MONTHYEARML16285A3252016-10-12012 October 2016 ROP PI Frequently Asked Questions (Faqs): 14-02 ML16125A5222016-05-0404 May 2016 FOIA/PA-2016-0455 - Resp 1 - Final, Agency Records Subject to the Request Are Enclosed ML15231A3642015-05-27027 May 2015 FOIA/PA-2014-0204 - Resp 1 - Final, Group a ML15014A1602015-01-14014 January 2015 Attachment 2 - NRC Working Group Recommendations to Revise the Substantive Cross-Cutting Issue Process ML15014A1532015-01-14014 January 2015 Attachment 1- NEI Comments on NRC Working Group Recommendations to Revise the Substantive Cross-Cutting Issue Process ML14314A5122014-11-13013 November 2014 Enclosure 2 - Frequently Asked Questions (Faqs) Discussed During the October 22 2014 Reactor Oversight Process Public Meeting ML14051A3882014-02-20020 February 2014 NFPA 805 Fpra F&O Tables ML14051A3972014-02-20020 February 2014 NFPA 805 IE PRA F&O Tables LIC-13-0140, Attachment 3 - Strategy to Protect Fort Calhoun Station from Beyond Design Basis Flood - Redacted2013-10-26026 October 2013 Attachment 3 - Strategy to Protect Fort Calhoun Station from Beyond Design Basis Flood - Redacted ML13253A3532013-09-27027 September 2013 Enclosuinformation Sheet, National Cancer Institute Study of Ft. Calhoun Area ML13273A3092013-09-19019 September 2013 FOIA/PA-2012-0235 - Resp 1 - Partial. Group a, Records Being Released in Their Entirety. Part 11 of 21 ML13273A3012013-09-19019 September 2013 FOIA/PA-2012-0235 - Resp 1 - Partial. Group a, Records Being Released in Their Entirety. Part 4 of 21 ML13273A3082013-09-19019 September 2013 FOIA/PA-2012-0235 - Resp 1 - Partial. Group a, Records Being Released in Their Entirety. Part 10 of 21 ML13273A3072013-09-19019 September 2013 FOIA/PA-2012-0235 - Resp 1 - Partial. Group a, Records Being Released in Their Entirety. Part 9 of 21 ML13273A3052013-09-19019 September 2013 FOIA/PA-2012-0235 - Resp 1 - Partial. Group a, Records Being Released in Their Entirety. Part 8 of 21 ML13273A3042013-09-19019 September 2013 FOIA/PA-2012-0235 - Resp 1 - Partial. Group a, Records Being Released in Their Entirety. Part 7 of 21 ML13273A3032013-09-19019 September 2013 FOIA/PA-2012-0235 - Resp 1 - Partial. Group a, Records Being Released in Their Entirety. Part 6 of 21 ML13273A3022013-09-19019 September 2013 FOIA/PA-2012-0235 - Resp 1 - Partial. Group a, Records Being Released in Their Entirety. Part 5 of 21 ML13273A3002013-09-19019 September 2013 FOIA/PA-2012-0235 - Resp 1 - Partial. Group a, Records Being Released in Their Entirety. Part 3 of 21 ML13273A2982013-09-19019 September 2013 FOIA/PA-2012-0235 - Resp 1 - Partial. Group a, Records Being Released in Their Entirety. Part 2 of 21 ML13273A2972013-09-19019 September 2013 FOIA/PA-2012-0235 - Resp 1 - Partial. Group a, Records Being Released in Their Entirety. Part 1 of 21 ML13273A3112013-09-19019 September 2013 FOIA/PA-2012-0235 - Resp 1 - Partial. Group a, Records Being Released in Their Entirety. Part 13 of 21 ML13273A3132013-09-19019 September 2013 FOIA/PA-2012-0235 - Resp 1 - Partial. Group a, Records Being Released in Their Entirety. Part 14 of 21 ML13273A3152013-09-19019 September 2013 FOIA/PA-2012-0235 - Resp 1 - Partial. Group a, Records Being Released in Their Entirety. Part 15 of 21 ML13273A3162013-09-19019 September 2013 FOIA/PA-2012-0235 - Resp 1 - Partial. Group a, Records Being Released in Their Entirety. Part 16 of 21 ML13273A3172013-09-19019 September 2013 FOIA/PA-2012-0235 - Resp 1 - Partial. Group a, Records Being Released in Their Entirety. Part 17 of 21 ML13273A3192013-09-19019 September 2013 FOIA/PA-2012-0235 - Resp 1 - Partial. Group a, Records Being Released in Their Entirety. Part 18 of 21 ML13273A3222013-09-19019 September 2013 FOIA/PA-2012-0235 - Resp 1 - Partial. Group a, Records Being Released in Their Entirety. Part 19 of 21 ML13273A3232013-09-19019 September 2013 FOIA/PA-2012-0235 - Resp 1 - Partial. Group a, Records Being Released in Their Entirety. Part 20 of 21 ML13273A3242013-09-19019 September 2013 FOIA/PA-2012-0235 - Resp 1 - Partial. Group a, Records Being Released in Their Entirety. Part 21 of 21 ML13273A3262013-09-19019 September 2013 FOIA/PA-2012-0235 - Resp 1 - Partial. Group C, Records Being Released in Part ML13273A3102013-09-19019 September 2013 FOIA/PA-2012-0235 - Resp 1 - Partial. Group a, Records Being Released in Their Entirety. Part 12 of 21 ML13203A0052013-07-23023 July 2013 Exigent Local Proposed Notice of Consideration of Issuance of Amendment, Revise Current Licensing Basis to Adopt Revised Design Basis/Methodology for Addressing Design-Basis Tornado/Tornado Missile Impact ML13191A0692013-06-18018 June 2013 G20130515/LTR-13-0597-Ticket - Senator Harry Reid Ltr Constituent Correspondence - Possible Storm Damage to America'S Nuclear Power Plants - Fort Calhoun (Alfredo Hannenberg) ML13109A2932012-12-20020 December 2012 G20120458/EDATS: OEDO-2012-0390 - Attachment 4 ML13109A2712012-12-20020 December 2012 G20120458/EDATS: OEDO-2012-0390 - Attachment 1 ML12352A2402012-12-17017 December 2012 G20120458/EDATS: OEDO-2012-0390 - Ft. Calhoun Containment Structure Failures ML12352A2742012-12-16016 December 2012 G20120458/EDATS: OEDO-2012-0390 - Additional Comments from 2.206 Petitioner W.Taylor ML12056A0522012-03-12012 March 2012 Enclosure 6 - List of Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status ML1019304602010-03-25025 March 2010 List of Historical Leaks and Spills at Us Commercial Nuclear Power Plants ML0933507512010-01-14014 January 2010 Temporary