ML13130A045
ML13130A045 | |
Person / Time | |
---|---|
Site: | Point Beach |
Issue date: | 05/17/2013 |
From: | Beltz T Plant Licensing Branch III |
To: | Meyer L Point Beach |
Beltz T | |
References | |
TAC MF0161, TAC MF0162 | |
Download: ML13130A045 (8) | |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555*0001 t-i'2y 17, 2013 Mr. Larry Meyer Site Vice President NextEra Energy Point Beach, LLC Point Beach Nuclear Plant 6610 Nuclear Road Two Rivers, WI 54241-9516
SUBJECT:
PLAN FOR THE REGULATORY AUDIT REGARDING SEISMIC WALKDOWNS AT THE POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2, TO SUPPORT IMPLEMENTATION OF NEAR-TERM TASK FORCE RECOMMENDATION 2.3 RELATED TO THE FUKUSHIMA DAI-ICHI NUCLEAR POWER PLANT ACCIDENT (TAC NOS. MF0161 AND MF0162)
Dear Mr. Meyer:
On March 12, 2012, the U.S. Nuclear Regulatory Commission staff (NRC or the staff) issued a 1
request for information letter per Title 10 to the Code of Federal Regulations, Subpart 50.54(f)
(the 50. 54(f) letter). The 50.54(f) letter was issued to power reactor licensees and holders of construction permits requesting addressees to provide further information to support the NRC staff's evaluation of regulatory actions to be taken in response to lessons learned from Japan's March 11, 2011, Great Tohoku Earthquake and subsequent tsunami. The request addressed the methods and procedures for plants to conduct seismic and flooding hazard walkdowns to identify and address degraded, nonconforming, or unanalyzed conditions through the corrective action program, and to verify the adequacy of the monitoring and maintenance procedures.
By letter dated November 26,2012, NextEra Energy Point Beach, LLC submitted a Seismic Walkdown Report as requested per Enclosure 3, "Recommendation 2.3: Seismic," of the 50.54(f) letter for the Point Beach Nuclear Plant (Point Beach), Units 1 and 2. The NRC staff plans to conduct a regulatory audit in accordance with the enclosed regulatory audit plan from June 17 - 19, 2013, to verify information and gain a better understanding of your conduct of the seismic walkdowns at Point Beach.
1 located in the Agencywide Document Access and Management System (ADAMS) at Accession No. Ml12053A340.
Mr. Meyer -2 If you have any questions, please contact me by telephone at 301-415-3049 or bye-mail at Terry.Beltz@nrc.gov.
Sincerely, Terry A. Beltz, Senior Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos.: 50-266 and 50-301
Enclosure:
As stated cc w/encl: Distribution via Listserv
Audit Plan Point Beach Nuclear Plant, Units 1 and 2
- 1. Background On March 12,2012, the U.S. Nuclear Regulatory Commission staff (NRC or the staff) issued a request for information letter1 per Title 10 to the Code of Federal Regulations, Subpart 50.54(f)
(the 50.54(f) letter). The request addressed, in part, the conduct of seismic walkdowns to identify and address degraded, non-conforming, or unanalyzed conditions through the corrective action program, and to verify the adequacy of the monitoring and maintenance procedures.
- 2. Regulatory Audit Bases The NRC staff is conducting regulatory audits at a small number of operating reactors to gain a better understanding of the seismic walkdown methods and associated procedures used by licensees to prepare the Seismic Walkdown Report and to assist the staff in preparing its safety assessment.
The guidance for performing the seismic walkdowns was developed by the Electric Power Research Institute (EPRI) with extensive review and input from NRC staff in numerous public meetings, webinars, and public conference calls during its development. The EPRI submitted EPRI-1025286, "Seismic Walkdown Guidance for Resolution of Fukushima Near-Term Task Force Recommendation 2.3: Seismic,,2 (walkdown guidance) for endorsement, and the staff subsequently endorsed the walkdown guidance by letter dated May 31, 2012 3 .
The 50.54(f) letter and the walkdown guidance are the basis documents for the conduct of the regulatory audit.
- 3. Regulatory Audit Scope The purpose of the seismic site audit will be to gain a better understanding of the conduct and outcomes of the seismic walkdowns and identify any need for additional information to facilitate the NRC staff's review of the licensee's walkdown report and prepare the staff assessment. If necessary, the NRC staff will request additional information using the appropriate regulatory process.
The scope of this regulatory audit is to determine if the seismic walkdowns conducted by NextEra Energy Point Beach, LLC (NextEra, the licensee) to identify and address degraded, non-conforming, or unanalyzed conditions, were conducted in accordance with the 50.54(f) letter and the walkdown guidance; and whether NextEra verified the adequacy of the monitoring and maintenance procedures in compliance with the 50.54(f) letter and the walkdown guidance.
1 Located in the Agencywide Document Access and Management System (ADAMS) at Accession No. ML12053A340.
2 Located in the Agencywide Document Access and Management System (ADAMS) at Accession No. ML12164A181 3 Located in the Agencywide Document Access and Management System (ADAMS) at Accession No. ML12145A529 Enclosure
2 The general process used to conduct the regulatory audit involves examination of related seismic walkdown documents, discussions with the seismic walkdown program participants, and examination of selected equipment or areas of the site that were walked down. This process is tailored for a site-specific audit as applicable.
The staff reviewed the licensee's walkdown report and compared it with the requested information in the 50.54(f) letter and the walkdown guidance. The factors that the NRC staff considered in choosing sites to audit were based, in part, on one or more of the following:
- Questions concerning whether the walkdown was performed consistent with the guidance
- Consideration of feedback and information gained during performance of regional inspections (e.g., Temporary Instruction 2515/188)
- Consideration of apparent seismicity relative to the current design basis or margins identified in the Individual Plant Examination for External Event (IPEEE) reviews Sections 4, 9, and 10 provide additional details regarding needed documentation, schedule, and specific focus areas.
- 4. Information Needs The licensee is requested to have the following information available on site for the audit team.
The information could be provided electronically or by paper copies. If provided electronically, the licensee is requested to have at least two computers available for the audit team, with a printer attached.
- Engineering reports and procedures which contain requirements or guidelines for the implementation of the seismic walkdown guidance including current seismic licensing basis.
- Description of process used for the peer review and the peer review report.
- Implementing procedures for the 10 CFR 50.54(f) letter, Enclosure 3, Seismic Walkdowns.
- Procedure for development of the seismic walkdown base lists and equipment lists (i.e.,
- Drawings of equipment anchorages for equipment selected for anchorage verifications.
- Discussion of training and qualifications (per Section 2) for personnel associated with seismic walkdown activities.
- Description of the process for licensing basis evaluations (per Section 5 of the walkdown guidance) and entry into the corrective action program, including condition report number, title, and brief summary of the issue or observation and its disposition.
The staff also requests the licensee to make personnel that performed the walkdowns (including site staff and contractors) accessible upon request (either in person or by phone).
Additional information needs identified during the audit will be communicated to the designated point of contact.
3
- 5. NRC Audit Team Management Oversight George Wilson (NRC)
Team Lead James Isom (NRC)
Technical Lead Annie Kammerer (NRC)
Technical Support Meghan Thorpe-Kavanaugh (NRC)
Technical Support Frankie Vega (NRC)
Technical Support Pravin Patel (NRC)
- 6. Logistics The audit will be conducted at Point Beach from June 17 - 19, 2013. Entrance and exit briefings will be held with the licensee at the beginning and end of this audit, respectively, as well as daily debriefings of team activities. A more detailed proposed audit schedule is provided below.
- 7. Deliverables An audit report/summary should be issued to the licensee within 90 days from the end of the audit. Additionally, the results of the audit will be utilized to focus the scope of any requests for additional information issued in the course of this review.
