MONTHYEARML24318A9432024-11-13013 November 2024 – Notification of Conduct of Phase II Inspection of Title 10 of the Code of Federal Regulations 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactor ML24310A0062024-11-0808 November 2024 – Acceptance of Requested Licensing Action Modification to Technical Specifications 3.6.1.2 and Main Stem Isolation Valve Leakage Requirements Amendment IR 05000352/20240032024-11-0808 November 2024 Integrated Inspection Report 05000352/2024003 and 05000353/2024003 ML24317A1432024-11-0404 November 2024 Constellation Energy Generation, LLC, 2024 Annual Report - Guarantees of Payment of Deferred Premiums ML24151A3842024-10-31031 October 2024 – Issuance of Amendment Nos. 264 and 226 Support to Digital Modernization Project Installation (EPID L-2023-LLA-0025) and Exemption from the Requirements of 10 CFR 50.62 ML24303A2782024-10-29029 October 2024 10 CFR 50.46 Annual Report ML24303A0902024-10-29029 October 2024 Operator Licensing Examination Approval ML24299A2642024-10-25025 October 2024 Response to Request for Supplemental Information Needed for Acceptance of Requested Licensing Action Regarding Primary Containment Leakage Technical Specifications IR 05000352/20240122024-10-17017 October 2024 Commercial Grade Dedication Inspection Report 05000352/2024012 and 05000353/2024012 RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24274A2372024-10-0707 October 2024 – Supplemental Information Needed for Acceptance of Requested Licensing Action Regarding Primary Containment Leakage Technical Specifications ML24278A3022024-10-0404 October 2024 Supplement to License Amendment Request to Revise Technical Specifications and Exemption Request from Requirements of 10 CFR 50.62 ATWS Rule to Support the Digital Modernization Project Installation - Rev Unit 2 Technical Spec ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing ML24263A0032024-09-27027 September 2024 Generation Station, Units 1 and 2 – Regulatory Audit Plan Supporting Review of the Component Interface Module System of the Limerick Digital Instrumentation and Controls License Amendment Request (EPID L-2022-LLA-0140) (Redacted) ML24243A0482024-09-19019 September 2024 Generation Station, Unit Nos. 1 and 2 - Schedule Update for License Amendment Request to Replace Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection System ML24215A4042024-09-18018 September 2024 Request for Withholding Information from Public Disclosure IR 05000352/20244202024-09-16016 September 2024 – Security Baseline Inspection Report 05000352/2024420 and 05000353/2024420 RS-24-090, Response to Request for Additional Information - Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds2024-09-12012 September 2024 Response to Request for Additional Information - Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds IR 05000352/20250102024-09-10010 September 2024 Information Request for Quadrennial Baseline Comprehensive Engineering Team Inspection; Notification to Perform Inspection 05000352/2025010 and 05000353/2025010 ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification IR 05000352/20230022024-09-0404 September 2024 Reissued Integrated Inspection Report 05000352/2023002 and 05000353/2023002 IR 05000352/20240052024-08-29029 August 2024 Updated Inspection Plan for Limerick Generating Station, Units 1 and 2 (Report 05000352/2024005 and 05000353/2024005) ML24241A1952024-08-28028 August 2024 License Amendment Request for Modification to Technical Specification 3.6.1.2 and Main Steam Isolation Valve Leakage Rate Requirements ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 ML24163A3902024-08-14014 August 2024 Request for Withholding Information from Public Disclosure IR 05000352/20240022024-08-12012 August 2024 Integrated Inspection Report 05000352/2024002 and 05000353/2024002 ML24220A2392024-08-12012 August 2024 Correction to Technical Specification Page 3/4 3-11 in Amendment No. 225 ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition ML24204A0712024-07-29029 July 2024 Issuance of Amendment Nos. 263 and 225 Technical Specifications for Main Steam Line Tunnel Temperature ML24208A0962024-07-25025 July 2024 57243-EN 57243 - Rssc Wire & Cable LLC, Dba Marmon - Part 21 Notification ML24208A1592024-07-25025 July 2024 Regulatory Audit Plan Supporting Review of the System Development Portion of Limerick Digital Instrumentation and Controls License Amendment Request (EPID L-2022-LLA-0140) - Non-Proprietary ML24201A1662024-07-19019 July 2024 Response to Request for Additional Information for License Amendment Request for Proposed Changes to the Technical Specification Isolation Actuation Instrumentation Tables and New Turbine Enclosure Main Steam L ML24199A1842024-07-15015 July 2024 RAI-LAR for Limerick EPID: L-2024-LLA-0079- Use This Version RS-24-070, Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions2024-07-12012 July 2024 Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions ML24180A1572024-06-28028 June 2024 Request to Return and Replace WEC Documents (EQ-EV-386-GLIM, EQ-QR- 433-GLIM, and APP-GW-GLR-611), to Meet 10CFR2.390 Request to Withdraw from Public Disclosure Requirements ML24170A7702024-06-20020 June 2024 Individual Notice of Consideration of Issuance of Amendments to Renewed Facility Operating Licenses, Proposed No Significant Hazards Consideration Determination, Opportunity for Hearing(Epid L-2024-LLA-0079) LTR 05000352/LER-2024-003, Core Operating Limits Report Thermal Limit Exceeded for Unit 1 Fuel Bundle GGK1232024-06-18018 June 2024 Core Operating Limits Report Thermal Limit Exceeded for Unit 1 Fuel Bundle GGK123 RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24166A1142024-06-14014 June 2024 Response to Requests for Additional Information (RAIs 15 Through 23) for License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog Control Systems ML24165A2642024-06-13013 June 2024 License Amendment Request for Proposed Changes to the Technical Specification Isolation Actuation Instrumentation Tables and New Turbine Enclosure Main Steam Line Tunnel Temperature TS 3/4.7.9 ML24151A2012024-06-10010 June 2024 Request for Withholding Information from Public Disclosure 05000352/LER-2024-001, Leakage for the Unit 1 `B Outboard Main Steam Isolation Valve Exceeded Technical Specification Limit2024-06-10010 June 2024 Leakage for the Unit 1 `B Outboard Main Steam Isolation Valve Exceeded Technical Specification Limit 05000352/LER-2024-002, Invalid Actuation Due to a Trip of 1B Reactor Protection System Circuit Breaker2024-06-10010 June 2024 Invalid Actuation Due to a Trip of 1B Reactor Protection System Circuit Breaker ML24151A2882024-06-10010 June 2024 Request for Withholding Information from Public Disclosure ML24150A0242024-05-29029 May 2024 Notification of Commercial Grade Dedication Inspection (05000352/2024012 and 05000353/2024012) and Request for Information ML24149A2112024-05-28028 May 2024 Supplement to License Amendment Request to Revise Technical Specifications and Exemption Request from Requirements of 10CFR50.62 ATWS Rule to Support the Digital Modernization Project Installation ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 IR 05000352/20243022024-05-20020 May 2024 Revised Initial Operator Licensing Examination Report 05000352/2024302 and 05000353/2024302 RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report 2024-09-06
[Table view] Category:Legal-Affidavit
MONTHYEARML24317A1432024-11-0404 November 2024 Constellation Energy Generation, LLC, 2024 Annual Report - Guarantees of Payment of Deferred Premiums ML24180A1572024-06-28028 June 2024 Request to Return and Replace WEC Documents (EQ-EV-386-GLIM, EQ-QR- 433-GLIM, and APP-GW-GLR-611), to Meet 10CFR2.390 Request to Withdraw from Public Disclosure Requirements ML24057A4272024-02-26026 February 2024 Response to Requests for Additional Information (RAIs 1, 2, and 3) for License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog Control ML23325A2062023-11-21021 November 2023 Supplement to License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection System ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums ML23212B2362023-07-31031 July 2023 Supplement to License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection System - WEC Documents ML23177A2242023-06-26026 June 2023 Supplement to License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection . ML23095A2232023-04-0505 April 2023 Supplement to License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection System (PPS)- Human Factors ML22320A5592022-11-16016 November 2022 2022 Annual Report - Guarantees of Payment of Deferred Premiums ML22301A1742022-10-28028 October 2022 Global Nuclear Fuel Americas, LLC (GNF) - Part 21 60-Day Interim Report Notification: GNF3 Raised Water Rod (SC-22-04 Rt) ML22224A1492022-08-15015 August 2022 Review of Limerick Generating Station Defense in Depth and Diversity Common Cause Failure Coping Analysis, WNA-AR-01074-GLIM-P, Revision 2, July 2022, and the Licensing Technical Report for the Limerick Generating Station