MONTHYEARML24023A0342024-02-0505 February 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0038 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) L-2024-010, Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3)2024-01-25025 January 2024 Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3) ML23341A2102024-01-22022 January 2024 LTR-23-0216-1 - Closure Letter - 2.206 Petition for License Renewal Plant Reactor Pressure Vessel Embrittlement ML23320A3062024-01-22022 January 2024 Issuance of Amendment Nos. 298 and 291 Regarding Revising the Fire Protection Program in Support of Reactor Coolant Pump Seal Replacement Project L-2024-007, Inservice Inspection Program Owner'S Activity Report (OAR-1)2024-01-18018 January 2024 Inservice Inspection Program Owner'S Activity Report (OAR-1) L-2023-173, Quality Assurance Topical Report (FPL-1) Revision 30 Update2023-12-15015 December 2023 Quality Assurance Topical Report (FPL-1) Revision 30 Update L-2023-166, Turkey Points Units 3 and 4, Correction to the 2022 Annual Radioactive Effluent Release Report2023-12-0606 December 2023 Turkey Points Units 3 and 4, Correction to the 2022 Annual Radioactive Effluent Release Report ML23340A0332023-12-0101 December 2023 FPL to Fws, Comments Submitted by Florida Power and Light on the Species Status Assessment Accompanying the September 20, 2023 Proposed Threatened Species Status with Section 4(d) Rule for the Miami Cave Crayfish L-2023-172, Supplement to Exemption Request Regarding Enhanced Weapons. Firearms Background Checks. and Security Event Notifications Final Rule2023-11-29029 November 2023 Supplement to Exemption Request Regarding Enhanced Weapons. Firearms Background Checks. and Security Event Notifications Final Rule L-2023-155, Supplement to Response to Request for Additional Information, Revised NextEra Common Emergency Plan, and Revised Site-Specific Emergency Plan Annexes Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-06542023-11-28028 November 2023 Supplement to Response to Request for Additional Information, Revised NextEra Common Emergency Plan, and Revised Site-Specific Emergency Plan Annexes Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, ML23333A0152023-11-27027 November 2023 Attachment G - Arcadis Memo Re FPL Year 4 Raasr Final (June 2, 2023, Appended to Derm letter)-1 ML23333A0102023-11-27027 November 2023 Attachment B - 11/07/2022 - Waterkeeper Scoping Comments-1 L-2023-146, Part 73 Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule2023-11-16016 November 2023 Part 73 Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule L-2023-078, License Amendment Request 278, Incorporate Advanced Fuel Products, Extend Surveillance Intervals and 10 CFR 50.46 Exemption Request to Facilitate Transition to 24-Month Fuel Cycles2023-11-15015 November 2023 License Amendment Request 278, Incorporate Advanced Fuel Products, Extend Surveillance Intervals and 10 CFR 50.46 Exemption Request to Facilitate Transition to 24-Month Fuel Cycles IR 05000250/20230032023-11-0909 November 2023 Integrated Inspection Report 05000250/2023003 and 05000251/2023003 ML23310A1342023-11-0404 November 2023 10 CFR 2.206 Petition - LTR-23-0216-1 Petition Amendment; Turkey Point Subsequent Renewal with Petitioner 11/04/2023 ML24016A2622023-10-25025 October 2023 Subsequent License Renewal Updated List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected Project L-2023-077, License Amendment Request 277 Updated Spent Fuel Pool Criticality Analysis2023-10-11011 October 2023 License Amendment Request 277 Updated Spent Fuel Pool Criticality Analysis ML23346A1322023-10-0606 October 2023 Communication from C-10 Research & Education Foundation Regarding NextEra Common Emergency Fleet Plan License Amendment Request and Related Documents Subsequently Published IR 05000250/20230102023-09-29029 September 2023 Biennial Problem Identification and Resolution Inspection Report 05000250/2023010 and 05000251/2023010 ML23234A1922023-09-27027 September 2023 Issuance of Amendment Nos. 297 and 290 Regarding Conversion to Improved Standard Technical Specifications ML23265A5492023-09-22022 September 2023 Transmittal of WCAP-18830-P/NP Turkey Point Fuel Storage Criticality Analysis for 24 Month Cycles to Support a License Amendment Request from FPL - License Amendment Request 277 Updated Spent Fuel Pool Criticality Analysis ML23243A9522023-09-0808 September 2023 Notice of Availability of the Draft Environmental Impact Statement for the Turkey Point Nuclear Generating Unit Numbers 3 and 4 Subsequent License Renewal Application ML23243A9542023-09-0808 September 2023 Notice of Availability of the Draft Environmental Impact Statement for the Turkey Point Nuclear Generating Unit Numbers 3 and 4 Subsequent License Renewal Application ML23243A9532023-09-0808 September 2023 Notice of Availability of the Draft Environmental Impact Statement for the Turkey Point Nuclear Generating Unit Numbers 3 and 4 Subsequent License Renewal Application ML23243A9552023-09-0808 September 2023 Notice of Availability of the Draft Environmental Impact Statement for the Turkey Point Nuclear Generating Unit Numbers 3 and 4 Subsequent License Renewal Application - Tribe- Section 106 Letters ML23199A2352023-09-0505 September 2023 Letter to EPA-Turkey Point Nuclear Generating Station, Units 3 and 4 - Notice of Availability of Draft Site-Specific Environmental Impact Statement for Subsequent License Renewal ML23199A2482023-09-0505 September 2023 Ltr to Florida Power and Light Co - Turkey Point Nuclear Generating Units 3 and 4 - Notice of Availability of Draft Site-Specific Environmental Impact Statement for Subsequent License Renewal L-2023-110, Response to Requests for Additional Information Regarding License Amendment Request No. 276, Revise Fire Protection Program in Support of Reactor Coolant Pump Seal Replacement Project2023-08-25025 August 2023 Response to Requests for Additional Information Regarding License Amendment Request No. 276, Revise Fire Protection Program in Support of Reactor Coolant Pump Seal Replacement Project IR 05000250/20230052023-08-21021 August 2023 Updated Inspection Plan for Turkey Point, Units 3 & 4 (Report 05000250/2023005 and 05000251/2023005) L-2023-115, Inservice Inspection Program Owner'S Activity Report (OAR-1)2023-08-21021 August 2023 Inservice Inspection Program Owner'S Activity Report (OAR-1) L-2023-114, Proposed Turkey Point Units 6 and 7; Seabrook Station; Point Beach Units 1 and 2 - Official Service List Update2023-08-17017 August 2023 Proposed Turkey Point Units 6 and 7; Seabrook Station; Point Beach Units 1 and 2 - Official Service List Update IR 05000250/20230022023-08-14014 August 2023 Integrated Inspection Report 05000250/2023002 and 05000251/2023002 L-2023-098, and Point Beach Units 1 and 2 - Response to Request for Additional Information Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 22023-08-0707 August 2023 and Point Beach Units 1 and 2 - Response to Request for Additional Information Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 2 ML23242A0922023-08-0606 August 2023 Request for Withholding Information from Public Disclosure for Turkey Point Nuclear Generating Unit Nos. 3 and 4 ML23201A0872023-08-0303 August 2023 Audit Plan in Support of Review of License Amendment ML23198A2702023-08-0303 August 2023 Issuance of the Site-Specific Environmental Impact Statement Scoping Process Summary Report Associated with the Turkey Point Nuclear Generating Unit Numbers 3 and 4, Subsequent License Renewal Application, Environmental Report Supplement 2 L-2023-094, Response to Requests for Additional Information Regarding License Amendment Request No. 276, Revise Fire Protection Program in Support of Reactor Coolant Pump Seal Replacement Project2023-07-27027 July 2023 Response to Requests for Additional Information Regarding License Amendment Request No. 276, Revise Fire Protection Program in Support of Reactor Coolant Pump Seal Replacement Project ML23178A1872023-07-25025 July 2023 Review of the Spring 2022 Steam Generator Tube Inspections During Refueling Outage No. 33 ML23188A1242023-07-20020 July 2023 Acknowledgment of Temporary Suspension Request for License Request for License Amendment Request Reactor Protection System, Engineered Safety Features System, and Nuclear Instrumentation System ML23200A0672023-07-18018 July 2023 Tp 2023 RQ Inspection Notification Letter ML23173A0812023-07-17017 July 2023 Supplement to Regulatory Audit Plan in Support of Review of License Amendment Request Supporting Digital Instrumentation & Control Modernization Project (EPID L-2022-LLA-0105) - Non-Proprietary L-2023-087, Florida Power & Light/Nextera Energy, Results of the Safety Culture Program Effectiveness Review, March 20, 2023 (ADAMS Accession No. ML22340A452)2023-06-29029 June 2023 Florida Power & Light/Nextera Energy, Results of the Safety Culture Program Effectiveness Review, March 20, 2023 (ADAMS Accession No. ML22340A452) 2024-02-05
[Table view] |
Text
NOV 2 0 2012 FPL. L-2012-417 10 CFR 50.54(f)U. S. Nuclear Regulatory Commission Attn.: Document Control Desk Washington, D.C. 20555-0001 Turkey Point Units 3 and 4 Docket Nos. 50-250 and 50-251 Response to NRC 10 CFR 50.54(f) Request for Information Regarding Near-Term Task Force Recommendation 2.3, Flooding
References:
- 1. NRC Letter, Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendations 2.1, 2.3, and 9.3, of the Near-Term Task Force Review of Insights from the Fukushima Dai-Ichi Accident; dated March 12, 2012, Accession No. ML12073A348.