- 8. Proposed Seismic Walkdown Audit Schedule Monday, June 17 7:30 a.m. Arrival of audit team members and site badging 10:00 a.m. Entrance Meeting 10:30 a.m. Walkdown Process Orientation with licensee 11:30 a.m. -12:15 p.m. LUNCH 12:15 p.m. - 4:00 p.m. Discussions with licensee, NRC document review, or plant walkdowns 4:00 p.m. Team meeting 5:30 p.m. Team Lead daily debrief with licensee
4 Tuesday, June 18 7:30 a.m. Team meeting 8:30 a.m. Continue discussions with licensee, plant walkdowns, etc.
11:30 a.m. -12:15 p.m. LUNCH 12:15 p.m. - 4:00 p.m. Discussions with licensee, plant walkdowns, etc.
4:00 p.m. Team meeting 5:30 p.m. Team Lead daily debrief with licensee Wednesday, June 19 7:30 a.m. Team meeting 8:30 a.m. Continue discussions with licensee, plant walkdowns, etc.
11:30 a.m. -12:15 p.m. LUNCH 12:15 p.m. - 3:00 p.m. Discussions with licensee, plant walkdowns, etc.
3:00 p.m. Exit Meeting
- 9. Specific Topics for Discussion The review will touch upon several key areas of the walkdown activities undertaken by PBNP including:
- Qualification and training of participants
- Participation of operations staff
- Conduct of the walkdowns
- Process to address potential seismic issues identified in the walkdowns
- The peer review process During the NRC's review of the walkdown report, some items of particular interest were identified.
- The seismic walkdown guidance document provides guidance on the need for participants to have certain specific backgrounds and qualifications to effectively carry out their roles. The staff would like to discuss the backgrounds of the team members as it relates to experience in the seismic field.
- The seismic walkdown guidance discusses the participation and roles of operations staff.
The staff would like to discuss the nature and timing of participation of operations staff in the seismic walkdown activities, including in the development of the SWEL
- The seismic walkdown guidance provides clear instructions on the scope of peer review and the experience and independence of the peer reviewers. The staff would like to discuss with appropriate peer review personnel the scope of the peer review and independence of the peer reviewers.
5
- The seismic walkdown guidance provides clear instructions on the reporting of development of the SWEL, including the provision of base lists and the SWEL in the report for each unit. Each unit's report must stand on its own. The staff would like to discuss the development and reporting of the base lists (1 and 2) and SWEL (1 and 2).
- The seismic walkdown guidance provides guidance and instructions on both the conduct and the reporting of the seismic walkdowns and area walk-bys. The staff would like to discuss the conduct of the equipment walkdowns and area walk-bys, including the approach to anchorage verification, the approach to inspecting cabinets, and the treatment of the checklists.
- The seismic walkdown guidance provides clear guidance on the approach to addressing potential seismic issues found in the walkdowns. The staff would like to discuss the approach used to disposition potential issues identified, including the timeline for these activities.
- The seismic walkdown guidance provides information on the reporting of IPEEE commitments. The staff would like to discuss the IPEEE commitment information provided and review the licensee's complete list of IPEEE commitments.
Mr. Meyer -2 If you have any questions, please contact me by telephone at 301-415-3049 or bye-mail at Terry.Beltz@nrc.gov.
Sincerely, IRA!
Terry A. Beltz, Senior Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos.: 50-266 and 50-301
Enclosure:
As stated cc w/encl: Distribution via Listserv DISTRIBUTION:
PUBLIC RidsRgn3MailCenter Resource LPL3-1 RlF RidsAcrsAcnw MailCTR Resource RidsNrrLASRohrer Resource RidsNrrDorlLpl3-1 Resource RidsNrrPMPointBeach Resource RidsNroDsea Resource RidsNrrDori Resource DHuyck, EDO RI, RII, Rill, RIV RidsOpaMailCenter Resource Jlsom, NRR
- concurrence be-mail JLD/PMBIPM NRRlDIRS: TL*
LRegner Jisom 05/14/13 05/14/13 NRRlJLD: SLS NRO/DSEA: DD* DORULPL3-1/BC DORULPL3-1/PM NAME GWilson NChokshi RCarlson /SWall for TBeitz DATE 05/14/13 05/14/13 05/16/13 05/17113