Response to March 12, 2012 Request for Information Enclosure 2, Recommendation 2.1 Flooding, Required Response 1, Integrated Assessment Approach
ML13024A366
Person / Time
Site: San Onofre  Southern California Edison icon.png
Issue date: 01/24/2013
From: Bauder D
Southern California Edison Co
To:
Office of Nuclear Reactor Regulation, Document Control Desk
References
Download: ML13024A366 (2)


Text

.;!:;1E"oTsooN' An EDISON INTERNA TIONAL ~ Company U.S. Nuclear Regulatory Commission ATTN: Document Control Desk 11555 Rockville Pike Rockville, MD 20852 January 24, 2013 Douglas R. Bauder Site Vice President & Station Manager San Onofre Nuclear Generating Station 10 CFR 50.54(f)

Subject:

Docket Nos. 50-361 and 50-362 Southern California Edison's Response to March 12, 2012 Request for Information Enclosure 2, Recommendation 2.1 Flooding, Required Response 1, Integrated Assessment Approach San Onofre Nuclear Generating Station, Units 2 and 3

References:

1)

NRC Letter, Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendations 2.1, 2.3, and 9.3, of the Near-Term Task Force Review of Insights from the Fukushima Dai-Ichi Accident; dated March 12, 2012, Accession No. ML12073A348.

2)

NRC Japan Lessons-Learned Project Directorate, JLD-ISG-2012-05, Guidance for Performing the Integrated Assessment for External Flooding, Interim Staff Guidance, Revision 0, dated November 30, 2012, Accession No. ML12311A214.

3)

NRC Letter, D.L. Skeen (NRC) to J.E. Pollock (NEI), Trigger Conditions for Performing and Integrated Assessment and Due Date for Response, dated December 3, 2012, Accession No. ML12325A912.

On March 12, 2012, the NRC issued Reference 1 to request information associated with Near-Term Task Force (NTTF) Recommendation 2.1 for Flooding. One of the Required Responses in this letter directed licensees to submit an approach for developing an Integrated Assessment Report, including criteria for identifying vulnerabilities, within 50 days after issue of the NRC's guidance on the subject (Reference 2). The following is Southern Californ ia Edison's 50-day response.

On November 30, 2012, the NRC issued the Reference 2 Interim Staff Guidance. Southern California Edison will use the Reference 2 guidance as the approach for developing the NTTF 2.1 Flooding Integrated Assessment Report for San Onofre Nuclear Generating Station (SONGS) Units 2 and Unit 3 if the reevaluated flooding hazard is not bounded by the current design basis flooding evaluation.

Southern California Edison also will use the guidance provided by Reference 3 regarding the trigger conditions and scope of any required Integrated Assessment.

This letter contains no regulatory commitments.

P.O. Box 128 San Clemente, CA 92672 (949) 368-9275 PAX 89275 Fax: (949) 368-9881 Doug.Bauder@sce.com

Document Control Desk January 24, 2013 Should you have any questions regarding this submittal, please contact the Licensing Lead,

Mark Morgan, at 949-368-6745.

I declare under penalty of perjury that the foregoing is true and correct.

Executed on I 'Jt{ flO I ~

Douglas R. Bauder Site Vice President and Station Manager By: -H---j~~""-------

cc:

Director, Office of Nuclear Reactor Regulation E. E. Collins, Regional Administrator, NRC Region IV G. G. Warnick, NRC Senior Resident Inspector, San Onofre Units 2 and 3 R. Hall, NRC Project Manager, San Onofre Units 2 and 3 B. Benney, NRC Project Manager, San Onofre Units 2 and 3