Official Exhibit - ENT000274-00-BD01 - Transmittal Letter for Five Copies of the Updated Final Exercise Report for the Indian Point Energy Center Radiological Emergency Preparedness Plume Pathway Exercises Conducted on December 3, 2008
ML12338A556
Person / Time
Site: Indian Point  Entergy icon.png
Issue date: 06/28/2010
From: Canton L
US Dept of Homeland Security, Federal Emergency Management Agency
To: Gibb J
Atomic Safety and Licensing Board Panel, State of NY, Emergency Management Office
SECY RAS
References
RAS 22117, 50-247-LR, 50-286-LR, ASLBP 07-858-03-LR-BD01
Download: ML12338A556 (1)


Text

United States Nuclear Regulatory Commission Official Hearing Exhibit ENT000274 Submitted: March 29, 2012 In the Matter of:

Entergy Nuclear Operations, Inc. u.s. Department of Homelaud Security (Indian Point Nuclear Generating Units 2 and 3) Region U v"V'-R REGlJ~>- ASLBP #: 07-858-03-LR-BD01 Jacob 1<.. lavits Federal Office Building 26 Federal Plaza, Room 1311

!~~\

Docket #: 05000247 l 05000286

~ 0 Exhibit #: ENT000274-00-BD01 Identified: 10/15/2012 New York, NY 10278-0002

~ it

~I),; FEMA

"'o ~ Admitted: 10/15/2012 Withdrawn:

~'1-1) ~&r;"

IV "

Rejected: Stricken:

.. ,..* .... Other:

( '\10 !;,~\...-

June 28,2010 Mr. John R. Gibb, Director New York State Emergency Management Office 1220 Washington Avenue, Building 22, Suite 101 Al bany_ New York 12226-2251

Dear Mr. Gibb:

Enclosed please fin d five copies of the Updated Final Exercise Report for the Indian Poi nt Energy Center radiological emergency preparedness Plume Pathway Exercise conducted on December 3, 2008. This repoli. dated June 20, 2010, is being re-issued because a number of related out-of-sequence drills and demonstrations were completed in the fall of 2009 and these are now included in the report. The previous report, dated September 18,2009, should be replaced with this version.

The State of New York and local emergency response organizations successfully demonstrated the capabili ties to implement their off-site radiological emergency response plans and procedures, based on 'the evaluatjon ofth is exercise by the Regional Assistanc Committee and a team of Federal evaluators. There w re no deficiencies; nine Areas Requiring Corrective Actio ns were identi fied, 2 of which have been already corrected as noted in the report.

State and local preparedness is adequate to protect the health and safety of the public living in the vicinity of the Indian Point NP S and will provide reasonable assurance that appropriate measures can be taken offsite in the event of a radiological emergency.

If you have any questions regarding this matter, please contact Rebecca Thomson, Chair of the .n Regional Assistance Committee at (2 12) 680-8509.

Sincerely yours,

,~4hrL-Lynn Canton Regional Administrator Enclosures cc: Andrew Feeney, First Deputy Director, SEMO H. K nnedy Bergmann, REP Program, SEMO Kevin Kraus, REP Program, SEMO www.fema.gov *PH: (212)680-3600