2012 LaSalle County Station Initial License Examination Proposed in Plant JPMs
ML12289A213
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 10/22/2012
From: Mcneil D
NRC/RGN-III/DRS/OLB
To:
Exelon Generation Co
References
Download: ML12289A213 (27)


Text

Exelon Nuclear Job Performance Measure Place a Standby Battery Charger in Service JPM Number: P-DC-02 Revision Number: 02 Date: 08/31/2012 Developed By:

Instructor Date Validated By:

SME or Instructor Date Reviewed By:

Operations Representative Date Approved By:

Training Department Date SRRS: 3D.105 (when utilized for operator initial or continuing training)

P-DC-02 Rev. 02 Page 2 of 8 JOB PERFORMANCE MEASURE VALIDATION CHECKLIST NOTE: All steps of this checklist should be performed upon initial validation.

Prior to JPM usage, revalidate JPM using steps 8 and 12 below.

________ 1. Task description and number, JPM description and number are identified.

________ 2. Knowledge and Abilities (K/A) references are included.

________ 3. Performance location specified. (in-plant, control room, simulator, or other)

________ 4. Initial setup conditions are identified.

________ 5. Initiating cue (and terminating cue if required) are properly identified.

________ 6. Task standards identified and verified by SME review.

________ 7. Critical steps meet the criteria for critical steps and are identified with an asterisk (*).

________ 8. Verify the procedure(s) referenced by this JPM reflects the current revision:

Procedure Rev:

Procedure Rev:

Procedure Rev:

________ 9. Verify cues both verbal and visual are free of conflict.

________ 10. Verify performance time is accurate

________ 11. If the JPM cannot be performed as written with proper responses, then revise the JPM.

________ 12. When JPM is initially validated, sign and date JPM cover page. Subsequent validations, sign and date below:

SME / Instructor Date SME / Instructor Date SME / Instructor Date SRRS: 3D.105 (when utilized for operator initial or continuing training)

P-DC-02 Rev. 02 Page 3 of 8 Revision Record (Summary)

1. Revision 00, New JPM
2. Revision 01, Added Initiating Cue to the Examinees initial conditions. Updated to revision 7 of LOA-DC-201.
3. Revision 02, Updated to current Procedures and Template for ILT 11-1 NRC Exam.

SRRS: 3D.105 (when utilized for operator initial or continuing training)

P-DC-02 Rev. 02 Page 4 of 8 INITIAL CONDITIONS

1. A fire has occurred in the operating Unit 2 Division 2 125 VDC Battery Charger 2BA.
2. The Fire Brigade has extinguished the fire.
3. Battery Charger 2BA has been removed from service.
4. No damage has occurred to MCC-236X-3 or DC Bus 2B[2DC15E].
5. The AC feed to 2BA battery charger is open and removed from service. (236X-3, B5)
6. All C/O for the 2BB Unit 2 Division 2 125 VDC Battery Charger have been lifted.
7. All levels of the Auxiliary Building are open for personnel access.
8. You are an extra NSO.
9. You have a plant radio.

INITIATING CUE The Unit 2 NSO directs you to place the standby Unit 2 Division 2 125 VDC Battery Charger 2BB in service IAW LOA-DC-201 starting at Section B.1 step 17.

Contact the Unit 2 NSO when Battery Charger 2BB float voltage is acceptable.

Fill in the JPM Start Time when the student acknowledges the Initiating Cue.

Information For Evaluators Use:

UNSAT requires written comments on respective step.

  • Denotes CRITICAL steps.

Number any comments in the Comment Number column on the following pages. Then annotate that comment in the Comments section at the bottom of the page. The comment section should be used to document the reason that a step is marked as unsatisfactory and to document unsatisfactory performance relating to management expectations.

Some operations that are performed from outside of the control room may require multiple steps. These items may be listed as individual steps in this JPM. It is acceptable for the candidate to direct the local operator to perform groups of procedure steps instead of calling for each individual item to be performed.

The timeclock starts when the candidate acknowledges the initiating cue.

SRRS: 3D.105 (when utilized for operator initial or continuing training)

P-DC-02 Rev. 02 Page 5 of 8 JPM Start Time:

1 STEP ELEMENT Comment UNSAT (LOA-DC-201) SAT Number NOTE: The procedure states, steps 1 and 2 must be done IN ORDER LISTED.

