LTR - Request for Additional Information Letter Review of Physical Security Plan
ML123520048
Person / Time
Site: Vermont Yankee File:NorthStar Vermont Yankee icon.png
Issue date: 12/31/2012
From: Richard Guzman
Plant Licensing Branch 1
To:
Entergy Nuclear Vermont Yankee
Guzman R, NRR/DORL 415-1030
Shared Package
ML123520047 List:
References
D91660
Download: ML123520048 (2)


Text

OFFICIAL USE ONLY SECURITY RELATED INFORMATION UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D,C, 20555-0001 December 31, 2012 Site Vice President Entergy Nuclear Operations, Inc, Vermont Yankee Nuclear Power Station p,O, Box 250 Governor Hunt Road Vernon, VT 05354

SUBJECT:

VERMONT YANKEE NUCLEAR POWER STATION - REQUEST FOR ADDITIONAL INFORMATION REGARDING REVIEW OF PHYSICAL SECURITY PLAN, TRAINING AND QUALIFICATION PLAN, AND SAFEGUARDS CONTINGENCY PLAN, REVISION 12

Dear Sir or Madam:

By letter dated August 21,2012 (Agencywide Documents Access and Management System Accession No, ML12240A225), Entergy Nuclear Operations, Inc, (Entergy. the licensee) submitted the Physical Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan, Revision 12, for Vermont Yankee Nuclear Power Station in accordance with paragraph 50.54(p)(2) of Title 10 of the Code of Federal Regulations. The enclosure to the letter contained Safeguards Information and has been withheld from public disclosure.

The U,S. Nuclear Regulatory Commission (NRC) staff has reviewed the information provided by the licensee and determined that the additional information identified in the enclosure to this letter is needed in order for the NRC staff to complete its review, The request for additional information was discussed with your staff on December 10, 2012, and it was agreed that your response would be provided by January 31, 2013.

If you have any questions, please contact me at 301-415-1030 or via e-mail at Richard,guzman@nrc,gov.

Sincerely, Docket No. 50-271

Enclosure:

Request for Additional Information cc w/o encls: Distribution via Listserv Richard V. Guzman, Senior Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Enclosure transmitted herewith contains Sensitive Unclassified Non-Safeguards Information, When separated from the enclosure, this transmittal document is decontrolled.

OFFICIAL USE ONLY SECURITY RELATED INFORMATION

OFFICIAL USE ONLY SECURITY RELATED INFORMATION December 31.2012 Site Vice President Entergy Nuclear Operations, Inc.

Vermont Yankee Nuclear Power Station P.O. Box 250 Governor Hunt Road Vernon. VT 05354

SUBJECT:

VERMONT YANKEE NUCLEAR POWER STATION - REQUEST FOR ADDITIONAL INFORMATION REGARDING REVIEW OF PHYSICAL SECURITY PLAN, TRAINING AND QUALIFICATION PLAN. AND SAFEGUARDS CONTINGENCY PLAN. REVISION 12

Dear Sir or Madam:

By letter dated August 21,2012 (Agencywide Documents Access and Management System Accession No. ML12240A225), Entergy Nuclear Operations, Inc. (Entergy, the licensee) submitted the Physical Security Plan. Training and Qualification Plan, and Safeguards Contingency Plan, Revision 12. for Vermont Yankee Nuclear Power Station in accordance with paragraph 50.54(p)(2) of Title 10 of the Code of Federal Regulations.

The enclosure to the letter contained Safeguards Information and has been withheld from public disclosure.

The U.S. Nuclear Regulatory Commission (NRC) staff has reviewed the information provided by the licensee and determined that the additional information identified in the enclosure to this letter is needed in order for the NRC staff to complete its review. The request for additional information was discussed with your staff on December 10. 2012, and it was agreed that your response would be provided by January 31,2013.

If you have any questions. please contact me at 301-415-1030 or via e-mail at Richard.guzman@nrc.gov.

Sincerely.

IRA by DPickett fori Richard V. Guzman, Senior Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-271 Enclosure transmitted herewith contains Sensitive Uncla..lfied Non-5afeguards Infonnation. When

Enclosure:

separated from the enclosure, this transmittal Request for Additional Information document Is decontrolled.

cc w/o encls: Distribution via Listserv DISTRIBUTION:

LPLI-1 R/F RidsAcrsAcnw_MailCTR Resource RidsNrrDorlDpr Resource RidsNrrDorlLpl1-1 Resource RidsRgn1MailCenter Resource RidsNrrPMVermontYankee Resource RidsNrrLALGoldstein Resource RidsNsirDspRslb Resource RidsOgcRp Resource JFrost, NSIR/DSP/RSLB RFeltsRCosta, NSIR/DSP/RSLB ADAMS ACCESSION NO.: Package: ML123520047 L TR' ML123520048, RAI' ML123520056

  • via memo
    • via email OFFICE LPL1-1/PM LPL1-1/LA NSiR/DSP/RSLB/BC LPL1-1/BC LPL 1-1/PM NAME RGuzman KGoldstein**

(ABaxter for)

RFelts' GWilson JDPickett for)

RGuzman JDPickett for)

DATE 12/21/12 12/19/12 11/14/12 12/31/12 12/31/12 OFFICIAL RECORD COpy OFFICIAL USE ONLY SECURITY RELATED INFORMATION