MONTHYEARIR 05000275/20230042024-02-0909 February 2024 Integrated Inspection Report 05000275/2023004 and 05000323/2023004 ML24002B1802024-01-29029 January 2024 LRA Audit Plan DCL-24-010, Nuclear Material Transaction Report for New Fuel2024-01-29029 January 2024 Nuclear Material Transaction Report for New Fuel ML24018A0152024-01-29029 January 2024 License Renewal Application Review Schedule Letter ML24017A2492024-01-24024 January 2024 Letter to Neil Peyron, Chairman, Tule River Tribe, Re. Diablo Canyon ML24024A1752024-01-24024 January 2024 Letter to Tribal Council San Luis Obispo County Chumash Indians on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24003A8902024-01-24024 January 2024 Letter to P. Gerfen - Diablo Canyon Notice of Intent to Conduct Scoping and Prepare an Environmental Impact Statement ML24012A1582024-01-24024 January 2024 Letter to Hon. Violet Sage Walker, Chairwoman Northern Chumash Tribal Council on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24012A0062024-01-24024 January 2024 Achp Scoping Letter for Diablo Canyon License Renewal ML24012A0552024-01-24024 January 2024 Letter to J. Polanco, Shpo, on Request to Initiate Section 106 Consultation and Scooping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24024A1562024-01-24024 January 2024 Letter to Hon. Gabe Frausto, Coastal Band of Chumash Indians on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24024A1652024-01-24024 January 2024 Letter to Hon. Mona Olivas Tucker, Yak Tityu Tityu Yak Tilhini Northern Chumas Indians on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24024A1612024-01-24024 January 2024 Letter Hon. Gary Pierce, Salian Tribe of Monterey and San Luis Obispo Counties on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24012A0362024-01-24024 January 2024 Request to Initiate Section 106 Consultation and Scoping Process for the Environmental Review License Renewal Application DCL-24-009, Nuclear Material Transaction Report for New Fuel2024-01-17017 January 2024 Nuclear Material Transaction Report for New Fuel DCL-24-008, Schedule Considerations for Review of the DCPP License Renewal Application2024-01-17017 January 2024 Schedule Considerations for Review of the DCPP License Renewal Application DCL-24-004, Supplement to License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2024-01-15015 January 2024 Supplement to License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b IR 05000275/20230112024-01-12012 January 2024 NRC License Renewal Phase 1 Inspection Report 05000275/2023011 DCL-23-129, Nuclear Material Transaction Report for New Fuel2023-12-27027 December 2023 Nuclear Material Transaction Report for New Fuel ML23326A0122023-12-21021 December 2023 12-21-23 Letter to the Honorable Byron Donalds from Chair Hanson Responds to Letter Regarding 2.206 Petition to Close Diablo Canyon Nuclear Power Plant, Unit 1 ML23341A0042023-12-19019 December 2023 LRA Acceptance Letter ML23352A2342023-12-18018 December 2023 Notification of Age-Related Degradation Inspection (05000275/2024014 and 05000323/2024014) and Request for Information DCL-23-122, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-14014 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation DCL-23-128, Emergency Plan Update2023-12-13013 December 2023 Emergency Plan Update ML23355A0952023-12-0808 December 2023 License Renewal Application Online Reference Portal DCL-23-125, Core Operating Limits Report for Unit 1 Cycle 252023-12-0606 December 2023 Core Operating Limits Report for Unit 1 Cycle 25 ML23291A2702023-11-28028 November 2023 Letter to Nakia Zavalla, Shpo, the Santa Ynez Band of Chumash Indians; Re., Diablo Canyon ISFSI Initiating Section 106 Consultation ML23320A2442023-11-28028 November 2023 Letter to Kerri Vera, Director of Department of Environmental Protection, Tule River Tribe; Re., Diablo Canyon ISFSI Initiating Section 106 Consultation ML23325A1382023-11-27027 November 2023 ISFSI Tribal Letter to San Luis Obispo County Chumash Indians ML23325A1322023-11-27027 November 2023 ISFSI Tribal Letter to Salian Tribe of Montgomery, San Luis Obispo ML23325A1332023-11-27027 November 2023 ISFSI Tribal Letter to Yak Tityu Tityu Northern Chumash Indians ML23307A0062023-11-27027 November 2023 ISFSI Tribal Letter to Northern Chumash Tribal Council ML24003A7242023-11-27027 November 2023 