1. At Battery Charger 2BB, The Examinee verifies the DC ____ ____ ____

(B.1.17) LOCALLY OPEN the DC Output Breaker on Battery Output Breaker. Charger 2BB is open. (off)

CUE: The breaker is in the position you describe.

2. At Battery Charger 2BB, The Examinee verifies the AC ____ ____ ____

(B.1.17) LOCALLY OPEN the AC Input Breaker on Battery Input Breaker. Charger 2BB is open. (off)

CUE: The breaker is in the position you describe.

  • 3. At MCC-236X-3, LOCALLY The Examinee simulates ____ ____ ____

(B.1.18) CLOSE AC Feed Breaker A6 closing the A6 Breaker on for the 2BB Battery Charger. MCC-236X-3.

CUE: The breaker is in the position you describe.

NOTE: The Examinee may verify breaker 2B[2DC15E], 2D (DC Feed Breaker) for Battery Charger 2BA is open. If this occurs, inform the Examinee that breaker 2D is open.

  • 4. At DC Bus 2B[2DC15E], The Examinee simulates ____ ____ ____

(B.1.19) LOCALLY CLOSE DC Feed closing the 2A Breaker on Breaker 2A for the 2BB 2B[2DC15E].

Battery Charger.

CUE: The breaker is in the position you describe.

NOTE: Steps 5, 6, and 7 are performed locally at Battery Charger 2BB and must be done IN ORDER LISTED.

  • 5. CLOSE the AC Input The Examinee simulates ____ ____ ____

(B.1.20) Breaker. closing the AC Input Breaker on Div 2 Charger 2BB CUE: The breaker is in the position you describe.

SRRS: 3D.105 (when utilized for operator initial or continuing training)

P-DC-02 Rev. 02 Page 6 of 8 1

STEP ELEMENT Comment UNSAT (LOA-DC-201) SAT Number

  • 6. DEPRESS the pushbutton The Examinee depresses the ____ ____ ____

(B.1.20) and VERIFY FLOAT light pushbutton and verifies Float-energized. light energized on Div 2 Charger 2BB CUE: The green light is lit.

  • 7. CLOSE DC Output Breaker. The Examinee simulates ____ ____ ____

(B.1.20) closing the DC Output Breaker on Div 2 Charger 2BB CUE: The breaker is in the position you describe.

CUE: Battery Charger Float voltage has been determined acceptable by another EO.

The JPM is complete when the Unit 2 NSO is notified that Battery Charger Float Voltage is acceptable.

JPM Stop Time:

SRRS: 3D.105 (when utilized for operator initial or continuing training)

P-DC-02 Rev. 02 Page 7 of 8 JPM

SUMMARY

Operators Name:

Job

Title:

EO RO SRO FS STA/IA SRO Cert JPM

Title:

Place a Standby Battery Charger in Service JPM Number:P-DC-02 Revision Number: 02 Task Number and

Title:

6.008 Startup or shutdown a battery charger K/A Number and Importance:263000 (DC Electrical Systems) 2.1.30 4.4/4.0 Ability to locate and operate components, including local controls Suggested Testing Environment: In-Plant Alternate Path: Yes No SRO Only: Yes No Time Critical: Yes No Reference(s): LOA-DC-201 Unit 2 DC Power System Failure, Rev 14 Actual Testing Environment: Simulator Control Room In-Plant Other Testing Method: Simulate Perform Estimated Time to Complete: 20 minutes Actual Time Used: minutes EVALUATION

SUMMARY

Were all the Critical Elements performed satisfactorily? Yes No The operators performance was evaluated against standards contained within this JPM and has been determined to be: Satisfactory Unsatisfactory Comments:

Evaluators Name: (Print)

Evaluators Signature: Date:

Page 8 of 8 INITIAL CONDITIONS

1. A fire has occurred in the operating Unit 2 Division 2 125 VDC Battery Charger 2BA.
2. The Fire Brigade has extinguished the fire.
3. Battery Charger 2BA has been removed from service.
4. No damage has occurred to MCC-236X-3 or DC Bus 2B[2DC15E].
5. The AC feed to 2BA battery charger is open and removed from service. (236X-3, B5)
6. All C/O for the 2BB Unit 2 Division 2 125 VDC Battery Charger have been lifted.
7. All levels of the Auxiliary Building are open for personnel access.
8. You are an extra NSO.
9. You have a plant radio.

