|
---|
Category:Letter
MONTHYEARIR 05000361/20240052024-10-0404 October 2024 NRC Inspection Report 05000361/2024005 and 05000362/2024005 ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status IR 07200041/20244012024-08-16016 August 2024 San Onofe Nuclear Generating Station, Security Baseline Inspection Report 07200041/2024401 IR 05000361/20240042024-08-0909 August 2024 NRC Inspection Report 05000361/2024004 and 05000362/2024004 ML24191A2472024-07-0202 July 2024 (Songs), Units 1, 2, and 3, and the Independent Spent Fuel Storage Installation - Revision to the ISFSI-Only Emergency Plan and Associated Changes to Emergency Plan Implementing Procedures ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities ML24141A0802024-05-15015 May 2024 (Songs), Units 1, 2 and 3 and Independent Spent Fuel Storage Installation - 2023 Annual Radiological Environmental Operating Report IR 05000361/20240022024-04-0101 April 2024 – NRC Inspection Report 050-00361/2024-002 and 050-00362/2024-002 ML24094A0642024-03-27027 March 2024 Independent Spent Fuel Storage Installation, Decommissioning Funding Status Report 2023 ML24065A0152024-02-28028 February 2024 Generation Station Units 1, 2 and 3, Annual Radioactive Effluent Release Report for Independent Spent Fuel Storage Installation 2023 ML24044A0812024-02-14014 February 2024 LTR-24-0008: NRC Response to Paul Blanch Email Safety of Spent Nuclear Fuel at SONGS ISFSI IR 05000361/20240012024-02-13013 February 2024 NRC Inspection Report 050-00361/2024-001 and 050-00362/2024-001 (1) ML24037A0542024-01-30030 January 2024 (Songs), Units 2 and 3, Submittal of Annual Corporate Financial Reports ML24022A1492024-01-17017 January 2024 Independent Spent Fuel Storage Installation, Revision 4 to the Physical Security Plan ML24017A2432024-01-15015 January 2024 LTR-24-0008 Paul Blanch, E-mails Request for Formal Response to Requests for Meeting to Discuss Safety Issues with NRC Staff IR 05000361/20230062023-11-29029 November 2023 NRC Inspection Report 05000361/2023-006 and 05000362/2023-006 ML23333A0682023-11-22022 November 2023 (SONGS) Units 1, 2, 3 and Independent Spent Fuel Storage Installation - Notification of Change in Nuclear Officer IR 05000361/20230052023-10-11011 October 2023 NRC Inspection Report 05000361/2023005 and 05000362/2023005 ML23276A5942023-09-28028 September 2023 And Independent Spent Fuel Storage Installation - Supplement to Decommissioning Funding Status Reports ML23268A0922023-09-20020 September 2023 Generation Station, Units 1, 2 and 3, and the Independent Spent Fuel Storage Facility (ISFSI) - Re-Registration of Dry Fuel Storage Casks for Amended Certificate of Compliance No. 1040 IR 05000361/20230012023-09-13013 September 2023 NRC Inspection Report 05000361 2023-001 and 05000362 2023-004 ML23240A5372023-08-18018 August 2023 Confirmatory Survey Activities Summary and Results for the Unit 2 and 3 Intake Structures at the San Onofre Nuclear Generating Station San Clemente CA ML23129A1802023-06-14014 June 2023 Cover Letter to State of CA on Draft EA Regarding San Onofre ISFSI Updated DFPs IR 05000361/20230032023-05-31031 May 2023 NRC Inspection Report 05000361/2023003 and 05000362/2023003 IR 05000361/20230022023-05-23023 May 2023 NRC Inspection Report 05000361/2023-002 and 05000362/2023-002 ML23137A1032023-05-11011 May 2023 (Songs), Units 1, 2 and 3, and Independent Spent Fuel Storage Installation - 2022 Annual Radiological Environmental Operating Report ML23123A0932023-04-28028 April 2023 (Songs), Units 1, 2 and 3, Submittal of Annual Radioactive Effluent Release Report - 2022 ML23230A0882023-04-10010 April 2023 Independent Spent Fuel Storage Installation - Decommissioning Quality Assurance Plan ML23094A1272023-03-29029 March 2023 Independent Spent Fuel Storage Installation - 10 CFR 50.82(a)(8)(v and VII) and 10 CFR 72.30(c) Decommissioning Funding Status Report 2021 ML23094A1332023-03-29029 March 2023 Nuclear Property Insurance ML23062A1172023-02-28028 February 2023 Generation Station Units 1, 2 and 3, Annual Radioactive Effluent Release Report for Independent Spent Fuel Storage Installation - 2022 ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities ML23059A2812023-02-22022 February 2023 (Songs), Units 1, 2 and 3, 2022 Annual Turtle Incidental Take Report ML23046A3792023-02-22022 February 2023 NRC Inspection Report 050-00361/2023-001 and 050-00362/2023-001 ML23045A2022023-02-0909 February 2023 Submittal of Annual Corporate Financial Reports for San Onofre Nuclear Generating Station (SONGS) Units 2 and 3 for Fy Ending June 30, 2022 ML22287A1352023-01-0505 January 2023 Issuance of Exemption from Title 10 of the Code of Federal Regulations Part 72.106(B), Independent Spent Fuel Storage Installation Controlled Area Boundary (L-2021-LLE-0056) ML22348A0622023-01-0404 January 2023 NRC to SCE, Transmittal of the National Marine Fisheries Services December 12, 2022, Letter of Concurrence for Decommissioning of San Onofre Nuclear Generating Statiion, Units 2 and 3 IR 05000206/20220062022-12-15015 December 2022 NRC Inspection Report 05000206/2022006, 05000361/2022-006, and 05000362/2022-006 ML22347A2122022-12-12012 December 2022 NMFS to NRC, Endangered Species Act Section 7(a)(2) Concurrence Letter for Decommissioning of the San Onofre Nuclear Generating Station ML22340A6652022-12-0505 December 2022 Letter from John Fassell, Chief; Re., State of California Department of Public Health Review and Comments on SONGS Draft Environmental Assessment ML22333A8192022-11-21021 November 2022 Submittal of San Onofre Nuclear Generating Station, Units 2 and 3, Defueled Safety Analysis Report, Revised November 2022 IR 05000361/20220052022-11-17017 November 2022 – NRC Inspection Report 05000361/2022-005 and 05000362/2022-005 ML22301A1462022-10-20020 October 2022 Report of Violations of the National Pollutant Discharge Elimination System Permit San Onofre Nuclear Generating Station (Songs), Units 2 and 3 ML22277A0162022-09-29029 September 2022 Independent Spent Fuel Storage Installation Response to Request for Additional Information Regarding Request for Exemption from 10 CFR 72.106(b) IR 05000361/20220042022-09-26026 September 2022 NRC Inspection Report 05000361/2022-004 and 05000362/2022-004 ML22238A0552022-08-29029 August 2022 U.S. Nuclear Regulatory Commissions Analysis of Southern California Edisons Decommissioning Funding Status Report for San Onofre Nuclear Generating Station, Units 1, 2, and 3 ML22234A1602022-07-31031 July 2022 Final Report Per 10 CFR Part 21, Degraded Snubber SF1154 Hydraulic Fluid Batch No. 18CLVS431 ML22207B8612022-07-26026 July 2022 NRC (Public) Inspection Report 05000361/2022003; 05000362/2022003 IR 05000361/20220032022-07-26026 July 2022 NRC Inspection Report (Public) 05000361-2022003 and 05000362-2022003 (002) IR 05000361/20220022022-05-12012 May 2022 NRC Inspection Report 05000361/2022-002 and 05000362/2022-002 2024-09-18
[Table view] Category:Financial Assurance Document
