1 WBN2Public Resource From:
Boyd, Desiree L [dlboyd@tva.gov]
Sent:
Thursday, July 19, 2012 3:37 PM To:
Epperson, Dan; Wilson, George; Poole, Justin; Milano, Patrick Cc:
Arent, Gordon; Hamill, Carol L; Boyd, Desiree L
Subject:
TVA letter to NRC_07-19-2012_OMA 732 Commitment Update Attachments:
07-19-2012_OMA 732 Commitment Update_Final.pdf Please see attached TVA letter that was sent to the NRC today.
Thank You,
~*~*~*~*~*~*~*~*~*~*~
Désireé L. Boyd WBN Unit 2 Licensing dlboyd@tva.gov 423-365-8764
Hearing Identifier:
Watts_Bar_2_Operating_LA_Public Email Number:
720 Mail Envelope Properties (7AB41F650F76BD44B5BCAB7C0CCABFAF2F802054)
Subject:
TVA letter to NRC_07-19-2012_OMA 732 Commitment Update Sent Date:
7/19/2012 3:36:30 PM Received Date:
7/19/2012 3:39:58 PM From:
Boyd, Desiree L Created By:
dlboyd@tva.gov Recipients:
"Arent, Gordon" <garent@tva.gov>
Tracking Status: None "Hamill, Carol L" <clhamill@tva.gov>
Tracking Status: None "Boyd, Desiree L" <dlboyd@tva.gov>
Tracking Status: None "Epperson, Dan" <Dan.Epperson@nrc.gov>
Tracking Status: None "Wilson, George" <George.Wilson@nrc.gov>
Tracking Status: None "Poole, Justin" <Justin.Poole@nrc.gov>
Tracking Status: None "Milano, Patrick" <Patrick.Milano@nrc.gov>
Tracking Status: None Post Office:
TVANUCXVS2.main.tva.gov Files Size Date & Time MESSAGE 269 7/19/2012 3:39:58 PM 07-19-2012_OMA 732 Commitment Update_Final.pdf 84148 Options Priority:
Standard Return Notification:
No Reply Requested:
Yes Sensitivity:
Normal Expiration Date:
Recipients Received:
Tennessee Valley Authority, Post Office Box 2000, Spring City, Tennessee 37381-2000 July 19, 2012 10 CFR 50.4 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Watts Bar Nuclear Plant, Unit 2 NRC Docket No. 50-391
Subject:
WATTS BAR NUCLEAR PLANT (WBN) UNIT 2 - RESOLUTION OF CONCERNS WITH FIRE PROTECTION REPORT OPERATOR MANUAL ACTION (OMA) 732 - COMMITMENT SCHEDULE UPDATE (TAC NO. ME3091)
Reference:
TVA letter to NRC dated June 27, 2012, Resolution of Concerns with Fire Protection Report (FPR) Operator Manual Action (OMA) 732 and Response to Requests for Additional Information (TAC No. ME3091)
The purpose of this letter is to update the schedule for the following commitment regarding Operator Manual Action (OMA) 732 that was made in the referenced TVA letter:
The problems impacting OMA 732 are being addressed under Problem Evaluation Report 558202 in TVAs Corrective Action Program. Once the required corrective actions are implemented, the Fire Protection Report (FPR) will be revised accordingly and an update to the report will be submitted to NRC by July 26, 2012.
As discussed on July 19, 2012, between Justin Poole, NRC Senior Project Manager, and Gordon Arent, Senior Manager Licensing, an additional error in the analysis that supports the application of OMA 732 in the WBN two-unit Fire Protection Report (FPR) was recently identified. As a result, the July 26, 2012, schedule for the submittal of an update to the FPR is being adjusted to September 13, 2012. The analysis error has been captured in TVAs Corrective Action Program as Service Request 580935.
U.S. Nuclear Regulatory Commission Page 3 July 19, 2012 bcc : George Wilson U.S. Nuclear Regulatory Commission MS 8 B1A One White Flint North 11555 Rockville Pike Rockville, Maryland 20852-2738 Fred Brown, Deputy Regional Administrator for Construction U. S. Nuclear Regulatory Commission Region II Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257