ML12200A255

From kanterella
Jump to navigation Jump to search
FOIA/PA-2012-0121 - Resp 1 - Partial
ML12200A255
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 06/12/2012
From: Sealing D
NRC/OIS/IRSD/RFSB
To: Kamps K
Beyond Nuclear
References
FOIA/PA-2012-0121
Download: ML12200A255 (7)


Text

NRC FORM 464 Part I U.S. NUCLEAR REGULATORY COMMISSION FOIA/PA RESPONSE NUMBER (4-2011) 2012-0121 1

RESPONSE TO FREEDOM OF INFORMATION ACT (FOIA) / PRIVACY

RESPONSE

ACT (PA) REQUEST TYPE 1

FINAL Z

PARTIAL REQUESTER DATE Kevin Kamps I

I PART I. -- INFORMATION RELEASED D

No additional agency records subject to the request have been located.

LJ 5D Requested records are available through another public distribution program. See Comments section.

APPENDICES Agency records subject to the request that are identified in the listed appendices are already available for A

public inspection and copying at the NRC Public Document Room.

APPENDICES-Agency records subject to the request that are identified in the listed appendices are being made available L

9 public inspection and copying at the NRC Public Document Room.

Enclosed is information on how you may obtain access to and the charges for copying records located at the NRC Public Document Room, 11555 Rockville Pike, Rockville, MD 20852-2738.

for APPENDICES 2/1

.N~

Agency records subject to the request are enclosed.

ED Records subject to the request that contain information originated by or of interest to another Federal agency have been referred to that agency (see comments section) for a disclosure determination and direct response to you.

We are continuing to process your request.

D See Comments.

PART L.A -- FEES AMOUNT*

D You will be billed by NRC for the amount listed.

F None. Minimum fee threshold not met.

]

D You will receive a refund' for the amount listed.

Dl Fees waived.

See comments for details PART I.B -- INFORMATION NOT LOCATED OR WITHHELD FROM DISCLOSURE D-No agency records subject to the request have been located.

D Certain information in the requested records is being withheld from disclosure pursuant to the exemptions described in and for the reasons stated in Part 11.

D This determination may be appealed within 30 days by writing to the FOIA/PA Officer, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001. Clearly state on the envelope and in the letter that it is a "FOIA/PA Appeal."

PART I.C COMMENTS (Use attached Comments continuation page if required)

The incoming request is in ADAMS at ML12032A047.

iAR N

T AND PRIVACY ACT OFFICER NRC FORM 464 Part 1 (4-2011)

FOIA/PA-2012-0121 APPENDIX A RECORDS ALREADY PUBLICLY AVAILABLE ACCESSION NUMBER NO.

DATE DESCRIPTION/ (PAGE COUNT)

1.

10/12/11 ML11294A349

2.

10/14/11 ML11292A005

3.

11/21/11 ML11332A094

4.

11/23/11 ML11329A085

5.

11/30/11 ML11356A037

6.

12/02/11 ML113360416 Email from S. CuadradoDeJesus, NRR to S. Dorts, First Energy on Davis-Besse Commitment List through LRA Amendment 19. (60 pages)

Letter from Sen. Markey to Chairman Jaczko on Safe Operation of Davis-Besse. (4 pages)

Letter from Rep. D. Kucinich to Chairman Jaczko on Cracks in the Concrete Wall of the Shield Building of the Davis-Besse Power Plant. (7 pages)

Letter from C. Pederson, Rill to D. Lochbaum regarding questions about the Shield Building Design at Davis-Besse. (2 pages)

Email from S. CuadradoDeJesus, NRR to R. Plasse, Rill on Davis-Besse Request for Additional Information Response. (775 pages)

Notice of Public Meeting with First Energy Nuclear Operating Company. (3 pages)

Letter from C. Pederson, Rill to B. Allen, First Energy Nuclear Operating on Confirmatory Action Letter. (5 pages)

Davis-Besse Shield Building Crack Root Cause Investigation. (2 pages)

Meeting Notice with Davis-Besse to Discuss Present the Results of its Evaluation of Shield Building Cracking. (4 pages)

Davis-Besse Public Meeting Slides. (24 pages)

Davis-Besse Public Meeting Slides ( 41 pages)

Motion for Admission of Contention No. 5 on Shield Building Cracking, filed by Intervenors. (61 pages)

Email from S. CuadradoDeJesus, NRR to S. Dorts, FirstEnergy forwarding a copy of the Confirmatory Action Letter. (7 pages) 7.

12/02/11 ML11336A355

8.

12/12/11 ML11348A043

9.

12/22/11 ML113560164

10.

01/04/12 ML12004AO10

11.

01/05/12 ML120050146

12.

01/10/12 ML12010A172

13.

01/10/12 ML12019A376

FOIA/PA-2012-0121

14.

01/10/12 ML12019A378 Email from S. CuadradoDeJesus, NRR to C. Custer, First Energy Corp on Davis-Besse 5 Open Items. (7 pages)

15.

01/13/12 ML12018A338 Letter from B. Allen, FirstEnergy Replying to Request for Additional Information for the Review of the License Renewal Application. (10 pages).

APPENDIX B RECORDS BEING RELEASED IN THEIR ENTIRETY (If copyrighted identify with *)

DESCRIPTION/ (PAGE COUNT)

NO.

DATE

1.

undated

2.

10/14/11

3.

10/18/11

4.

10/18/11

5.

10/19/11

6.

10/20/11

7.

10/21/11

8.

10/28/11

9.

11/04/11

10.

11/07/11

11.

11/08/11

12.

11/09/11

13.

11/09/11

14.

11/10/11 Davis-Besse Nuclear Power Plant, Unit Licensing Basis Seismic Ground Motion Concern. (3 pages)

Email from P. Hernandez, NRR to J. Zimmerman, NRR RE: 2011-10-13, POP - Davis-Besse Containment Shield Building. (1 page)

Email from J. Zimmerman, NRR to P. Hernandez, NRR Re: FYI - Davis Besse Shield Building issue update. (1 page)

Email from S. CuardadoDeJesus, NRR to R. Auluck, NRR et al. on Davis-Besse Shield Building Issue Summary. (2 pages)

Email from T. Lupold, NRR to A. Rezai, NRR RE: Davis Besse Shield Building Call. (1 page)

Email from P. Hernandez, NRR to J. Zimmerman, NRR RE: GT. (1 page)

Email from P. Hernandez, NRR to E. Thomas, NRR on Davis Besse Shield Building Issue. (1 page)

Email from P. Hernandez, NRR to R. Auluck, NRR et al., on Davis Besse SB Dist Group. (3 pages)

Email from P. Hernandez, NRR to E. Sanchez Santiago, Rill on Questions about Davis Besse Shield Building Report from DORL.

(2 pages)

Davis Besse Shield Building Issue NRC Technical Reviewer Focus Questions. (1 page)

Email from P. Hernandez, NRR to R. Auluck, NRR on Davis Besse questions for licensee. (1 page)

Email from J. Zimmerman, NRR to P. Hernandez, NRR Query: Letter from UCS. (1 page) (Enclosure is public in ADAMS at ML11327A126)

Email from P. Hernandez, NRR to R. Auluck, NRR et al. Re: Davis Besse Shield Building teleconference. (1 page)

Email from T. Lupold, NRR to A. Rezai, NRR RE: Davis Besse SB extent of condition. (1 page)

FOIA/PA-2012-0121.

15.

11/11/11 Email from J. Zimmerman, NRR to M. Evans, NRR re: DB shield building. (1 page)

16.

11/12/11 Discussion points relayed to-the licensee after our internal technical discussion -(1 page)

17.

11/14/11 Email from W. Jessup, NRR to M. Murphy, NRR on November 13, 2011 Davis-Besse External Call. (1 page)

18.

11/15/11 Email from P. Hernandez, NRR to J. Zimmerman, NRR on Draft email.

(1 page)

19.

11/15/11 Email from P. Hernandez, NRR to M. Evans, NRR et al. RE: Updated Davis-Besse Containment Shield Building POP. (1 page)

20.

11/15/11 Email from P. Hernandez, NRR to M. Evans, NRR et al. on Davis Besse Call Summary. (1 page)

21.

11/16/11 Email from P. Hernandez, NRR to R. Auluck, NRR et al., on Davis Besse conf call. (1 page),

22.

11/17/11 Email from P. Hernandez, NRR to E. Sanchez Santiago, Rill on Davis Besse Operability question. (1 page)

23.

11/17/11 Davis-Besse Containment System Primary Steel Containment an Shield Building. (1 page)

24.

11/17/11 Email from P. Hernandez, NRR to M. Evans, NRR et al., on Davis Besse Operability question. (2 pages)

25.

11/21/11 Davis-Besse Nuclear Power Station Containment Shield Building Issue.

(8 pages)

26.

11/22/11 Email from A. Sheikh, NRR to E. Sanchez Santiago, RilI on Questions for the Conference Call. (1 page)

27.

11/23/11 Email from A. Howe, NRR to S. West, Rill et al. on Where do we stand on Davis Besse? (1 page)

28.

11/23/11 Email from A. Howe, NRR to M. Evans, NRR et al., on Call with Steve West on Davis Besse. (1 page)

29.

11/23/11 Email from J. Zimmerman, NRR to D. Hills, Rill on NSLAOrdersCommPlan.wpd. (5 pages)

30.

11/27/11 Email from J. Zimmerman, NRR to M. Evans, NRR Re: Davis-Besse Draft CAL. (2 pages)

31.

11/28/11 Email from B. Lehman, NRR to S. CuadradoDeJesus, NRR RE: Shield building discussion with Melanie next week. (1 page)

FOIA/PA-2012-0121

32.

12/01/11

33.

12/01/11

34.

12/01/11

35.

12/02/11

36.

12/02/11

37.

12/03/11

38.

12/05/11

39.

12/05/11

40.

12/06/11

41.

12/06/11

42.

12/08/11

43.

12/13/11

44.

12/13/11

45.

12/13/11

46.

12/14/11

47.

12/14/11 Email from R. Haskell, NRR on New OpE Forum Possting: Davis Besse

- Cracks Discovered in Shield Building During Reactor Vessel Head Replacement. (1 page)

Email from B. Lehman, NRR to A. Sheikh, NRR et al., on Davis-Besse Shield Building. (1 page)

Email from D. Morey, NRR to S. CuadradoDeJesus, NRR Re: Davis-Besse Shield Building. (1 page)

Email from D. Morey, NRR to B. Lehman, NRR et al RE: Davis-Besse Shield Building. (1 page)

Email from B. Lehman, NRR to S. Sakai, NRR et al. FW: Davis Besse POP. (2 pages)

Email from J. Zimmerman, NRR to M. Evans, NRR et al. Fw: Press Release has been issued. Attachment is publicly available at (3 pages)

Email from V. Mitlyng, Rill to T. Briley, Rill et al. on Davis-Besse coverage. (3 pages)

Email from B. Lehman, NRR to S. Sakai, NRR et al., on Davis-Besse Shield Building Brief-Lehman.pptx. (1 page)

Email from B. Lehman, NRR to S. CuadradoDeJesus, NRR on Shield Building RAI. (1 page)

Presentation Slides on Davis-Besse Shield Building Crack. (6 pages)

Email from M. Murphy, NRR to W. Jessup, NRR et al., FW: ET Significant Topic: Containment Delamination. (2 pages)

Email from M. Murphy, NRR to C. Roquecruz, NRR RE: G20110823 -

Cracks in the Concrete Wall of the Shield Building of the Davis-Besse Power Plant. (1 page)

Email from M. Galloway, NRR to A. Sheikh, NRR et al., RE: Davis-Besse Shield Building. (1 page)

Email from A. Sheikh, NRR to B. Lehman, NRR et al RE: Davis-Besse Shield Building RAI. (2 pages)

Email from P. Hernandez, NRR to E.Sanchez Santiago, Rill et al., FW:

ET/LT Brief 12-22 Containment Delamination Davis-Besse/ CR-3.

(1 page)

Email from R. Auluck, NRR to S CuadradoDeJesus, NRR et al., on DB Containment Crack RAI Abdul-RA. (2 pages)

FOIA/PA-2012-0121

48.

12/15/11

49.

12/22/11

50.

01/12/12

51.

01/19/12

52.

01/19/12

53.

01/26/12 Email from P. Hernandez, NRR to A. Erickson, NRR, FW: ET/LT Brief 12-22 Containment Delamination Davis-Besse/ CR-3. (5 pages)

Presentation Slides on Shield Building /Containment Delamination.

(11 pages)

Email from D. Morey, NRR to M. Galloway, NRR et al., FW: Summary of meeting with OGC to dicuss Davis Besse-s new contention on the shield building crack. (2 pages)

Davis-Besse Root Cause Review - Status Call 1/19/2012. (3 pages)

Email from P. Hiland, NRR to M. Murphy, NRR RE: Without the Root Cause. (1 page)

Davis-Besse Root Cause Review - Status Call 1-26-2012. (3 pages)