performing the task. Instrumentation not required to be filled and vented may be identified as Not Applicable.

(N/A).

2 May be identified as Not Applicable (N/A) ifinstrument was not used to verify/record quantitative acceptance criteria data.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 302 of 371 Appendix C (Page 6 of 9)

PERMANENT PLANT INSTRUMENTATION LOG INSTRUMENT OR CAL DUE FILLED AND PLACED IN USED FOR POST-TEST POST-TEST INSTRUMENT LOOP # DATE VENTED 1 SERVICE 1 QUANTITATIVE CAL DATE 2 CALIBRATION2 ACC CRIT ACCEPTABLE INITIAL/DATE INITIAL/DATE YES NO INITIAL/DATE 2-PI-3-73B (Local) 2-PI-2-207 (2-L-33) 2-PI-3-66B (2-L-33) 2-1PI-46-5006 (2-L-276) 2-TI-3-58 (2-L-34) 2-PI-2-213 (2-L-34) 2-PI-2-80B (2-L-34) 2-XX-3-63A/B (2-M-1 1) 2-SI-46-20D (2-L-275) 2-PI-46-4 (2-L-275)

These items may be initialed and dated by personnel performing the task. Instrumentation not required to be filled and vented may be identified as Not Applicable.

(N/A).

2 May be identified as Not Applicable (N/A) if instrument was not used to verify/record quantitative acceptance criteria data.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 303 of 371 Appendix C (Page 7 of 9)

PERMANENT PLANT INSTRUMENTATION LOG INSTRUMENT OR CAL DUE FILLED AND PLACED IN USED FOR POST-TEST POST-TEST INSTRUMENT LOOP # DATE VENTED1 SERVICE 1 QUANTITATIVE CAL DATE 2 CALIBRATION ACC CRIT ACCEPTABLE 2 INITIAL/DATE INITIAL/DATE YES NO INITIAL/DATE 2-PI-46-19A (2-L-275) 2-PI-46-19B (2-L-275) 2-TI-3-217 (2-L-517) 2-TI-3-214 (Local) 2-PI-3-213 (Local) 2-PI-54-9A (2-L-69) 2-PI-54-9B (2-L-69) 2-TI-54-37 (Local) 2-PI-54-38 (Local) 2-PI-3-203B (2-L-517)

These items may be initialed and dated by personnel performing the task. Instrumentation not required to be filled and vented may be identified as Not Applicable.

(N/A).

2 May be identified as Not Applicable (N/A) if instrument was not used to verify/record quantitative acceptance criteria data

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 304 of 371 Appendix C (Page 8 of 9)

PERMANENT PLANT INSTRUMENTATION LOG INSTRUMENT OR CAL DUE FILLED AND PLACED IN USED FOR POST-TEST POST-TEST INSTRUMENT LOOP # DATE VENTED1 SERVICE1 QUANTITATIVE CAL DATE 2 CALIBRATION ACC CRIT ACCEPTABLE 2 INITIAL/DATE INITIAL/DATE YES NO INITIAL/DATE 2-TI-3-57 (2-L-33) 2-FR-2-35 (2-M-3) 2-TI-3-85B (Local) 2-SC-46-1 3A (2-L-275) 2-SC-46-13B (2-L-275) 2-POS-46-13 (2-L-275) 2-SC-46-40A (2-L-276) 2-SC-46-40B (2-L-276) 2-POS-46-40 (2-L-276) 2-PI-2-273 (2-L-517)

These items may be initialed and dated by personnel performing the task. Instrumentation not required to be filled and vented may be identified as Not Applicable.

(N/A).

2 May be identified as Not Applicable (N/A) if instrument was not used to verify/record quantitative acceptance criteria data.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 305 of 371 Appendix C (Page 9 of 9)

PERMANENT PLANT INSTRUMENTATION LOG INSTRUMENT OR CAL DUE FILLED AND PLACED IN USED FOR POST-TEST POST-TEST INSTRUMENT LOOP # DATE VENTED1 SERVICE 1 QUANTITATIVE CAL DATE2 CALIBRATION 2 ACC CRIT ACCEPTABLE INITIAL/DATE INITIAL/DATE YES NO INITIAL!DATE 2-PS-3-212A 2-PS-3-212B 2-PS-3-212C

.1. 4 1 I J I I I I I

+ 4 1 4 1 4 4 These items may be initialed and dated by personnel performing the task. Instrumentation not required to be filled and vented may be identified as Not Applicable.

(N/A).

2 May be identified as Not Applicable (N/A) if instrument was not used to verify/record quantitative acceptance criteria data.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 306 of 371 Appendix D (Page 1 of 1)

BACKGROUND CALCULATIONS Minimum flow (GPM) = Required Flow (GPM) x (1 + M&TE Percent Error)

Standby Pump:

Minimum flow (GPM) = 1100 GPM x (1 + 0.02) = 1122 GPM or Main Feed Pump "A" or "B":

Minimum flow (GPM) = 2650 GPM x (1 + 0.02) = 2703 GPM

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 307 of 371 Table I (Page 1 of 5)

COMPUTER POINT VERIFICATION LOG Date COMPUTER DESCRIPTION STATUS INITIAL/DATE POINT SET RESET Y2211D FPT A OPERATING STATUS TRIP NOTTR Y2212D FPT B OPERATING STATUS TRIP NOT TR Y2400D FPT A TRIP-PMP TB BRG OIL PRESS LOW NOT LO Y2401D STANDBY MAIN FW PMP BRK CLOSED OPEN Y2402D FPT A TRIP-THRUST BRG WEAR TRBL N TRBL Y2403D FPT A TRIP-SUCTION VALVE CLOSED NOT CL Y2404D STANDBY MAIN FW PMP TR-SUCT VLV CLOSED NOT CL Y2405D INJECTION WATER PMP DISCH PRESS N/A N/A Y2406D FPT A TRIP-COND VACUUM LOW NOT LO Y2410D FPT B TRIP-PMP TB BRG OIL PRESS LOW NOT LO Y2412D FPT B TRIP-THRUST BRG WEAR TRBL N TRBL Y2413D FPT B TRIP-SUCTION VALVE CLOSED NOT CL Y2415D INJECTION WATER PMP DISCH PRESS N/A N/A Y2416D FPT B TRIP-COND VACUUM LOW NOT LO FD2008 HTR 2A-2 INLET FLOW CONT VLV NOT OPEN OPEN FD2009 HTR 2A-2 OUTLET FLOW CONT VLV NOT OPEN OPEN FD2356 HTR 2B-2 INLET FLOW CONT VLV NOT OPEN OPEN FD2357 HTR 2B-2 OUTLET FLOW CONT VLV NOT OPEN OPEN FD2011 HTR 2C-2 INLET FLOW CONT VLV NOT OPEN OPEN FD2012 HTR 2C-2 OUTLET FLOW CONT VLV NOT OPEN OPEN FD2007 FWP 2A OUTLET FLOW CONT VLV NOT OPEN OPEN

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 308 of 371 Table 1 (Page 2 of 5)

COMPUTER POINT VERIFICATION LOG Date COMPUTER DESCRIPTION STATUS INITIAL/DATE POINT SET RESET FD2355 FWP 2B OUTLET FLOW CONT VLV NOT OPEN OPEN XD2001 TD FW PUMP-A CNTL VLV 2-FCV-1-39 NOT CLOSED CLOSED XD2056 TD FW PUMP-A CNTL VLV 2-FCV-1-39 NOT CLOSED CLOSED FD4004 120V AC PWR FOR SYS 3 & 46 INSTR PWR PWR ON PWR OFF Q2828A STANDBY MAIN FW PMP ELECT PWR N/A N/A P2224A FEEDWATER PUMPS SUCTION HEADER P N/A N/A P2416A STANDBY MAIN FW PMP SUCTION P N/A N/A P2417A STANDBY MAIN FW PMP DIS P N/A N/A P2243A HOTWELL PUMPS SUCTION HEADER P N/A N/A P2244A HOTWELL PUMPS DISCH HEADER P N/A N/A F2264A HOTWELL PUMPS DISCH HDR F N/A N/A T2355A STANDBY MAIN FW PMP DISCH T N/A N/A T2263A FEEDWATER HEATER A2 OUTLET T N/A N/A T2264A FEEDWATER HEATER B2 OUTLET T N/A N/A T2265A FEEDWATER HEATER C2 OUTLET T N/A N/A T2450A STANDBY MAIN FW PMP THRUST BRG T N/A N/A T2451A STANDBY MAIN FW PMP OUTBRD BRG T N/A N/A T2452A STANDBY MAIN FW PMP INBRD BRG T N/A N/A T2455A STANDBY MAIN FW PMP PH A WDG N/A N/A T2456A STANDBY MAIN FW PMP PH B WDG N/A N/A T2457A STANDBY MAIN FW PMP PH C WDG N/A N/A T2458A STANDBY MAIN FWP SPD INC BRG N/A N/A T2459A STANDBY MAIN FWP SPD INC BRG N/A N/A

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 309 of 371 Table 1 (Page 3 of 5)

