Letter Sequence Acceptance Review |
---|
TAC:MF0562, Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection (Approved, Closed) TAC:MF0563, Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection (Approved, Closed) TAC:MF0564, Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection (Approved, Closed) TAC:MF0565, Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection (Approved, Closed) |
|
MONTHYEARNL-13-0081, Application to Revise Technical Specifications to Adopt TSTF-510, Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection,Using the Consolidated Line Item Improvement...2013-01-23023 January 2013 Application to Revise Technical Specifications to Adopt TSTF-510, Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection,Using the Consolidated Line Item Improvement... Project stage: Request ML13032A2572013-01-30030 January 2013 NRR E-mail Capture - Acceptance Review for Revision of Stream Generator Tube Inspection Program Farley and Vogtle Project stage: Acceptance Review NL-13-1297, Application to Revise Technical Specifications to Adopt TSTF-510, Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection, Using Consolidated Line Item Improvement Process Revised Clean-Typed Page2013-07-17017 July 2013 Application to Revise Technical Specifications to Adopt TSTF-510, Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection, Using Consolidated Line Item Improvement Process Revised Clean-Typed Page Project stage: Request ML13218B2742013-09-26026 September 2013 Issuance of Amendments Regarding Steam Generator Tube Inspection Program Project stage: Approval 2013-01-30
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML24304A8922024-10-30030 October 2024 Acceptance Review - Farley Units 1 and 2 - RG 1.183 Table 3 Footnote 11 Exception UFSAR Change LAR ML24297A6042024-10-22022 October 2024 Acceptance Review - License Amendment Request to Revise TS SR 3.4.14.3 and Correct Admin Oversight ML24290A1552024-10-16016 October 2024 NRR E-mail Capture - for Your Action - RAI - Farley, Hatch, and Vogtle 1 and 2 - Proposed Alternative Request for Code Case N-572 ML24290A1572024-10-16016 October 2024 NRR E-mail Capture - for Your Action - RAI - Farley and Vogtle 1 and 2 - Alternative Request for Pressurizer Welds (L-2024-LLR-0047) ML24289A2002024-10-15015 October 2024 NRR E-mail Capture - for Your Action - RAI - Proposed License Amendment Request (LAR) for Vogtle Electric Generating Plant, Units 3 and 4 TS 3.7.6 Action E and SR 3.7.6.5 (L-2024-LLA-0083) ML24276A1132024-10-0202 October 2024 Acceptance Review - License Amendment Request to Revise TS SR 3.4.14.3 and Correct Administrative Oversight ML24271A0052024-09-26026 September 2024 NRR E-mail Capture - for Your Response - RAI - Farley and Vogtle 1 and 2 - Proposed Alternative Request for Steam Generator Welds (L-2024-LLR-0041) ML24261B9282024-09-17017 September 2024 NRR E-mail Capture - for Your Action Discussion Points - Steam Generator Tube Inspection Call with SNC Regarding Vogtle, Unit 3 ML24250A1132024-09-0303 September 2024 Inspection Report 2024004 Radiation Safety Baseline Inspection Information Request ML24247A0092024-09-0303 September 2024 NRR E-mail Capture - Fyi - Revised Estimated Completion Date - Vogtle 3 and 4 - UFSAR Scheduler Exemption Request ML24250A1922024-08-29029 August 2024 Amendment Nos. 223/206 (1) - Email ML24232A0052024-08-16016 August 2024 NRR E-mail Capture - Acceptance Review - LAR and Exemption Request to Remove Tier 1 and Tier 2 Requirements for Vogtle 3 and 4 ML24253A0722024-08-15015 August 2024 Perspectives on Proposed Removal of Tier 1 and Tier 2 Requirements ML24227A0512024-08-14014 August 2024 August 14, 2024 - Request for Additional Information - Farley, Units 1 and 2 - Proposed LAR to Revise TS SR 3.6.6.8 Frequency ML24225A0062024-08-0909 August 2024 NRR E-mail Capture - Acceptance Review - Vogtle 3 and 4 - LAR Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves), Action a and SR 3.7.6.6 (L-2024-LLA-0101) ML24212A2232024-07-30030 