Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.David Moorman 8111 Pennington Dr Huntington Beach, CA 92646-6737 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Nanette Johns PO Box 1670 Topanga, CA 90290-1670 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Timothy Hanson 223 Strand St Apt F Santa Monica, CA 90405-3428 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Vincent De Stefano 580 N Sierra Madre Blvd Pasadena, CA 91107-2727 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Rhonda Weir 18819 Towne Ave Carson, CA 90746-2162 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Saul Holguin 2735 7th Ave Apt 4 Los Angeles, CA 90018-2409 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Olga Moreno 27221 Camino Espada San Juan Capistrano, CA 92675 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Angeles Chapter CA 91748-3344 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Glenn Britton 1915 W 43rd St Los Angeles, CA 90062-1450 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 2055570001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Jan Mcquain 6465 Blewett Ave Van Nuys, CA 91406-6048 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Kathleen Engberg 5432 Canehill Ave Lakewood, CA 90713-1618 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Sherman Dearth Wheatstone Ave Norwalk, CA 90650 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Linda Goldenberg 22726 Mulholland Dr Woodland Hills, CA 91364-4942 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.As I live close to the San Onofre plant I have been anxious and worried about any restart. It should be closed permanently.
Please consider my request for a permanent shutdown.Thank you for your attention to these concerns.Elizabeth Rudrigues 1211 Avenida Buena Suerte San Clemente, CA 92672-2349 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded nuaterous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Co~nmittee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are coztpleted, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a conprehensive and open review process.Thank you for your attention to these concerns.Monica Camacho 1811 7th St Apt 9 Santa Monica, CA 90401-3355 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.This plant needs to be shut down and we need to focus on clean energy.Nuclear energy is way to dangerous and produce terrible toxic waste.How can that be good??????
Thank you for your attention to these concerns.Jennie Jensen 6106 Matilija Ave Van Nuys, CA 91401-2920 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Harlan Goldberg 12721 Woodley Ave Granada Hills, CA 91344-1823 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Maureen Mehler 415 Avenida Castilla Unit B Laguna Woods, CA 92637-8729 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Theda Ray 801 W 232nd St Torrance, CA 90502-2500 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Karla Figueroa 11934 Old Rvr Sch Rd Apt la Downey, CA 90242-2141 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Dimitar Minkovsky 35 Via Barcelona Rancho Santa Margarita, CA 92688-2344 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Ilene Minnich 3706 Tunales Dr Fullerton, CA 92835-1329 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Christina Labrado 11533 Richeon Ave Downey, CA 90241-4441 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Steve Rosin 80 N Euclid Ave Apt 202 Pasadena, CA 91101-1701 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Suzanne Camarillo 941 N Orlando Ave Los Angeles, CA 90069-4205 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Kinsey Mclean 2303 Hidalgo Ave Los Angeles, CA 90039-3633 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70%.power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Martha Diaz 640 Camino De Encanto Redondo Beach, CA 90277-6534 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Katherine Huff 23831 Ionian Bay Dana Point, CA 92629-4409 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.John Gilles 2278 Luana Ln Montrose, CA 91020-1211 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Mike Boulet 2530 Plaza Del Amo Torrance, CA 90503-7366 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Bonnie Malonry 116 25th P1 Manhattan Beach, CA 90266-2102 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Angelique Higgins 2385 Roscomare Rd Unit F4 Los Angeles, CA 90077-1822 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Georgia Brewer 5518 Ventura Canyon Ave Sherman Oaks, CA 91401-5228 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.I live only 3 miles away from the nuclear power plant and am uncomfortable with the thought of it being used again. With the recent nuclear disaster in Japan my senses are hightened to the extent of the pollution and radiation exposure a meltdown could release.Thank you for your attention to these concerns.Kelly Bartels 102 Avenida Dolores Apt 1 San Clemente, CA 92672-3480 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is. essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Linda Lapetino 3271 Sawtelle Blvd Apt 107 Los Angeles, CA 90066-2411 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Please do not let this faopopen Thank you for your attention to these concerns.Pierre Bala Suriya 905 Lombard Ct Costa Mesa, CA 92626-6916 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Zack Frank 836 Melrose Hill St Los Angeles, CA 90029-3714 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Jon Grutman 1136 S Dunsmuir Ave Los Angeles, CA 90019-6756 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Gonzalo Villalobos 1826 Cerritos Ave Apt B Long Beach, CA 90806-5151 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
As a resident of San Clemente, I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Hal Forsen 204 Avenida Serra San Clemente, CA 92672-4708 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Cameron Heravi 25162 Mustang Dr Laguna Hills, CA 92653-5745 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Ana Fantin Rua Leandro Teixeira, 240, Blo Sao Paulo, CA 90210 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Richard Gary 2040 Broadway Santa Monica, CA 90404-2910 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Erin Warrack 3008 Rosalinda San Clemente, CA 92673-3230 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of, tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Karen Nawrocki 10742 Molony Rd Culver City, CA 90230-5449 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Michael Nielsen 18453 Santa Eugenia St Fountain Valley, CA 92708-5601 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.lanny cordola 7890 E Spring St Unit 41 Long Beach, CA 90815-1639 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Susan Davis Mantee 23908 De Ville Way Apt A Malibu, CA 90265-4850 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Deborah Kashinsky 210 Muerdago Rd Topanga, CA 90290-3545 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Christian Manfredi 10845 Camarillo St Apt 101 North Hollywood, CA 91602-1361 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation-and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at. 