INITIATING CUE The Unit 2 NSO directs you to place the standby Unit 2 Division 2 125 VDC Battery Charger 2BB in service IAW LOA-DC-201 starting at Section B.1 step 17.

Contact the Unit 2 NSO when Battery Charger 2BB float voltage is acceptable.

Exelon Nuclear Job Performance Measure Local Emergency Start of 1C VP Chiller JPM Number: P-VP-03 Revision Number: 12 Date: 08/31/2012 Developed By:

Instructor Date Validated By:

SME or Instructor Date Reviewed By:

Operations Representative Date Approved By:

Training Department Date SRRS: 3D.105 (when utilized for operator initial or continuing training)

P-VP-03 Rev. 12 Page 2 of 9 JOB PERFORMANCE MEASURE VALIDATION CHECKLIST NOTE: All steps of this checklist should be performed upon initial validation.

Prior to JPM usage, revalidate JPM using steps 8 and 12 below.

________ 1. Task description and number, JPM description and number are identified.

________ 2. Knowledge and Abilities (K/A) references are included.

________ 3. Performance location specified. (in-plant, control room, simulator, or other)

________ 4. Initial setup conditions are identified.

________ 5. Initiating cue (and terminating cue if required) are properly identified.

________ 6. Task standards identified and verified by SME review.

________ 7. Critical steps meet the criteria for critical steps and are identified with an asterisk (*).

________ 8. Verify the procedure(s) referenced by this JPM reflects the current revision:

Procedure Rev:

Procedure Rev:

Procedure Rev:

________ 9. Verify cues both verbal and visual are free of conflict.

________ 10. Verify performance time is accurate

________ 11. If the JPM cannot be performed as written with proper responses, then revise the JPM.

________ 12. When JPM is initially validated, sign and date JPM cover page. Subsequent validations, sign and date below:

SME / Instructor Date SME / Instructor Date SME / Instructor Date SRRS: 3D.105 (when utilized for operator initial or continuing training)

P-VP-03 Rev. 12 Page 3 of 9 Revision Record (Summary)

1. Revision 07, Reformatted and minor editorial changes.
2. Revision 08, Revised task numbers to reflect current task numbers Revised K/A numbers to reflect NUREG 1021 Rev 8 Revised format to meet NTAFT JLOR03 Rev 2 Revised to reflect Rev 6 of LGA-VP-01 Made JPM specific to Unit 1.

Incorporated comments from TR 98-2238

3. Revision 09, Minor corrections. Changed estimated time to complete to 10 minutes based on validation.
4. Revision 10, Changed procedure from LGA-VP-01 to LOP-VP-02. Changed the task based on a new task in the operating matrix. Changed estimate completion time based on year 2000 data.
5. Revision 11, Added the initiating cue to the examinees initial conditions.
6. Revision 12, Updated to current procedures and templates for ILT 11-1 NRC Exam SRRS: 3D.105 (when utilized for operator initial or continuing training)

P-VP-03 Rev. 12 Page 4 of 9 Materials

1. The following material is required to be provided to examinee:
a. One copy of LOP-VP-02 (after demonstrating knowledge of location of controlled copy)
b. One laser pointer SRRS: 3D.105 (when utilized for operator initial or continuing training)

P-VP-03 Rev. 12 Page 5 of 9 INITIAL CONDITIONS

  • You are an extra NSO.
  • Unit scrammed due to high drywell pressure.
  • Drywell temperature is 141°F and increasing at approximately 1°F/minute.
  • LGA-03 has been entered.
  • LGA-VP-01 is in progress and completed up to and including Step C.9.b.
  • 1C (2C) VP Chiller had been running prior to the scram on the 1A (2A) VP loop.
  • The SAT is supplying all AC buses.
  • All support systems are operating as expected.
  • Radiological conditions are at or below normal levels.
  • You have a plant radio.

INITIATING CUE The Unit 1 (2) NSO has directed you to perform an emergency restart 1C (2C) VP Chiller IAW LOP-VP-02.

Inform the Unit NSO when 1C (2C) VP Chiller is restarted.

Fill in the JPM Start Time when the student acknowledges the Initiating Cue.

Information For Evaluators Use:

UNSAT requires written comments on respective step.

  • Denotes CRITICAL steps.

Number any comments in the Comment Number column on the following pages. Then annotate that comment in the Comments section at the bottom of the page. The comment section should be used to document the reason that a step is marked as unsatisfactory and to document unsatisfactory performance relating to management expectations.

Some operations that are performed from outside of the control room may require multiple steps. These items may be listed as individual steps in this JPM. It is acceptable for the candidate to direct the local operator to perform groups of procedure steps instead of calling for each individual item to be performed.

The timeclock starts when the candidate acknowledges the initiating cue.

SRRS: 3D.105 (when utilized for operator initial or continuing training)

P-VP-03 Rev. 12 Page 6 of 9 JPM Start Time:

Comme UNSAT STEP ELEMENT STANDARD (LOP- SAT nt VP-02)

1. Obtain copy of LOP-VP-02 Examinee identifies where ___ ___ ___

copy of LOP-VP-02 can be obtained.

CUE After examinee identifies where copy of LOP-VP-02 can be obtained, provide examinee with copy of LOP-VP-02.

Note The following steps should be performed at 1C (2C) VP Chiller Unit, 1(2)VP01CC at PRIM. CNMT. WATER CHILLER 1VP14S (2VP14S) (U1 AB 786 L-19) (U2 AB 786 L-19).

  • 2. DEPRESS RESET push Examinee depresses the ___ ___ ____

button RESET pushbutton.

(E.2.1)

CUE The button you identified has been depressed.

3. VERIFY no alarms except Examinee verifies that all ___ ___ ____

COMPRESSOR LOW OIL alarms except COMPR. LOW (E.2.1) OIL DIFFRNT'L PRESS. are DIFFERENTIAL PRESSURE alarm. clear.

CUE Alarm lights are all OFF except for COMPR. LOW OIL DIFFRNT'L PRESS.

4. VERIFY Chiller Panel Examinee verifies that the ___ ___ ____

TROUBLE alarm power Chiller Panel Trouble Alarm (E.2.2) power switch in ON.

switch in ON position.

CUE The switch you have identified is in the ON position.

5. Notify the NSO of pending Examinee notifies the Unit 1 ___ ___ ____

(E.2.3) chiller start. (2) NSO of the pending start of 1 (2) VP01CC, C VP Chiller.

CUE As Unit 1 NSO, acknowledge the pending start of 1 (2) VP01CC, C VP Chiller.

  • 6. DEPRESS START Examinee depresses START ___ ___ ____

(E.2.4) pushbutton. pushbutton.

CUE The START pushbutton has been depressed.

SRRS: 3D.105 (when utilized for operator initial or continuing training)

P-VP-03 Rev. 12 Page 7 of 9 Comme UNSAT STEP ELEMENT STANDARD (LOP- SAT nt VP-02)

7. Verify start sequence as COMPR OIL PUMP ON ___ ___ ___

follows: indicating light verified (E.2.5.1) energized Oil pump starts and COMPR OIL PUMP ON indicating light (amber) energized CUE The oil pump started and the COMPR OIL PUMP ON amber indicating light is energized.

8. Verify start sequence as Chiller Compressor Motor 1 ___ ___ ___

follows: (2) VP14C verified running (E.2.5.2)

Chiller Compressor Motor 1 (2) VP14C starts.

CUE The 1 (2) VP14C Compressor Motor Ammeter indication spikes high and then indicates approximately 400 amps.

9. Verify start sequence as COMPR MOTOR ON ___ ___ ___

follows: indicating light verified (E.2.5.2) energized COMPR MOTOR ON indicating light (amber) is energized CUE The COMPR MOTOR ON amber indicating light is energized.

Note If the Examinee takes action to verify operating parameters per LOP-VP-02, inform the examinee that operating parameters are per procedure.

