Comment (225) of 100 Individuals Opposing Application and Amendment to Facility Operating License Involving Proposed No Significant Hazards Consideration Determination; San Onofre Nuclear Generating Station, Unit 2; License Amendment Reques
ML13144A760
Person / Time
Site: San Onofre Southern California Edison icon.png
Issue date: 04/28/2013
From: Barker M, Black J, Marilyn Evans
- No Known Affiliation
To: Cindy Bladey
Rules, Announcements, and Directives Branch
References
78FR22576 00225, NRC-2013-0070
Download: ML13144A760 (1)


Text

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Mary Barker 2550 E Avenue I Spc 47 Lancaster, CA 93535-1018

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S.

Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC.of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

John Black 341 Leucadia Rd La Habra Heights, CA 90631-7808

May 3, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Michael W Evans 3731 S Sepulveda Blvd Apt 1 Los Angeles, CA 90034-6888

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Tracey Richardson 15425 Vanowen St Apt 11 Van Nuys, CA 91406-6384

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Russell Blandino 337 S Sparks St Burbank, CA 91506-2743

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Albert Miller 9 Emperor

Irvine, CA 92604-1918

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the. San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Leslie Brooks 13480 Wentworth Ln Unit 1251 Seal Beach, CA 90740-4652

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Lonnie Sheinart 12108 Ivy Pl Los Angeles, CA 90064-3521

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Shanna Bennington 1907 190th St Redondo Beach, CA 90278-4818

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Vera Mijojlic Los Angeles, CA

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Helene Smati 8211 San Angelo Dr Apt L12 Huntington Beach, CA 92647-7294

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Mary Kate Ziesmer 10573 W Pico Blvd # 114 Los Angeles, CA 90064-2333

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Wendy Suhr 817 Chautauqua Blvd Pacific Palisades, CA 90272-3802

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Mell Banez 919 Albany St Los Angeles, CA 90015-1211

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Jessica Likens 8137 Santa Inez Way Buena Park, CA 90620-3156

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

terance tashiro 8036 Westlawn Ave Los Angeles, CA 90045-2751

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns, Tippi and Neal Dobrofsky Santa Monica, Ca 90403 Thank you for your attention to these concerns.

Tippi Dobrofsky

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Carey Million 5401 Magnolia Ave

Whittier, CA 90601-2749

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Susan Siering 4481 Mont Eagle P1 Los Angeles, CA 90041-3416

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S.

Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Brenda Howell 1638 Avenida Selva Fullerton, CA 92833-1533

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S.

Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Pamela Wylie 311 S Shamrock Ave

Monrovia, CA 91016-3026

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Josephine Contreras 3655 Brunswick Ave Los Angeles, CA 90039-1727

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S.

Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Diane Seaman 958 18th St Unit 6 Santa Monica, CA 90403-3259

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Kara Pewthers 833 Willow Dr

Brea, CA 92821-5051

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Mir Bahmanyar 6708 Aldea Ave Van Nuys, CA 91406-5407

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S.

Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review.process.

Thank you for your attention to these concerns.

Theda Zaretsky 4922 Beverly Blvd Apt 4 Los Angeles, CA 90004-3932

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment'. that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Barry Levy 620 S Gramercy Pl Los Angeles, CA 90005-3259

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Terza Tessel 5430 Burnet Ave Sherman Oaks, CA 91411-3506

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

As a resident of San Clemente, I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Hal Forsen 204 Avenida Serra San Clemente, CA 92672-4708

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S.

Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totallyinappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Brian Dowling 15320 Casino Dr Hacienda Heights, CA 91745-6172

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Marilyn Alexander 1321 Harvard St Apt 5 Santa Monica, CA 90404-2435

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Susan Sanocki 18342 E Woodcroft St

Azusa, CA 91702-5842

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Nanette Johns PO Box 1670

Topanga, CA 90290-1670

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial'or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Chris Gerolmo 12311 Rochedale Ln # Ca Los Angeles, CA 90049-1936

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Mark DiMaria 9037 W 24th St Los Angeles, CA 90034-1938

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Jamie Weber 340 Stanford Dr Claremont, CA 91711-4634

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Diana Dee 12814 Victory Blvd North Hollywood, CA 91606-3013

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Charles Masters 140 Fernleaf Ave Corona Del Mar, CA 92625-3211

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts.procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Robert Meier 6241 Morse Ave North Hollywood, CA 91606-2919

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Sadaf Ebrahimi 27877 Mariposa St Valencia, CA 91355-6034

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Deborah Ainza 4605 Aire De La Sal San Clemente, CA 92673-6406

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Charles Masters 140 Fernleaf Ave Corona Del Mar, CA 92625-3211

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S.

Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Catherine Kamas 13674 Eastbridge St Westminster, CA 92683-2985

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S.

Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Colleen Carter 18139 Erik Ct Unit 258 Canyon Country, CA 91387-4990

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Oscar Banda 25132 Oceanknoll Dana Point, CA 92629-2669

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Joanne Saldana 141 S Kenmore Ave Los Angeles, CA 90004-5602

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Bill Crane 22351 Mission Cir Chatsworth, CA 91311-1257

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Linda Klein 1257 E Maple Ave El Segundo, CA 90245-3259

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S.

Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Kimberly Anne Halizak 1933 N Beachwood Dr Apt 205 Los Angeles, CA 90068-4035

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S.

Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Tammie Haugen 11305 Graham P1 Los Angeles, CA 90064-3751

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Irma & Eugene Strantz 1930 Homewood Dr Altadena, CA 91001-2840

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Gordon Richiusa 603 Avenida Sevilla Unit G Laguna Woods, CA 92637-7127

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Pamena Butler 1500 4th Ave Los Angeles, CA 90019-3406

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Brian Mertan 5050 Klump Ave Apt 315 North Hollywood, CA 91601-5010

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Dennis Niggl 20 Hunter Irvine, CA 92620-3359

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Ever Garcia 4434 Gateside Dr Los Angeles, CA 90032-3702

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Ramin Mortazavi 3310 North Bound Street Agoura Hills, CA 91376

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Pamela Perryman 2025 Le Droit Dr South Pasadena, CA 91030-3423

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Shirley Camfield 2007 Pullman Ln Redondo Beach, CA 90278-4935

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Annette Gordon 4160 Sebren Ave

Lakewood, CA 90713-3036

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Oscar Banda 25132 Oceanknoll Dana Point, CA 92629-2669

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Beverly Johnson 31176 Calle San Pedro San Juan Capistrano, CA 92675-2213

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Victoria Jensen 2310 6th St Apt 3 Santa Monica, CA 90405-2443

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Joni Madere 522 Altair P1 Venice, CA 90291-4205

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Mark Graski 1330 W West Ave Fullerton, CA 92833-4033

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Gary Schneider 12630 Bonaparte Ave Los Angeles, CA 90066-6522

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Gloria Sanchez 9 Vista Sabana Rancho Santa Margarita, CA 92688-2908

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

MYRON GOLDENBERG 22726 Mulholland Dr Woodland Hills, CA 91364-4942

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow, such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

D Stokes 1714 Royal Oaks Dr Duarte, CA 91010-1840

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Jinx Hydeman 18806 Vista Modjeska Rd Trabuco Canyon, CA 92679-1108

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Karen Spiegel 1074 E Tujunga Ave Burbank, CA 91501-1438

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Kathleen Hallal 43 Prairie Grass Irvine, CA 92603-0402

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Peter Friedman 101 Warwick P1 South Pasadena, CA 91030-4062

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Marjorie Rooney 117 Vermillion Irvine, CA 92603-0619

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Rhen Kohan 31061 Via Santo Tomas San Juan Capistrano, CA 92675-2241

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Jeronimo Barajas 2445 Kent St Apt 3 Los Angeles, CA 90026-4053

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S.

Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Stephanie Satie 16600 Hamlin St Van Nuys, CA 91406-5615

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S.

Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Gillian Smith 1550 N Fairfax Ave Los Angeles, CA 90046-2608

Apr 28, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Evangelina Contreras 4540 Lindsey Ave Pico Rivera, CA 90660-2026

Apr 29, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S.

Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Sheryl Shoemaker 5260 Raber St Los Angeles, CA 90042-1030

Apr 29, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S.

Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Carlos Navarrette 1329 Cordon Dr Los Angeles, CA 90063-3202

Apr 29, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Maureen Toth 11206 Laurie Dr Studio City, CA 91604-3877

Apr 29, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Diane Berliner 2160 Laurel Canyon Blvd Los Angeles, CA 90046-2004

Apr 29, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC2013007.0.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Jeff Doucette 6255 Whitsett Ave North Hollywood, CA 91606-3129

Apr 29, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S.

Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Dan Squires Long Beach, CA 90802-3737

Apr 29, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S.

Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Lee Jordan 6224 Condon Ave Los Angeles, CA 90056-1906

Apr 29, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Kirk Margo 11127 La Maida St Unit 33 North Hollywood, CA 91601-4534

Apr 29, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Robert Frcek 961 Amherst Ave Los Angeles, CA 90049-5801

Apr 29, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Brent Riggs 1157 E Hyde Park Blvd Inglewood, CA 90302-1846

Apr 29, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Holly Sklar 1878 Greenfield Ave Los Angeles, CA 90025-6435

Apr 29, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Margaret Meinschein 4213 Le Bourget Ave Culver City, CA 90232-3412

Apr 29, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S.

Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Kathy Beckwith 12001 Chaucer Rd Los Alamitos, CA 90720-4531

Apr 29, 2013 Ms Cindy Bladey U.S.

Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Douglas Donehoo 100 S Hayworth Ave Apt 302 Los Angeles, CA 90048-3659

Apr 29, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S.

Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Salvatore Esposto 2311 W Clark Ave

Burbank, CA 91506-1911

Apr 29, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S.

Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Robert Sullivan 4017 Ocean Dr Manhattan Beach, CA 90266-3162

Apr 29, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S.

Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Eric Von Brink 108 W 2nd St Los Angeles, CA 90012-1586

Apr 29, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either tailed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Wendy Crandall 1544 Elm Ave # A Costa Mesa, CA 92626-3802

Apr 29, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Nina Macdonald 10 Handel Ct

Irvine, CA 92617-4079

Apr 29, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S.

Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Maryann LaNew 12 Corte Loarre San Clemente, CA 92673-6520

Apr 29, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S. Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Victor Nepomnyashchy 9131 Burnet Ave Unit 7 North Hills, CA 91343-2325

Apr 29, 2013 Ms Cindy Bladey U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Ms Bladey,

The comments that follow are regarding Docket ID NRC20130070.

We ask that the Nuclear Regulatory Commission (NRC) take no action that could lead to a restart of the San Onofre nuclear power plant before the Commission completes a comprehensive investigation and provides full opportunity for public participation and independent expert testimony.

Southern California Edison (SCE) is attempting to shortcut the license review process by calling on the NRC to make a fast-track restart decision. We and other environmental groups have joined with U.S.

Senator Boxer and U.S.

Representative Markey in urging the NRC not to follow such a course.

We were deeply disturbed when on April 10 the NRC staff disregarded numerous statements of concern and announced a "preliminary finding" that a San Onofre restart at 70% power posed no significant safety risk.

We join a wide range of concerned citizens and public officials in believing that a full and transparent review of the failed San Onofre generators is essential before the NRC considers any potential restart at either partial or full power of the failed generator.

We support Senator Boxer, Chair of the Environment and Public Works Committee, who stated on April 10, 2013: "The NRC staff

proposal, which could pave the way for the restart of the San Onofre nuclear power plant before the investigations of the crippled plant are completed, is dangerous and premature."

Given the recent failure of tubes that carry radioactive water, speeding restart of San Onofre through a so-called "license amendment" that shortcuts procedures is totally inappropriate.

SCE's request to weaken its license requirements was made despite evidence showing that there could be a significant hazard from the operation of the deficient steam generators.

Given the troubled history and current condition of the plant and the raised level of public concern, the public deserves a full review by the NRC of conditions at San Onofre before it considers a restart of either failed generator.

I support the call by the Sierra Club for the NRC to block any restart of the failed San Onofre generators at this time, and to conduct a comprehensive and open review process.

Thank you for your attention to these concerns.

Frank Hanrahan 2545 Fairway Dr Costa Mesa, CA 92627-1311