MONTHYEARML23045A2012022-06-30030 June 2022 Annual Financial Statements for Fiscal Year Ended June 30, 2022; City of Riverside ML23045A2002022-06-30030 June 2022 Annual Financial Statements for Fiscal Year Ended June 30, 2022; City of Anaheim ML21077A0762021-03-11011 March 2021 Nuclear Property Insurance ML20079J0322020-03-17017 March 2020 Independent Spent Fuel Storage Installation (ISFSI) - Decommissioning Funding Status Report for Calendar Year 2019 ML18152A8622018-05-29029 May 2018 Annual Report of Guarantee of Payment of Deferred Premium ML18129A2142018-04-23023 April 2018 American Nuclear Insurers - Notification of Change in the Number of Power Reactors in the Secondary Financial Protection (SFP) Program ML18082A3662018-03-19019 March 2018 Nuclear Property Insurance ML17146A9052017-05-24024 May 2017 Annual Report of Guarantee of Payment of Deferred Premium ML16153A2352016-05-26026 May 2016 Annual Report of Guarantee of Payment of Deferred Premium - ML16032A1252016-01-0808 January 2016 Certificate of Liability Insurance ML15092A1342015-03-31031 March 2015 Submittal of Decommissioning Funding Status Report ML15092A1612015-03-31031 March 2015 Submittal of Decommissioning Funding Status Report ML14090A0912014-03-26026 March 2014 Nuclear Property Insurance ML13148A0592013-05-23023 May 2013 Southern California Edison (SCE) - Annual Report of Guarantee of Payment of Deferred Premium ML13091A0732013-03-27027 March 2013 CFR 50.75(f)(1) Decommissioning Funding Report ML13081A2692013-03-20020 March 2013 Nuclear Property Insurance ML13053A2102013-01-30030 January 2013 Annual Corporate Financial Reports ML12152A3102012-05-31031 May 2012 Annual Report of Guarantee of Payment of Deferred Premium ML1123719022011-11-14014 November 2011 2010 DFS Report Analysis for San Onofre Nuclear Generating Station, Unit 3 ML1123718932011-11-14014 November 2011 2010 DFS Report Analysis for San Onofre Nuclear Generating Station, Unit 2 ML11154A1272011-06-0101 June 2011 Annual Report of Guarantee of Payment of Deferred Premium ML1109003792011-03-30030 March 2011 Nuclear Property Insurance ML0612104532006-04-24024 April 2006 Annual Certified Financial Statement ML0413904152004-05-13013 May 2004 Annual Certified Financial Statement 2022-06-30
[Table view] |
Text
SOUTHERN CALIFORNIA Richard J. 81. Ong e EDISON Director, Nuclear Regulatory Affairs and Emergency Planning An ED ISON INTERNATlO NA L Company 10 CFR 50.54 March 20, 2013 ATTN: Document Control Desk U. S. Nuclear Regulatory Commission Washington, D.C. 20555-0001
Subject:
Docket Nos. 50-206, 50-361 and 50-362 Nuclear Property Insurance San Onofre Nuclear Generating Station Units 1, 2, and 3
Dear Sir or Madam:
This letter is the report required by 10 CFR 50.54(w)(3). The following Nuclear Property and Decontamination Liabil ity Insurance will be in effect for the San Onofre Nuclear Generating Station on the April 1, 2013 policy renewal date:
Policy (Amount) Source Primary Property and Nuclear Electric Insurance Decontamination Liability Limited (NEIL Primary)
Insurance Policy
($500 million)
Decontamination Liability, Nuclear Electric Insurance Decommissioning Liability Limited (NEIL II) and Excess Property Insurance Policy
($2,250 million)
All policies prov iding coverage mentioned above comply with 10 CFR 50.54(w),
including provisions for the insurance proceeds to be prioritized for dedicated reactor stabilization/safety and then for decontamination of the site.
P.O. Box 128 San Clemente, CA 92672
Document Control Desk March 20, 2013 There are no commitments contained in this letter.
If you have any questions or require additional information, please contact Mr. Mark Morgan, Licensing Lead, at (949) 368-6745.
Sincerely, cc: E. E. Collins, Regional Administrator, NRC Region IV J. E. Whitten, Region IV, San Onofre Unit 1 R. Hall, NRC Project Manager, San Onofre Units 2 and 3 B. Benney, NRC Project Manager, SONGS Units 2and 3 J. C. Shepherd, NRC Project Manager, San Onofre Unit 1 G. G. Warnick, NRC Senior Resident Inspector, San Onofre Units 2 and 3