COMPUTER POINT VERIFICATION LOG Date COMPUTER DESCRIPTION STATUS INITIAL/DATE POINT SET RESET P2500A MAIN FW PUMP 2A SUCTION P N/A N/A P2214A MAIN FW PUMP 2A DISCH HDR P N/A N/A T2460A FW PUMP A INBD BRG T N/A N/A T2461A FW PUMP A OUTBD BRG T N/A N/A T2462A FW PUMP A THRUST BRG T N/A N/A T2362A MAIN FW PUMP A DISCHARGE T N/A N/A T3106A MFPT 2A REV TH DIR BRG PAD T N/A N/A T3107A MFPT 2A NORM TH DIR BRG PAD T N/A N/A T3170A MFPT 2A OIL COOLER INLET N/A N/A T3171A MFPT 2A OIL NO. 1 BRG DRAIN N/A N/A T3172A MFPT 2A OIL NO. 2 BRG DRAIN N/A N/A T3173A MFPT 2A OIL THRUST BRG DRAIN N/A N/A T3178A MFPT 2A HI PRESS STOP VALVE TEMP N/A N/A P2501A MAIN FW PUMP 2B SUCTION P N/A N/A P2215A MAIN FW PUMP 2B DISCH HDR P N/A N/A T2463A FW PUMP B.INBD BRG T N/A N/A T2464A FW PUMP B OUTBD BRG T N/A N/A T2465A FW PUMP B THRUST BRG T N/A N/A T3108A MFPT 2B REV TH DIR BRG PAD T N/A N/A T3109A MFPT 2B NORM TH DIR BRG PAD T N/A N/A T3174A MFPT 2B OIL COOLER INLET N/A N/A T3175A MFPT 2B OIL NO. 1 BRG DRAIN N/A N/A T3176A MFPT 2B OIL NO. 2 BRG DRAIN N/A N/A T3177A MFPT 2B OIL THRUST BRG DRAIN N/A N/A

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 310 of 371 Table I (Page 4 of 5)

COMPUTER POINT VERIFICATION LOG Date COMPUTER DESCRIPTION STATUS INITIALIDATE POINT SET RESET T3179A MFPT 2B HI PRESS STOP VALVE TEMP N/A N/A V9044A 2A MFP INBOARD VIBRATION - X - HOR N/A N/A V9045A 2A MFP INBOARD VIBRATION - Y - VERT N/A N/A V9046A 2A MFP THRUST - A N/A N/A V9047A 2A MFP THRUST - B N/A N/A V9048A 2A MFP OUTBOARD VIBRATION - X - HOR N/A N/A V9049A 2A MFP OUTBOARD VIBRATION - Y - VERT N/A N/A V9050A 2B MFP INBOARD VIBRATION - X - HOR N/A N/A V9051A 2B MFP INBOARD VIBRATION - Y - VERT N/A N/A V9052A 2B MFP OUTBOARD VIBRATION - X - HOR N/A N/A V9053A 2B MFP OUTBOARD VIBRATION - Y - VERT N/A N/A V9054A 2B MFP THRUST - A N/A N/A V9055A 2B MFP THRUST - B N/A N/A V9056A 2A MFPT OUTBOARD VIBRATION - X - HOR N/A N/A V9057A 2A MFP KEYPHASOR N/A N/A V9058A 2A MFPT OUTBOARD VIBRATION - Y - VERT N/A N/A V9059A 2A MFPT THRUST - A N/A N/A V9060A 2A MFPT THRUST - B N/A N/A V9061A 2A MFPT INBOARD VIBRATION - X - HOR N/A N/A V9062A 2A MFPT INBOARD VIBRATION - Y - VERT N/A N/A V9063A 2B MFPT OUTBOARD VIBRATION - X - HOR N/A N/A V9064A 2B MFP KEYPHASOR N/A N/A V9065A 2B MFPT OUTBOARD VIBRATION - Y - VERT N/A N/A V9066A 2B MFPT THRUST - A N/A N/A.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 311 of 371 Table 1 (Page 5 of 5)

COMPUTER POINT VERIFICATION LOG Date COMPUTER DESCRIPTION STATUS INITIAL/DATE POINT SET RESET V9067A 2B MFPT THRUST - B N/A N/A V9068A 2B MFPT INBOARD VIBRATION - X - HOR N/A N/A V9069A 2B MFPT INBOARD VIBRATION - Y - VERT N/A N/A

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 312 of 371 Table 2 (Page 1 of 3)

M&TE HOOKUP LOCATIONS Date

[1] SMFP suction pressure gage installed on the calibration tap of 2-PT-2-273, STANDBY MAIN FW PUMP SUCTION HDR PRESS, (729/T16-J). (Subsection 6.32)

M&TE ID#

CV

[2] SMFP discharge pressure gage installed on the calibration tap of 2-PI-3-203B, STANDBY MAIN FW PMP DISCH PRESSURE, (729/T1I6-J). (Subsection 6.32)

M&TE ID#

CV

[3] SMFP 4" RECIRC flow ultrasonic flowmeter installed on the recirc line upstream of Valve 2-FCV-3-208, STANDBY MAIN FEEDWATER PUMP MIN FLOW, (729/T16-J).

(Subsection 6.32)

M&TE ID#

CV

[4] MFPT 2A suction pressure gage installed on the calibration tap of 2-PI-2-207, MAIN FEEDWATER PUMP 2A SUCTION PRESS, (729/T16-H). (Subsection 6.34)

M&TE ID#

CV

[5] MFPT 2A discharge pressure gage installed on the calibration tap of 2-PI-3-66B, MAIN FEEDWATER PUMP A DISCHARGE PRESSURE, (729/TI6-H). (Subsection 6.34)

M&TE ID#

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 313 of 371 Table 2 (Page 2 of 3)

M&TE HOOKUP LOCATIONS Date

[6] MFPT 2A 8" RECIRC flow ultrasonic flowmeter installed on the recirc line upstream of Valve 2-FCV-3-70, MAIN FEEDWATER PUMP A RECIRC, (729/TI'5-H). (Subsection 6.34)

M&TE ID#

CV

[7] MFPT 2B 8" RECIRC flow ultrasonic flowmeter installed on the recirc line upstream of Valve 2-FCV-3-84, MAIN FEEDWATER PUMP B RECIRC, (729/T15-G). (Subsection 6.36)

M&TE ID#

CV

[8] MFPT 2B suction pressure gage installed on the calibration tap of 2-PI-2-213, MAIN FEEDWATER PUMP 2B SUCTION PRESS, (729/TI'6-G). (Subsection 6.36)

M&TE ID#

CV

[9] MFPT 2B discharge pressure gage installed on the calibration tap of 2-PI-3-80B, FW PUMP B OUTLET PRESS IND, (729/T16-G). (Subsection 6.36)

M&TE ID#

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 314 of 371 Table 2 (Page 3 of 3)

M&TE HOOKUP LOCATIONS Date

[10] Install the three 0-200 PSIG gauges on the following points:

(Subsection 6.31)

A. Valve 2-54-574 (common injection water pump suction pressure)

M&TE ID#

CV B. Test Connection on 2-PI-54-9A (Injection Water Pump 2A discharge)

M&TE ID#

CV A. Test Connection on 2-PI-54-9B (Injection Water Pump 2B discharge)

M&TE ID#

CV

[11] Install the Ultrasonic flowmeter on the vertical section of the common pump discharge header. (Subsection 6.31)

M&TE ID#

CV

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 315 of 371 Table 3 (Page I of 1)

SMFP COMPUTER TRENDS NOTE Computer points listed are to be setup to update continuously throughout SMFP operation.

The plant computer has 10 blocks available for trend points with 16 points in each block.

Sufficient trend blocks need to be reserved and setup for trending during this instruction.

Initiate trending at 2 minute intervals beginning at initial start of operation. The printouts are to be provided to the Test Director upon completion.

COMPUTER POINT DESCRIPTION Q2828A STANDBY MAIN FW PMP ELECT PWR P2224A FEEDWATER PUMPS SUCTION HEADER P P2416A STANDBY MAIN FW PMP SUCTION P P2217A STANDBY MAIN FW PMP DISCH HDR P P2243A HOTWELL PUMPS SUCTION HEADER P P2244A HOTWELL PUMPS DISCH HEADER P F2264A HOTWELL PUMPS DISCH HDR F T2355A STANDBY MAIN FW PMP DISCH T T2263A FEEDWATER HEATER A2 OUTLET T T2264A FEEDWATER HEATER B2 OUTLET T T2265A FEEDWATER HEATER C2 OUTLET T T2450A STANDBY MAIN FW PMP THRUST BRG T T2451A STANDBY MAIN FW PMP OUTBRD BRG T T2452A STANDBY MAIN FW PMP INBRD BRG T T2455A STANDBY MAIN FW PMP PH AWDG T2456A STANDBY MAIN FW PMP PH B WDG T2457A STANDBY MAIN FW PMP PH C WDG T2458A STANDBY MAIN FWP SPD INC BRG T2459A STANDBY MAIN FWP SPD INC BRG

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 316 of 371 Data Sheet I (Page 1 of 2)

SMFP INITIAL PUMP RUN (Prior to Start)

Date INSTRUMENT NOMENCLATURE DATA INITIAL/DATE 2-TI-3-217 (2-L-517) SMFP CASE TEMP OF 2-TI-3-214 (Local) SMFP OIL TEMP OF 2-PI-3-213 -(Local) SMFPMP OIL PRESS PSIG 2-PI-3-203B (2-L-517) SMFP DISCH PRESS PSIG M&TE ID SMFP DISCH PRESS PSIG 2-PI-2-273 (2-L-517) SMFP SUCTION PRESS PSIG M&TE ID SMFP SUCTION PRESS PSIG M&TE ID SMFP DISCH RECIRC FLOW (Ultrasonic) GPM 2-PI-54-9A (2-L-69) INJECTION WATER PUMP 2A DISCHARGE PRESS PSIG 2-PI-54-9B (2-L-69) INJECTION WATER PUMP 2B DISCHARGE PRESS PSIG 2-PDIC-54-33 (2-L-490) SMFP SEAL WTR DIFF PRESS PSIG 2-PIC-54-35 (2-L-490) SMFP SEAL WTR PRESS PSIG

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 317 of 371 Data Sheet I (Page 2 of 2)

SMFP INITIAL PUMP RUN (Prior to Start)

Date INSTRUMENT NOMENCLATURE DATA INITIALIDATE 2-PI-2-34 (2-L-95) COND HOTWELL PUMP 2A DISCHARGE PRESS PSIG 2-PI-2-27 (2-L-95) COND HOTWELL PUMP 2B DISCHARGE PRESS PSIG 2-PI-2-21 (2-L-95) COND HOTWELL PUMP 2C DISCHARGE PRESS PSIG 2-TI-54-37 (Local) SMFP SEAL WTR OUTLET TEMP OF 2-TI-54-38 (Local) SMFP SEAL WTR OUTLET TEMP OF

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 318 of 371 Data Sheet 2 (Page 1 of 2)

SMFP RECIRC FLOW Date INSTRUMENT NOMENCLATURE DATA INITIAUDATE M&TE ID SMFP MOTOR SPEED RPM NO ID SMFP MTR AMPS (6900V-UNIT BD 2D, PNL 7) Amps NO ID SMFP 2BUS VOLTS (6900V-UNIT BD 2D, PNL 7) Volts 2-TI-3-217 (2-L-517) SMFP CASE TEMP OF 2-TI-3-214 (Local) SMFP OIL TEMP OF 2-PI-3-213 (Local) SMFPMP OIL PRESS PSIG 2-PI-3-203B (2-L-517) SMFP DISCH PRESS PSIG M&TEID SMFP SUCT PRESS PSIG M&TEID SMFP DISCH RECIRC FLOW (Ultrasonic) GPM 2-PI-54-9A (2-L-69) INJECTION WATER PUMP 2A DISCHARGE PRESS PSIG 2-PI-54-9B (2-L-69) INJECTION WATER PUMP 2B DISCHARGE PRESS PSIG 2-PDIC-54-33 (2-L-490) SMFP SEAL WTR DIFF PRESS PSIG

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 319 of 371 Data Sheet 2 (Page 2 of 2)

SMFP RECIRC FLOW Date INSTRUMENT NOMENCLATURE DATA INITIAL/DATE 2-PIC-54-35 (2-L-490) SMFP SEAL WTR PRESS PSIG 2-PI-2-34 (2-L-95) COND HOTWELL PUMP 2A DISCHARGE PRESS PSIG 2-PI-2-27 (2-L-95) COND HOTWELL PUMP 2B DISCHARGE PRESS PSIG 2-PI-2-21 (2-L-95) COND HOTWELL PUMP 2C DISCHARGE PRESS PSIG 2-TI-54-37 (Local) SMFP SEAL WTR OUTLET TEMP OF 2-TI-54-38 (Local) SMFP SEAL WTR OUTLET TEMP OF

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 320 of 371 Table 4 (Page I of 2)

MFPT 2A COMPUTER TRENDS NOTE Computer points listed are to be setup to update continuously throughout MFP operation.

Sufficient trend blocks need to be reserved and setup for trending during this instruction.

Initiate trending at 2-minute intervals beginning at initial start of operation. The printouts are to be provided to the Test Director upon completion. The electronic files are to be attached to this test.

COMPUTER POINT DESCRIPTION P2224A FEEDWATER PUMPS SUCTION HDR PRESS P2500A MAIN FW PUMP 2A SUCTION P P2214A MAIN FW PUMP 2A DISCH HDR P P2243A HOTWELL PUMPS SUCTION HDR PRESS P2244A HOTWELL PUMPS DISCH HDR PRESS F2264A HOTWELL PUMPS DISCH HDR FLOW T2460A FW PUMP A INBD BRG TEMP T2461A FW PUMP A OUTBD BRG TEMP T2462A FW PUMP A THRUST BRG TEMP T2362A MAIN FW PUMP A DISCHARGE TEMP T2263A FEEDWATER HEATER A2 OUTLET TEMP T2264A FEEDWATER HEATER B2 OUTLET TEMP T2265A FEEDWATER HEATER C2 OUTLET TEMP T3106A MFPT 2A REV TH DIR BRG PAD TEMP T3107A MFPT 2A NORM TH DIR BRG PAD TEMP T3170A MFPT 2A OIL COOLER INLET T3171A MFPT 2A OIL NO. 1 BRG DRAIN T3172A MFPT 2A OIL NO. 2 BRG DRAIN T3173A MFPT 2A OIL THRUST BRG DRAIN T3178A MFPT 2A HI PRESS STOP VALVE TEMP V9044A 2A MFP INBOARD VIBRATION - X - HOR V9045A 2A MFP INBOARD VIBRATION - Y - VERT

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 321 of 371 Table 4 (Page 2 of 2)

MFPT 2A COMPUTER TRENDS COMPUTER POINT DESCRIPTION V9046A 2A MFP THRUST - A V9047A 2A MFP THRUST - B V9048A 2A MFP OUTBOARD VIBRATION - X - HOR V9049A 2A MFP OUTBOARD VIBRATION - Y - VERT V9056A 2A MFPT OUTBOARD VIBRATION - X - HOR V9057A 2A MFP KEYPHASOR V9058A 2A MFPT OUTBOARD VIBRATION - Y - VERT V9059A 2A MFPT THRUST - A V9060A 2A MFPT THRUST - B V9061A 2A MFPT INBOARD VIBRATION - X - HOR V9062A 2A MFPT INBOARD VIBRATION - Y - VERT

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 322 of 371 Data Sheet 3 (Page 1 of 2)

MFPT 2A INITIAL PUMP DATA (Prior to Start) (Uncoupled)

Date INSTRUMENT NOMENCLATURE DATA INITIALIDATE M&TE ID MFPT 2A SPEED RPM 2-SI-46-20D (2-L-275) MFPT 2A SPEED RPM 2-PI-46-4 (2-L-275) MFPT 2A BRG OIL PRESS PSIG 2-PI-46-19A (2-L-275) MFPT 2A HP OIL FLTR INLET PSIG 2-PI-46-19B (2-L-275) MFPT 2A HP OIL FLTR OUTLET PSIG 2-TIS-46-59 (2-L-275) MFPT 2A OIL DISCH TEMP ALM OF 2-TIS-46-61 (2-L-275) MFPT 2A NO. 1 BRG OIL TEMP ALM OF 2-TIS-46-63 (2-L-275) MFPT 2A NO. 2 BRG OIL TEMP ALM OF 2-TIS-46-65 (2-L-275) MFPT 2A THRUST BRG OIL TEMP ALM OF 2-IPI-46-5001 (2-L-275) HAND SPEED CHANGER PRESS MFPT 2A (0-160 PSIG) PSIG 2-IPI-46-5002 (2-L-275) E. H. OUT PRESS MFPT 2A (0-200 PSIG) PSIG 2-IPI-46-5003 (2-L-275) GOV. VALVE POSITION PRESS MFPT 2A (0-100 PSIG) PSIG

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 323 of 371 Data Sheet 3 (Page 2 of 2)

MFPT 2A INITIAL PUMP DATA (Prior to Start) (Uncoupled)

Date INSTRUMENT NOMENCLATURE DATA INITIAL/DATE 2-IPI-46-5004 (2-L-275) SPEED GOVERNOR PRESS MFPT 2A (0-160 PSIG) PSIG 2-1PI-46-5005 (2-L-275) CONTROL OIL PRESS MFPT 2A (0-100 PSIG) PSIG 2-TI-24-56A (2-L-258) RCW DISCH FWP TURB OIL COOLERS A OF

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 324 of 371 Data Sheet 4 (Page 1 of 2)

MFPT 2A @ 900 RPM (Uncoupled)

Date INSTRUMENT NOMENCLATURE DATA INITIAL/DATE M&TE ID MFPT 2A SPEED RPM 2-SI-46-20D (2-L-275) MFPT 2A SPEED RPM 2-PI-46-4 (2-L-275) MFPT 2A BRG OIL PRESS PSIG 2-PI-46-19A (2-L-275) MFPT 2A HP OIL FLTR INLET PSIG 2-PI-46-19B (2-L-275) MFPT 2A HP OIL FLTR OUTLET PSIG 2-TIS-46-59 (2-L-275) MFPT 2A OIL DISCH TEMP ALM OF 2-TIS-46-61 (2-L-275) MFPT 2A NO. 1 BRG OIL TEMP ALM OF 2-TIS-46-63 (2-L-275) MFPT 2A NO. 2 BRG OIL TEMP ALM OF 2-TIS-46-65 (2-L-275) MFPT 2A THRUST BRG OIL TEMP ALM OF 2-IPI-46-5001 (2-L-275) HAND SPEED CHANGER PRESS MFPT 2A (0-160 PSIG) PSIG 2-IPI-46-5002 (2-L-275) E. H. OUT PRESS MFPT 2A (0-200 PSIG) PSIG 2-IPI-46-5003 (2-L-275) GOV. VALVE POSITION PRESS MFPT 2A (0-100 PSIG) PSIG

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 325 of 371 Data Sheet 4 (Page 2 of 2)

MFPT 2A @ 900 RPM (Uncoupled)

Date INSTRUMENT NOMENCLATURE DATA INITIAL/DATE 2-IPI-46-5004 (2-L-275) SPEED GOVERNOR PRESS MFPT 2A (0-160 PSIG) PSIG 2-IPI-46-5005 (2-L-275) CONTROL OIL PRESS MFPT 2A (0-100 PSIG) PSIG 2-TI-24-56A (2-L-258) RCW DISCH FWP TURB OIL COOLERS A OF

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 326 of 371 Data Sheet 5 (Page 1 of 2)

MFPT 2A @ 1800 rpm (Uncoupled)

Date INSTRUMENT NOM ENCLATURE DATA INITIAL/DATE M&TE ID MFPT 2A SPEED RPM 2-SI-46-20D (2-L-275) MFPT 2A SPEED RPM 2-PI-46-4 (2-L-275) MFPT 2A BRG OIL PRESS PSIG 2-PI-46-19A (2-L-275) MFPT 2A HP OIL FLTR INLET PSIG 2-PI-46-19B (2-L-275) MFPT 2A HP OIL FLTR OUTLET PSIG 2-TIS-46-59 (2-L-275) MFPT 2A OIL DISCH TEMP ALM OF 2-TIS-46-61 (2-L-275) MFPT 2A NO. I BRG OIL TEMP ALM OF 2-TIS-46-63 (2-L-275) MFPT 2A NO. 2 BRG OIL TEMP ALM OF 2-TIS-46-65 (2-L-275) MFPT 2A THRUST BRG OIL TEMP ALM OF 2-IPI-46-5001 (2-L-275) HAND SPEED CHANGER PRESS MFPT 2A (0-160 PSIG) PSIG 2-IPI-46-5002 (2-L-275) E. H. OUT PRESS MFPT 2A (0-200 PSIG) PSIG 2-IPI-46-5003 (2-L-275) GOV. VALVE POSITION PRESS MFPT 2A (0-100 PSIG) PSIG