10. NOTIFY the Unit 1 (2) NSO Examinee notifies the Unit 1 ___ ___ ___

that the 1C (2C) VP Chiller (2) NSO that the 1C (2C) VP has been restarted. Chiller has been restarted.

JPM Stop Time:

SRRS: 3D.105 (when utilized for operator initial or continuing training)

P-VP-03 Rev. 12 Page 8 of 9 JPM

SUMMARY

Operators Name:

Job

Title:

EO RO SRO FS STA/IA SRO Cert JPM

Title:

Local start of 1C VP Chiller JPM Number: P-VP-03 Revision Number: 12 Task Number and

Title:

96.006 Given a tripped PCCW chiller, perform an emergency start of that chiller.

K/A Number and Importance: 295028 (High Drywell Temperature) EA1.03 3.9/3.9 Ability to operate and/or monitor the following as they apply to HIGH DRYWELL TEMPERATURE: Drywell Cooling System Suggested Testing Environment: In-Plant Alternate Path: Yes No SRO Only: Yes No Time Critical: Yes No Reference(s): LOP-VP-02 Startup Operation and shutdown of Primary Containment Chilled Water and Ventilation system, Rev 41 Actual Testing Environment: Simulator Control Room In-Plant Other Testing Method: Simulate Perform Estimated Time to Complete: 11 minutes Actual Time Used: minutes EVALUATION

SUMMARY

Were all the Critical Elements performed satisfactorily? Yes No The operators performance was evaluated against standards contained within this JPM and has been determined to be: Satisfactory Unsatisfactory Comments:

Evaluators Name: (Print)

Evaluators Signature: Date:

Page 9 of 9 INITIAL CONDITIONS

  • You are an extra NSO.
  • Unit scrammed due to high drywell pressure.
  • Drywell temperature is 141°F and increasing at approximately 1°F/minute.
  • LGA-03 has been entered.
  • LGA-VP-01 is in progress and completed up to and including Step C.9.b.
  • 1C (2C) VP Chiller had been running prior to the scram on the 1A (2A) VP loop.
  • The SAT is supplying all AC buses.
  • All support systems are operating as expected.
  • Radiological conditions are at or below normal levels.
  • You have a plant radio.

INITIATING CUE The Unit 1 (2) NSO has directed you to perform an emergency restart 1C (2C) VP Chiller IAW LOP-VP-02.

Inform the Unit NSO when 1C (2C) VP Chiller is restarted.

Exelon Nuclear Job Performance Measure Lineup a Fire Hose To 2A TDRFP for Injection Into The RPV JPM Number: P-FP-04 Revision Number: 00 Date: 08/31/2012 Developed By:

Instructor Date Validated By:

SME or Instructor Date Reviewed By:

Operations Representative Date Approved By:

Training Department Date SRRS: 3D.105 (when utilized for operator initial or continuing training)

P-FP-04 Rev. 00 Page 2 of 10 JOB PERFORMANCE MEASURE VALIDATION CHECKLIST NOTE: All steps of this checklist should be performed upon initial validation.

Prior to JPM usage, revalidate JPM using steps 8 and 12 below.

________ 1. Task description and number, JPM description and number are identified.

________ 2. Knowledge and Abilities (K/A) references are included.

________ 3. Performance location specified. (in-plant, control room, simulator, or other)

________ 4. Initial setup conditions are identified.

________ 5. Initiating cue (and terminating cue if required) are properly identified.

________ 6. Task standards identified and verified by SME review.

________ 7. Critical steps meet the criteria for critical steps and are identified with an asterisk (*).

________ 8. Verify the procedure(s) referenced by this JPM reflects the current revision:

Procedure Rev:

Procedure Rev:

Procedure Rev:

________ 9. Verify cues both verbal and visual are free of conflict.

________ 10. Verify performance time is accurate

________ 11. If the JPM cannot be performed as written with proper responses, then revise the JPM.

________ 12. When JPM is initially validated, sign and date JPM cover page. Subsequent validations, sign and date below:

SME / Instructor Date SME / Instructor Date SME / Instructor Date SRRS: 3D.105 (when utilized for operator initial or continuing training)

P-FP-04 Rev. 00 Page 3 of 10 Revision Record (Summary)

1. Revision 00, New JPM based on bank JPM P-FP-03, Rev. 0. Connects FP to the 2A TDRFP rather than the 1A TDRFP. Updated to current template and procedures for ILT 11-1 NRC Exam SRRS: 3D.105 (when utilized for operator initial or continuing training)

P-FP-04 Rev. 00 Page 4 of 10 SETUP INSTRUCTIONS

1. Be prepared to provide a copy of pages 1-7 and 34-40 of LGA-FP-01, Alternate Vessel Injection Using the Fire Protection System.

