P.O. Box 63 CENGSM Lycoming, New York 13093 a joint venture of 0 ostllation eD NINE MILE POINT NUCLEAR STATION June 22, 2012 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 ATTENTION:

Document Control Desk

SUBJECT:

Nine Mile Point Nuclear Station Unit Nos. 1 & 2; Docket Nos. 50-220 & 50-410 Changes to the Nine Mile Point Nuclear Station Physical Security, Safeguards Contingency, and Security Training and Qualification Plan - Response to NRC Request for Additional Information

REFERENCE:

(1) Letter from A. Verno (NMPNS) to Document Control Desk (NRC), dated May 17, 2012, Changes to the Nine Mile Point Nuclear Station Physical Security, Safeguards Contingency, and Security Training and Qualification Plan By letter dated May 17, 2012 (Reference 1), Nine Mile Point Nuclear Station, LLC (NMPNS) submitted changed pages for Issue 7, Revision 3, of the Nine Mile Point Nuclear Station Physical Security, Safeguards Contingency, and Security Training and Qualification Plan (the Plan). In a subsequent email from the NRC to NMPNS dated June 11, 2012, the NRC requested additional information (RAI) regarding Section 15.3 of the Plan, which describes intrusion detection system (IDS) equipment that NMPNS may employ. This RAI was discussed in a telephone conference between NRC and NMPNS staff members on June 12, 2012. At the conclusion of the telephone conference, NMPNS agreed to address the RAI by revising Section 15.3 of the Plan to list only the IDS equipment that is actually employed, and to submit this Plan revision to the NRC by August 3, 2012. This regulatory commitment is listed in the Attachment to this letter.

Should you have any questions regarding the information in this submittal, please contact John J. Dosa, Director Licensing, at (315) 349-5219.

Very truly yours, Anthony Verno Director Security

Document Control Desk June 22, 2012 Page 2

Attachment:

List of Regulatory Commitments AV/MHS cc:

Regional Administrator, Region I, NRC Project Manager, NRC Resident Inspector, NRC

.f ATTACHMENT LIST OF REGULATORY COMMITMENTS The following table identifies the regulatory commitments in this document. Any other statements in this submittal represent intended or planned actions. They are provided for information purposes and are not considered to be regulatory commitments.

REGULATORY COMMITMENT DUE DATE NMPNS will revise Section 15.3 of the Nine Mile Point Nuclear August 3, 2012 Station Physical Security, Safeguards Contingency, and Security Training and Qualification Plan to list only the intrusion detection system (IDS) equipment that is actually employed, and will submit this Plan revision to the NRC.