Additional Actions for Emergency Diesel Generators 1 and 3
ML12348A009
Person / Time
Site: Surry  
(DPR-032, DPR-037)
Issue date: 11/13/2012
From: Lane N
Virginia Electric & Power Co (VEPCO)
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
12-706
Download: ML12348A009 (3)


Text

VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGINIA 23261 November 13, 2012 U.S. Nuclear Regulatory Commission Serial No.:

12-706 Attention: Document Control Desk SPS/BAG:

RO Washington, D.C. 20555-0001 Docket Nos.:

50-280 50-281 License Nos.: DPR-32 DPR-37 VIRGINIA ELECTRIC AND POWER COMPANY SURRY POWER STATION UNITS I AND 2 ADDITIONAL ACTIONS FOR SURRY EMERGENCY DIESEL GENERATORS I AND 3 On November 1, 2012, the NRC held a conference call with Virginia Electric and Power Company (Dominion) to discuss future actions to be taken on Surry's EDG 1 and 3 based on an evaluation of EDG 2 wrist pin bearing failure. During the conference call Dominion stated that the following actions would be taken:

1. If the confirmed analysis of lube oil samples on EDG 1 or 3 indicate that the silver concentration is ->0.1 ppm, the affected EDG will be declared inoperable and its power packs replaced. The industry recommended action level for silver in the EDG lube oil is >0.3 ppm.

In light of the unanticipated nature of the EDG 2 wrist pin damage, the lowering of this action level to -0.1 ppm is considered to be a conservative and prudent measure.

2. Based upon the results of the root cause evaluation, the EDG 3 power packs will be replaced in January 2013 and the EDG 1 power packs will be replaced in February 2013. The twelve (12) year EDG power pack replacement preventive maintenance frequency previously established the target date for EDG 1 and EDG 3 power pack replacement as September 2013 and July 2014, respectively.

Also discussed during the conference call was consideration of an additional action to remove EDG 1 and 3 from service, drain the lube oil, and inspect the sump for silver material that might be indicative of bearing degradation. Dominion noted that they had evaluated inspecting the sumps and concluded that these inspections would be of limited benefit. The last inspection on EDG 1 sump was in June 2010 and in November 2011 for EDG 3.

Both inspections found the sumps in satisfactory condition.

Re-performing the sump inspections would result in additional out of service time with attendant increased plant risk. In addition, all of the oil (-500 gallons) would need to be drained to inspect the sump. When the oil is returned to the EDG, it is either replaced with new oil or the used oil is filtered prior to returning it to the EDG.

If excessive bearing wear has started, but the silver concentration is below detectable limits,

replacing or filtering the used oil would re-baseline oil monitoring and may mask a possible degraded condition.

These actions were discussed with the Electromotive Diesel (EMD) Owners Group who considered the oil analysis appropriate to monitor for wrist pin bearing wear and that the sump inspections would not provide additional insight.

In summary, monitoring the lube oil for silver continues to be the vendor recommended method for detection of wrist pin bearing degradation.

Lowering the action level for silver content is an acceptable measure to ensure diesel reliability. Replacement of the EDG power packs in a controlled manner through the work management process is the best method to safely address the present concerns regarding the diesels.

These actions are temporary and apply only until the EDG 1 and 3 power packs have been replaced. If you have any questions, please contact Mr. Barry Garber at 757-365-2725.

Sincerely, N. L. Lane Site Vice President Surry Power Station Commitments made by this letter:

1. When confirmed silver content in EDG 1 or 3 lube oil is >0.1 ppm, the EDG with the silver in the oil will be declared inoperable and its power packs replaced.
2. EDG 3 power packs will be replaced in January 2013 and the EDG 1 power packs will be replaced in February 2013.

cc:

U. S. Nuclear Regulatory Commission, Region II Attn.: Regional Administrator Marquis One Tower 245 Peachtree Center Ave., NE - Suite 1200 Atlanta, GA 30303-1257 Ms. K. R. Cotton NRC Project Manager Surry U. S. Nuclear Regulatory Commission Mail Stop 08 G9A One White Flint North 11555 Rockville Pike Rockville, MD 20852-2738 Dr. V. Sreenivas NRC Project Manager North Anna U. S. Nuclear Regulatory Commission Mail Stop 08 G9A One White Flint North 11555 Rockville Pike Rockville, MD 20852-2738 NRC Senior Resident Inspector Surry Power Station