July 2024 Acceptance Review - License Amendment Request to Adopt TSTF-500, Rev 2 DC Electrical Rewrite (EPID L-2024-LLA-0091) - Email ML24205A2142024-07-23023 July 2024 Acceptance Review - License Amendment Request to Change TS 3.6.5, Containment Air Temperature ML24206A0252024-07-20020 July 2024 NRR E-mail Capture - for Your Comments - State of Georgia - Vogtle Unit 1 - Emergency License Amendment Request for Technical Specification 3.7.9 ML24199A1592024-07-17017 July 2024 NRR E-mail Capture - Request for Additional Information - Vogtle 3 and 4 - Exemption for the Requirements in 10 CFR 50.71 Pertaining to the Submittal of Updated Final Safety Analysis Report ML24198A1672024-07-16016 July 2024 NRR E-mail Capture - Acceptance Review Vogtle 3 and 4 - License Amendment Request Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Surveillance Requirement L-2024-LLA-0083 ML24197A1572024-07-15015 July 2024 NRR E-mail Capture - Acceptance Review - Farley and Vogtle 1 and 2, LAR - TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown ML24197A0172024-07-12012 July 2024 NRR E-mail Capture - Fyi - Acceptance Review - Farley and Vogtle 1 and 2 - Alternative Request for Pressurizer Welds ML24194A0032024-07-11011 July 2024 NRR E-mail Capture - Fyi - Acceptance Review - Farley, Hatch, and Vogtle 1 and 2 - Alternative Request for Code Case N-572 ML24180A0012024-06-26026 June 2024 NRR E-mail Capture - Acceptance Review Farley 1 and 2 and Vogtle 1 and 2 - Proposed Inservice Inspection Alternative GEN-ISI-ALT-2024-002 for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1) (L-2024-LLR-0041) ML24170A9362024-06-18018 June 2024 NRR E-mail Capture - Fyi - Change to Estimated Completion Date for the SNC Fleet Physical Barrier Exemptions (L-2023-LLE-0018 and L-2023-LLE-0021) ML24142A4992024-05-21021 May 2024 NRR E-mail Capture - Acceptance Review - Farley and Hatch - LAR to Revise TS 1.1 and Add Online Monitoring (OLM) Program (L-2024-LLA-0058) ML24178A3422024-05-16016 May 2024 NRR E-mail Capture - Request for Call - Proposed Vogtle 3 & 4 Tier 1 and Tier 2 Exemptions and LAR ML24120A0462024-04-29029 April 2024 COL Docs - Re Fyi - SNC Notification Received of Vogtle Unit 4 - Completion of Power Ascension Tests ML24120A0262024-04-29029 April 2024 COL Docs - FW Vogtle Electric Generating Plant, Unit 4 - Project Manager Reassignment ML24119A0012024-04-28028 April 2024 COL Docs - Fyi - SNC Notification Received of Vogtle Unit 4 - Completion of Power Ascension Tests ML24114A2452024-04-23023 April 2024 Acceptance Review - Farley, Units 1 and 2-Proposed LAR to Revise TS SR 3.6.6.8 ML24108A0132024-04-16016 April 2024 NRR E-mail Capture - (External_Sender) Responses from Wednesday 4/10/2024 Call with Southern Nuclear Operating Co. Vogtle 3&4 Licensing Actions ML24107A9322024-04-15015 April 2024 Document Request for Vogtle Electric Generating Plant Units 1 & 2 - Radiation Protection Inspection Report 2024-02 ML24107A7292024-04-15015 April 2024 Request for Vogtle Electric Generating Plant Units 1 & 2 - Radiation Protection Inspection - Inspection Report 2024-02 ML24106A0522024-04-12012 April 2024 NRR E-mail Capture - Acceptance Review - Vogtle 1 and 2 - Emergency Diesel Generator (EDG) Voltage and Frequency License Amendment Request (LAR) (L-2024-LLA-0031) ML24100A7842024-04-0909 April 2024 NRR E-mail Capture - for Your Action - Request for Additional Information (RAI) - Vogtle, Units 3 and 4 - Alternative Request for Explosively Actuated Valves (L-2023-LLR-0016) ML24099A0372024-04-0505 April 2024 NRR E-mail Capture - Acceptance Review - Vogtle Unit 3, License Amendment Request (LAR) Technical Specification (TS) 5.5.13, Ventilation Filter Testing Program (VFTP) - L-2024-LLA-0043 ML24095A2412024-04-0404 April 2024 NRR E-mail Capture - Acceptance Review for the Exemption Request Regarding the Final Safety Analysis Report Update Schedule at Vogtle, Units 3 and 4 ML24072A3982024-03-12012 March 2024 NRR E-mail Capture - for Your Action - Second Round Request for