SRRS: 3D.105 (when utilized for operator initial or continuing training)

P-FP-04 Rev. 00 Page 5 of 10 INITIAL CONDITIONS

1. A reactor scram has occurred on Unit 2 and all rods are full in.
2. There is no injection into the vessel; Diesel Fire Pumps are the only injection source.
3. The Unit 2 NSO is coordinating LGA-FP-01, Diesel Fire Pump Makeup to the Reactor.
4. An Operator has just been assigned to perform the in-plant actions to line up Fire Protection to the MDRFP.
5. The 2B TDRFP is OOS with the pump casing removed.
6. The Unit 2 NSO has verified that all Feedwater System valves are aligned per LGA-FP-01 at control room panels 2PM03J and 2H13-P601.
7. Fire protection header pressure is normal.
8. There is NO fire.
9. The Chemical Feed system is out of service.
10. You have a plant radio.

INITIATING CUE The Unit 2 NSO directs you to connect the Fire Protection System to the 2A TDRFP IAW LGA-FP-01 Attachment 2A.

Inform the Unit 2 NSO when the alignment is complete.

Fill in the JPM Start Time when the student acknowledges the Initiating Cue.

Information For Evaluators Use:

UNSAT requires written comments on respective step.

  • Denotes CRITICAL step.

Tell examinee he may assume all second verifications and associated paperwork is simulated complete as necessary.

Number any comments in the Comment Number column on the following pages. Then annotate that comment in the Comments section at the bottom of page. The comment section should be used to document the reason that a step is marked as unsatisfactory and to document unsatisfactory performance relating to management expectations.

Some operations that are performed from outside of the control room may require multiple steps. These items may be listed as individual steps in this JPM. It is acceptable for the candidate to direct the local operator to perform groups of procedure steps instead of calling for each individual item to be performed.

The timeclock starts when the candidate acknowledges the initiating cue.

SRRS: 3D.105 (when utilized for operator initial or continuing training)

P-FP-04 Rev. 00 Page 6 of 10 JPM Start Time:

STEP ELEMENT STANDARD Comment (LGA-FP-01 SAT UNSAT Attachment Number 2A)

1. Obtain a copy of LGA-FP-01 Examinee simulates obtaining ____ ____ ____

and an LGA Support Locker procedure and LGA Support Key Locker Key CUE: Provide examinee with the prepared copy of LGA-FP-01 when he/she describes/demonstrates where to get procedure and Support Locker Key.

NOTE: The Evaluator will act as Safety Person as required.

2. Obtain equipment from the Examinee simulates obtaining ____ ____ ____

Main LGA Support Locker equipment from LGA Support Locker (Unit 2 LGA FP-01 Equipment Bag)

CUE: You have obtained the equipment you identified.

3. OBTAIN equipment from Examinee simulates obtaining ____ ____ ____

Local LGA Support Locker equipment from Local LGA Support Locker CUE: You have obtained the equipment you identified.

  • 4. Remove fire hose from Hose Examinee simulates removing ____ ____ ____

(1st Line) Station FB451 and install a fire hose from Hose Station wye connector FB451 and installing a wye connector CUE: The fire hose and wye connector are positioned as you describe.

  • 5. Connect fire station fire hose Examinee simulates connecting nd (2 Line) to one end of wye and run it fire station fire hose to one end into 2A TDRFP Room of wye and running it into 2A TDRFP Room CUE: The fire hose and wye connector are positioned as you describe.

NOTE: The next step of LGA-FP-01 Attachment 2A is N/A because it performs the same action on the 2B TDRFP, which is out of service per initiating cue.

