MONTHYEARIR 05000244/20243012024-10-22022 October 2024 Initial Operator Licensing Examination Report 05000244/2024301 IR 05000317/20240032024-10-22022 October 2024 Integrated Inspection Report 05000317/2024003, 05000318/2024003, and Independent Spent Fuel Storage Installation Report 07200008/2024001 ML24268A3382024-10-16016 October 2024 Issuance of Amendment No. 253 Regarding the Modification of TS Surveillance Requirement 4.3.6.a Related to Adoption of TSTF-425, Revision 3 ML24286A0022024-10-11011 October 2024 Core Operating Limits Report Cycle 45, Revision 0 RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24283A0012024-10-0909 October 2024 Senior Reactor and Reactor Operator Initial License Examinations IR 05000317/20245012024-10-0707 October 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000317/2024501 and 05000318/2024501 ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing IR 05000220/20243022024-10-0303 October 2024 Initial Operator Licensing Examination Report 05000220/2024302 RS-24-092, Revised Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-09-25025 September 2024 Revised Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000244/20245012024-09-24024 September 2024 LLC - Emergency Preparedness Biennial Exercise Inspection Report 05000244/2024501 NMP1L3608, Supplemental Information Letter No. 3 - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation2024-09-20020 September 2024 Supplemental Information Letter No. 3 - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation RS-24-090, Response to Request for Additional Information - Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds2024-09-12012 September 2024 Response to Request for Additional Information - Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 IR 05000220/20240052024-08-29029 August 2024 Updated Inspection Plan for Nine Mile Point Nuclear Station, Units 1 and 2 (Report 05000220/2024005 and 05000410/2024005) IR 05000244/20240052024-08-29029 August 2024 Updated Inspection Plan for R.E. Ginna Nuclear Power Plant (Report 05000244/2024005) IR 05000317/20240052024-08-29029 August 2024 Updated Inspection Plan for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Report 05000317/2024005 and 05000318/2024005) ML24240A1112024-08-27027 August 2024 Registration of Use of Casks to Store Spent Fuel ML24240A2462024-08-27027 August 2024 Submittal of the Reactor Vessel Material Surveillance Program Capsule Technical Report IR 05000220/20240102024-08-22022 August 2024 Age-Related Degradation Inspection Report 05000220/2024010 and 05000410/2024010 ML24234A0922024-08-21021 August 2024 Requalification Program Inspection NMP1L3603, Submittal of Preliminary Decommissioning Cost Estimate and Irradiated Fuel Management Plan2024-08-20020 August 2024 Submittal of Preliminary Decommissioning Cost Estimate and Irradiated Fuel Management Plan IR 05000244/20240102024-08-19019 August 2024 Biennial Problem Identification and Resolution Inspection Report 05000244/2024010 ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition IR 05000317/20240022024-08-0606 August 2024 Integrated Inspection Report 05000317/2024002 and 05000318/2024002 IR 05000244/20240022024-08-0505 August 2024 LLC - Integrated Inspection Report 05000244/2024002 and Independent Spent Fuel Storage Installation Report 07200067/2024001 IR 05000220/20240022024-08-0505 August 2024 Integrated Inspection Report 05000220/2024002 and 05000410/2024002 ML24215A3002024-08-0202 August 2024 Operator Licensing Examination Approval NMP1L3601, Supplemental Information Letter No. 2 - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation2024-07-31031 July 2024 Supplemental Information Letter No. 2 - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation ML24213A1412024-07-31031 July 2024 Requalification Program Inspection IR 05000317/20240102024-07-31031 July 2024 Age-Related Degradation Inspection Report 05000317/2024010 and 05000318/2024010 NMP2L2883, Fourth Inservice Inspection Interval, Second Inservice Inspection Period 2024 Owner’S Activity Report for RFO-19 Inservice Examinations2024-07-24024 July 2024 Fourth Inservice Inspection Interval, Second Inservice Inspection Period 2024 Owner’S Activity Report for RFO-19 Inservice Examinations ML24179A3262024-07-23023 July 2024 LTR - Constellation - SG Welds and Nozzles (L-2023-LLR-0053, L-2023-LLR-0054, L-2023-LLR-0055, L-2023-LLR-0056) ML24198A0442024-07-16016 July 2024 Inservice Inspection Report ML24198A0852024-07-16016 July 2024 Senior Reactor and Reactor Operator Initial License Examinations ML24170A3852024-07-16016 July 2024 R. E. Ginna Nuclear Power Plant - Alternative Associated with Inservice Testing of B Auxiliary Feedwater Pump - PR-03 ML24197A0302024-07-15015 July 2024 LLC - Operator Licensing Examination Approval RS-24-070, Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions2024-07-12012 July 2024 Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions IR 05000317/20244012024-07-0909 July 2024 Security Baseline Inspection Report 05000317/2024401 and 05000318/2024401 05000317/LER-2024-001, Submittal of LER 2024-001-01 for Calvert Cliffs Nuclear Power Plant, Unit 1, Condition Prohibited by Technical Specifications Due to Safety Injection Check Valve Not Full Closed2024-07-0202 July 2024 Submittal of LER 2024-001-01 for Calvert Cliffs Nuclear Power Plant, Unit 1, Condition Prohibited by Technical Specifications Due to Safety Injection Check Valve Not Full Closed ML24177A1832024-06-25025 June 2024 Inservice Inspection Report IR 05000244/20244022024-06-20020 June 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000244/2024402 RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations NMP1L3584, License Amendment Request to Revise Technical Specifications to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling2024-06-13013 June 2024 License Amendment Request to Revise Technical Specifications to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling ML24161A0012024-06-0909 June 2024 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report IR 05000220/20244012024-05-30030 May 2024 Security Baseline Inspection Report 05000220/2024401 and 05000410/2024401(Cover Letter Only) ML24150A0522024-05-29029 May 2024 Operator Licensing Examination Approval ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 ML24143A0752024-05-22022 May 2024 Re. Ginna Nuclear Power Plant and Independent Spent Fuel Storage Installation (ISFSI) Registration for Use of General License ISFSI Casks 2024-09-06
[Table view] |
Text
James A. Spina Vice President, Corporate Site Operations 100 Constellation Way Suite 200C Baltimore, Maryland 21202 410-470-5203 OENG-1 ajoint venture of 0l conswe~at w' -'-eDF EWne W 0 I January 29, 2013 U.S. Nuclear Regulatory Commission 11555 Rockville Pike Rockville, MD 20852 ATTENTION: Document Control Desk
SUBJECT:
Calvert Cliffs Nuclear Power Plant, Units 1 and 2 Renewed Facility Operating License Nos. DPR-53 and DPR-69 Docket Nos. 50-317 and 50-318 Nine Mile Point Nuclear Station, Units 1 and 2 Renewed Facility Operating License Nos. DPR-63 and NPF-69 Docket Nos. 50-220 and 50-4 10 R.E. Ginna Nuclear Power Plant Renewed Facility Operating License No. DPR-18 Docket No. 50-244 Response to Request for Information Recommendation 2.1, Flooding, Required Response 1, Integrated Assessment Approach
REFERENCES:
(a) Letter from E. J. Leeds (NRC) and M. R. Johnson (NRC) to All Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status, dated March 12, 2012, Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendations 2.1, 2.3, and 9.3, of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident, ML12073A348 (b) NRC Japan Lessons-Learned Project Directorate, JLD-ISG-2012-05, Guidance for Performing the Integrated Assessment for External Flooding, Interim Staff Guidance, Revision 0, dated November 30, 2012, ML12311A214 (c) Letter from D. L. Skeen (NRC) to J. E. Pollock (NEI), dated December 3, 2012, Trigger Conditions for Performing an Integrated Assessment and Due Date for Response, ML12326A912
Document Control Desk January 29, 2013 Page 2 On March 12, 2012, the Nuclear Regulatory Commission (NRC) issued Reference (a) to request information associated with the Near-Term Task Force (NTTF) Recommendation 2.1 for flooding. One request was for licensees to submit an approach for developing an Integrated Assessment Report, including criteria for identifying vulnerabilities, within 60 days after issue of the NRC's guidance on the subject. Reference (b) provided that guidance on November 30, 2012.
Nine Mile Point Nuclear Station, R.E. Ginna Nuclear Power Plant, and Calvert Cliffs Nuclear Power Plant will use the Reference (b) guidance as the approach for developing the NTTF 2.1 Flooding Integrated Assessment Report if the reevaluated flooding hazard is not bounded by the current design basis flooding evaluation.
Nine Mile Point Nuclear Station, R.E. Ginna Nuclear Power Plant, and Calvert Cliffs Nuclear Power Plant will use the guidance provided by Reference (c) regarding the trigger conditions and scope of any required integrated assessment.
This letter contains regulatory commitments as listed in Attachment (1).
If there are any questions regarding this submittal, please contact Everett (Chip) Perkins everett.perkinsacengllc.com at 410-470-3928.
I declare under penalty of perjury that the foregoing is true and correct. Executed on January 29, 2013.
Sincer Ja s A. Spina JAS/EMT/bjd
Attachment:
(1) Regulatory Commitments Contained in this Correspondence cc: B. K. Vaidya, NRC Resident Inspector, Calvert Cliffs M. C. Thadani, NRC Resident Inspector, Ginna N. S. Morgan, NRC Resident Inspector, Nine Mile Point W. M. Dean, NRC S. Gray, DNR
ATTACHMENT (1)
REGULATORY COMMITMENTS CONTAINED IN THIS CORRESPONDENCE Constellation Energy Nuclear Group, LLC January 29, 2013
ATTACHMENT (1)
REGULATORY COMMITMENTS CONTAINED IN THIS CORRESPONDENCE The following table identifies actions committed to in this document. Any other statements in this submittal are provided for information purposes and are not considered to be regulatory commitments.
REGULATORY COMMITMENT DUE DATE Use the JLD-ISG-2012-05 guidance as the approach for When the assessment report is developing the NTTF 2.1 Flooding Integrated Assessment developed.
Report if the reevaluated flooding hazard is not bounded by the current design basis flooding evaluation.
Use the guidance in the D. L. Skeen letter to NEI to When the assessment report is determine trigger conditions and scope of any required developed.
integrated assessment.
1 of I