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 327 of 371 Data Sheet 5 (Page 2 of 2)

MFPT 2A @ 1800 rpm (Uncoupled)

Date INSTRUMENT NOMENCLATURE DATA INITIAL/DATE 2-IPI-46-5004 (2-L-275) SPEED GOVERNOR PRESS MFPT 2A (0-160 PSIG) PSIG 2-1PI-46-5005 (2-L-275) CONTROL OIL PRESS MFPT 2A (0-100 PSIG) PSIG 2-TI-24-56A (2-L-258) RCW DISCH FWP TURB OIL COOLERS A OF

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 328 of 371 Data Sheet 6 (Page 1 of 2)

MFPT 2A @ 2700 RPM (Uncoupled)

Date INSTRUMENT NOMENCLATURE DATA INITIALIDATE M&TE ID MFPT 2A SPEED RPM 2-SI-46-20D (2-L-275) MFPT 2A SPEED RPM 2-PI-46-4 (2-L-275) MFPT 2A BRG OIL PRESS PSIG 2-PI-46-19A (2-L-275) MFPT 2A HP OIL FLTR INLET PSIG 2-PI-46-19B (2-L-275) MFPT 2A HP OIL FLTR OUTLET PSIG 2-TIS-46-59 (2-L-275) MFPT 2A OIL DISCH TEMP ALM OF 2-TIS-46-61 (2-L-275) MFPT 2A NO. 1 BRG OIL TEMP ALM OF 2-TIS-46-63 (2-L-275) MFPT 2A NO. 2 BRG OIL TEMP ALM OF 2-TIS-46-65 (2-L-275) MFPT 2A THRUST BRG OIL TEMP ALM OF 2-IPI-46-5001 (2-L-275) HAND SPEED CHANGER PRESS MFPT 2A (0-160 PSIG) PSIG 2-IPI-46-5002 (2-L-275) E. H. OUT PRESS MFPT 2A (0-200 PSIG) PSIG 2-IPI-46-5003 (2-L-275) GOV. VALVE POSITION PRESS MFPT 2A (0-100 PSIG) PSIG

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 329 of 371 Data Sheet 6 (Page 2 of 2)

MFPT 2A @ 2700 RPM (Uncoupled)

Date INSTRUMENT NOMENCLATURE DATA INITIAL/DATE 2-IPI-46-5004 (2-L-275) SPEED GOVERNOR PRESS MFPT 2A (0-160 PSIG) PSIG 2-IPI-46-5005 (2-L-275) CONTROL OIL PRESS MFPT 2A (0-100 PSIG) PSIG 2-TI-24-56A (2-L-258) RCW DISCH FWP TURB OIL COOLERS A OF

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 330 of 371 Data Sheet 7 (Page 1 of 2)

MFPT 2A @ 3300 RPM (Uncoupled)

Date INSTRUMENT NOMENCLATURE DATA INITIAL/DATE M&TEID MFPT 2A SPEED RPM 2-SI-46-20D (2-L-275) MFPT 2A SPEED RPM 2-PI-46-4 (2-L-275) MFPT 2A BRG OIL PRESS PSIG 2-PI-46-19A (2-L-275) MFPT 2A HP OIL FLTR INLET PSIG 2-PI-46-19B (2-L-275) MFPT 2A HP OIL FLTR OUTLET PSIG 2-TIS-46-59 (2-L-275) MFPT 2A OIL DISCH TEMP ALM OF 2-TIS-46-61 (2-L-275) MFPT 2A NO. 1 BRG OIL TEMP ALM OF 2-TIS-46-63 (2-L-275) MFPT 2A NO. 2 BRG OIL TEMP ALM OF 2-TIS-46-65 (2-L-275) MFPT 2A THRUST BRG OIL TEMP ALM OF 2-1PI-46-5001 (2-L-275) HAND SPEED CHANGER PRESS MFPT 2A (0-160 PSIG) PSIG 2-1PI-46-5002 (2-L-275) E. H. OUT PRESS MFPT 2A (0-200 PSIG) PSIG 2-1PI-46-5003 (2-L-275) GOV. VALVE POSITION PRESS MFPT 2A (0-100 PSIG) PSIG

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 331 of 371 Data Sheet 7 (Page 2 of 2)

MFPT 2A @ 3300 RPM (Uncoupled)

Date INSTRUMENT NOMENCLATURE DATA INITIAL/DATE 2-1PI-46-5004 (2-L-275) SPEED GOVERNOR PRESS MFPT 2A (0-160 PSIG) PSIG 2-1PI-46-5005 (2-L-275) CONTROL OIL PRESS MFPT 2A (0-100 PSIG) PSIG 2-TI-24-56A (2-L-258) RCW DISCH FWP TURB OIL COOLERS A OF

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 332 of 371 Data Sheet 8 (Page 1 of 2)

MFPT 2A @ 4500 RPM (Uncoupled)

Date INSTRUMENT NOMENCLATURE DATA INITIAL/DATE M&TE ID MFPT 2A SPEED RPM 2-SI-46-20D (2-L-275) MFPT 2A SPEED RPM 2-PI-46-4 (2-L-275) MFPT 2A BRG OIL PRESS PSIG 2-PI-46-19A (2-L-275) MFPT 2A HP OIL FLTR INLET PSIG 2-PI-46-19B (2-L-275) MFPT 2A HP OIL FLTR OUTLET PSIG 2-TIS-46-59 (2-L-275) MFPT 2A OIL DISCH TEMP ALM OF 2-TIS-46-61 (2-L-275) MFPT 2A NO. 1 BRG OIL TEMP ALM OF 2-TIS-46-63 (2-L-275) MFPT 2A NO. 2 BRG OIL TEMP ALM OF 2-TIS-46-65 (2-L-275) MFPT 2A THRUST BRG OIL TEMP ALM OF 2-IPI-46-5001 (2-L-275) HAND SPEED CHANGER PRESS MFPT 2A (0-160 PSIG) PSIG 2-IPI-46-5002 (2-L-275) E. H. OUT PRESS MFPT 2A (0-200 PSIG) PSIG 2-IPI-46-5003 (2-L-275) GOV. VALVE POSITION PRESS MFPT 2A (0-100 PSIG) PSIG

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 333 of 371 Data Sheet 8 (Page 2 of 2)

MFPT 2A @ 4500 RPM (Uncoupled)

Date INSTRUMENT NOMENCLATURE DATA INITIAL/DATE 2-IPI-46-5004 (2-L-275) SPEED GOVERNOR PRESS MFPT 2A (0-160 PSIG) PSIG 2-IPI-46-5005 (2-L-275) CONTROL OIL PRESS MFPT 2A (0-100 PSIG) PSIG 2-Ti-24-56A (2-L-258) RCW DISCH FWP TURB OIL COOLERS A OF J. .1. _________________ _______________

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 334 of 371 Data Sheet 9 (Page I of 2)

MFPT 2A @ 5000 RPM (Uncoupled)

Date INSTRUMENT NOMENCLATURE DATA INITIALIDATE M&TE ID MFPT 2A SPEED RPM 2-SI-46-20D (2-L-275) MFPT 2A SPEED RPM 2-PI-46-4 (2-L-275) MFPT 2A BRG OIL PRESS PSIG 2-PI-46-19A (2-L-275) MFPT 2A HP OIL FLTR INLET PSIG 2-PI-46-19B (2-L-275) MFPT 2A HP OIL FLTR OUTLET PSIG 2-TIS-46-59 (2-L-275) MFPT 2A OIL DISCH TEMP ALM oF 2-TIS-46-61 (2-L-275) MFPT 2A NO. 1 BRG OIL TEMP ALM OF 2-TIS-46-63 (2-L-275) MFPT 2A NO. 2 BRG OIL TEMP ALM OF 2-TIS-46-65 (2-L-275) MFPT 2A THRUST BRG OIL TEMP ALM OF 2-IPI-46-5001 (2-L-275) HAND SPEED CHANGER PRESS MFPT 2A (0-160 PSIG) PSIG 2-1PI-46-5002 (2-L-275) E. H. OUT PRESS MFPT 2A (0-200 PSIG) PSIG 2-IPI-46-5003 (2-L-275) GOV. VALVE POSITION PRESS MFPT 2A (0-100 PSIG) PSIG

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 335 of 371 Data Sheet 9 (Page 2 of 2)

MFPT 2A @ 5000 RPM (Uncoupled)

Date INSTRUMENT NOMENCLATURE DATA INITIAL/DATE 2-1PI-46-5004 (2-L-275) SPEED GOVERNOR PRESS MFPT 2A (0-160 PSIG) PSIG 2-1PI-46-5005 (2-L-275) CONTROL OIL PRESS MFPT 2A (0-100 PSIG) PSIG 2-TI-24-56A (2-L-258) RCW DISCH FWP TURB OIL COOLERS A OF

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 336 of 371 Data Sheet 10 (Page I of 2)

MFPT 2A @ 5625 RPM (Uncoupled)