- 2. M. Kiley (FPL) to U.S. Nuclear Regulatory Commission (L-2012-237), "Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding the Flooding Aspects of Recommendation 2.1 and 2.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident," Accession No. ML 12174A206, June 11, 2012.3. NRC Letter to Nuclear Energy Institute, Endorsement of Nuclear Energy Institute (NEI)12-07, "Guidelines for Performing Verification Walkdowns of Plant Flood Protection Features," dated May 31, 2012, Accession No. ML12144A142.
On March 12, 2012, the NRC staff issued Reference 1 requesting information pursuant to Title 10 of the Code of Federal Regulations 50.54(f).
Enclosure 4 of that letter contains specific Requested Information associated with Near-Term Task Force Recommendation 2.3 for Flooding.
Item 2 of the Requested Information asks for a final walkdown report, which is to include the following:
- a. Describe the design basis flood hazard level(s) for all flood-causing mechanisms, including groundwater ingress.b. Describe protection and mitigation features that are considered in the licensing basis evaluation to protect against external ingress of water into SSCs important to safety.c. Describe any warning systems to detect the presence of water in rooms important to safety.d. Discuss the effectiveness of flood protection systems and exterior, incorporated, and temporary flood barriers.
Discuss how these systems and barriers were evaluated using the acceptance criteria developed as part of Requested Information item 1 .h.e: Present information related to the implementation of the walkdown process (e.g., details of selection of the walkdown team and procedures) using the documentation template discussed in Requested Information item 1.j, including actions taken in response to the peer review.Florida Power & Light Company 9760 SW 3 4 4 St., Florida City, FL 33035 Turkey Point Nuclear Plant L-2012-417 Docket Nos. 50-250 and 50-251 Page 2 of 2 f. Results of the walkdown, including key findings and identified degraded, nonconforming or unanalyzed conditions.
Include a detailed description of the actions taken or planned to address these conditions using the guidance in Regulatory Issues Summary 2005-20, Revision 1, including entering the condition in the corrective action program.g. Document any cliff-edge effects identified and the associated basis. Indicate those that were entered into the corrective action program. Also include a detailed description of the actions taken or planned to address these effects.h. Describe any other planned or newly installed flood protection systems or flood mitigation measures including flood barriers that further enhance the flood protection.
Identify results and any subsequent actions taken in response to the peer review.Per Reference 1, the above report is to be submitted within 180 days of the NRC's endorsement of the walkdown procedure and should include a list of any areas that could not be inspected due to inaccessibility and should identify a schedule for when the walkdown will be completed.
Per Reference 2, Florida Power & Light (FPL) confirmed that it will use the NRC-endorsed flooding walkdown procedure NEI 12-07, "Guidelines for Performing Verification Walkdowns of Plant Flood Protection Features" and submit a report by November 27, 2012, which corresponds to 180 days after NRC endorsement of the NEI. guidance (Reference 3). The enclosed report, Flooding Walkdown Report FPL061-PR-001, Rev. 0, was prepared in accordance with the guidance of NEI 12-07 and provides the requested flooding walkdown information.
This submittal completes FPL's response to the Reference 1, Enclosure 4 information request.This letter contains no new Regulatory Commitments and no revision to existing Regulatory Commitments.
If you have any questions or require additional information, please contact Mr. Robert J.Tomonto, Licensing Manager, at (305) 246-7327.I declare under penalty of perjury that the foregoing is true and correct.Executed on November -2 2 2012.V e r y t ul yu r s Michael Kiley Site Vice President Turkey Point Nuclear Plant Enclosure cc: USNRC Regional Administrator, Region II USNRC Project Manager, Turkey Point Nuclear Plant USNRC Senior Resident Inspector, Turkey Point Nuclear Plant