UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555*0001 June 26, 2013 MEMORANDUM TO: Anneliese Simmons, Acting Chief Projects Branch 2 Division of License Renewal

)***wl.

Office of Nuclear Reactor Regulation FROM: Leslie Perkins, Project Manager Projects Branch 2 Division of License Renewal .

Office of Nuclear Reactor Regulati

SUBJECT:

SUMMARY

OF PUBLIC MEETINGS CONDUCTED TO DISCUSS THE DRAFT SUPPLEMENTAL ENVIRONMENTAL IMPACT STATEMENT RELATED TO THE REVIEW OF LIMERICK GENERATING STATION UNITS 1 AND 2, LICENSE RENEWAL APPLICATION On Thursday, May 23, 2013, members of the U.S. Nuclear Regulatory Commission (NRC) staff held public meetings in Pottstown, Pennsylvania concerning the staff's environmental review of the application submitted by Exelon Generation Company, LLC (Exelon) for renewal of Limerick Generating Station Units 1 and 2 (LGS) operating licenses. The purpose of the meeting was to provide the public with an opportunity to comment on the draft supplemental environmental impact statement (DSEIS) which was issued on April 30, 2013. The public meetings were held at the Sunnybrook Ballroom in Pottstown, Pennsylvania. Formal presentations were made by the NRC staff.

The DSEIS is a plant-specific supplement for LGS to the "Generic Environmental Impact Statement for License Renewal of Nuclear Plants" (NUREG-1437). The NRC staff described the overall license renewal process, provided a description of the National Environmental Policy Act review process, and discussed the environmental requirements outlined in Title 10 of the Code of Federal Regulations Par151 (10 CFR Par151). The NRC staff also described the preliminary results of their analyses. The environmental impacts of continued operation were predicted to be small in all areas. The impacts of alternatives (including the no-action alternative) were predicted to have impacts in at least some environmental aspects that could reach moderate or large significance.

After the formal presentations were given by the NRC staff, members of the public were invited to provide comments. Approximately 40 people attended the two sessions. Attendees included members of the public, representatives of the NRC, Exelon, and the news media.

CONTACT: Leslie Perkins, NRR/DLR/RPB2 301-415-2375

2 In an effort to improve communication and increase interaction with members of the public, the NRC staff conducted open houses for one hour before each meeting and encouraged the public to submit meeting feedback forms. The staff provided brochures and met with members of the public to answer questions about the proposed renewal of the LGS operating licenses.

A combined listing of attendees for both sessions is provided in Enclosure 1. Enclosure 2 is a copy of the meeting agenda. Enclosures 3 and 4 contain the official corrected transcripts for the afternoon and evening meetings, respectively. Enclosure 5 contains a copy of the slides used during the NRC's presentation.

The closing date to accept comments on the LGS DSEIS is June 27,2013. The NRC staff will consider all comments on the LGS DSEIS and make any necessary revisions to the document prior to issuing its final supplemental environmental impact statement, scheduled for November 2013.

Docket Nos. 50-352 and 50-353

Enclosures:

1. List of Attendees
2. Meeting Agenda
3. Afternoon Transcript (Corrected): ML13172A019
4. Evening Transcript (Corrected): ML13172A023
5. Slides: ML13141A188 Package: ML13172A026 cc w/enclosures: Via Listserv

2 In an effort to improve communication and increase interaction with members of the public, the NRC staff conducted open houses for one hour before each meeting and encouraged the public to submit meeting feedback forms. The staff provided brochures and met with members of the public to answer questions about the proposed renewal of the LGS operating licenses.

A combined listing of attendees for both sessions is provided in Enclosure 1. Enclosure 2 is a copy of the meeting agenda. Enclosures 3 and 4 contain the official corrected transcripts for the afternoon and evening meetings, respectively. Enclosure 5 contains a copy of the slides used during the NRC's presentation.

The closing date to accept comments on the LGS DSEIS is June 27, 2013. The NRC staff will consider all comments on the LGS DSEIS and make any necessary revisions to the document prior to issuing its final supplemental environmental impact statement, scheduled for November 2013.