Units 1&2 Digital ML22080A1992022-03-18018 March 2022 Affidavit for Proprietary Presentation for March 31, 2022 Pre-Submittal Meeting with Constellation Energy Generation, LLC Regarding Planned Digital Modernization License Amendment Request for Limerick Generating Station, Units 1 and 2 ML22046A0742022-02-14014 February 2022 Review of Limerick Generating Station Defense in Depth and Diversity Common Cause Failure Coping Analysis, WNA-AR-01074-GLIM-P, Rev 1. Without Attachment 3 Enclosure ML21307A0542021-11-0202 November 2021 Annual Report - Guarantees of Payment of Deferred Premiums ML21272A2772021-09-29029 September 2021 Update to Application for Order Approving License Transfers and Proposed Conforming License Amendments ML21182A1002021-06-30030 June 2021 Proposed Alternative to Utilize Code Case N-893 RS-21-070, Proposed Alternative to Utilize Code Case N-8932021-06-30030 June 2021 Proposed Alternative to Utilize Code Case N-893 ML21084A1792021-03-23023 March 2021 Introduction of High Burnup Lead Use Assemblies ML21057A2732021-02-25025 February 2021 Application for Order Approving License Transfers and Proposed Conforming License Amendments NMP1L3371, Summary of Changes, Quality Assurance Topical Report, NO-AA-10 & Decommissioning Quality Assurance Program, NO-DC-102021-02-10010 February 2021 Summary of Changes, Quality Assurance Topical Report, NO-AA-10 & Decommissioning Quality Assurance Program, NO-DC-10 ML20310A1152020-11-0404 November 2020 Annual Report - Guarantees of Payment of Deferred Premiums ML20273A2152020-09-29029 September 2020 License Amendment Request: Relocation of Pressure and Temperature Limit Curves to the Pressure and Temperature Limits Report ML19318G1702019-11-14014 November 2019 2019 Annual Report - Guarantees of Payment of Deferred Premiums ML18316A0032018-11-0707 November 2018 Submittal of 2018 Annual Report - Guarantees of Payment of Deferred Premiums ML15323A2572015-11-19019 November 2015 License Amendment Request - Safety Limit Minimum Critical Power Ratio Change ML15254A4142015-08-31031 August 2015 Revision of the Core Operating Limits Report (COLR) for Reload 15, Cycle 16 ML14321A7052014-11-14014 November 2014 2014 Annual Report - Guarantees of Payment of Deferred Premiums ML14204A7092014-07-23023 July 2014 Enclosure 3, Affidavit of Peter M. Yandow RS-14-160, Co. - Submission of Standard Practice Procedure Plans and Foreign Ownership Control or Influence Package2014-07-0202 July 2014 Co. - Submission of Standard Practice Procedure Plans and Foreign Ownership Control or Influence Package ML14112A5832014-04-11011 April 2014 Issuance of the Core Operating Limits Report for Cycle 16 Revision 11 ML13123A0342013-04-26026 April 2013 Issuance of the Core Operating Limits Report for Cycle 15, Revision 10 RS-12-227, Exelongeneration, Submission of Standard Practice Procedure Plans and Updated Foreign Ownership Control or Influence Package2012-12-19019 December 2012 Exelongeneration, Submission of Standard Practice Procedure Plans and Updated Foreign Ownership Control or Influence Package ML1127000682011-09-26026 September 2011 Enclosure 3, Mfn 10-245 R4, Affidavit ML1104905722011-02-17017 February 2011 Response to Request for Additional Information Concerning the Safety Limit Minimum Critical Power Ratio Change License Amendment Request ML1031904262010-11-0808 November 2010 Corp. - 2010 Annual Report - Guarantees of Payment of Deferred Premiums ML1008503912010-03-18018 March 2010 GE-Hitachi Nuclear Energy Americas, LLC Affidavit Requesting That GEH Proprietary Report, NEDC-33484P Be Withheld from Public Disclosure ML0520003282005-07-14014 July 2005 Surveillance Program for Channel-Control Blade Interference ML0507000112005-02-25025 February 2005 Response to Information Request Regarding Significance Determination Process Risk-informed Inspection Notebook 2024-06-28
[Table view] |
Text
Exelon Nuclear nLimerick Exe onh o Generation G ei A Generating Station 3146 Sanatoga Road Pottstown. PA 19464 610 718 3324 Fax T.S. 6.9.1.12 April 26, 2013 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 Limerick Generating Station, Unit 2 Facility Operating License No. NPF-85 NRC Docket Nos. 50-353
Subject:
Issuance of the Core Operating Limits Report For Cycle 15 Revision 10 Enclosed is a copy of the Core Operating Limits Report (COLR) for Limerick Generating Station (LGS)
Unit 2 Reload 12 Cycle 13 Revision 8 which incorporates the revised cycle specific parameters resulting from the new configuration implemented for LGS, Unit 2.