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Shady Hakim 2507 28th St Apt 1 Santa Monica, CA 90405-2900 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Philip Harris 26200 Frampton Ave Spc 70 Harbor City, CA 90710-4378 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Joe Wolcott 3127 Belden Dr Hollywood, CA 90068-1947 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.James Odling 5170 0 Sullivan Dr Los Angeles, CA 90032-4051 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Please, again, realize the potential danger you will putting the public in, if you fail to conduct a comprehensive review.Sincerely, Josephine Eure Thank you for your attention to these concerns.Josephine Eure 4137 Don Tomaso Dr Apt 4 Los Angeles, CA 90008-5334 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Jamie Weber 340 Stanford Dr Claremont, CA 91711-4634 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Bella Seppell PO Box 453 Los Angeles, CA 90078-0453 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I wholeheartedly support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process. Please block the San Onofre restart.Thank you for your attention to these concerns.Anne Dugaw 385 Ogle St # C Costa Mesa, CA 92627-3207 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Jena Ardell 5455 Zelzah Ave Encino, CA 91316-2272 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Jim Belsley 3993 Black Bird Way Calabasas, CA 91302-1883 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Jim Robertson 446 San Vicente Blvd Santa Monica, CA 90402-1731 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make, a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Zia Islam 20011 Arminta St Winnetka, CA 91306-2303 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at.this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Bruce Burness 1260 Yocum St Pasadena, CA 91103-1947 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.C Cronin 8748 Dorrington Ave West Hollywood, CA 90048-1724 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time.Thank you for your attention to these concerns.Patricia Gleason 1203 N Sweetzer Ave Los Angeles, CA 90069-3045 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Michael Wilson 32510 Pinebluff P1 Westlake Vlg, CA 91361-5541 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time.Thank you for your attention to these concerns.Patricia Gleason 1203 N Sweetzer Ave Los Angeles, CA 90069-3045 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Raz Reinecke 6 Paradise Cove Rd Malibu, CA 90265-8006 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Damiana Hook 3320 Merced St Los Angeles, CA 90065-1615 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Ruth Quinnan 26902 Quevedo Ln Mission Viejo, CA 92691-6021 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San. Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.A Sugerman 3576 Dixie Canyon Ave Sherman Oaks, CA 91423-4822 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Steve Kehela 4525 Coldwater Canyon Ave Studio City, CA 91604-1088 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Bonnie Maloney 116 25th P1 Manhattan Beach, CA 90266-2102 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential.
restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Nicholas Aquino 500 W Temple St Los Angeles, CA 90012-2713 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Frank Di Stefano 5472 Maemurray Dr Los Angeles, CA 90041-1449 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the. troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Melanie Cohen 115 S Guadalupe Ave Unit H Redondo Beach, CA 90277-3481 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Akemi Imai 703 Locust St Pasadena, CA 91101-1660 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Kathleen Yanakis 25760 Perlman P1 Stevenson Ranch, CA 91381-2369 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Susan Lynch 732 Greentree Rd Pacific Palisades, CA 90272-3909 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Jon Burras 14 Monarch Bay Plz # 372 Monarch Beach, CA 92629-3424 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Chip Phillips 2033 N Beachwood Dr Los Angeles, CA 90068-3454 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I strongly support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Irving Paul Ackerman, MD 1960 N Edgemont St Los Angeles, CA 90027-1806 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Joyce Rice 4018 Mount Vernon Dr Los Angeles, CA 90008-4816 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Angeles Chapter 10563 Cheviot Dr Los Angeles, CA 90064-4351 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Gene Trautmann 414 N Curson Ave Apt 216 Los Angeles, CA 90036-6243 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Long Nguyen 7810 Kenyon Ave Los Angeles, CA 90045-1082 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Moira Nelson 2415 Silverstrand Ave Hermosa Beach, CA 90254-2664 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Julie Mcknight Los Angeles, CA Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the-plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.D Figus 11229 Blix St North Hollywood, CA 91602-1206 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Steffanie Gee 2368 S Beverly Glen Blvd Los Angeles, CA 90064-2484 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Cori Tite 13037 Kismet Ave Sylmar, CA 91342-3423 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal,.which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Victoria Pyle PO Box 417 Monrovia, CA 91017-0417 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Jerry Levesque 4901 W 120th St Hawthorne, CA 90250-2774 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 20 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Jane Madoff 4121 La Salle Ave Culver City, CA 90232-3209 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Kathy Seal 2431 32nd St Santa Monica, CA 90405-2029 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Gary And Karla Peebles 1740 Tam Oshanter Rd Apt lb Seal Beach, CA 90740-4766 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Daniel Orozco 2922 Grand Ave Walnut Park, CA 90255-6227 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Travis Corona 5042 Hartwick St Los Angeles, CA 90041-2307 Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear RegUlatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
The future threat of plant failure due to a natural or human-made disaster as evidenced in Japan and elsewhere should be a huge example that even the best efforts made to contain and correct a contamination are no match for the extreme danger it will cause to the surrounding area and it's impact on residents, all lifeforms, minerals, air and water.I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time.Thank you for your attention to these concerns.Lynettte Lee Pasadena, CA Apr 30, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Ms Bladey,
The comments that follow are regarding Docket ID NRC20130070.
We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.
Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision.
We and other environmental groups have joined with U.S.Senator Boxer and'U.S. Representative Markey in urging the NRC not to follow such a course.We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.
We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature." Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendmyent" that shortcuts procedures is totally inappropriate.
SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.
Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.
I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.Thank you for your attention to these concerns.Elizabeth Crawford 16820 Oak View Dr Encino, CA 91436-3240