Docket Nos. 50-352 and 50-353

Enclosures:

1. List of Attendees
2. Meeting Agenda
3. Afternoon Transcript (Corrected): ML13172A019
4. Evening Transcript (Corrected): ML13172A023
5. Slides: ML13141A188 Package: ML13172A026 cc w/enclosures: Via Listserv DISTRIBUTION: wlo Encls. 3, 4, and 5 See next page ADAMS Accession Number' ML13156A090 OFFICE LA:DLR PM:DLR:RPB2 BC:DLR:RPB2 NAME YEdmonds LPerkins ASimmons DATE 6/25/2013 6/25/2013 6/26/2013 OFFICIAL RECORD COPY

LIST OF ATTENDEES LIMERICK GENERATING STATION UNITS 1 AND 2 DRAFT SUPPLEMENTAL ENVIRONMENTAL IMPACT STATEMENT PUBLIC MEETINGS MAY 23,2013 Participants Affiliation Leslie Perkins U.S. Nuclear Regulatory Commission (NRC)

Anneliese Simmons NRC Matt Kluge NRC Mel Gray NRC Richard Barkley NRC Kevin Folk NRC Neil Sheehan NRC Stephen Walsh Delaware River Basin Commission Dr. Lewis Cuthbert Alliance for Clean Environment (ACE)

Donna Cuthbert ACE Charles Shank ACE Betty Shank ACE Loraine Ruppe ACE Jesse Bookspan Pennsylvania Energy Alliance Les Rinehart Pennsylvania Energy Alliance Steve Aaron Pennsylvania Energy Alliance Kara Maxwell Pennsylvania Energy Alliance Zach Chizar Pennsylvania Energy Alliance Tana Rinehart Pennsylvania Energy Alliance Mark Davletich Pennsylvania Energy Aliiance/Organixy Michael Murphy Pennsylvania Department of Environmental Protection Paul Gunter Beyond Nuclear Kim Murphy Berks Conservancy Keugo Takahima Japan Broadcasting Corp Naoki Sakurai Japan Broadcasting Corp Kevin Magerr EPA Region 3 Tom Troutman Resident Ed Nugent Resident Gail Brown Resident Tina Daly Resident Shirley Whyte Resident Jacequeline Wise Resident Charlie Koeneg Resident Barb Cornish Resident Janish Monger Resident Dr. Ann Baly Resident Marci Dietrich Resident Bob Harkin Resident Peggy Hartzell Resident Leroy Watters Schuylkill River Gloria Frances SRC Resident Eddie Noguchi NHK ENCLOSURE 1

2 Participants Affiliation T akamitsu Munoi NHK Rick Sands URS Evan Brandt Pottstown Mercury Michael Moyer East Conventry Township Supervisor Mariea Geho East Conventry Township Supervisor C. Ryan Barber Reading Eagle Brook Morgan Lewis Kurt Imhof Senator Bob Casey's office Scott Portzline TMI Alert Alan Brinser DEMA Jeannie Liggett Exelon Dana Melia Exelon David Tillar Exelon Chris Conroy Exelon Alisa Otteni Exelon Christina Pratt Exelon Mike Gallagher Exelon Leanne Brickmire Exelon Chris Wilson Exelon Nancy Ranek Exelon Thom Chiomerdo Exelon

AGENDA FOR PUBLIC MEETINGS TO DISCUSS THE DRAFT SUPPLEMENTAL ENVIRONMENTAL IMPACT STATEMENT FOR THE LICENSE RENEWAL OF LIMERICK GENERATING STATION Thursday, May 23, 2013 Two Meeting Sessions - 2:00 p.m. to 4:00 p.m. and 7:00 p.m. to 9:00 p.m.*

I. Welcome and Purpose of Meeting 5 minutes (Richard Barkley)

II. Overview of License Renewal Process 5 minutes (Leslie Perkins)

III. Results of the Environmental Review 10 minutes (Leslie Perkins)

IV. How Comments can be Submitted 5 minutes (Leslie Perkins)

V. Public Comments As Required (Richard Barkley)

VI. Closing/Availability of Transcripts, etc. 5 minutes (Richard Barkley)

  • The NRC staff will host informal discussions one hour prior to each meeting session. No formal comments on the draft Supplemental Environmental Impact Statement (DSEIS) will be accepted during the informal discussions. To be considered, comments must be provided either at the transcribed public meetings (see agenda, above) or in writing, as described in the Federal Register Notice.

For the security of everyone attending this meeting, local law enforcement officers may be conducting searches of bags (briefcases, purses, backpacks, equipment cases, etc.) outside the entry into the meeting room. Additionally, signs, banners, posters and displays affixed to any sticks, poles or other similar devices will not be permitted in the meeting room.

ENCLOSURE 2

SUBJECT:

SUMMARY

OF PUBLIC MEETINGS CONDUCTED TO DISCUSS THE DRAFT SUPPLEMENTAL ENVIRONMENTAL IMPACT STATEMENT RELATED TO THE REVIEW OF THE LIMERICK GENERATING STATION UNITS 1 AND 2, LICENSE RENEWAL APPLICATION DISTRIBUTION:

E-MAIL:

PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsNrrDraApla Resource RidsOgcMailCenter LPerkins ASimmons RPlasse REnnis, DORL CKanatas, OGC EDiPaolo, SRI NMcNamara, RI DScrenci, RI NSheehan, RI