  • 6. (In 2A TDRFP Room) Examinee simulates installing (4th Line) Install wye connector at end wye connector at end of fire of fire hose hose SRRS: 3D.105 (when utilized for operator initial or continuing training)

P-FP-04 Rev. 00 Page 7 of 10 STEP ELEMENT STANDARD Comment (LGA-FP-01 SAT UNSAT Attachment Number 2A)

  • 7. Connect fire hoses to the Examinee simulates connecting (5th Line) two ends of this wye fire hoses to the two ends of connector. this wye connector CUE: The Fire hose is connected as you describe
  • 8. Install FP to 1" converter Examinee simulates installing (6th Line) on 2FW041A/42A, 2A FP to 1" converter on TDRFP Dsch Line 2FW041A/42A Upstrm/Dwnstr Lo Point Drain CUE: The converter is installed as you described.
  • 9. Connect one fire hose to 1" Examinee simulates connecting (7th Line) converter one fire hose to 1" converter CUE: The Fire hose is connected as you describe
  • 10. Install FP to 3/4" converter Examinee simulates installing (8th Line) on 2CB022C, A TDRFP FP to 3/4" converter on Suct Lo Point Drain Valve 2CB022C CUE: The converter is installed as you described.
  • 11. Connect other fire hose to Examinee simulates connecting (9th Line) 3/4" converter other fire hose to 3/4" converter CUE: The Fire hose is connected as you describe
12. Notify Unit 2 NSO that The Examinee simulates ____ ____ ____

alignment of FP to 2A notifying the Unit 2 NSO that TDRFP is complete alignment of FP to 2A TDRFP is complete CUE: As the Unit 2 NSO, acknowledge the report that FP is aligned to the 2A TDRFP.

13. Complete all required The Examinee completes or signatures, dates, and simulates completing all times on Attachment 2A required signatures, dates, and times on Attachment 2A TERMINATING CUE The JPM is complete when the Unit 2 NSO is notified.

JPM Stop Time:

SRRS: 3D.105 (when utilized for operator initial or continuing training)

P-FP-04 Rev. 00 Page 8 of 10 JPM

SUMMARY

Operators Name:

Job

Title:

EO RO SRO FS STA/IA SRO Cert JPM

Title:

Lineup a Fire Hose to 2A TDRFP for Injection into the RPV JPM Number: P-FP-04 Revision Number: 00 Task Number and

Title:

414.020 Evaluate plant conditions and control RPV water level using FP K/A Number and Importance:295031 (Reactor Low Water Level) EA1.08 3.8/3.9 Ability to operate and/or monitor the following as they apply to REACTOR LOW WATER LEVEL: Alternate Injection Systems Suggested Testing Environment: In-Plant Alternate Path: Yes No SRO Only: Yes No Time Critical: Yes No Reference(s): LGA-FP-01 Alternate Vessel Injection Using the Fire Protection System, Rev 15 Actual Testing Environment: Simulator Control Room In-Plant Other Testing Method: Simulate Perform Estimated Time to Complete: 10 minutes Actual Time Used: minutes EVALUATION

SUMMARY

Were all the Critical Elements performed satisfactorily? Yes No The operators performance was evaluated against standards contained within this JPM and has been determined to be: Satisfactory Unsatisfactory Comments:

Evaluators Name: (Print)

Evaluators Signature: Date:

Page 9 of 10 KEY

Page 10 of 10 INITIAL CONDITIONS

1. A reactor scram has occurred on Unit 2 and all rods are full in.
2. There is no injection into the vessel; Diesel Fire Pumps are the only injection source.
3. The Unit 2 NSO is coordinating LGA-FP-01, Diesel Fire Pump Makeup to the Reactor.
4. An Operator has just been assigned to perform the in-plant actions to line up Fire Protection to the MDRFP.
5. The 2B TDRFP is OOS with the pump casing removed.
6. The Unit 2 NSO has verified that all Feedwater System valves are aligned per LGA-FP-01 at control room panels 2PM03J and 2H13-P601.
7. Fire protection header pressure is normal.
8. There is NO fire.
9. The Chemical Feed system is out of service.
10. You have a plant radio.

INITIATING CUE The Unit 2 NSO directs you to connect the Fire Protection System to the 2A TDRFP IAW LGA-FP-01 Attachment 2A.

Inform the Unit 2 NSO when the alignment is complete.