UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 April 9, 2013 Mr. Kevin Walsh, Site Vice President clo Michael O'Keefe Seabrook Station NextEra Energy Seabrook, LLC P.O. Box 300 Seabrook, NH 03874

SUBJECT:

SEABROOK STATION, UNIT 1 - REVIEW OF THE PHYSICAL SECURITY PLAN, REVISION 18

Dear Mr. Walsh:

By letter dated August 1,2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML12216A086), as supplemented November 27,2012 (ADAMS Accession No. ML12335A010), NextEra Energy Seabrook, LLC (NextEra, the licensee) submitted the Seabrook Station's Physical Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan, Revision 18. The enclosures to the letters contained Safeguards Information and were withheld from public disclosure.

The U.S. Nuclear Regulatory Commission (NRC) staff reviewed the submittal to ensure compliance with Title 10 of the Code of Federal Regulations, Section 50.54(p)(2). The NRC staff has completed its review and has no further questions at this time.

If you have questions, you can contact me at 301-415-3100 or John.Lamb@nrc.gov.

~Wp J.b n G. Lamb, Senior Project Manager Iflant licensing Branch 1-2 I:\>ivision of Operating Reactor Licensing dffice of Nuclear Reactor Regulation Docket No. 50-443 cc: Distribution via Listserv

April 9, 2013 Mr. Kevin Walsh, Site Vice President c/o Michael O'Keefe Seabrook Station NextEra Energy Seabrook, LLC P.O. Box 300 Seabrook, NH 03874

SUBJECT:

SEABROOK STATION, UNIT 1 - REVIEW OF THE PHYSICAL SECURITY PLAN, REVISION 18

Dear Mr. Walsh:

By letter dated August 1, 2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML12216A086), as supplemented November 27,2012 (ADAMS Accession No. ML12335A010), NextEra Energy Seabrook, LLC (NextEra, the licensee) submitted the Seabrook Station's Physical Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan, Revision 18. The enclosures to the letters contained Safeguards Information and were withheld from public disclosure.

The U.S. Nuclear Regulatory Commission (NRC) staff reviewed the submittal to ensure compliance with Title 10 of the Code of Federal Regulations, Section 50.54(p)(2). The NRC staff has completed its review and has no further questions at this time.

If you have questions, you can contact me at 301-415-3100 or John.Lamb@nrc.gov.

Sincerely,

/ra!

John G. Lamb, Senior Project Manager Plant Licensing Branch 1-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-443 cc: Distribution via Listserv DISTRIBUTION:

PUBLIC LPLI-2 R/F RidsAcrsAcnw_MailCTR Resource RidsNrrDorlDpr Resource RidsNrrDorlLpl1-2 Resource RidsRgn1MailCenter Resource RidsNrrPMSeabrook Resource RidsNrrLAABaxter Resource RidsNsirDspERslb Resource ARoundtree, NSIR ADAMS ACCESSION NO' ML13092A166 OFFICE LPL1-2/PM LPL1-21LA NSIR/DSP/BC LPL1-2/BC LPL1-2/PM NAME JLamb ABaxter* RFelts MKhanna JLamb DATE 04/08/1 3 04108/13 03/21/13 04/09113 04/09/13 OFFICIAL RECORD COPY