Instruction 2515/180, Managing Fatigue ML0729606902007-10-31031 October 2007 Proposed Changes to Public Radiation Safety SDP ML0732400242007-10-25025 October 2007 Examples of Max Thermal Power License Conditions ML0720004162007-07-26026 July 2007 Ft. Calhoun Surveillance Test Procedure Excerpts ML0721104332007-07-25025 July 2007 Questions from 1 Through 8 ML0727401082006-12-18018 December 2006 Differing Professional Opinion from E. Marinos ML0634705992006-12-14014 December 2006 Plant Service List ML0617300862006-06-20020 June 2006 FCS - Event Numbers 41947, 42366, 42412 ML0727105902006-06-0101 June 2006 Et/Lt Brief on the Status of the Measurement Uncertainty Recapture Issue LIC-05-0057, Revised Relaxation Request for First Revised Order (EA-03-009) Establishing Interim Inspection Requirements for Reactor Pressure Vessel Heads at Pressurized Water Reactors2005-05-14014 May 2005 Revised Relaxation Request for First Revised Order (EA-03-009) Establishing Interim Inspection Requirements for Reactor Pressure Vessel Heads at Pressurized Water Reactors 2016-05-04
[Table view] |
Text
Ft. Calhoun Containment Structure Failures Admitted December 13th, 2012 l Add a Comment
[Translate]
Representatives from Ft. Calhouns operator OPPD, hired engineering firms, and the NRC held a meeting Wesnesday to discuss details of what has been described as issues with containment structures.
The portion of the containment structure that is being investigated was described as a portion that supports plant equipment including air handling, steam generators and class 1 piping.
A number of concrete beams within this structure were found to be failed as part of a plan to obtain a power uprate for the plant. Babcock & Wilcox were to begin engineering work for the uprate during the spring 2011 refueling outage that turned into the massive spring 2011 flood. Calculation work for the uprate was stopped after the first 6 beams investigated were considered failed.
The problems go back to the original design of the plant. Further investigation discovered that the original design drawings submitted for the plant license had missing and incorrect calculations. They also differed from the construction drawings. OPPD, Ft. Calhouns owner and operator has known about this since the 1990s. The source of these original designs appears to be Gibbs, Hill, Durham & Richardson Inc., an Omaha, NE are architect firm that may have gone out of business at some point. No reference for this company could be found online except their work on Ft. Calhoun.
OPPD has known since the 1990s about the missing calculations through safety checks at that time. They claim they were not aware of the miscalculations but they also did nothing about the missing calculations.
They decided to do nothing about the unknowns and only worry about them if they had to make a change or modification to the plant. OPPD had to reconstitute the design of the water intake systems in 2007 due to these same problems.
The planned uprate would have caused system pipes to run hotter than normal causing additional loads on the air coolers and pipe systems. The beams could not handle the uprated power demands and they didnt
meet the design specs of the current operation of the plant. The beams under the air coolers all failed the design requirements. The beams under the new steam generators, OPPD claims are sound enough to hold up but provided no proof to back up this claim.
OPPD has hired a number of engineering firms to review their design and help them convince the NRC they should be allowed to restart with no changes. The first engineering firm took the as constructed building plans and attempted to create a 3-d model and computer modeling to prove the critical plant systems are sound. Someone from the NRC asked about visual walkdowns but there appears to have been no technical attempts to confirm the as constructed matches the actual construction. All other 3rd party technical consultants worked off of the first engineering firms computer models meaning that many kinds of miscalculations could have been repeated by the additional firms. If the initial assumptions were wrong, the other firms wouldnt find it since they are only checking the outcomes of the first firms work. The consultants do mention that the as built does not meet the design standard of the license.
This modeling did not include the slab the critical containment structures sits on. There are known concerns with erosion, OPPD had had two different geo-tech companies investigating the site but have been tight lipped about what was found. The modeling also did not include missiles such as projectiles inside the containment caused by a failure at the plant.
OPPDs plan stated in the meeting was that they want to restart without making changes to the structure then to restore the licensing basis of the plant later after it is running. They were also unable to explain if or how it would change critical operating factors like air flow within the containment building and on critical equipment. OPPD did not explain why the NRC should allow them to restart when the plant can no longer meet the established licensing requirements.
NRC representatives did mention that the review of this issue will be a very long process and may take months. There has been no mention to the media from OPPD if they still intend to restart at a low power in December as they previously claimed, or if that is even possible at this point.