ML12286A045

From kanterella
Jump to navigation Jump to search

Acceptance Review Email, License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement 3.8.1.10 to Increase Voltage Limit for Diesel Generator Load Rejection Test
ML12286A045
Person / Time
Site: Wolf Creek Wolf Creek Nuclear Operating Corporation icon.png
Issue date: 10/11/2012
From: Brian Benney
Plant Licensing Branch IV
To: Wideman S
Wolf Creek
Benney B
References
TAC ME9603
Download: ML12286A045 (1)


Text

From:

Benney, Brian To:

"Wideman Steve G" Cc:

Burkhardt, Janet; Chen, Qiao-Lynn

Subject:

ME9603 Acceptance for review Date:

Thursday, October 11, 2012 4:12:20 PM

Dear Mr. Wideman:

By letter dated September 19, 2012, (Agencywide Documents Access and Management System Accession No. ML12272A279), the Wolf Creek Nuclear Operating Corporation submitted a license amendment request (LAR) for the Wolf Creek Generating Station. The LAR includes a proposed change to increase the voltage limit for the emergency diesel generator (DG) full load rejection test specified by Technical Specification (TS) 3.8.1, "AC Sources - Operating," Surveillance Requirement (SR) 3.8.1.10.

The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.

If you have any questions, please contact me at (301) 415-2767.

Sincerely,

Brian Benney, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation