ML13017A103

From kanterella
Jump to navigation Jump to search
Notification of Inspection and Request for Information
ML13017A103
Person / Time
Site: Harris 
Issue date: 01/17/2013
From: Brian Bonser
NRC/RGN-II/DRS/PSB1
To: Hamrick G
Carolina Power & Light Co
Linda K. Gruhler 404-997-4633
References
Download: ML13017A103 (6)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 January 17, 2013 Mr. George T. Hamrick Vice President Shearon Harris Nuclear Plant Carolina Power & Light Company P.O. Box 165, Mail Code: Zone 1 New Hill, NC 27562-0165

SUBJECT:

SHEARON HARRIS NUCLEAR PLANT - NOTIFICATION OF INSPECTION AND REQUEST FOR INFORMATION

Dear Mr. Hamrick:

During the period of March 18 - 22, 2013, the U.S. Nuclear Regulatory Commission (NRC) will conduct a supplemental inspection at the Shearon Harris Nuclear Plant. The inspection will evaluate activities in the Emergency Preparedness cornerstone using NRC Inspection Procedure (IP) 95001, Supplemental Inspection for One or Two White Inputs in a Strategic Performance Area, and IP 92702 Follow-up on Traditional Enforcement Actions.

To minimize the impact to your onsite resources and to ensure a productive inspection, we have enclosed a request for documents needed for this inspection. It is important that all of these documents are up to date and complete, thereby minimizing the number of additional documents requested during the preparation and/or the onsite portions of the inspection.

We have discussed the schedule for these inspection activities with your staff and understand that our regulatory contact for this inspection will be Mr. Dave Corlett of your organization. If there are any questions about this inspection or the material requested, please contact the lead inspector, Mark Speck, at (404) 997-4759.

In accordance with 10 CFR 2.390 of the NRC Rules of Practice, a copy of this letter, and your response, if any, will be available electronically for public inspection in the NRC Public

2 G. Hamrick Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Brian Bonser, Chief Plant Support Branch 1 Division of Reactor Safety Docket No. 50-400 License No. NPF-63

Enclosure:

Supplemental Inspection Document Request List cc: (See page 3 and 4)

ML13017A103 X SUNSI REVIEW COMPLETE X FORM 665 ATTACHED OFFICE RII:DRS/PSB1 RII:DRS/PSB1 SIGNATURE MES4 BRB1 NAME M. Speck B. Bonser DATE 1/ 16 /2013 1/ 16 /2013 E-MAIL COPY YES NO YES NO

G. Hamrick 3

cc:

Brian Bernard Manager, Nuclear Services and EP Nuclear Protective Services Shearon Harris Nuclear Power Plant Electronic Mail Distribution Brian C. McCabe Manager, Nuclear Oversight Shearon Harris Nuclear Power Plant Progress Energy Electronic Mail Distribution George T. Hamrick Vice President Carolina Power and Light Company Shearon Harris Nuclear Power Plant Electronic Mail Distribution Lara S. Nichols Deputy General Counsel Duke Energy Corporation Electronic Mail Distribution M. Christopher Nolan Director - Regulatory Affairs General Office Duke Energy Corporation Electronic Mail Distribution Robert J. Duncan II Senior Vice President Progress Energy Electronic Mail Distribution Sean T. O'Connor Manager, Support Services Shearon Harris Nuclear Power Plant Electronic Mail Distribution Donald L. Griffith Training Manager Shearon Harris Nuclear Power Plant Progress Energy Electronic Mail Distribution R. Keith Holbrook Manager, Support Services Shearon Harris Nuclear Power Plant Electronic Mail Distribution David H. Corlett Supervisor Licensing/Regulatory Programs Progress Energy Electronic Mail Distribution David T. Conley Senior Counsel Legal Department Progress Energy Electronic Mail Distribution Donna B. Alexander Manager, Nuclear Regulatory Affairs (interim)

Progress Energy Electronic Mail Distribution John H. O'Neill, Jr.

Shaw, Pittman, Potts & Trowbridge 2300 N. Street, NW Washington, DC 20037-1128 Joseph W. Donahue Vice President Nuclear Oversight Progress Energy Electronic Mail Distribution W. Lee Cox, III Section Chief Radiation Protection Section N.C. Department of Environmental Commerce & Natural Resources Electronic Mail Distribution Public Service Commission State of South Carolina P.O. Box 11649 Columbia, SC 29211 Chairman North Carolina Utilities Commission Electronic Mail Distribution cc: (Continued on page 4)

G. Hamrick 4

cc: (Continued from page 3)

Terrence E. Slake Manager Nuclear Plant Security Shearon Harris Nuclear Power Plant Electronic Mail Distribution Robert P. Gruber Executive Director Public Staff - NCUC 4326 Mail Service Center Raleigh, NC 27699-4326 Chair Board of County Commissioners of Wake County P.O. Box 550 Raleigh, NC 27602 Ernest J. Kapopoulos Jr.

Plant General Manager Carolina Power and Light Company Shearon Harris Nuclear Power Plant Electronic Mail Distribution Chair Board of County Commissioners of Chatham County P.O. Box 1809 Pittsboro, NC 27312 Senior Resident Inspector U.S. Nuclear Regulatory Commission Shearon Harris Nuclear Power Plant U.S. NRC 5421 Shearon Harris Rd New Hill, NC 27562-9998

Enclosure Supplemental Inspection Document Request List Inspection Dates:

March 18 - 22, 2013 Inspection Procedures:

IP 95001 Supplemental Inspection for One or Two White Inputs in a Strategic Performance Area IP 92702 Follow-up on Traditional Enforcement Actions Including Violations, Deviations, Confirmatory Action Letters, Confirmatory Orders, and Alternative Dispute Resolution Confirmatory Orders Note: This is a list of the documents to be delivered to the NRC Region II Office (245 Peachtree Center Avenue, NE, Suite 1200, Atlanta, GA 30303-1257, Attention: Mark Speck).

The current version of these documents is expected unless specified otherwise. Electronic media is preferred, if readily available (the preferred file format is Word or searchable.pdf files on CDROM or thumb drive). Please organize the information as it is arranged below. It is not the intent that large or burdensome data be scanned for this purpose. This data will be inspected using original documentation. If there are questions regarding the documents requested, please do not hesitate to contact the inspector.

Final causal analysis, extent of condition analysis, and supporting documents related to the NOV List of analysis team members, team charter, qualifications of team members Documentation of corrective actions taken and/or proposed determined to be appropriate for all root and contributing causes (e.g., procedure changes, training requirements, records, etc.)

Actions performed or proposed determined to be adequate to demonstrate/verify effectiveness of corrective actions Results of any effectiveness reviews, audits, self-assessments, mock inspections, etc.,

used to validate preparation for the inspection Site procedures governing causal analysis performance and corrective action program procedures Inspector Contact Information:

Mark E. Speck (404) 997-4759 Mark.Speck@nrc.gov