Independent Safety Committee; Diab Lo Canyon Nuclear Power Plant Operations, Thirty-Third Annual Report on the Safety ML23325A1292023-11-27027 November 2023 ISFSI Tribal Letter to Coastal Band of Chumash ML23320A1502023-11-17017 November 2023 Individual Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed No Significant Hazards Consideration Determination, & Opportunity for Hearing (Exigent Circumstances) (EPID L-2023-LLA-0155) - LTR DCL-23-121, Supplement to License Amendment Request 23-03, Revision to Technical Specification3.7.8, Auxiliary Saltwater System2023-11-16016 November 2023 Supplement to License Amendment Request 23-03, Revision to Technical Specification3.7.8, Auxiliary Saltwater System ML23296A0982023-11-15015 November 2023 Notification and Request for Consultation Regarding Pacific Gas and Electric Diablo Canyon Independent Spent Fuel Storage Installation Material License Renewal Request (Docket Number: 72-26) DCL-23-120, License Amendment Request 23-03 Revision to Technical Specification 3.7.8, Auxiliary Saltwater (Asw) System2023-11-14014 November 2023 License Amendment Request 23-03 Revision to Technical Specification 3.7.8, Auxiliary Saltwater (Asw) System ML23293A1052023-11-14014 November 2023 Receipt and Availability of License Renewal Application IR 05000275/20230032023-11-13013 November 2023 Integrated Inspection Report 05000275/2023003 and 05000323/2023003 ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV DCL-23-118, License Renewal Application2023-11-0707 November 2023 License Renewal Application ML23318A2102023-10-31031 October 2023 Independent Safety Committee; Thirty-Third Annual Report on the Safety of Diablo Canyon Nuclear Power Plant Operations DCL-2023-520, Discharge Self-Monitoring at Diablo Canyon Power Plant (DCPP)2023-10-19019 October 2023 Discharge Self-Monitoring at Diablo Canyon Power Plant (DCPP) DCL-23-103, Independent Spent Fuel Storage Installation - Withdrawal of License Amendment Request 22-01, Request for Approval of Alternative Security Measures for Early Warning System2023-10-13013 October 2023 Independent Spent Fuel Storage Installation - Withdrawal of License Amendment Request 22-01, Request for Approval of Alternative Security Measures for Early Warning System IR 05000275/20240152023-10-10010 October 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection (050002752024015 and 050003232024015) 2024-02-09
[Table view] |
Text
Enclosures 3 and 4 contain Proprietary Information
-Withhold Under 10 CFR 2.390 Pacific Gas and Electric Company March 5, 2013 PG&E Letter DCL-13-021 U.S. Nuclear Regulatory Commission ATTN: Docu ment Control Desk Washington, DC 20555-0001 Docket No. 50-323, OL-DPR-82 Diablo Canyon Unit 2 B arr y S. All e n Site Vice President 10 CFR 50.55a ASME Section Xllnservice Inspection Program Relief Request REP-1 U2, Revision 2
References:
- 1. PG&E Letter DCL-07-038, "ASME Section XI Inservice Inspection Program Relief Request REP-1 U2," dated March 28, 2007. Diablo Canyon Power Plant Mail Code 104/6 P. O. Box 56 Avila Beach, CA 93424 805.545.4888 Internal:
691.4888 Fax: 805.545.6445
- 2. PG&E Letter DCL-07-099, "ASME Section XI Inservice Inspection Program Relief Request REP-1 U2,Revision 1, and Response to Request for Additional Information," dated October 22, 2007. 3. PG&E Letter DCL-07-105, "ASME Section XI Inservice Inspection Program Relief Request REP-1 U2, Revision 1; Response to Request for Additional Information," dated November 29, 2007. 4. NRC Letter, "Diablo Canyon Power Plant, Unit No.2 -Approval of Relief Request REP-1 U2, Revision 1, for the Application of Weld Overlay on Dissimilar Metal Welds of Pressurizer Nozzles (TAC No. MD4974 )," dated February 6, 2008 Dear Commissioners and Staff: Pursuant to 10 CFR 50.55a(a)(3)(i), Pacific Gas and Electric Company (PG&E) hereby requests NRC approval for Inservice Inspection Program Relief Request REP-1 U2, Revision 2. This request for relief contains alternative requirements for the ASME Section XI Repair/Replacement Program for preemptive full structural weld overlays to mitigate the potential for primary water stress corrosion cracking of susceptible material at Diablo Canyon Power Plant (DCPP) Unit 2. Enclosures 3 and 4 contain Proprietary Information When separated from Enclosures 3 and 4, this document is decontrolled.