Date INSTRUMENT NOMENCLATURE DATA INITIAL/DATE M&TEID MFPT 2A SPEED RPM 2-SI-46-20D (2-L-275) MFPT 2A SPEED RPM 2-PI-46-4 (2-L-275) MFPT 2A BRG OIL PRESS PSIG 2-PI-46-19A (2-L-275) MFPT 2A HP OIL FLTR INLET PSIG 2-PI-46-19B (2-L-275) MFPT 2A HP OIL FLTR OUTLET PSIG 2-TIS-46-59 (2-L-275) MFPT 2A OIL DISCH TEMP ALM OF 2-TIS-46-61 (2-L-275) MFPT 2A NO. 1 BRG OIL TEMP ALM OF 2-TIS-46-63 (2-L-275) MFPT 2A NO. 2 BRG OIL TEMP ALM OF 2-TIS-46-65 (2-L-275) MFPT 2A THRUST BRG OIL TEMP ALM OF 2-1PI-46-5001 (2-L-275) HAND SPEED CHANGER PRESS MFPT 2A (0-160 PSIG) PSIG 2-1PI-46-5002 (2-L-275) E. H. OUT PRESS MFPT 2A (0-200 PSIG) PSIG 2-IPI-46-5003 (2-L-275) GOV. VALVE POSITION PRESS MFPT 2A (0-100 PSIG) PSIG

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 337 of 371 Data Sheet 10 (Page 2 of 2)

MFPT 2A @ 5625 RPM (Uncoupled)

Date INSTRUMENT NOMENCLATURE DATA INITIAL/DATE 2-IPI-46-5004 (2-L-275) SPEED GOVERNOR PRESS MFPT 2A (0-160 PSIG) PSIG 2-IPI-46-5005 (2-L-275) CONTROL OIL PRESS MFPT 2A (0-100 PSIG) PSIG 2-TI-24-56A (2-L-258) RCW DISCH FWP TURB OIL COOLERS A OF

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 338 of 371 Data Sheet 11 (Page I of 3)

MFP 2A INITIAL PUMP DATA (Prior to Start) (Coupled)

Date INSTRUMENT NOMENCLATURE DATA INITIALIDATE M&TEID MFPT 2A SPEED RPM 2-SI-46-20D (2-L-275) MFPT 2A SPEED RPM 2-PI-46-4 (2-L-275) MFPT 2A BRG OIL PRESS PSIG 2-PI-46-19A (2-L-275) MFPT 2A HP OIL FLTR INLET PSIG 2-PI-46-19B (2-L-275) MFPT 2A HP OIL FLTR OUTLET PSIG 2-TIS-46-59 (2-L-275) MFPT 2A OIL DISCH TEMP ALM OF 2-TIS-46-61 (2-L-275) MFPT 2A NO. I BRG OIL TEMP ALM OF 2-TIS-46-63 (2-L-275) MFPT 2A NO. 2 BRG OIL TEMP ALM OF 2-TIS-46-65 (2-L-275) MFPT 2A THRUST BRG OIL TEMP ALM OF 2-IPI-46-5001 (2-L-275) HAND SPEED CHANGER PRESS MFPT 2A (0-160 PSIG) PSIG 2-1PI-46-5002 (2-L-275) E. H. OUT PRESS MFPT 2A (0-200 PSIG) PSIG 2-IP1-46-5003 (2-L-275) GOV. VALVE POSITION PRESS MFPT 2A (0-100 PSIG) PSIG

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 339 of 371 Data Sheet 11 (Page 2 of 3)

MFP 2A INITIAL PUMP DATA (Prior to Start) (Coupled)

Date INSTRUMENT NOMENCLATURE DATA INITIAL/DATE 2-IPI-46-5004 (2-L-275) SPEED GOVERNOR PRESS MFPT 2A (0-160 PSIG) PSIG 2-IPI-46-5005 (2-L-275) CONTROL OIL PRESS MFPT 2A (0-100 PSIG) PSIG 2-TI-24-56A (2-L-258) RCW DISCH FWP TURB OIL COOLERS A OF 2-TI-3-71A (Local) MFP 2A INBOARD BRG OIL DRAIN TEMP OF 2-PI-3-73A (Local) MFP 2A BRG OIL PRESS PSIG 2-TI-3-71B (Local) MFP 2A OUTBOARD BRG OIL DRAIN TEMP OF 2-PI-3-73B (Local) MFP 2A BRG OIL PRESS PSIG 2-TI-3-71 D (Local) MFP 2A THRUST BRG OIL DRAIN TEMP OF 2-TI-3-57 (2-L-33) MAIN FEEDWATER PUMP A CASING TEMP OF 2-PI-2-207 (2-L-33) MAIN FEEDWATER PUMP 2A SUCTION PRESS PSIG 2-PI-3-66B (2-L-33) MAIN FEEDWATER PUMP A DISCHARGE PRESS PSIG

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 340 of 371 Data Sheet 11 (Page 3 of 3)

MFP 2A INITIAL PUMP DATA (Prior to Start) (Coupled)

Date INSTRUMENT NOMENCLATURE DATA INITIALIDATE M&TE ID MFPT 2A DISCH RECIRC FLOW (Ultrasonic) GPM 2-PI-54-9A (2-L-69) INJECTION WATER PUMP 2A DISCHARGE PRESS PSIG 2-PI-54-9B (2-L-69) INJECTION WATER PUMP 2B DISCHARGE PRESS PSIG 2-PDIC-54-1 (2-L-33) MAIN FEEDWATER PUMP 2A SEAL WTR DIFF PRESS PSIG 2-PIC-54-2 (2-L-33) MAIN FEEDWATER PUMP 2A SEAL WTR PRESS PSIG 2-FR-2-35 (2-M-3) GLAND SEAL EXH RECIRC FLOW GPM 2-PI-2-34 (2-L-95) COND HOTWELL PUMP 2A DISCHARGE PRESS PSIG 2-PI-2-27 (2-L-95) COND HOTWELL PUMP 2B DISCHARGE PRESS PSIG 2-PI-2-21 (2-L-95) COND HOTWELL PUMP 2C DISCHARGE PRESS PSIG M&TE ID MFP 2A SUCTION PRESS PSIG M&TE ID MFP 2A DISCHARGE PRESS PSIG

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 341 of 371 Data Sheet 12 (Page I of 3)

MFP 2A RECIRC FLOW AT 2650 GPM (Coupled)

Date INSTRUMENT NOMENCLATURE DATA INITIALIDATE M&TE ID MFPT 2A SPEED RPM 2-SI-46-20D (2-L-275) MFPT 2A SPEED RPM 2-PI-46-4 (2-L-275) MFPT 2A BRG OIL PRESS PSIG 2-PI-46-19A (2-L-275) MFPT 2A HP OIL FLTR INLET PSIG 2-PI-46-19B (2-L-275) MFPT 2A HP OIL FLTR OUTLET PSIG 2-TIS-46-59 (2-L-275) MFPT 2A OIL DISCH TEMP ALM OF 2-TIS-46-61 (2-L-275) MFPT 2A NO. 1 BRG OIL TEMP ALM OF 2-TIS-46-63 (2-L-275) MFPT 2A NO. 2 BRG OIL TEMP ALM OF 2-TIS-46-65 (2-L-275) MFPT 2A THRUST BRG OIL TEMP ALM OF 2-IPI-46-5001 (2-L-275) HAND SPEED CHANGER PRESS MFPT 2A (0-160 PSIG) PSIG 2-IPI-46-5002 (2-L-275) E. H. OUT PRESS MFPT 2A (0-200 PSIG) PSIG 2-IPI-46-5003 (2-L-275) GOV. VALVE POSITION PRESS MFPT 2A (0-100 PSIG) PSIG

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 342 of 371 Data Sheet 12 (Page 2 of 3)

MFP 2A RECIRC FLOW AT 2650 GPM (Coupled)

Date INSTRUMENT NOMENCLATURE DATA INITIAL/DATE 2-IPI-46-5004 (2-L-275) SPEED GOVERNOR PRESS MFPT 2A (0-160 PSIG) PSIG 2-IPI-46-5005 (2-L-275) CONTROL OIL PRESS MFPT 2A (0-100 PSIG) PSIG 2-TI-24-56A (2-L-258) RCW DISCH FWP TURB OIL COOLERS A OF 2-TI-3-71A (Local) MFP 2A INBOARD BRG OIL DRAIN TEMP OF 2-PI-3-73A (Local) MFP 2A BRG OIL PRESS PSIG 2-TI-3-71B (Local) MFP 2A OUTBOARD BRG OIL DRAIN TEMP OF 2-PI-3-73B (Local) MFP 2A BRG OIL PRESS PSIG 2-TI-3-71D (Local) MFP 2A THRUST BRG OIL DRAIN TEMP OF 2-TI-3-57 (2-L-33) MAIN FEEDWATER PUMP A CASING TEMP OF 2-PI-2-207 (2-L-33) MAIN FEEDWATER PUMP 2A SUCTION PRESS PSIG 2-PI-3-66B (2-L-33) MAIN FEEDWATER PUMP A DISCHARGE PRESS PSIG

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 343 of 371 Data Sheet 12 (Page 3 of 3)

MFP 2A RECIRC FLOW AT 2650 GPM (Coupled)

Date INSTRUMENT NOMENCLATURE DATA INITIAL/DATE M&TE ID MFPT 2A DISCH RECIRC FLOW (Ultrasonic) GPM 2-PI-54-9A (2-L-69) INJECTION WATER PUMP 2A DISCHARGE PRESS PSIG 2-PI-54-9B (2-L-69) INJECTION WATER PUMP 2B DISCHARGE PRESS PSIG 2-PDIC-54-1 (2-L-33) MAIN FEEDWATER PUMP 2A SEAL WTR DIFF PRESS PSIG 2-PIC-54-2 (2-L-33) MAIN FEEDWATER PUMP 2A SEAL WTR PRESS PSIG 2-FR-2-35 (2-M-3) GLAND SEAL EXH RECIRC FLOW GPM 2-PI-2-34 (2-L-95) COND HOTWELL PUMP 2A DISCHARGE PRESS PSIG 2-PI-2-27 (2-L-95) COND HOTWELL PUMP 2B DISCHARGE PRESS PSIG 2-PI-2-21 (2-L-95) COND HOTWELL PUMP 2C DISCHARGE PRESS PSIG M&TE ID MFP 2A SUCTION PRESS PSIG M&TE ID MFP 2A DISCHARGE PRESS PSIG

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 344 of 371 Table 5 (Page I of 2)

MFPT 2B COMPUTER TRENDS NOTE Computer points listed are to be setup to update continuously throughout MFP operation.