The COLR is being submitted to the NRC in accordance LGS, Unit 2 Technical Specification 6.9.1.12.
Enclosure 1 contains an affidavit from Global Nuclear Fuels-Americas which provides the basis for withholding Enclosure 2 from public disclosure.
Enclosure 2 contains the COLR with an Appendix A -Proprietary Class III (Confidential) which contains confidential information from a private company, the disclosure of which would constitute a release of commercial information. Therefore, the information in Enclosure 2 Appendix A (confidential) is being submitted to the Commission with a request that it be withheld from public disclosure in accordance with 10CFR2.390(a)(4).
Enclosure 3 contains the COLR with an Appendix A-Proprietary Class I (Public) which is releasable to the public.
If you have any questio require additional information, please do not hesitate to contact us.
Sincerely, Thomas J. Dougherty Site Vice President-LGS Exelon Generation Company, LLC Enclosure 1: Affidavit- Global Nuclear Fuels-Americas Enclosure 2: Unit 2 COLR for Cycle 13 Rev. 8 Appendix A Proprietary Class III (Confidential)
Enclosure 3: Unit 2 COLR for Cycle 13 Rev. 8 Appendix A Non-Proprietary Information-Class I (Public) cc: W. Dean, Administrator, Region I, USNRC (w/Attachments)
E. DiPaolo, USNRC Sr. Resident Inspector, LGS (w/o Attachments)
R. Ennis, USNRC Project Manager for LGS (w/Attachments)
R. R. Janati, PADEP-BRP(w/Attachments)
bcc: T. Dougherty-GML-5 (w/o Attachments)
D. Lewis-GML-5 (w/o Attachments)
R. Kreider-GML-5 (w/o Attachments)
G. Rubinacio-SSB 4-2 (w/o Attachments)
R. Dickinson-SSB 2-4 (w/Attachments)
D. Helker-KSA (w/o Attachments)
A. Donell KSA (w/o Attachments) (w/o Attachments)
M. Murphy-PADEP BRP (SSB 2-4) (w/o Attachments)
ENCLOSURE 1 AFFIDAVIT GLOBAL NUCLEAR FUEL AMERICAS
Global Nuclear Fuel - Americas AFFIDAVIT I, Lukas Trosman, state as follows:
(1) I am Engineering Manager, Reload Design and Analysis, Global Nuclear Fuel -
Americas, LLC (GNF-A), and have been delegated the function of reviewing the information described in paragraph (2) which is sought to be withheld, and have been authorized to apply for its withholding.
(2) The information sought to be withheld is contained in GNF-A proprietary report 0000-0157-6733-FBIR-P, Fuel Bundle Information Report for Limerick Unit 2 Reload 12 Cycle 13, Revision 0, February 2013. GNF-A proprietary information in 0000-0157-6733-FBIR-P, Fuel Bundle Information Report for Limerick Unit 2 Reload 12 Cycle 13, Revision 0, February 2013 is identified by a dotted underline inside double square brackets. ((This.setn....pe.)) Figures and large equation objects are identified with double square brackets before and after the object. In each case, the superscript notation (3( refers to Paragraph (3) of this affidavit, which provides the basis for the proprietary determination.
(3) In making this application for withholding of proprietary information of which it is the owner or licensee, GNF-A relies upon the exemption from disclosure set forth in the Freedom of Information Act ("FOIA"), 5 USC Sec. 552(b)(4), and the Trade Secrets Act, 18 USC Sec. 1905, and NRC regulations 10 CFR 9.17(a)(4), and 2.390(a)(4) for "trade secrets" (Exemption 4). The material for which exemption from disclosure is here sought also qualify under the narrower definition of "trade secret", within the meanings assigned to those terms for purposes of FOIA Exemption 4 in, respectively, Critical Mass Energy Project v. Nuclear Regulatory Commission, 975 F2d 871 (DC Cir. 1992), and Public Citizen Health Research Group v. FDA, 704 F2d 1280 (DC Cir. 1983).
