ML12346A349

From kanterella
Jump to navigation Jump to search

Pennsylvania State University - Email to Extend RAI Response Time for Facility Operating License No. R-2 Breazeale Reactor
ML12346A349
Person / Time
Site: Pennsylvania State University
Issue date: 12/03/2012
From: Xiaosong Yin
Research and Test Reactors Licensing Branch
To: Trump M
Pennsylvania State Univ
References
TAC ME8001
Download: ML12346A349 (2)


Text

From:

Yin, Xiaosong Sent:

Monday, December 03, 2012 4:02 PM To:

Mark A. Trump

Subject:

RE: Request for Additional Information Breazeale Nuclear Reactor license admendment request Okay. I'll be looking forward to your response by january 16th. Thanks!

From: Mark A. Trump [mtrump@engr.psu.edu]

Sent: Monday, December 03, 2012 3:35 PM To: Yin, Xiaosong

Subject:

RE: Request for Additional Information Breazeale Nuclear Reactor license admendment request How about Wednesday January 16th?

Mark A. Trump Associate Director for Operations Breazeale Nuclear Reactor Radiation Science and Engineering Center Pennsylvania State University University Park, PA 16802 814 865 6351 admin 814 863 2745 direct From: Yin, Xiaosong [1]

Sent: Monday, December 03, 2012 2:04 PM To: Mark A. Trump

Subject:

RE: Request for Additional Information Breazeale Nuclear Reactor license admendment request

Mark, Happy Holidays to you too!

Taking into the consideration of this special time of the year, it is reasonable for you to ask to extend the responding time from the regular 30 days. Just let me know when you can reasonably provide the response (date please).

Thanks, Xiaosong From: Mark A. Trump [mtrump@engr.psu.edu]

Sent: Monday, December 03, 2012 10:18 AM To: Yin, Xiaosong

Subject:

Request for Additional Information Breazeale Nuclear Reactor license admendment request Happy Holiday Xiaosong!

The Facility received the RAI on 11/30 (issue date 11/21).

I have reviewed the scope of the RAI and I believe I can generate the answers in a reasonable period.

However with the pending holidays and the need for internal review of my answers, I will not be able to provide a docketed response within the 30 day from date of the letter specified in the RAI.

Since, I hope you get some time off for the holidays, I suspect you werent planning on reviewing the response on 12/22.

Would you find a mid-January response date acceptable?

Mark A. Trump Associate Director for Operations Breazeale Nuclear Reactor Radiation Science and Engineering Center Pennsylvania State University University Park, PA 16802 814 865 6351 admin 814 863 2745 direct