Sufficient trend blocks need to be reserved and setup for trending during this instruction.

Initiate trending at 2-minute intervals beginning at initial start of operation. The printouts are to be provided to the Test Director upon completion. The electronic files are to be attached to this test.

COMPUTER POINT DESCRIPTION P2224A FEEDWATER PUMPS SUCTION HEADER P P2501A MAIN FW PUMP 2B SUCTION P P2215A MAIN FW PUMP 2B DISCH HDR P P2243A HOTWELL PUMPS SUCTION HDR PRESS P2244A HOTWELL PUMPS DISCH HDR PRESS F2264A HOTWELL PUMPS DISCH HDR FLOW T2463A FW PUMP B INBD BRG T T2464A FW PUMP B OUTBD BRG T T2465A FW PUMP B THRUST BRG T T2362A MAIN FW PUMP A DISCHARGE TEMP T2263A FEEDWATER HEATER A2 OUTLET TEMP T2264A FEEDWATER HEATER B2 OUTLET TEMP T2265A FEEDWATER HEATER C2 OUTLET TEMP T3108A MFPT 2B REV TH DIR BRG PAD T T3109A MFPT 2B NORM TH DIR BRG PAD T T3174A MFPT 2B OIL COOLER INLET T3175A MFPT 2B OIL NO. 1 BRG DRAIN T3176A MFPT 2B OIL NO. 2 BRG DRAIN T3177A MFPT 2B OIL THRUST BRG DRAIN T3179A MFPT 2B HI PRESS STOP VALVE TEMP V9050A 2B MFP INBOARD VIBRATION - X - HOR V9051A 2B MFP INBOARD VIBRATION - Y - VERT

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 345 of 371 Table 5 (Page 2 of 2)

MFPT 2B COMPUTER TRENDS COMPUTER POINT DESCRIPTION V9052A 2B MFP OUTBOARD VIBRATION - X - HOR V9053A 2B MFP OUTBOARD VIBRATION - Y - VERT V9054A 2B MFP THRUST - A V9055A 2B MFP THRUST - B V9063A 28 MFPT OUTBOARD VIBRATION - X - HOR V9064A 2B MFP KEYPHASOR V9065A 2B MFPT OUTBOARD VIBRATION - Y - VERT V9066A 2B MFPT THRUST - A V9067A 2B MFPT THRUST - B V9068A. 2B MFPT INBOARD VIBRATION - X - HOR V9069A 2B MFPT INBOARD VIBRATION - Y - VERT

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 346 of 371 Data Sheet 13 (Page 1 of 2)

MFPT 2B INITIAL PUMP DATA (Prior to Start) (Uncoupled)

Date INSTRUMENT NOMENCLATURE DATA INITIAL/DATE M&TE ID MFPT 2B SPEED RPM 2-SI-46-20E (2-L-276) MFPT 2B SPEED RPM 2-PI-46-31 (2-L-276) MFPT 2B BRG OIL PRESS PSIG 2-PI-46-52A (2-L-276) MFPT 2B HP OIL FLTR INLET PSIG 2-PI-46-52B (2-L-276) MFPT 2B HP OIL FLTR OUTLET PSIG 2-TIS-46-60 (2-L-276) MFPT 2B OIL DISCH TEMP ALM OF 2-TIS-46-62 (2-L-276) MFPT 2B NO. 1 BRG OIL TEMP ALM OF 2-TIS-46-64 (2-L-276) MFPT 2B NO. 2 BRG OIL TEMP ALM OF 2-TIS-46-66 (2-L-276) MFPT 2B THRUST BRG OIL TEMP ALM OF 2-IPI-46-5006 (2-L-276) HAND SPEED CHANGER PRESS MFPT 2B (0-160 PSIG) PSIG 2-IPI-46-5007 (2-L-276) E. H. OUT PRESS MFPT 2B (0-200 PSIG) PSIG 2-1PI-46-5008 (2-L-276) GOV. VALVE POSITION PRESS MFPT 2B (0-100 PSIG) PSIG

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000

. Page 347 of 371 Data Sheet 13 (Page 2 of 2)

MFPT 2B INITIAL PUMP DATA (Prior to Start) (Uncoupled)

Date INSTRUMENT NOMENCLATURE DATA INITIAL/DATE 2-IPI-46-5009 (2-L-276) SPEED GOVERNOR PRESS MFPT 2B (0-160 PSIG) PSIG 2-IPI-46-5010 (2-L-276) CONTROL OIL PRESS MFPT 2B (0-100 PSIG) PSIG 2-TI-24-56B (2-L-258) RCW DISCH FWP TURB OIL COOLERS B OF

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 348 of 371 Data Sheet 14 (Page 1 of 2)

MFPT 2B @ 900 RPM (Uncoupled)

Date INSTRUMENT NOMENCLATURE DATA INITIAL/DATE M&TE ID MFPT 2B SPEED RPM 2-SI-46-20E (2-L-276) MFPT 2B SPEED RPM 2-PI-46-31 (2-L-276) MFPT 2B BRG OIL PRESS PSIG 2-PI-46-52A (2-L-276) MFPT 2B HP OIL FLTR INLET PSIG 2-PI-46-52B (2-L-276) MFPT 2B HP OIL FLTR OUTLET PSIG 2-TIS-46-60 (2-L-276) MFPT 2B OIL DISCH TEMP ALM OF 2-TIS-46-62 (2-L-276) MFPT 2B NO. 1 BRG OIL TEMP ALM OF 2-TIS-46-64 (2-L-276) MFPT 2B NO. 2 BRG OIL TEMP ALM OF 2-TIS-46-66 (2-L-276) MFPT 2B THRUST BRG OIL TEMP ALM OF 2-IPI-46-5006 (2-L-276) HAND SPEED CHANGER PRESS MFPT 2B (0-160 PSIG) PSIG 2-IPI-46-5007 (2-L-276) E. H. OUT PRESS MFPT 2B (0-200 PSIG) PSIG 2-IPI-46-5008 (2-L-276) GOV. VALVE POSITION PRESS MFPT 2B (0-100 PSIG) PSIG

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 349 of 371 Data Sheet 14 (Page 2 of 2)

MFPT 2B @ 900 RPM (Uncoupled)

Date INSTRUMENT NOMENCLATURE DATA INITIAL/DATE 2-IPI-46-5009 (2-L-276) SPEED GOVERNOR PRESS MFPT 2B (0-160 PSIG) PSIG 2-IPI-46-5010 (2-L-276) CONTROL OIL PRESS MFPT 2B (0-100 PSIG) PSIG 2-TI-24-56B (2-L-258) RCW DISCH FWP TURB OIL COOLERS B OF

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 350 of 371 Data Sheet 15 (Page 1 of 2)

MFPT 2B @ 1800 RPM (Uncoupled)

Date INSTRUMENT NOMENCLATURE DATA INITIAL/DATE M&TE ID MFPT 2B SPEED RPM 2-SI-46-20E (2-L-276) MFPT 2B SPEED RPM 2-PI-46-31 (2-L-276) MFPT 2B BRG OIL PRESS PSIG 2-PI-46-52A (2-L-276) MFPT 2B HP OIL FLTR INLET PSIG 2-PI-46-52B (2-L-276) MFPT 2B HP OIL FLTR OUTLET PSIG 2-TIS-46-60 (2-L-276) MFPT 2B OIL DISCH TEMP ALM OF 2-TIS-46-62 (2-L-276) MFPT 2B NO. 1 BRG OIL TEMP ALM OF 2-TIS-46-64 (2-L-276) MFPT 2B NO. 2 BRG OIL TEMP ALM OF 2-TIS-46-66 (2-L-276) MFPT 2B THRUST BRG OIL TEMP ALM OF 2-IPI-46-5006 (2-L-276) HAND SPEED CHANGER PRESS MFPT 2B (0-160 PSIG) PSIG 2-IPI-46-5007 (2-L-276) E. H. OUT PRESS MFPT 2B (0-200 PSIG) PSIG 2-1PI-46-5008 (2-L-276) GOV. VALVE POSITION PRESS MFPT 2B (0-100 PSIG) PSIG

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 351 of 371 Data Sheet 15 (Page 2 of 2)

MFPT 2B @ 1800 RPM (Uncoupled)

Date INSTRUMENT NOMENCLATURE DATA INITIAL/DATE 2-IPI-46-5009 (2-L-276) SPEED GOVERNOR PRESS MFPT 2B (0-160 PSIG) PSIG 2-IPI-46-5010 (2-L-276) CONTROL OIL PRESS MFPT 2B (0-100 PSIG) PSIG 2-TI-24-56B (2-L-258) RCW DISCH FWP TURB OIL COOLERS B OF

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 352 of 371 Data Sheet 16 (Page 1 of 2)

MFPT 2B @ 2700 RPM (Uncoupled)