(4) Some examples of categories of information which fit into the definition of proprietary information are:
- a. Information that discloses a process, method, or apparatus, including supporting data and analyses, where prevention of its use by GNF-A's competitors without license from GNF-A constitutes a competitive economic advantage over other companies;
- b. Information which, if used by a competitor, would reduce his expenditure of resources or improve his competitive position in the design, manufacture, shipment, installation, assurance of quality, or licensing of a similar product;
- c. Information which reveals aspects of past, present, or future GNF-A customer-funded development plans and programs, resulting in potential products to GNF-A;
- d. Information which discloses patentable subject matter for which it may be desirable to obtain patent protection.
0000-01 57-6733-FBIR-P Affidavit Page I of 3
The information sought to be withheld is considered to be proprietary for the reasons set forth in paragraphs (4)a. and (4)b. above.
(5) To address 10 CFR 2.390 (b) (4), the information sought to be withheld is being submitted to NRC in confidence. The information is of a sort customarily held in confidence by GNF-A, and is in fact so held. The information sought to be withheld has, to the best of my knowledge and belief, consistently been held in confidence by GNF-A, no public disclosure has been made, and it is not available in public sources. All disclosures to third parties including any required transmittals to NRC, have been made, or must be made, pursuant to regulatory provisions or proprietary agreements which provide for maintenance of the information in confidence. Its initial designation as proprietary information, and the subsequent steps taken to prevent its unauthorized disclosure, are as set forth in paragraphs (6) and (7) following.
(6) Initial approval of proprietary treatment of a document is made by the manager of the originating component, the person most likely to be acquainted with the value and sensitivity of the information in relation to industry knowledge, or subject to the terms under which it was licensed to GNF-A. Access to such documents within GNF-A is limited on a "need to know" basis.
(7) The procedure for approval of external release of such a document typically requires review by the staff manager, project manager, principal scientist or other equivalent authority, by the manager of the cognizant marketing function (or his delegate), and by the Legal Operation, for technical content, competitive effect, and determination of the accuracy of the proprietary designation. Disclosures outside GNF-A are limited to regulatory bodies, customers, and potential customers, and their agents, suppliers, and licensees, and others with a legitimate need for the information, and then only in accordance with appropriate regulatory provisions or proprietary agreements.
(8) The information identified in paragraph (2) is classified as proprietary because it contains details of GNF-A's fuel design and licensing methodology. The development of this methodology, along with the testing, development and approval was achieved at a significant cost to GNF-A.
The development of the fuel design and licensing methodology along with the interpretation and application of the analytical results is derived from an extensive experience database that constitutes a major GNF-A asset.
(9) Public disclosure of the information sought to be withheld is likely to cause substantial harm to GNF-A's competitive position and foreclose or reduce the availability of profit-making opportunities. The information is part of GNF-A's comprehensive BWR safety and technology base, and its commercial value extends beyond the original development cost. The value of the technology base goes beyond the extensive physical database and analytical methodology and includes development of the expertise to determine and apply the appropriate evaluation 0000-01 57-6733-FBIR-P Affidavit Page 2 of 3
process. In addition, the technology base includes the value derived from providing analyses done with NRC-approved methods.
The research, development, engineering, analytical, and NRC review costs comprise a substantial investment of time and money by GNF-A.
The precise value of the expertise to devise an evaluation process and apply the correct analytical methodology is difficult to quantify, but it clearly is substantial.
GNF-A's competitive advantage will be lost if its competitors are able to use the results of the GNF-A experience to normalize or verify their own process or if they are able to claim an equivalent understanding by demonstrating that they can arrive at the same or similar conclusions.
The value of this information to GNF-A would be lost if the information were disclosed to the public. Making such information available to competitors without their having been required to undertake a similar expenditure of resources would unfairly provide competitors with a windfall, and deprive GNF-A of the opportunity to exercise its competitive advantage to seek an adequate return on its large investment in developing and obtaining these very valuable analytical tools.
I declare under penalty of perjury that the foregoing affidavit and the matters stated therein are true and correct to the best of my knowledge, information, and belief.
Executed on this 14th day of February 2013.
Lukas Trosman Engineering Manager, Reload Design and Analysis Global Nuclear Fuel - Americas, LLC 0000-01 57-6733-FBIR-P Affidavit Page 3 of 3