NRR-PMDAPEm Resource From: Beltz, Terry Sent: Friday, October 19, 2012 9:21 AM To: Loeffler, Richard A.

Cc: Kissinger, Peter W.; Frankl, Istvan; Grover, Ravinder

Subject:

Monticello Nuclear Generating Plant - Acceptance Review re: License Amendment Request to Adopt TSTF-476, Revision 1 (TAC No. ME9600)

Dear Mr. Loeffler:

By letter dated September 18, 2012 (Agencywide Documents Access and Management System (ADAMS)

Accession No. ML122630063), Northern States Power Company - Minnesota, doing business as Xcel Energy, Inc., submitted a license amendment request (LAR) for the Monticello Nuclear Generating Plant. The LAR proposes to adopt Technical Specifications Task Force (TSTF) Traveler TSTF-476, Revision 1, Improved BPWS [Banked Position Withdrawal Sequence] Control Rod Insertion Process (NEDO-33091).

The purpose of this e-mail is to provide the final results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed change. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

The NRC staff has reviewed your application and concluded that there appears to be sufficient technical information, both in scope and depth, to enable the staff to proceed with its detailed technical review and make an independent assessment regarding the acceptability of the LAR in terms of regulatory requirements and the protection of public health and safety and the environment.

If additional information is needed for the staff to complete its technical review, you will be advised by separate correspondence.

Should you have any questions regarding this review, please contact me at (301) 415-3049.

Sincerely, Terry A. Beltz, Senior Project Manager Plant Licensing Branch III-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation (301) 415-3049 Terry.Beltz@nrc.gov 1

Hearing Identifier: NRR_PMDA Email Number: 512 Mail Envelope Properties (7E9EA9BB82325E46B07B0F04F99B40D87C56031619)

Subject:

Monticello Nuclear Generating Plant - Acceptance Review re: License Amendment Request to Adopt TSTF-476, Revision 1 (TAC No. ME9600)

Sent Date: 10/19/2012 9:21:22 AM Received Date: 10/19/2012 9:21:00 AM From: Beltz, Terry Created By: Terry.Beltz@nrc.gov Recipients:

"Kissinger, Peter W." <Peter.Kissinger@xenuclear.com>

Tracking Status: None "Frankl, Istvan" <Istvan.Frankl@nrc.gov>

Tracking Status: None "Grover, Ravinder" <Ravinder.Grover@nrc.gov>

Tracking Status: None "Loeffler, Richard A." <Richard.Loeffler@xenuclear.com>

Tracking Status: None Post Office: HQCLSTR01.nrc.gov Files Size Date & Time MESSAGE 2024 10/19/2012 9:21:00 AM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:

Recipients Received: