Text

Entergy Entergy Nuclear Operations, Inc.

Vermont Yankee 320 Governor Hunt Rd.

Vernon, VT 802-257-7711 Christopher J. Wamser Site Vice President BVY 13-024 March 29, 2013 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001

SUBJECT:

REFERENCES:

Technical Specifications Proposed Change 300, Supplement 2 Vermont Yankee Nuclear Power Station Docket No. 50-271 License No. DPR-28

1.

Letter, Entergy Nuclear Operations, Inc. to USNRC, "Proposed Change No. 300 Renewed Facility Operating License Condition 3.P and 3.Q Changes," BVY 12-015, dated March 5, 2012

2.

Letter, Entergy Nuclear Operations, Inc. to USNRC, "Technical Specifications Proposed Change No. 300, Supplement 1, Response to Request for Additional Information," BVY 12-067, dated November 20, 2012

Dear Sir or Madam:

In Reference 1, Entergy Nuclear Operations, Inc. (Entergy) submitted a request for an amendment to the Vermont Yankee (VY) renewed facility operating license (RFOL) to revise license conditions (LC) 3.P and 3.Q related to license renewal commitments. Reference 2 provided a response to an NRC request for additional information (RAI). The RAI response included a proposed revision to LC 3.Q that would result in the LC being historical in context. As discussed with the NRC Office of Nuclear Reactor Regulation Project Manager for VY, VY proposes that LC 3.Q be deleted in its entirety because VY is already in the period of extended operation and LC 3.Q would no longer be applicable. This proposed change is considered administrative in nature.

This supplement to the original license amendment request does not change the scope or conclusions in the original application, nor does it change Entergy's determination of no significant hazards consideration.

There are no new regulatory commitments being made in this letter.

Should you have any questions concerning this letter or require additional information, please contact Robert Wanczyk at 802-451-3166.

A kt1

BVY 13-024 / Page 2 of 2 I declare under penalty of perjury that the foregoing is true and correct.

Executed on March 29, 2013.

Sincerely, CJW/plc cc:

Mr. William M. Dean Regional Administrator, Region 1 U.S. Nuclear Regulatory Commission 2100 Renaissance Blvd, Suite 100 King of Prussia, PA 19406-2713 Mr. Richard V. Guzman, Project Manager Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Mail Stop O-8-C2 Washington, DC 20555 USNRC Resident Inspector Entergy Nuclear Vermont Yankee, LLC 320 Governor Hunt Road Vernon, Vermont 05354 Mr. Christopher Recchia Commissioner Vermont Department of Public Service 112 State Street - Drawer 20 Montpelier, Vermont 05620-2601