Date INSTRUMENT NOMENCLATURE DATA INITIAL/DATE M&TE ID MFPT 2B SPEED RPM 2-SI-46-20E (2-L-276) MFPT 2B SPEED RPM 2-PI-46-31 (2-L-276) MFPT 2B BRG OIL PRESS PSIG 2-PI-46-52A (2-L-276) MFPT 2B HP OIL FLTR INLET PSIG 2-PI-46-52B (2-L-276) MFPT 2B HP OIL FLTR OUTLET PSIG 2-TIS-46-60 (2-L-276) MFPT 2B OIL DISCH TEMP ALM OF 2-TIS-46-62 (2-L-276) MFPT 2B NO. I BRG OIL TEMP ALM OF 2-TIS-46-64 (2-L-276) MFPT 2B NO. 2 BRG OIL TEMP ALM OF 2-TIS-46-66 (2-L-276) MFPT 2B THRUST BRG OIL TEMP ALM OF 2-IPI-46-5006 (2-L-276) HAND SPEED CHANGER PRESS MFPT 2B (0-160 PSIG) PSIG 2-IPI-46-5007 (2-L-276) E. H. OUT PRESS MFPT 2B (0-200 PSIG) PSIG 2-IPI-46-5008 (2-L-276) GOV. VALVE POSITION PRESS MFPT 2B (0-100 PSIG) PSIG

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 353 of 371 Data Sheet 16 (Page 2 of 2)

MFPT 2B @ 2700 RPM (Uncoupled)

Date INSTRUMENT NOMENCLATURE DATA INITIAL/DATE 2-IPI-46-5009 (2-L-276) SPEED GOVERNOR PRESS MFPT 2B (0-160 PSIG) PSIG 2-IPI-46-5010 (2-L-276) CONTROL OIL PRESS MFPT 2B (0-100 PSIG) PSIG 2-TI-24-56B (2-L-258) RCW DISCH FWP TURB OIL COOLERS B OF

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 354 of 371 Data Sheet 17 (Page 1 of 2)

MFPT 2B @ 3300 RPM (Uncoupled)

Date INSTRUMENT NOMENCLATURE DATA INITIAL/DATE M&TE ID MFPT 2B SPEED RPM 2-SI-46-20E (2-L-276) MFPT 2B SPEED RPM 2-PI-46-31 (2-L-276) MFPT 2B BRG OIL PRESS PSIG 2-PI-46-52A (2-L-276) MFPT 2B HP OIL FLTR INLET PSIG 2-PI-46-52B (2-L-276) MFPT 2B HP OIL FLTR OUTLET PSIG 2-TIS-46-60 (2-L-276) MFPT 2B OIL DISCH TEMP ALM OF 2-TIS-46-62 (2-L-276) MFPT 2B NO. 1 BRG OIL TEMP ALM OF 2-TIS-46-64 (2-L-276) MFPT 2B NO. 2 BRG OIL TEMP ALM OF 2-TIS-46-66 (2-L-276) MFPT 2B THRUST BRG OIL TEMP ALM OF 2-IPI-46-5006 (2-L-276) HAND SPEED CHANGER PRESS MFPT 2B (0-160 PSIG) PSIG 2-IPI-46-5007 (2-L-276) E. H. OUT PRESS MFPT 2B (0-200 PSIG) PSIG 2-IPI-46-5008 (2-L-276) GOV. VALVE POSITION PRESS MFPT 2B (0-100 PSIG) PSIG

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 355 of 371 Data Sheet 17 (Page 2 of 2)

MFPT 2B @ 3300 RPM (Uncoupled)

Date INSTRUMENT NOMENCLATURE DATA INITIAL/DATE 2-IPI-46-5009 (2-L-276) SPEED GOVERNOR PRESS MFPT 2B (0-160 PSIG) PSIG 2-IPI-46-5010 (2-L-276) CONTROL OIL PRESS MFPT 2B (0-100 PSIG) PSIG 2-TI-24-56B (2-L-258) RCW DISCH FWP TURB OIL COOLERS B OF

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 356 of 371 Data Sheet 18 (Page 1 of 2)

MFPT 2B @ 4500 RPM (Uncoupled)

Date INSTRUMENT NOMENCLATURE DATA INITIAL/DATE M&TE ID MFPT 2B SPEED RPM 2-SI-46-20E (2-L-276) MFPT 2B SPEED RPM 2-PI-46-31 (2-L-276) MFPT 2B BRG OIL PRESS PSIG 2-PI-46-52A (2-L-276) MFPT 2B HP OIL FLTR INLET PSIG 2-PI-46-52B (2-L-276) MFPT 2B HP OIL FLTR OUTLET PSIG 2-TIS-46-60 (2-L-276) MFPT 2B OIL DISCH TEMP ALM OF 2-TIS-46-62 (2-L-276) MFPT 2B NO. 1 BRG OIL TEMP ALM OF 2-TIS-46-64 (2-L-276) MFPT 2B NO. 2 BRG OIL TEMP ALM OF 2-TIS-46-66 (2-L-276) MFPT 2B THRUST BRG OIL TEMP ALM OF 2-IPI-46-5006 (2-L-276) HAND SPEED CHANGER PRESS MFPT 2B (0-160 PSIG) PSIG 2-IPI-46-5007 (2-L-276) E. H. OUT PRESS MFPT 2B (0-200 PSIG) PSIG 2-IPI-46-5008 (2-L-276) GOV. VALVE POSITION PRESS MFPT 2B (0-100 PSIG) PSIG

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 357 of 371 Data Sheet 18 (Page 2 of 2)

MFPT 2B @ 4500 RPM (Uncoupled)

Date INSTRUMENT NOMENCLATURE DATA INITIAL/DATE 2-IPI-46-5009 (2-L-276) SPEED GOVERNOR PRESS MFPT 2B (0-160 PSIG) PSIG 2-IPI-46-5010 (2-L-276) CONTROL OIL PRESS MFPT 2B (0-100 PSIG) PSIG 2-TI-24-56B (2-L-258) RCW DISCH FWP TURB OIL COOLERS B OF

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 358 of 371 Data Sheet 19 (Page I of 2)

MFPT 2B @ 5000 RPM (Uncoupled)

Date INSTRUMENT NOMENCLATURE DATA INITIAL/DATE M&TE ID MFPT 2B SPEED RPM 2-SI-46-20E (2-L-276) MFPT 2B SPEED RPM 2-PI-46-31 (2-L-276) MFPT 2B BRG OIL PRESS PSIG 2-PI-46-52A (2-L-276) MFPT 2B HP OIL FLTR INLET PSIG 2-PI-46-52B (2-L-276) MFPT 2B HP OIL FLTR OUTLET PSIG 2-TIS-46-60 (2-L-276) MFPT 2B OIL DISCH TEMP ALM OF 2-TIS-46-62 (2-L-276) MFPT 2B NO. 1 BRG OIL TEMP ALM OF 2-TIS-46-64 (2-L-276) MFPT 2B NO. 2 BRG OIL TEMP ALM OF 2-TIS-46-66 (2-L-276) MFPT 2B THRUST BRG OIL TEMP ALM OF 2-IPI-46-5006 (2-L-276) HAND SPEED CHANGER PRESS MFPT 2B (0-160 PSIG) PSIG 2-IPI-46-5007 (2-L-276) E. H. OUT PRESS MFPT 2B (0-200 PSIG) PSIG 2-IPI46-5008 (2-L-276) GOV. VALVE POSITION PRESS MFPT 2B (0-100 PSIG) PSIG

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 359 of 371 Data Sheet 19 (Page 2 of 2)

MFPT 2B @ 5000 RPM (Uncoupled)

Date INSTRUMENT NOMENCLATURE DATA INITIAL/DATE 2-IPI-46-5009 (2-L-276) SPEED GOVERNOR PRESS MFPT 2B (0-160 PSIG) PSIG 2-IPI-46-5010 (2-L-276) CONTROL OIL PRESS MFPT 2B (0-100 PSIG) PSIG 2-TI-24-56B (2-L-258) RCW DISCH FWP TURB OIL COOLERS B OF

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 360 of 371 Data Sheet 20 (Page I of 2)

MFPT 2B @ 5625 RPM (Uncoupled)

Date INSTRUMENT NOMENCLATURE DATA INITIAL/DATE M&TE ID MFPT 2B SPEED RPM 2-SI-46-20E (2-L-276) MFPT 2B SPEED RPM 2-PI-46-31 (2-L-276) MFPT 2B BRG OIL PRESS PSIG 2-PI-46-52A (2-L-276) MFPT 2B HP OIL FLTR INLET PSIG 2-PI-46-52B (2-L-276) MFPT 2B HP OIL FLTR OUTLET PSIG 2-TIS-46-60 (2-L-276) MFPT 2B OIL DISCH TEMP ALM OF 2-TIS-46-62 (2-L-276) MFPT 2B NO. 1 BRG OIL TEMP ALM OF 2-TIS-46-64 (2-L-276) MFPT 2B NO. 2 BRG OIL TEMP ALM OF 2-TIS-46-66 (2-L-276) MFPT 2B THRUST BRG OIL TEMP ALM OF 2-IPI-46-5006 (2-L-276) HAND SPEED CHANGER PRESS MFPT 2B (0-160 PSIG) PSIG 2-IPI-46-5007 (2-L-276) E. H. OUT PRESS MFPT 2B (0-200 PSIG) PSIG 2-IPI-46-5008 (2-L-276) GOV. VALVE POSITION PRESS MFPT 2B (0-100 PSIG) PSIG

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 361 of 371 Data Sheet 20 (Page 2 of 2)

MFPT 2B @ 5625 RPM (Uncoupled)

Date INSTRUMENT NOMENCLATURE DATA INITIAL/DATE 2-IPI-46-5009 (2-L-276) SPEED GOVERNOR PRESS MFPT 2B (0-160 PSIG) PSIG 2-IPI-46-5010 (2-L-276) CONTROL OIL PRESS MFPT 2B (0-100 PSIG) PSIG 2-TI-24-56B (2-L-258) RCW DISCH FWP TURB OIL COOLERS B OF

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 362 of 371 Data Sheet 21 (Page 1 of 3)

MFP 2B INITIAL PUMP DATA (Prior to Start) (Coupled)

