MONTHYEARML13128A1042013-05-0101 May 2013 Inservice Testing Program for Pumps and Valves Fifth Ten Year Interval Update and Associated Relief Requests Project stage: Request ML13282A5762013-10-0202 October 2013 NRR E-mail Capture - RAI for Surry Power Station Unit 1, Relief Request P-5 Project stage: RAI ML13316A0062013-11-0505 November 2013 Inservice Testing Program for Pumps and Valves, Fifth Ten Year Interval Updated and Associated Relief Requests Response to Request for Additional Information - Relief Request P-5 Project stage: Response to RAI ML14125A4712014-05-0909 May 2014 Relief from the Requirements of the ASME Code Project stage: Approval 2013-11-05