ML12181A221
| ML12181A221 | |
| Person / Time | |
|---|---|
| Site: | Watts Bar |
| Issue date: | 06/28/2012 |
| From: | - No Known Affiliation |
| To: | Division of Operating Reactor Licensing |
| References | |
| Download: ML12181A221 (7) | |
Text
1 WBN2Public Resource From:
Boyd, Desiree L [dlboyd@tva.gov]
Sent:
Thursday, June 28, 2012 8:19 AM To:
Poole, Justin; Arent, Gordon; Bryan, Robert H Jr Cc:
Boyd, Desiree L; Templeton, Pamela J
Subject:
2012-06-28 - WBN Project Plan - Unit 2.pdf Attachments:
2012-06-28 - WBN Project Plan - Unit 2.pdf Please see attached for 9:00 phone call.
~*~*~*~*~*~*~*~*~*~*~
Désireé L. Boyd WBN Unit 2 Licensing dlboyd@tva.gov 423-365-8764
Hearing Identifier:
Watts_Bar_2_Operating_LA_Public Email Number:
711 Mail Envelope Properties (7AB41F650F76BD44B5BCAB7C0CCABFAF2E9ADAE8)
Subject:
2012-06-28 - WBN Project Plan - Unit 2.pdf Sent Date:
6/28/2012 8:18:44 AM Received Date:
6/28/2012 8:18:47 AM From:
Boyd, Desiree L Created By:
dlboyd@tva.gov Recipients:
"Boyd, Desiree L" <dlboyd@tva.gov>
Tracking Status: None "Templeton, Pamela J" <pjtempleton@tva.gov>
Tracking Status: None "Poole, Justin" <Justin.Poole@nrc.gov>
Tracking Status: None "Arent, Gordon" <garent@tva.gov>
Tracking Status: None "Bryan, Robert H Jr" <rhbryan@tva.gov>
Tracking Status: None Post Office:
TVANUCXVS2.main.tva.gov Files Size Date & Time MESSAGE 228 6/28/2012 8:18:47 AM 2012-06-28 - WBN Project Plan - Unit 2.pdf 197366 Options Priority:
Standard Return Notification:
No Reply Requested:
Yes Sensitivity:
Normal Expiration Date:
Recipients Received:
WBN UNIT 2 PROJECT PLAN: 06/28/2012 Page 2 SOURCE: POD UPDATES, COMMITMENTS I.
SUBMITTAL LOOK-AHEAD Item No.
Description Resp. Person Due Date License Amendments / Technical Specifications
- 1.
Common Service Station Transformer (CSST) A & B Credit Shea October 12, 2012
- 2.
U1 Hydrology LAR Shea July 31, 2012
- 3.
U2 Hydrology FSAR & TS Update Stockton August 16, 2012
- 4.
SSER Open Item 32: Revise Diesel Generator Frequency Allowable Value.
Hilmes January 13, 2013 SSER Appendix HH Open Items (requiring submittal)
- 1.
SSER Open Items 5 & 8:
Provide updated core map.
Westinghouse/Koontz September 21, 2012
- 2.
SSER Open Item 13:
Submit an ASME Section XI Inservice Test Program for the first ten year interval six months before receiving an Operating License. [Commitment NCO080008033:
Item 017 of Enclosure 2 of letter T90 080128 001]
McDonald/Crouch March 2014
- 3.
SSER Open Item 25:
Submit documentation of liability insurance coverage pursuant to 10 CFR 140.11(a)(4).
Arent June 2014
- 4.
SSER Open Item 37:
Submit changes to the Emergency Plan (REP) prior to fuel load.
[Commitment 111032952]
Detchemendy June 2014
- 5.
SSER Open Item 41:
Update Plant design displays & dose assessment models to provide two unit capability.
Hilmes/Koontz December 2013
WBN UNIT 2 PROJECT PLAN: 06/28/2012 Page 3 SOURCE: POD UPDATES, COMMITMENTS Item No.
Description Resp. Person Due Date
- 6.
SSER Open Item 61:
Fuel Thermal Conductivity Degradation Model (PAD Code) - Note: currently this is a License Condition - tracking PWROG activity to update code Koontz October 26, 2012
- 7.
SSER Open Item 70:
Submit Pre-Service Inspection program update.
McDonald/Crouch September 28, 2012
- 8.
SSER Open Item 77/81:
Provide Electronic Filter Test Results for General Atomic High Range Rad Monitor.
Hilmes August 31, 2012
- 9.
SSER Open Item 83:
Provide Letter verifying completion of data storm test on DCS.
Hilmes January 2015
- 10.
SSER Open Item 115:
Requires phone call with NRR Staff to determine remaining actions Arent TBD
- 11.
SSER Open Item 117:
Provide calculational basis for access to vital areas - mission dose and update FSAR.
(Amendment 109) [Commitment 112046729]
Koontz/Arent August 16, 2012
- 12.
SSER Open Item 132:
Submit letter documenting that plant modifications to add high VCT level alarm to main control room annunciator system have been completed. [Commitment 113111704]
Submit letter documenting that procedure changes associated with limiting the number of operating primary water pumps and isolating potential boron dilution paths have been made. [Commitment 113111704]
Arent/Wallace May 24, 2013
- 13.
SSER Open Item 134:
Provide resolution of dam stability analysis for Cherokee and Douglas Dams finite element analysis.
Ray August 31, 2012
WBN UNIT 2 PROJECT PLAN: 06/28/2012 Page 4 SOURCE: POD UPDATES, COMMITMENTS Item No.
Description Resp. Person Due Date
- 14.
SSER Open Item 138:
Following update of ODCM, update annual Chi/Q values in the FSAR. (Amendment 109)
NRC to verify that the ODCM average annual X/Q & D/Q Valves have been updated to match the FSAR.
Bryan August 16, 2012
- 15.
SSER Open Item 139:
Include cost benefit analysis in next update to FSAR. (Amend 109)
Bryan August 16, 2012
- 16.
Submit a Technical Specification and Bases change package to TVA Licensing to change Table 3.3.3-1, Line item 6 (Reactor Vessel Water Level) to remove the reference to note (g) and bases to show RVLIS as a Type A variable.
Need calculation WBNO4SG4047 revised.
PER 488815 [Commitment 113307292]
Crouch/Hilmes/Clark August 16, 2012
- 17.
Submit a FSAR Change Package to TVA Licensing to Amendment 108, Table 7.5-2, Regulatory Guide 1.97 Post Accident Monitoring Variables Lists, will be updated to show RVLIS as a Type A variable.
Need calculation WBNO4SG4047 revised.
PER 488815 [Commitment 113307350]
Crouch/Hilmes/Clark August 16, 2012
WBN UNIT 2 PROJECT PLAN: 06/28/2012 Page 5 SOURCE: POD UPDATES, COMMITMENTS Item No.
Description Resp. Person Due Date Other Submittals
- 1.
As-Constructed Fire Protection Report [Commitment 113461862]
Hilmes July 2014
- 2.
U2 FSAR With As-Constructed Figures [Commitment 112068531]
Arent July 2014
- 3.
Prior to fuel load, a final report will be submitted following certain validation activities as described in the IPEEE Design Report (Enclosure 1). [Commitment 111027893]
Koontz/Enis July 2014
- 4.
TVA will provide the NRC staff an updated [security] classification scheme that reflects these changes for WBN Unit 2. [Commitment 111033038: RAI Response 3.r of. of Letter T02 100427 001]
Reynolds May 2014
- 5.
Submit a merged U2 FSAR / U1 UFSAR [Commitment 111360889]
Licensing April 2016
- 6.
10 CFR Part 70 License Extension Bryan August 15, 2012
- 7.
2 Unit ODCM Woods/Shea September 14, 2012
- 8.
As-Constructed PRA Guey/Koontz October 2014
- 9.
TMI Commitment Review Letter Licensing January 2014
- 10.
Letter to terminate Part 30/40 License after receipt of Part 50 License Licensing January 2015
- 11.
ASME Section III N-3 Report Crouch September 2014
- 12.
Letter to NRC for notification of Vital Area Boundary Restoration Licensing May 2014
- 13.
Unit 2 Completion Letter Licensing December 2014
- 14.
Fire Protection Report Hilmes/Wiggal July 26, 2012
WBN UNIT 2 PROJECT PLAN: 06/28/2012 Page 6 SOURCE: POD UPDATES, COMMITMENTS Item No.
Description Resp. Person Due Date Other Submittals
- 15.
PAM variable Calc for EOP reviews.
Crouch 2012 Regional Submittals
- 1.
NOV 391/2010-603-08: Heinemann Breakers Wiggall/Enis/Stockton July 17, 2012