A member o'f the STARS (Strategic Teaming and Resource Sharing) Alliance Callaway
- Wolf Creek m Enclosures 3 and 4 contain Proprietary Information
-Withhold Under 10 CFR 2.390 Document Control Desk PG&E Letter DCL-13-021 I March 5, 2013 Page 2 The bases for the request for relief are provided in Enclosure
- 1. The Performance Demonstration Initiative Program alternatives and their bases with respect to ASME Code Section XI , Appendix VIII, Supplement 11 requirements are included in Enclosure
- 2. Enclosures 3 and 4 to this letter contain AREVA Calculation
- 32-9199805-000, "Diablo Canyon Power Plant Unit 2 PZR Safety and Spray Nozzles Planar Flaw Analysis" and AREVA Ca lculation
- 32-9199937-000, "DCPP Unit 2 -Evaluat i on of Laminar Indications in Pressurizer Nozzles," respectively, which contain information proprietary to AREVA. Accordingly, Enclosure 5 includes AREVA's Affidavit for the calculations mentioned above. The affidavit is signed by AREVA, the owner of the information.
The affidavit sets forth the basis on which the AREVA proprietary information contained in Enclosures 3 and 4 may be withheld from public disclosure by the Commission, and it addresses with specificity the considerations listed in paragraph (b )(4) of 10 CFR 2.390 of the Commission's regulations.
PG&E requests that the AREVA proprietary information be withheld from public disclosure in accordance with 10 CFR 2.390. Correspondence with respect to the AREVA Affidavit or the AREVA proprietary information provided in Enclosu.res 3 and 4 should reference AREVA Affidavit and be addressed to Gayle F. Elliott, Product Licensing Manager, AREVA NP, 3315 Old Forest Road, Lynchburg, VA 24501. Enclosure 6 contains AREVA Calculation
- 32-9200249-000, "Diablo Canyon Power Plant Unit 2 PZR Safety and Spray Nozzles Planar Flaw Analysis -Non Proprietary." Enclosure 7 contains AREVA Calculation
- 32-9200291-000, "DCPP Unit 2 -Evaluation of Laminar Indications in Pressurizer Nozzles Proprietary)." PG&E requests authorization of this relief request no later than March 11, 2013, to allow DCPP to transition into Hot Shutdown Mode (Mode 4). This communication contains one new regulatory commitment (as defined by NEI 99-04), which is contained in Enclosure
- 7. If you have any questions, or require additional information, please contact Tom Baldwin at (805) 545-4720.
Enclosures 3 and 4 contain Proprietary Information When separated from Enclosures 3 and 4, this document is decontrolled.
A member of the STARS (StrategiC Teaming and Resource Sharing) Alliance Callaway
- Wolf Creek Enclosures 3 and 4 contain Proprietary Information
-Withhold Under 10 CFR 2.390 Document Control Desk PG&E Letter DCL-13-021 M a rch 5 , 2013 Pa ge 3 Sincerely, Site Vice President pns3/6984 SAPN 50540188 Enclosures cc: Diablo Distribution cc/enc: Gonzalo L. Perez, Branch Chief, California Department of Public Health Elmo E. Collins, NRC Region IV Thomas R. Hipschman, NRC Senior Resident Inspector James T. Polickoski, NRR Project Manager State of California, Pressure Vessel Unit Enclosures 3 and 4 contain Proprietary Information When separated from Enclosures 3 and 4, this document is decontrolled.