Response Letter to La Chamber of Commerce Letter of October 15, 2012 Regarding San Onofre Nuclear Generating Station
ML13031A747
Person / Time
Site: San Onofre Southern California Edison icon.png
Issue date: 01/31/2013
From: Howell A
NRC Region 4
To: Toebben G
Los Angeles Area Chamber of Commerce
Lantz R
References
Download: ML13031A747 (3)


Text

January 31, 2013 Gary Toebben President and CEO Los Angeles Area Chamber of Commerce 350 S. Bixel Street Los Angeles, CA 90017

Dear Mr. Toebben:

On behalf of the U.S. Nuclear Regulatory Commission (NRC), I am responding to your letter dated October 15, 2012, in which you conveyed your members concerns about the San Onofre Nuclear Generating Station (SONGS) and a request by your members to be included more in future public meetings.

As with all members of the public, we encourage participation in all public meetings, as well as other activities where the NRC provides information and solicits public input. The primary mission of the NRC is the protection of public health and safety and the environment. The NRC has seven organizational values that support this mission, including:

openness in communications and decision-making; service to the public and others who are affected by our work; and respect for individuals diversity, roles, beliefs, viewpoints, and work/life balance.

All points of view are valued. Throughout this extended shutdown and inspections, we have had a series of meetings where people were allowed to ask questions or make comments regarding SONGS. We began this series of public meetings with the Augmented Inspection Team exit meeting on June 18, 2012. The public meeting that you reference in your letter occurred on October 9. We held another public meeting on November 30. The next public meeting is scheduled for February 12, 2013, at the Capo Beach Church from 6 - 9 p.m. and your participation is encouraged.

The NRC will continue its independent, in-depth inspections and detailed review of the issues at SONGS, including aspects of the approval process for replacing the steam generators. The NRC will not allow the plant to restart until we are satisfied that the licensee can operate the plant without undue risk to public health and safety. The NRC will take the time needed to determine the appropriate actions to ensure the safety of the public and will communicate our determinations regarding the safety of SONGS, Units 2 and 3.

The NRC has heard the safety concerns of the citizens in your community and others located near SONGS and has committed itself to ensuring that the public is informed UNITED STATES NUCLEAR REGULATORY COMMISSION RE G IO N I V 1600 EAST LAMAR BLVD ARLINGTON, TEXAS 76011-4511

Gary Toebben about the condition of the plant and our work to assure its safety. As noted above, the next public meeting is scheduled for February 12, 2013. In addition, the NRC plans to have future public meetings concerning SONGS. Public meetings are announced on the NRCs website at http://www.nrc.gov/public-involve/public-meetings/index.cfm.

Should you have any further questions, please contact Ryan Lantz of my staff at 817-200-1173.

Sincerely,

/RA/

Arthur T. Howell III Team Manager SONGS Special Project cc:

Senator Barbara Boxer Senator Diane Feinstein Congressman Darrell Isa NRC Chairman Allison MacFarlane

Gary Toebben Internal distribution:

E. Collins, RA SONGS Oversight Panel S:\\DNMS\\SONGS\\Response Letter to LA Chamber of Commerce.docx ML13031A747 ADAMS: No Yes SUNSI Review Complete Reviewer Initials: ATH Publicly Available Non-Sensitive Non-publicly Available Sensitive RIV:I&AL:SONGS PB BC:SONGS PB TM:SONGS SP GEWerner;dlf RELantz ATHowell

/RA/

/RA/

/RA/

11/19/12 1/31/13 1/31/13 OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax