Updated Plans and Schedule for ONS Standby Shutdown Facility Design Review Project
ML123550039
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 12/14/2012
From: Gillespie T
Duke Energy Carolinas
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
Download: ML123550039 (2)


Text

Duke Energy T. PRESTON GILLESPIE, Jr.

Vice President Oconee Nuclear Station Duke Energy ON01 VP / 7800 Rochester Hwy.

Seneca, SC 29672 864-873-4478 864-873-4208 fax T. Gillespie@duke-energy. com December 14, 2012 U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555-0001

Subject:

Reference:

Duke Energy Carolinas, LLC Oconee Nuclear Station (ONS), Units 1, 2 and 3 Renewed Facility Operating License Numbers DPR-38, -47, -55; Docket Numbers 50-269, 50-270 and 50-287; Updated Plans and Schedule for ONS Standby Shutdown Facility Design Review Project Duke Energy letter from T. Preston Gillespie to Victor McCree (Nuclear Regulatory Commission), Standby Shutdown Facility Design Review Project Plan and Schedule, dated February 17, 2012 By the referenced letter, Duke Energy Carolinas, LLC (Duke Energy) submitted to the Nuclear Regulatory Commission (NRC) the plan and schedule for the Standby Shutdown Facility (SSF)

Design Review Project. Since that time, there have been two updates to the plan and schedule.

The purpose of this letter is to document that these updates have been informally shared with the NRC. Revision 1 to the plan and schedule was presented to the NRC at a meeting with the ONS Senior Resident Inspector on August 27, 2012. Revision 2 to the plan and schedule was informally given to the ONS NRC Senior Resident Inspector on Monday, October 22, 2012.

Upon request, Duke Energy will make the existing and any future revisions to the SSF Design Review Project plan and schedule available to the NRC for inspection in the Senior Resident Inspector's ONS office.

This submittal document contains no regulatory commitments.

If there are any questions regarding this letter, please contact Lenny Azzarello of Duke Energy Fleet Design Engineering at (704) 382-8168.

Sincerely, TF-IL0*C T. Preston Gillespie, Jr.,

Vice President Oconee Nuclear Station www. duke-energy, corn

U. S. Nuclear Regulatory Commission December 14, 2012 Page 2 cc:

Mr. Victor McCree, Regional Administrator U. S. Nuclear Regulatory Commission - Region II Marquis One Tower 245 Peachtree Center Ave., NE, Suite 1200 Atlanta, Georgia 30303-1257 Mr. John Boska, Project Manager (by electronic mail only)

Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission 11555 Rockville Pike Mail Stop O-8G9A Rockville, MD 20852 Mr. Jonathan Bartley U. S. Nuclear Regulatory Commission - Region II Marquis One Tower 245 Peachtree Center Ave., NE, Suite 1200 Atlanta, Georgia 30303-1257 Senior Resident Inspector Oconee Nuclear Site Ms. Susan E. Jenkins, Manager Radioactive & Infectious Waste Management Division of Waste Management South Carolina Department of Health and Environmental Control 2600 Bull St.

Columbia, SC 29201