Date INSTRUMENT NOMENCLATURE DATA INITIAL/DATE M&TE ID MFPT 2B SPEED RPM 2-SI-46-20E (2-L-276) MFPT 2B SPEED RPM 2-PI-46-31 (2-L-276) MFPT 2B BRG OIL PRESS PSIG 2-PI-46-52A (2-L-276) MFPT 2B HP OIL FLTR INLET PSIG 2-PI-46-52B (2-L-276) MFPT 2B HP OIL FLTR OUTLET PSIG 2-TIS-46-60 (2-L-276) MFPT 2B OIL DISCH TEMP ALM OF 2-TIS-46-62 (2-L-276) MFPT 2B NO. 1 BRG OIL TEMP ALM OF 2-TIS-46-64 (2-L-276) MFPT 2B NO. 2 BRG OIL TEMP ALM OF 2-TIS-46-66 (2-L-276) MFPT 2B THRUST BRG OIL TEMP ALM OF 2-IPI-46-5006 (2-L-276) HAND SPEED CHANGER PRESS MFPT 2B (0-160 PSIG) PSIG 2-1PI-46-5007 (2-L-276) E. H. OUT PRESS MFPT 2B (0-200 PSIG) PSIG 2-1PI-46-5008 (2-L-276) GOV. VALVE POSITION PRESS MFPT 2B (0-100 PSIG) PSIG

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 363 of 371 Data Sheet 21 (Page 2 of 3)

MFP 2B INITIAL PUMP DATA (Prior to Start) (Coupled)

Date INSTRUMENT NOMENCLATURE DATA INITIAL/DATE 2-IPI-46-5009 (2-L-276) SPEED GOVERNOR PRESS MFPT 2B (0-160 PSIG) PSIG 2-IPI-46-5010 (2-L-276) CONTROL OIL PRESS MFPT 2B (0-100 PSIG) PSIG 2-TI-24-56B (2-L-258) RCW DISCH FWP TURB OIL COOLERS B OF 2-TI-3-85A (Local) MFP 2B INBOARD BRG OIL DRAIN TEMP OF 2-PI-3-89A (Local) MFP 2B BRG OIL PRESS PSIG 2-TI-3-85B (Local) MFP 2B OUTBOARD BRG OIL DRAIN TEMP OF 2-TI-3-85D (Local) MFP 2B THRUST BRG OIL DRAIN TEMP OF 2-TI-3-58 (2-L-34) MAIN FEEDWATER PUMP B CASING TEMP 0 F

2-PI-2-213 (2-L-34) MAIN FEEDWATER PUMP 2B SUCTION PRESS PSIG 2-PI-3-80B (2-L-34) MAIN FEEDWATER PUMP B DISCHARGE PRESS PSIG M&TE ID MFPT 2B DISCH RECIRC FLOW (Ultrasonic) GPM

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 364 of 371 Data Sheet 21 (Page 3 of 3)

MFP 2B INITIAL PUMP DATA (Prior to Start) (Coupled)

Date INSTRUMENT NOMENCLATURE DATA INITIAL/DATE 2-PI-54-9A (2-L-69) INJECTION WATER PUMP 2A DISCHARGE PRESS PSIG 2-PI-54-9B (2-L-69) INJECTION WATER PUMP 2B DISCHARGE PRESS PSIG 2-PDIC-54-5 (2-L-34) MAIN FEEDWATER PUMP 2B SEAL WTR DIFF PRESS PSIG 2-PIC-54-6 (2-L-34) MAIN FEEDWATER PUMP 2B SEAL WTR PRESS PSIG 2-PI-2-34 (2-L-95) COND HOTWELL PUMP 2A DISCHARGE PRESS PSIG 2-PI-2-27 (2-L-95) COND HOTWELL PUMP 2B DISCHARGE PRESS PSIG 2-PI-2-21 (2-L-95) COND HOTWELL PUMP 2C DISCHARGE PRESS PSIG M&TE ID MFP 2B SUCTION PRESS PSIG M&TE ID MFP 2B DISCHARGE PRESS PSIG

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 365 of 371 Data Sheet 22 (Page I of 3)

MFP 2B RECIRC FLOW AT 2650 GPM (Coupled)

Date INSTRUMENT NOMENCLATURE DATA INITIAL/DATE M&TE ID MFPT 2B SPEED RPM 2-SI-46-20E (2-L-276) MFPT 2B SPEED RPM 2-PI-46-31 (2-L-276) MFPT 2B BRG OIL PRESS PSIG 2-PI-46-52A (2-L-276) MFPT 2B HP OIL FLTR INLET PSIG 2-PI-46-52B (2-L-276) MFPT 2B HP OIL FLTR OUTLET PSIG 2-TIS-46-60 (2-L-276) MFPT 2B OIL DISCH TEMP ALM OF 2-TIS-46-62 (2-L-276) MFPT 2B NO. 1 BRG OIL TEMP ALM OF 2-TIS-46-64 (2-L-276) MFPT 2B NO. 2 BRG OIL TEMP ALM OF 2-TIS-46-66 (2-L-276) MFPT 2B THRUST BRG OIL TEMP ALM OF 2-1PI-46-5006 (2-L-276) HAND SPEED CHANGER PRESS MFPT 2B (0-160 PSIG) PSIG 2-IPI-46-5007 (2-L-276) E. H. OUT PRESS MFPT 2B (0-200 PSIG) PSIG 2-IPI-46-5008 (2-L-276) GOV. VALVE POSITION PRESS MFPT 2B (0-100 PSIG) PSIG

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 366 of 371 Data Sheet 22 (Page 2 of 3)

MFP 2B RECIRC FLOW AT 2650 GPM (Coupled)

Date INSTRUMENT NOMENCLATURE DATA INITIAL/DATE 2-IPI-46-5009 (2-L-276) SPEED GOVERNOR PRESS MFPT 2B (0-160 PSIG) PSIG 2-IPI-46-5010 (2-L-276) CONTROL OIL PRESS MFPT 2B (0-100 PSIG) PSIG 2-TI-24-56B(2-L-258) RCW DISCH FWP TURB OIL COOLERS B OF 2-TI-3-85A (Local) MFP 2B INBOARD BRG OIL DRAIN TEMP OF 2-PI-3-89A (Local) MFP 2B BRG OIL. PRESS PSIG 2-TI-3-85B (Local) MFP 2B OUTBOARD BRG OIL DRAIN TEMP OF 2-TI-3-85D (Local) MFP 2B THRUST BRG OIL DRAIN TEMP OF 2-TI-3-58 (2-L-34) MAIN FEEDWATER PUMP B CASING TEMP OF 2-PI-2-213 (2-L-34) MAIN FEEDWATER PUMP 2B SUCTION PRESS PSIG 2-PI-3-80B (2-L-34) MAIN FEEDWATER PUMP B DISCHARGE PRESS PSIG M&TE ID MFPT 2B DISCH RECIRC FLOW (Ultrasonic) GPM

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 367 of 371 Data Sheet 22 (Page 3 of 3)

MFP 2B RECIRC FLOW AT 2650 GPM (Coupled)

Date INSTRUMENT NOMENCLATURE DATA INITIAL/DATE 2-PI-54-9A (2-L-69) INJECTION WATER PUMP 2A DISCHARGE PRESS PSIG 2-PI-54-9B (2-L-69) INJECTION WATER PUMP 2B DISCHARGE PRESS PSIG 2-PDIC-54-5 (2-L-34) MAIN FEEDWATER PUMP 2B SEAL WTR DIFF PRESS PSIG 2-PIC-54-6 (2-L-34) MAIN FEEDWATER PUMP 2B SEAL WTR PRESS PSIG 2-PI-2-34 (2-L-95) COND HOTWELL PUMP 2A DISCHARGE PRESS PSIG 2-PI-2-27 (2-L-95) COND HOTWELL PUMP 2B DISCHARGE PRESS PSIG 2-PI-2-21 (2-L-95) COND HOTWELL PUMP 2C DISCHARGE PRESS PSIG M&TE ID MFP 2B SUCTION PRESS PSIG M&TE ID MFP 2B DISCHARGE PRESS PSIG

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 368 of 371 Data Sheet 23 (Page 1 of 1)

Injection Water Pumps 2A and 2B Performance Data Injection Water Pump 2A Suction Discharge Data Set Flow (GPM) Temperature (°F) Pressure (PSIG) Pressure (PSIG) Initial/Date 1

2 3

4 5

6 7

M&TE ID Injection Water Pump 2B Suction Discharge Data Set Flow (GPM) Temperature (F) Pressure (PSIG) Pressure (PSIG) Initial/Date 1

2 3

4 5

6 7

M&TE ID To plot the values on the curve (Figure 3), convert the discharge and suction pressures from PSIG to feet head by multiplying both by 2.307. To get the differential head, subtract the suction head from the discharge head.

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 369 of 371 Figure 1 (Page 1 of 1)

STANDBY MAIN FEEDWATER PUMP WIMNOW I

2. aAR 097%

II a a-a a 04..

ca-

~ '7

~

I a

C2 0r I

2

!9 0 -

i U-

- - - 0 m 0 I 'C C4

'333-N! QY3.q IVI.1 dII~ 9-

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 370 of 371 Figure 2 (Page 1 of 1)

MAIN FEEDWATER PUMPS 2A and 2B N N% Mq% R I WIM5 A 3 rgWS TTALS I In I P2 I

I-

'C

ý3J-N I WS.4N I

Ia. -'C ~

-- ~~---- --- - --- ~ ~ ~ i 1L. ~r-ic:':

0

~WI C)

    • C~~ 0
  • .- - - - - - ,-IS

~

CD; g~mI In I

0 i

8 133A-M I CY3 I.J VYfIG 40 94

WBN MAIN FEEDWATER SYSTEM 2-PTI-003A-03 Unit 2 FUNCTIONAL TEST Rev. 0000 Page 371 of 371 Figure 3 (Page 1 of 1)

Injection Water Pumps 2A and 2B 41--

I:L Lij i -'

F IS U SE II thE .... " Date--:

-U I l i II !i . a

  • LEGIBItUITY :EVUIArE'D ANt)

ACCEPAT.AD FOR ISSUE.