Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding the Flood Hazard Reevaluation of Recommendation 2.1
ML13095A195
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 03/11/2013
From: Kiley M
Florida Power & Light Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
L-2013-087
Download: ML13095A195 (2)


Text

0 March 11, 2013 FPL.

L-2013-087 10 CFR 50.54(f)

U.S. Nuclear Regulatory Commission Attn: Document Control Desk 11555 Rockville Pike, Rockville, MD 20852 Re: Turkey Point Units 3 and 4 Docket Nos. 50-250 and 50-251 Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding the Flood Hazard Reevaluation of Recommendation 2.1

References:

1. NRC Letter, Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendations 2.1, 2.3, and 9.3, of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident, dated March 12, 2012, ML12073A348.
2. NRC Letter, Prioritization of Response Due Dates for Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Flooding Hazard Reevaluations for Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident, dated May 11, 2012, ML12097A509.

On March 12, 2012, the Nuclear Regulatory Commission (NRC) issued Reference 1 to all power reactor licensees and holders of construction permits in active or deferred status. Enclosure 2 of Reference 1 contains specific Requested Actions, Requested Information and Required Responses associated with Recommendation 2.1 for Flooding Hazard Reevaluation. Item 1 of the Requested Information asks for a final Hazard Reevaluation Report.

Per Reference 2, the Flood Hazard Reevaluation Report for Turkey Point is to be submitted by March 12, 2013, which corresponds to one (1) year from the date of Reference 1.

Submitted herein is the Florida Power & Light Company (FPL) Turkey Point Units 3 and 4 Flood Hazard Reevaluation Report. The report includes an Interim Action Plan that documents actions planned or taken to address the reevaluated hazard.

Florida Power & Light Company 9760 S.W. 344th Street Homestead, FL 33035

L-2013-087 Page 2 Subsequently, as requested in Item 2, of Enclosure 2 of Reference 1, FPL will perform an integrated assessment, which will 1) evaluate the effectiveness of the current licensing basis (i.e., flood protection and mitigation systems), 2) identify plant-specific vulnerabilities, and 3) assess the effectiveness of existing or planned systems and procedures for protecting against and mitigating consequences for the entire duration of the flood event.

In accordance with the required responses as identified in Enclosure 2 of Reference 1, FPL will complete and submit to NRC the Turkey Point Units 3 and 4 Integrated Assessment Report prior to March 12, 2015.

This letter contains no new regulatory commitments.

Should you have any questions concerning the content of this letter, please contact Robert J. Tomonto, Licensing Manager, at (305) 746-7327.

I declare under penalty of perjury that the foregoing is true and correct.

Executed on March //, 2013.

Sincerely, Michael Kiley Vice President Turkey Point Nuclear Plant Enclosure cc:

USNRC Regional Administrator, Region II, USNRC Senior Resident Inspector Turkey Point USNRC Project Manager for Turkey Point