Additional Information (RAI) - Vogtle, Unit 1 - SG Tube Inspection Report - 1R24 (L-2023-LRO-0067) ML24061A2372024-03-0101 March 2024 SNC Email Dated March 1, 2024, Regarding SNC Response to NRC Letter for Vogtle 3 & 4 RES Info ML24057A0872024-02-23023 February 2024 NRR E-mail Capture - Acceptance Review - Alternative Request for Explosively Actuated Valves at Vogtle, Units 3 and 4 ML24046A1352024-02-15015 February 2024 COL Docs - Fyi - SNC Notification Received of Vogtle Unit 4 - Completion of Initial Criticality and Low-Power Testing ML24039A1922024-02-0808 February 2024 COL Docs - Correction - Re Fyi - SNC Notification Received of Vogtle Unit 4 Completion of Pre-Critical Tests ML24039A1122024-02-0808 February 2024 COL Docs - Re Fyi - SNC Notification Received of Vogtle Unit 4 Completion of Pre-Critical Tests ML24039A0882024-02-0808 February 2024 COL Docs - Fyi - SNC Notification Received of Vogtle Unit 4 Completion of Pre-Critical Tests ML24037A1352024-02-0505 February 2024 E-mail ML24031A0502024-01-31031 January 2024 COL Docs - FW Erroneous Description of Tier 2 Change Process in Construction Lessons-Learned Report ML24017A1122024-01-17017 January 2024 NRR E-mail Capture - Request for Access to Cyber Security Data - Vogtle, Units 3 and 4 ML23360A0042023-12-23023 December 2023 NRR E-mail Capture - Fyi - Office of Nuclear Regulatory Research (RES) Requests for Vogtle 3 & 4 ML23348A0782023-12-13013 December 2023 NRR E-mail Capture - Voluntary Request for Closed Meeting Regarding Cyber Security Assessments at Vogtle, Units 3 and 4 2024-09-03
[Table view] |
Text
NRR-PMDAPEm Resource From: Martin, Robert Sent: Wednesday, January 30, 2013 1:55 PM To: crpierce@souuthernco.com Cc: McElroy, G. Ken; Hill, Lesa P.; Brown, Eva
Subject:
Acceptance Review for Revision of Stream Generator Tube Inspection Program - Farley and Vogtle Mr. Pierce:
By letter dated January 23, 2013, SNC submitted a license amendment request (NL-13-0081), for the Joseph M. Farley Nuclear Plant and the Vogtle Electric Generating Plant, Application to Revise Technical Specifications to Adopt TSTF-510, "Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection," Using The Consolidated Line Item Improvement Process."
The purpose of this e-mail is to provide the results of the Nuclear Regulatory Commission (NRC) staffs acceptance review of this license amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to continue its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), an amendment to the license (including the technical specifications) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required.
This section stipulates that the submittal addresses the design and operating characteristics, unusual or novel design features, and principal safety considerations.
The NRC staff has reviewed your application and concludes that it does provide technical information in sufficient detail to enable the staff to proceed with its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. If additional information is needed for the staff to complete its technical review, you will be advised by separate correspondence.
R. Martin NRR-DORL Plant Licensing Branch II-1 TACs MF0562, MF0563, MF0564, MF0565 Dockets: 50-348, 50-364, 50-424, 50-425 1
Hearing Identifier: NRR_PMDA Email Number: 597 Mail Envelope Properties (Robert.Martin@nrc.gov20130130135500)
Subject:
Acceptance Review for Revision of Stream Generator Tube Inspection Program
- Farley and Vogtle Sent Date: 1/30/2013 1:55:12 PM Received Date: 1/30/2013 1:55:00 PM From: Martin, Robert Created By: Robert.Martin@nrc.gov Recipients:
"McElroy, G. Ken" <GKMCELRO@southernco.com>
Tracking Status: None "Hill, Lesa P." <LPHILL@southernco.com>
Tracking Status: None "Brown, Eva" <Eva.Brown@nrc.gov>
Tracking Status: None "crpierce@souuthernco.com" <crpierce@souuthernco.com>
Tracking Status: None Post Office:
Files Size Date & Time MESSAGE 2173 1/30/2013 1:55:00 PM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:
Recipients Received: