WBN2Public Resource From: Boyd, Desiree L [dlboyd@tva.gov]

Sent: Tuesday, March 12, 2013 8:16 AM To: Hon, Andrew; Epperson, Dan; Quichocho, Jessie; Poole, Justin Cc: Arent, Gordon; Odell, James Hollace; Boyd, Desiree L; Hamill, Carol L

Subject:

TVA letter to NRC_03-12-2013_Code Transition Change to two Previous Statements Attachments: 03-12-2013_Code Transition Change to two Previous Statements_Final.pdf Please see attached TVA letter that was sent to the NRC today.

Thank You

~*~*~*~*~*~*~*~*~*~*~

Désireé L. Boyd WBN Unit 2 Licensing dlboyd@tva.gov 423-365-8764 NOTICE: This electronic message transmission contains information which may be TVA SENSITIVE, TVA RESTRICTED, or TVA CONFIDENTIAL. Any misuse or unauthorized disclosure can result in civil penalties. If you are not the intended recipient, be aware that any disclosure, copying, distribution or use of the content of this information is prohibited. If you have receive this communication in error, please notify me immediately by e-mail and delete the original message.

1

Hearing Identifier: Watts_Bar_2_Operating_LA_Public Email Number: 796 Mail Envelope Properties (7AB41F650F76BD44B5BCAB7C0CCABFAF3E97316A)

Subject:

TVA letter to NRC_03-12-2013_Code Transition Change to two Previous Statements Sent Date: 3/12/2013 8:16:23 AM Received Date: 3/12/2013 8:16:29 AM From: Boyd, Desiree L Created By: dlboyd@tva.gov Recipients:

"Arent, Gordon" <garent@tva.gov>

Tracking Status: None "Odell, James Hollace" <jhodell@tva.gov>

Tracking Status: None "Boyd, Desiree L" <dlboyd@tva.gov>

Tracking Status: None "Hamill, Carol L" <clhamill@tva.gov>

Tracking Status: None "Hon, Andrew" <Andrew.Hon@nrc.gov>

Tracking Status: None "Epperson, Dan" <Dan.Epperson@nrc.gov>

Tracking Status: None "Quichocho, Jessie" <Jessie.Quichocho@nrc.gov>

Tracking Status: None "Poole, Justin" <Justin.Poole@nrc.gov>

Tracking Status: None Post Office: TVANUCXVS2.main.tva.gov Files Size Date & Time MESSAGE 759 3/12/2013 8:16:29 AM 03-12-2013_Code Transition Change to two Previous Statements_Final.pdf 86041 Options Priority: Standard Return Notification: No Reply Requested: Yes Sensitivity: Normal Expiration Date:

Recipients Received:

Tennessee Valley Authority, Post Office Box 2000, Spring City, Tennessee 37381-2000 March 12, 2013 10 CFR 50.55a U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Watts Bar Nuclear Plant, Unit 2 NRC Docket No. 50-391

Subject:

WATTS BAR NUCLEAR PLANT (WBN) UNIT 2 - TRANSITION FROM AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME) BOILER AND PRESSURE VESSEL CODE SECTION III DIVISION I TO SECTION XI -

MODIFICATION OF TWO PREVIOUS STATEMENTS

References:

1. TVA letter to NRC dated October 11, 2010, Watts Bar Nuclear Plant (WBN)

Unit 2 - Transition from American Society of Mechanical Engineers (ASME)

Boiler and Pressure Vessel Code Section III Division I to Section XI

2. TVA letter to NRC dated September 1, 2011, Watts Bar Nuclear Plant (WBN) Unit 2 - American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code Transition - Revised Commitment The purpose of this submittal is to provide modification to two statements contained in Reference 1. The first statement appears in the first paragraph on page 2 of Reference 1, which states as follows:

Upon completion of system N-Stamping, the ASME Section III Owner, TVA Nuclear Generation Development and Construction (NGDC), will transfer jurisdiction of the ASME Section III Code piping system to TVA Nuclear Power Group (NPG), for control under their ASME Section XI Program, QA Program, TVA-NQA-PLN89-A, and related procedures.

U.S. Nuclear Regulatory Commission Page 2 March 12, 2013 By this letter, TVA modifies this statement to read as follows:

Upon completion of system N-Stamping, WBN Unit 2 may elect to transfer jurisdiction of the ASME Section III Code piping system to the ASME Section XI Program, NPG-SPP-09.1, QA Program, TVA-NQA-PLN89-A, and related procedures.

The second statement requiring modification also appears on page 2 of Reference 1 as the second sentence of the second paragraph and reads as follows:

All subsequent repair and replacement activities will be performed using the TVA NPG and WBN Unit 1 ASME Section XI Repair and Replacement Program procedures which comply with ASME Section XI-2001 Edition through 2003 Addenda.

TVA modifies this statement to read as follows:

All subsequent repair and replacement activities will be performed using the TVAs ASME Section XI Repair and Replacement Program procedures which comply with ASME Boiler and Pressure Vessel Code Section XI, Division 1, 2001 Edition through 2003 Addenda, Article IWX-4000, for the Repair and Replacement of class 1, 2 and 3 and class MC components.

TVA makes these changes to provide greater flexibility for TVA to define internally when the jurisdiction for a given system transfers to Section XI. If a system is transferred to ASME Section XI, the Unit 2 Nuclear Construction organization will follow TVAs ASME Section XI requirements/processes until the system is transferred to the Operating plant organization.

It is also important to note that neither of these two changes affects clarifications for the Section III to Section XI transition made in Reference 2. The clarifications made in Reference 2 remain valid as stated in that reference.

U.S. Nuclear Regulatory Commission Page 4 March 12, 2013 bcc: Jessie Quichocho U.S. Nuclear Regulatory Commission MS 08G9A One White Flint North 11555 Rockville Pike Rockville, Maryland 20852-2738 Fred Brown, Deputy Regional Administrator for Construction U. S. Nuclear Regulatory Commission Region II Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257